CN110424532A - Large-span prestressed structure floor and high-precision construction floor one-pass molding construction method - Google Patents

Large-span prestressed structure floor and high-precision construction floor one-pass molding construction method Download PDF

Info

Publication number
CN110424532A
CN110424532A CN201910673125.3A CN201910673125A CN110424532A CN 110424532 A CN110424532 A CN 110424532A CN 201910673125 A CN201910673125 A CN 201910673125A CN 110424532 A CN110424532 A CN 110424532A
Authority
CN
China
Prior art keywords
construction
floor
frame body
pass molding
precompressed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910673125.3A
Other languages
Chinese (zh)
Inventor
袁尚锋
付航航
鲍素贞
罗文杰
曾凡林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
First Construction Co Ltd of China Construction Third Engineering Division
Original Assignee
First Construction Co Ltd of China Construction Third Engineering Division
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by First Construction Co Ltd of China Construction Third Engineering Division filed Critical First Construction Co Ltd of China Construction Third Engineering Division
Priority to CN201910673125.3A priority Critical patent/CN110424532A/en
Publication of CN110424532A publication Critical patent/CN110424532A/en
Priority to PCT/CN2020/090566 priority patent/WO2021012759A1/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/16Structures made from masses, e.g. of concrete, cast or similarly formed in situ with or without making use of additional elements, such as permanent forms, substructures to be coated with load-bearing material
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/02Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for rooms as a whole by which walls and floors are cast simultaneously, whole storeys, or whole buildings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/12Mounting of reinforcing inserts; Prestressing
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention discloses a kind of large-span prestressed structure floors and high-precision construction floor one-pass molding construction method, the following steps are included: expiring hall frame body system and concrete unit column combination progress Three-dimensional finite element modeling to prestressed reinforced concrete construction, high-supported formwork, and FEM Simulation is carried out, obtaining post-cast strip closing embodiment, concrete unit plate prestressed stretch-draw scheme and high-supported formwork expires form erection plan, precompressed scheme and the demoulding scheme of hall frame body;Carry out the construction of prestressing force high-supported formwork;The precompressed of full hall scaffold frame body is carried out according to precompressed scheme;Carry out structure flooring one-pass molding construction;Concrete unit plate is subjected to pre-stress construction;Embodiment is closed according to post-cast strip, determines and carries out pouring band piecemeal combined closing after reasonable plate built-up sequence carries out.Large-span prestressed structure floor proposed by the present invention and high-precision construction floor one-pass molding construction method, can reduce construction cost, while effectively shorten the construction period.

