CN110410101A - Tunnel deformation segment again supporting when heavy type inverted arch steelframe construction method - Google Patents

Tunnel deformation segment again supporting when heavy type inverted arch steelframe construction method Download PDF

Info

Publication number
CN110410101A
CN110410101A CN201910719995.XA CN201910719995A CN110410101A CN 110410101 A CN110410101 A CN 110410101A CN 201910719995 A CN201910719995 A CN 201910719995A CN 110410101 A CN110410101 A CN 110410101A
Authority
CN
China
Prior art keywords
inverted arch
steelframe
heavy
arch
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910719995.XA
Other languages
Chinese (zh)
Inventor
王海军
赵月生
郭自敏
刘晓亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 12th Bureau Group Co Ltd
Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Original Assignee
China Railway 12th Bureau Group Co Ltd
Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 12th Bureau Group Co Ltd, Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd filed Critical China Railway 12th Bureau Group Co Ltd
Priority to CN201910719995.XA priority Critical patent/CN110410101A/en
Publication of CN110410101A publication Critical patent/CN110410101A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/15Plate linings; Laggings, i.e. linings designed for holding back formation material or for transmitting the load to main supporting members
    • E21D11/152Laggings made of grids or nettings
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/18Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/28Longitudinal struts, i.e. longitudinal connections between adjoining arches
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • E21D20/003Machines for drilling anchor holes and setting anchor bolts
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • E21D20/02Setting anchoring-bolts with provisions for grouting

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The present invention provide a kind of tunnel deformation segment again supporting when heavy type inverted arch steelframe construction method, comprising: S0) in pneumatically placed concrete at the beginning of the inverted arch portion of tunnel deformation segment;S1 inverted arch portion) is divided into multiple circulation construction sections, in each circulation construction section internal labeling inverted arch installation site, each inverted arch installation site is correspondingly arranged with the position for being equipped with arch wall heavy type steelframe;S2) assembled heavy inverted arch steelframe, and the heavy inverted arch steelframe after assembly is hoisted in specified inverted arch installation site, so that the heavy inverted arch steelframe in the inverted arch installation site closes cyclization with corresponding arch wall heavy type steelframe;S3 multiple inverted arch connectors are performed between the heavy inverted arch steelframe after two adjacent assembly) to connect two adjacent two heavy inverted arch steelframes.Assembled heavy inverted arch steelframe is hoisted to the installation of inverted arch installed position by the construction method, is saved the shipping time that transport one by one forms the inverted arch steelframe section of heavy inverted arch steelframe, is improved the construction efficiency of heavy inverted arch steelframe.