Description

Large-span prestressed structure floor and high-precision construction floor one-pass molding construction method
Technical field
The present invention relates to the method for construction technical field of large-scale logistics workshop more particularly to a kind of large-span prestressed structures Floor and high-precision construction floor one-pass molding construction method.
Background technique
With rapid economic development, original single layer structure workshop has been unable to meet the market demand, according to domestic and international current factory The status of room design and construction tends to develop toward multi storied factory building, is on the one hand able to satisfy the demand of national economic development, another Aspect can economize the land resource, and alleviate the problem of domestic city construction land anxiety.For logistic storage class workshop, due to it Higher to flooring required precision using functional characteristics, flatness requirement is usually no more than 3mm/2m, very poor to be no more than 20mm; And for multi storied factory building, two layers and the above flooring surface layer and structural concrete are typically designed as one-time-concreting construction molding.
It is once flattened due to carrying out flooring on large-span prestressed structure floor, flatness will reach the high-precision flat of design It is required that must be controlled at two aspects in work progress: first is that the deformation of total system must be controlled in regulation model In enclosing, second is that flooring leveling construction quality must control within the specified scope, wherein the Deformation control of structural system is difficult point It is key point.
Summary of the invention
The main purpose of the present invention is to provide a kind of large-span prestressed structure floor and high-precision construction floor once at Type construction method, it is intended to reduce construction cost, while effectively shorten the construction period.
To achieve the above object, the present invention provide a kind of large-span prestressed structure floor and high-precision construction floor once at Type construction method, comprising the following steps:
Hall frame body system is expired to prestressed reinforced concrete construction, high-supported formwork and the combination of concrete unit column carries out three-dimensional and has Meta Model is limited, and carries out FEM Simulation, obtains post-cast strip closing embodiment, concrete unit plate prestressed stretch-draw Scheme and high-supported formwork expire form erection plan, precompressed scheme and the demoulding scheme of hall frame body;
Expire the form erection plan of hall frame body according to the high-supported formwork being calculated, carries out the construction of prestressing force high-supported formwork;
The precompressed of full hall scaffold frame body is carried out according to precompressed scheme;
Carry out structure flooring one-pass molding construction;
According to concrete unit plate prestressed stretch-draw scheme, concrete unit plate is subjected to pre-stress construction;
Embodiment is closed according to post-cast strip, determines and carries out pouring band piecemeal combination envelope after reasonable plate built-up sequence carries out It closes.
Preferably, include following procedure when progress FEM Simulation:
Prestressed reinforced concrete construction is analyzed after concreting molding, after tensioning construction and high-supported formwork expires hall frame Vertical deformation after body is removed under three kinds of states;
Analysis high-supported formwork expires the stress and deformation values of hall frame body, determines the springing height of primary-secondary beam;
The variation for analyzing structure secondary axes power brought by the various combinations of concrete unit plate, determines secondary axes force value The smallest combination.
Preferably, the high-supported formwork that the basis is calculated expires the form erection plan of hall frame body, carries out prestressing force high-supported formwork Before the step of construction further include:
Complete system is formed using two-step evolution using total station and level closure horizontal control network and vertical control point One observing and controlling system;
It being measured during measurement using annexed leveling line, the survey of construction elevation point is located on standard section of tower crane, and Perform label.
Preferably, the construction of prestressing force high-supported formwork includes full hall scaffold erection construction, beam forms installation, floor template peace It is filled with and reinforcement installation, full hall scaffold uses fastener type steel pipe scaffold or disk buckle type scaffold, full hall scaffold setting is cut Frame body is reinforced in knife support.
Preferably, when carrying out the precompressed of full hall scaffold frame body, after bed die is mated formation, precompressed is carried out to full hall scaffold, is adopted With sandbag precompressed, precompressed loading sequence is successively symmetrically to carry out from beam-ends position to span centre position, point multistage progress precompressed.
Preferably, when full hall scaffold before precompressed, absolute altitude is reserved at top will calculate ground relative settlement amount, including frame body bullet Property and non-resilient value.
Preferably, carrying out structure flooring one-pass molding construction includes: the control of concrete absolute altitude, concreting, laser booth Paving machine concrete leveling, warehouse dispense abrasion-resistant powder, grinding, polishing, maintenance and flooring protection.
Preferably, when carrying out structure flooring one-pass molding construction,
Concreting: first pouring vertical structure, then pour horizontal structure, from low toward high, placement layer by layer;
Concrete vibrating: avoiding presstressed reinforcing steel and Grouting Pipe position, vibration compacting, and it is default deep that when placement layer by layer gos deep into lower layer Degree;
Grinding, polishing: dispensing abrasion-resistant powder several times, after abrasion-resistant powder is impregnated with, install additional with sanding machine the machinery of disk Trowel is polished, and after mechanical grinding, the mechanical trowel for remove disk receives light.
Preferably, include: when pre-stress construction
It spreads muscle: covering upper termination device in one end of every steel strand wires, and it is pre-buried that it by root is penetrated concrete unit column Bellows in;
Tensioning: after steel strand wires put on limit plate, stretch-draw jack is connected, and put on reusable tool anchor slab, In After installation tool intermediate plate, oil is sent to stretch-draw jack tensioning oil cylinder, until reaching control stress for prestressing;
Anchoring: that unclamps stretch-draw jack send oil circuit shut-off valve, and tensioning piston drives next time in presstressed reinforcing steel retraction force In journey pre-determined distance, pass through work clip sheet anchoring prestress muscle;
Sealing end: at away from work clip sheet pre-determined distance, cutting off extra presstressed reinforcing steel, seal anchor head with concrete, presets After time into tensioning duct mud jacking, and with concrete anchor head end sealed flat.
Large-span prestressed structure floor proposed by the present invention and high-precision construction floor one-pass molding construction method, construction It is at low cost, and be effectively shortened the duration and be obviously improved the wearability of flooring, it can promote and improve domestic longspan structure Floor and high-precision construction floor one-pass molding construction technology are horizontal, especially the successful application in warehouse logistics workshop, after being The design and construction of warehouse logistics workshop provide reliable decision-making foundation and technical indicator, and social benefit and environmental benefit are aobvious It writes.This method is conducive to promote the application of multi storied factory building, reduces appropriation of land, while saving construction material, has good Environmental benefit.
Detailed description of the invention
Fig. 1 shows for the process of large-span prestressed structure floor of the invention and high-precision construction floor one-pass molding construction method It is intended to;
Fig. 2 is large-span prestressed structure floor of the invention and high-precision one embodiment of construction floor one-pass molding construction method The structural schematic diagram that middle concrete unit column divides;
Fig. 3 is large-span prestressed structure floor of the invention and high-precision one embodiment of construction floor one-pass molding construction method The construction built-up sequence schematic diagram of middle concrete unit column.
The embodiments will be further described with reference to the accompanying drawings for the realization, the function and the advantages of the object of the present invention.
Specific embodiment
It should be appreciated that the specific embodiments described herein are merely illustrative of the present invention, it is not intended to limit the present invention.
It should be noted that in the description of the present invention, term " transverse direction ", " longitudinal direction ", "upper", "lower", "front", "rear", The orientation or positional relationship of the instructions such as "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outside" is based on attached drawing institute The orientation or positional relationship shown, is merely for convenience of description of the present invention and simplification of the description, and is not the dress of indication or suggestion meaning It sets or element must have a particular orientation, be constructed and operated in a specific orientation, therefore should not be understood as to limit of the invention System.In addition, term " first ", " second " etc. are used for descriptive purposes only and cannot be understood as indicating or suggesting relative importance.
Referring to Fig.1, in this preferred embodiment, a kind of large-span prestressed structure floor and high-precision construction floor one-pass molding Construction method, comprising the following steps:
Step S10, hall frame body system expired to prestressed reinforced concrete construction, high-supported formwork and concrete unit column combine into Row Three-dimensional finite element modeling, and FEM Simulation is carried out, it is pre- to obtain post-cast strip closing embodiment, concrete unit plate Stress tension scheme and high-supported formwork expire form erection plan, precompressed scheme and the demoulding scheme of hall frame body;
Step S20 expires the form erection plan of hall frame body according to the high-supported formwork being calculated, and carries out applying for prestressing force high-supported formwork Work;
Step S30 carries out the precompressed of full hall scaffold frame body according to precompressed scheme;
Step S40 carries out structure flooring one-pass molding construction;
Step S50 applies concrete unit plate progress prestressing force according to concrete unit plate prestressed stretch-draw scheme Work;
Step S60 closes embodiment according to post-cast strip, determines and carries out pouring band point after reasonable plate built-up sequence carries out Block combined closing.
In step S10, carry out FEM Simulation when include following procedure:
Prestressed reinforced concrete construction is analyzed after concreting molding, after tensioning construction and high-supported formwork expires hall frame Vertical deformation after body is removed under three kinds of states;
Analysis high-supported formwork expires the stress and deformation values of hall frame body, determines the springing height of primary-secondary beam;
The variation for analyzing structure secondary axes power brought by the various combinations of concrete unit plate, determines secondary axes force value The smallest combination.
By MIDAS software, hall frame body system is expired to entire prestressed reinforced concrete construction, high-supported formwork and unit column combines Carry out Three-dimensional finite element modeling.FEM Simulation checking computations include the following contents: deformation gauge when frame body ground bearing load It calculates, deforms calculating, the deformation calculating of frame body construction load-bearing, structure when high-supported formwork expires the Force Calculation of hall frame body, frame body precompressed Structure secondary axes power calculates when the Force Calculation of girder pre-stressed tensioning and deformation calculate, pre-stress element plate combines, frame body is removed The deformation of structure calculates afterwards.
Further, before step S20 further include:
Step S11, using total station and level closure horizontal control network and vertical control point, using two-step evolution, shape At complete unified observing and controlling system;
Step S12 uses annexed leveling line to measure (to eliminate or reduce instrument and other mistakes during measurement Influence of the difference to construction), the survey of construction elevation point is located on standard section of tower crane, and performs label (can use paint).
In step S30, the construction of prestressing force high-supported formwork includes full hall scaffold erection construction, beam forms installation, flooring mould Plate installation and reinforcement installation, full hall scaffold are set using fastener type steel pipe scaffold or disk buckle type scaffold, full hall scaffold Bridging is set to reinforce frame body.
Beam span is greater than 4m, and beam bottom mother plate presses 0.1% arch camber of span.After beam bottom board installation, reinforcement installation completion divides again Secondary installation side form, pressure foot and diagonal brace;
When span of slab is greater than or equal to 4m, template presses 0.1% arch camber of span.
In step S40, when carrying out the precompressed of full hall scaffold frame body, after bed die is mated formation, precompressed is carried out to full hall scaffold, Using sandbag precompressed, precompressed loading sequence is successively symmetrically to carry out from beam-ends position to span centre position, point multistage progress precompressed.In advance Press load by 1.2 times of considerations of concrete solid gravity, the precompressed phase is not less than 3 days.Can divide three-level carry out precompressed: 60% → 80% → 120%;
When full hall scaffold before precompressed, absolute altitude is reserved at top will calculate ground relative settlement amount, including frame body elasticity and non- Elasticity number.Ground relative settlement amount determines that the flexible deformation of frame body is with husky general soft to calculate after testing inspection when basement process Part program node, which calculates, to be determined.Frame body construction is heavy to stay value in 15~20mm or so, adjusts after preloading observation.
In step S40, carrying out structure flooring one-pass molding construction includes: the control of concrete absolute altitude, concreting, laser Paver concrete leveling, warehouse dispense abrasion-resistant powder, grinding, polishing, maintenance and flooring protection.When concrete absolute altitude controls, Flooring absolute altitude introduction point is projected on standard section of tower crane, then is introduced on floor structure column and is spread out by the absolute altitude on standard section of tower crane On the laser emitter of paving machine.
When carrying out structure flooring one-pass molding construction,
Concreting: first pouring vertical structure, then pour horizontal structure, from low toward high, placement layer by layer;
Concrete vibrating: avoiding presstressed reinforcing steel and Grouting Pipe position, vibration compacting, and it is default deep that when placement layer by layer gos deep into lower layer It spends (500mm);
Grinding, polishing: dispense several times abrasion-resistant powder (such as can in two times, first time dosage is 60%, and second of dosage be 40%) it, after abrasion-resistant powder is impregnated with, is polished with the mechanical trowel that sanding machine install additional disk, after mechanical grinding, carries out removing disk Mechanical trowel receive light.
In concrete initial set (people has a footprint when trampling upper ground surface, but unobvious sagging when), polished using two-wheel Machine carries out the first mechanical trowel operation for installing disk additional, removes laitance, warehouse.
In step S50, when pre-stress construction, includes:
It spreads muscle: covering upper termination device (special sub warhead can be used) in one end of every steel strand wires, and it is penetrated by root In the pre-buried bellows of concrete unit column;
Tensioning: after steel strand wires put on limit plate, stretch-draw jack is connected, and put on reusable tool anchor slab, In After installation tool intermediate plate (clip surface, which is coated, moves back anchor spirit), oil is slowly sent to the tensioning oil cylinder of stretch-draw jack, is opened until reaching Draw proof stress;
Anchoring: that unclamps stretch-draw jack send oil circuit shut-off valve, and tensioning piston drives next time in presstressed reinforcing steel retraction force In journey pre-determined distance (6-8 millimeters), pass through work clip sheet anchoring prestress muscle;
Sealing end: at away from work clip sheet pre-determined distance (50m), cutting off extra presstressed reinforcing steel, seal anchor head with concrete, Mud jacking in the duct Xiang Zhangla (in 48 hours) after preset time, and with concrete sealed anchor head end flat.
In step S60, influence of the sequence to prestressing force secondary axes power is poured by finite element model analysis post-cast strip, proposes to close Close embodiment in the post-cast strip of reason;And post-cast strip piecemeal combined closing is carried out by reasonable plate built-up sequence is formulated.With Fig. 2 For the concrete unit column of this structure, sequence shown in Fig. 3 can be used and carry out post-cast strip pouring construction.
Compared with prior art, the present invention has the beneficial effects that
With structure and the secondary Construction Comparison of construction floor, the duration is shorter.Referring to table 1, with a 1000m2Structure job step It compares, the duration saves 5 days.
The new and old arrangement and method for construction duration contrast table of table 1
There is preferable economic benefit, with a 1000m with structure and the secondary Construction Comparison of construction floor referring to table 22 Structure job step compares, and saves project cost 14.3%.
The new and old arrangement and method for construction of table 2 unit price and total price contrast table
The large-span prestressed structure floor and high-precision construction floor one-pass molding construction method that the present embodiment proposes, are applied Work is at low cost, and is effectively shortened the duration and has been obviously improved the wearability of flooring, can promote and improve domestic large span knot Structure floor and high-precision construction floor one-pass molding construction technology are horizontal, especially the successful application in warehouse logistics workshop, for The design and construction of warehouse logistics workshop provide reliable decision-making foundation and technical indicator afterwards, and social benefit and environmental benefit are aobvious It writes.This method is conducive to promote the application of multi storied factory building, reduces appropriation of land, while saving construction material, has good Environmental benefit.
The above is only a preferred embodiment of the present invention, is not intended to limit the scope of the invention, all to utilize this hair Equivalent structure transformation made by bright specification and accompanying drawing content is applied directly or indirectly in other relevant technical fields, Similarly it is included within the scope of the present invention.

Claims (9)

1. a kind of large-span prestressed structure floor and high-precision construction floor one-pass molding construction method, which is characterized in that including Following steps:
Hall frame body system is expired to prestressed reinforced concrete construction, high-supported formwork and the combination of concrete unit column carries out three-dimensional finite element Modeling, and FEM Simulation is carried out, obtain post-cast strip closing embodiment, concrete unit plate prestressed stretch-draw scheme And high-supported formwork expires form erection plan, precompressed scheme and the demoulding scheme of hall frame body;
Expire the form erection plan of hall frame body according to the high-supported formwork being calculated, carries out the construction of prestressing force high-supported formwork;
The precompressed of full hall scaffold frame body is carried out according to precompressed scheme;
Carry out structure flooring one-pass molding construction;
According to concrete unit plate prestressed stretch-draw scheme, concrete unit plate is subjected to pre-stress construction;
Embodiment is closed according to post-cast strip, determines and carries out pouring band piecemeal combined closing after reasonable plate built-up sequence carries out.
2. large-span prestressed structure floor as described in claim 1 and high-precision construction floor one-pass molding construction method, Be characterized in that, carry out FEM Simulation when include following procedure:
Prestressed reinforced concrete construction is analyzed after concreting molding, after tensioning construction and high-supported formwork is expired hall frame body and torn open Except the vertical deformation under rear three kinds of states;
Analysis high-supported formwork expires the stress and deformation values of hall frame body, determines the springing height of primary-secondary beam;
The variation for analyzing structure secondary axes power brought by the various combinations of concrete unit plate determines that secondary axes force value is minimum Combination.
3. large-span prestressed structure floor as described in claim 1 and high-precision construction floor one-pass molding construction method, It is characterized in that, the high-supported formwork that the basis is calculated expires the form erection plan of hall frame body, carries out the construction of prestressing force high-supported formwork Before step further include:
Using total station and level closure horizontal control network and vertical control point, completely unified using two-step evolution, formation Observing and controlling system;
It is measured during measurement using annexed leveling line, the survey of construction elevation point is located on standard section of tower crane, and is performed Label.
4. large-span prestressed structure floor as claimed in claim 3 and high-precision construction floor one-pass molding construction method, Be characterized in that, the construction of prestressing force high-supported formwork include full hall scaffold erection construction, beam forms installation, floor template installation and Reinforcement installation, full hall scaffold use fastener type steel pipe scaffold or disk buckle type scaffold, and bridging pair is arranged in full hall scaffold Frame body is reinforced.
5. large-span prestressed structure floor as described in claim 1 and high-precision construction floor one-pass molding construction method, It is characterized in that, when carrying out the precompressed of full hall scaffold frame body, after bed die is mated formation, precompressed is carried out to full hall scaffold, using sandbag Precompressed, precompressed loading sequence are successively symmetrically to carry out from beam-ends position to span centre position, point multistage progress precompressed.
6. large-span prestressed structure floor as claimed in claim 5 and high-precision construction floor one-pass molding construction method, It is characterized in that, when full hall scaffold before precompressed, absolute altitude is reserved at top will calculate ground relative settlement amount, including frame body elasticity and non- Elasticity number.
7. large-span prestressed structure floor as described in claim 1 and high-precision construction floor one-pass molding construction method, Be characterized in that, carry out the one-pass molding of structure flooring construction include: the control of concrete absolute altitude, concreting, laser paver mix Solidifying soil is levelling, warehouse, dispenses abrasion-resistant powder, grinding, polishing, maintenance and flooring protection.
8. large-span prestressed structure floor as claimed in claim 7 and high-precision construction floor one-pass molding construction method, It is characterized in that, when carrying out structure flooring one-pass molding construction,
Concreting: first pouring vertical structure, then pour horizontal structure, from low toward high, placement layer by layer;
Concrete vibrating: avoiding presstressed reinforcing steel and Grouting Pipe position, vibration compacting, and when placement layer by layer gos deep into lower layer's predetermined depth;
Grinding, polishing: dispensing abrasion-resistant powder several times, after abrasion-resistant powder is impregnated with, is beaten with the mechanical trowel that sanding machine install additional disk It grinds, after mechanical grinding, the mechanical trowel for remove disk receives light.
9. large-span prestressed structure floor as described in claim 1 and high-precision construction floor one-pass molding construction method, It is characterized in that, when pre-stress construction includes:
It spreads muscle: covering upper termination device in one end of every steel strand wires, and it is penetrated into the pre-buried wave of concrete unit column by root In line pipe;
Tensioning: after steel strand wires put on limit plate, stretch-draw jack is connected, and put on reusable tool anchor slab, installed After tool clamping piece, oil is sent to stretch-draw jack tensioning oil cylinder, until reaching control stress for prestressing;
Anchoring: that unclamps stretch-draw jack send oil circuit shut-off valve, and the backhaul under the drive of presstressed reinforcing steel retraction force of tensioning piston is pre- If passing through work clip sheet anchoring prestress muscle apart from interior;
Sealing end: at away from work clip sheet pre-determined distance, extra presstressed reinforcing steel is cut off, seals anchor head, preset time with concrete Mud jacking in backward tensioning duct, and anchor head end is sealed with concrete and is put down.
CN201910673125.3A 2019-07-24 2019-07-24 Large-span prestressed structure floor and high-precision construction floor one-pass molding construction method Pending CN110424532A (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN201910673125.3A CN110424532A (en) 2019-07-24 2019-07-24 Large-span prestressed structure floor and high-precision construction floor one-pass molding construction method
PCT/CN2020/090566 WO2021012759A1 (en) 2019-07-24 2020-05-15 Long-span pre-stressed structure floor slab and high-precision building floor topping one-time forming construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910673125.3A CN110424532A (en) 2019-07-24 2019-07-24 Large-span prestressed structure floor and high-precision construction floor one-pass molding construction method

Publications (1)

Publication Number Publication Date
CN110424532A true CN110424532A (en) 2019-11-08

Family

ID=68412238

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910673125.3A Pending CN110424532A (en) 2019-07-24 2019-07-24 Large-span prestressed structure floor and high-precision construction floor one-pass molding construction method

Country Status (2)

Country Link
CN (1) CN110424532A (en)
WO (1) WO2021012759A1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2021012759A1 (en) * 2019-07-24 2021-01-28 中建三局第一建设工程有限责任公司 Long-span pre-stressed structure floor slab and high-precision building floor topping one-time forming construction method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004132008A (en) * 2002-10-09 2004-04-30 Nippon Kaiser Kk Slab designing method and slab
CN102322142A (en) * 2011-06-16 2012-01-18 永升建设集团有限公司 Construction method for 45-DEG-inclined long-overhanging reinforced concrete structure project
CN103603449A (en) * 2013-10-21 2014-02-26 傅礼铭 Construction method of hidden frame dense rib cavity floor
CN105133841A (en) * 2015-07-29 2015-12-09 五洋建设集团股份有限公司 Spatial curved surface steel structure pipe truss roof installation construction method
CN108319755A (en) * 2017-12-29 2018-07-24 黑龙江大学 A kind of overall process optimization method of Super High hydraulic climbing formwork scaffold construction
CN108330835A (en) * 2018-01-31 2018-07-27 中铁二十二局集团第工程有限公司 The construction method of setting bracket
CN109267683A (en) * 2018-08-28 2019-01-25 重庆大学 A kind of high-precision flatness control methods of prestressed structure flooring one-pass molding

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110424532A (en) * 2019-07-24 2019-11-08 中建三局第一建设工程有限责任公司 Large-span prestressed structure floor and high-precision construction floor one-pass molding construction method

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004132008A (en) * 2002-10-09 2004-04-30 Nippon Kaiser Kk Slab designing method and slab
CN102322142A (en) * 2011-06-16 2012-01-18 永升建设集团有限公司 Construction method for 45-DEG-inclined long-overhanging reinforced concrete structure project
CN103603449A (en) * 2013-10-21 2014-02-26 傅礼铭 Construction method of hidden frame dense rib cavity floor
CN105133841A (en) * 2015-07-29 2015-12-09 五洋建设集团股份有限公司 Spatial curved surface steel structure pipe truss roof installation construction method
CN108319755A (en) * 2017-12-29 2018-07-24 黑龙江大学 A kind of overall process optimization method of Super High hydraulic climbing formwork scaffold construction
CN108330835A (en) * 2018-01-31 2018-07-27 中铁二十二局集团第工程有限公司 The construction method of setting bracket
CN109267683A (en) * 2018-08-28 2019-01-25 重庆大学 A kind of high-precision flatness control methods of prestressed structure flooring one-pass molding

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2021012759A1 (en) * 2019-07-24 2021-01-28 中建三局第一建设工程有限责任公司 Long-span pre-stressed structure floor slab and high-precision building floor topping one-time forming construction method

Also Published As

Publication number Publication date
WO2021012759A1 (en) 2021-01-28

Similar Documents

Publication Publication Date Title
CN101230563B (en) Method for replacing bridge bearing without traffic interruption and special device thereof
CN210066671U (en) Novel rectangular gallery structure
CN105507168A (en) Multi-span box girder integral ultrahigh alternate jacking construction system and method
CN105839985A (en) Hydropower station rectangular high tower hydraulic climb slip form system and construction method
CN112211113A (en) Cast-in-place construction method for large-span diamond-shaped bent cap of high pier
CN108755394B (en) Method for reinforcing special-shaped pier column of bridge by using prestressed tendons
CN110424532A (en) Large-span prestressed structure floor and high-precision construction floor one-pass molding construction method
CN114457682A (en) Cast-in-place construction method of cast-in-place concrete bridge
CN106498855B (en) A kind of construction method for the small headroom Cast-in-situ Beam of bridge
CN109112903A (en) Solid concrete roabed trackless construction technology is cheated in a kind of phase library inner column formula inspection
CN109881699B (en) Method for molding and installing concrete tire of assembled tongue-and-groove Miller type universal raft foundation
Rios et al. Adaptations of the flat jack test for its application in cob walls
CN100570066C (en) Change the Template Location method of laminated rubber bearing on the road bridge abutment
CN114277672B (en) Large-span prestressed concrete bent cap structure and construction method thereof
CN102926532B (en) Mounting method for templates of box-type steel skeleton inclined column
CN113756601B (en) Frame column replacement reinforcement construction method
CN205035732U (en) Interim support of combined type bridge
CN113833003A (en) Construction method of raft plate of oversized clean workshop
CN106836794A (en) A kind of construction method of concatermer sliding formwork
CN112726517A (en) Construction method of aqueduct above bridge
CN102071612A (en) Method for constructing arched uneven pavement slab
CN111794278A (en) Plugging structure and construction method for plugging reserved hole of middle plate by using plugging structure
CN110578298A (en) Concrete pouring process for top of viaduct upright post
Frosch et al. Development and Splice Lengths for High-Strength Reinforcement, Volume I: General Bar Development
CN115467255A (en) Mounting method for newly-added support additionally provided with concrete member for anti-overturning reconstruction of single-column pier bridge

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20191108