Description

Tunnel deformation segment again supporting when heavy type inverted arch steelframe construction method
Technical field
The present invention relates to technical field of tunnel construction, and in particular, to a kind of tunnel deformation segment again supporting when heavy type face upward Encircle the construction method of steelframe.
Background technique
In constructing tunnel, when in the stratum that construction tunnel is in weak surrounding rock, especially construction tunnel is in coal measures In stratum, by anticlinal nucleus rock stratum it is slow incline, rock stratum is weak, by factors such as high low stress, hole group's effects is influenced that supporting is completed Tunnel deforms, even if main tunnel is put down using the lining cutting of large deformation A type, III type lining cutting of large deformation after optimization in construction early period It leads and has excavated and do not apply the floor section just measures such as Zhi Zengshe heavy type inverted arch steelframe progress supporting, the part paragraph in tunnel still meets with Serious deformation failure has been arrived, the short abutment wall cracking of just branch chip off-falling, steelframe torsional deformation, inverted arch, lining concrete flake-off has occurred Phenomena such as block and bar bending, inverted arch tunnel bottom protuberance.In order to guarantee tunnel support structure and construction safety, guarantee what secondary village was built Design thickness, must the supporting construction to soft rock large deformation section remove and country rock digs, while performing and meeting construction requirement New supporting construction.When performing the inverted arch portion supporting construction in new supporting construction, a large amount of heavy inverted arch is set up in inverted arch portion Steelframe, as the important feature of inverted arch supporting, the erection speed of heavy inverted arch steelframe influences whether the construction efficiency of inverted arch supporting, Every Pin heavy type inverted arch steelframe is all made of multiple inverted arch steelframe sections, and current heavy inverted arch steelframe construction method is will be heavy Inverted arch steelframe section in inverted arch steelframe is routed to the designated position in inverted arch portion, the time-consuming and laborious construction effect for influencing inverted arch supporting one by one Therefore rate needs a kind of construction method of heavy inverted arch steelframe to solve the problems, such as above-mentioned at least one.
Summary of the invention
The purpose of the present invention is be directed to the generation large deformation in the tunnel main tunnel in weak surrounding rock, coal measure strata to cause inverted arch Surrouding rock deformation around portion causes inverted arch Supporting Structure deformation, when performing inverted arch supporting construction again, in heavy inverted arch steelframe Inverted arch steelframe section one by one assembled laying construction low efficiency the problem of, provide a kind of tunnel deformation segment again supporting when heavy type inverted arch The construction method of steelframe performs construction efficiency when heavy inverted arch steelframe to improve again.
To achieve the goals above, the embodiment of the present invention provide a kind of tunnel deformation segment again supporting when heavy type inverted arch steelframe Construction method, the construction method executes after the completion of the arch wall supporting of supporting section tunnel deformation segment, the arch wall branch Agree with the arch wall during shield and arch wall steelframe be installed, the construction method is the following steps are included: S0) facing upward in tunnel deformation segment Just spray the concrete of the first given thickness in arch;S1 the inverted arch portion of tunnel deformation segment) is divided into multiple circulation construction sections, and Each circulation construction section internal labeling goes out multiple inverted arch installation sites, wherein each inverted arch installation site and being equipped with the arch The position of wall heavy type steelframe is correspondingly arranged;S2) assembled heavy inverted arch steelframe, and the heavy inverted arch steelframe after assembly is hoisted to finger In fixed inverted arch installation site, so that the heavy inverted arch steelframe being mounted in the inverted arch installation site and corresponding arch wall heavy-duty steel Frame closing cyclization;S3 multiple inverted arch connectors) are performed between the heavy inverted arch steelframe after two adjacent assembly, to connect Heavy inverted arch steelframe after stating two adjacent assembly.
Specifically, step S1) in each circulation construction section internal labeling go out multiple inverted arch installation sites, wherein each face upward Arch installation site is correspondingly arranged with the position for being equipped with the arch wall heavy type steelframe, comprising: along tunnel deformation segment to supporting section It is longitudinal, mark arch wall heavy type steelframe quantity corresponding with the circulation construction section identical more in the inverted arch portion of the circulation construction section A inverted arch camber line, so that the position of each inverted arch camber line and the arch wall heavy type steelframe of label is correspondingly arranged;Based on more A inverted arch camber line determines the multiple inverted arch installation site.
Specifically, the construction method further include: after step S2) and before step S3), construct in the circulation The inverted arch portion of section is laid with steel mesh, and the heavy inverted arch steelframe is fixed with the steel mesh near the heavy type inverted arch steelframe.
Specifically, the construction method further include: after step S3), sprayed again to the circulation construction section in inverted arch portion The concrete of second given thickness simultaneously performs inverted arch in the circulation construction section after the concrete of multiple spray reaches given set strength Anchor pole.
Specifically, the inverted arch anchor pole that performs includes: along the longitudinal according to given longitudinal pitch mark of the circulation construction section Remember multiple inverted arch construction lines and determines multiple construction coordinates according to given lateral loops spacing on each inverted arch construction line Point;The bolthole of given depth is drilled out on each construction coordinate point;Long anchor pole is placed into bolthole described in each, And slip casting is stopped until reaching predetermined grouting amount by each long anchor pole slip casting into bolthole.
Specifically, the longitudinal pitch and the lateral loops spacing are between 1.0m-1.3m.
The present invention provide a kind of tunnel deformation segment again supporting when heavy type inverted arch steelframe construction method, which exists It is executed after the completion of arch wall supporting, the inverted arch portion of tunnel deformation segment is divided into multiple circulation construction sections using when the construction method, It constructs in each circulation construction section, in order to ensure the supporting intensity of each circulation construction section, is applied in each circulation one by one The quantity of the quantity of the heavy inverted arch steelframe performed in workshop section arch wall heavy type steelframe corresponding with the circulation construction section is identical, is pacifying When filling heavy inverted arch steelframe, first go out inverted arch installation site in a circulation construction section internal labeling, then the heavy type that assembly is completed is faced upward Arch steelframe is hoisted to specified inverted arch installed position, is hoisted to inverted arch installation site using by assembled heavy inverted arch steelframe Method, when saving transport required when handling one by one forms inverted arch steelframe section in heavy inverted arch steelframe to inverted arch installation site Between, improve the construction efficiency of heavy inverted arch steelframe, will be hoisted to later the heavy inverted arch steelframe of inverted arch installed position with it is right The arch wall heavy type steelframe connection closing cyclization answered, connection heavy inverted arch steelframe per adjacent two reinforce the integer support in tunnel Intensity.
Tunnel deformation segment provided by the invention again supporting when heavy type inverted arch steelframe construction method, by assembly complete weight Type inverted arch steelframe is hoisted to the installation of inverted arch installed position, saves the inverted arch steelframe section that transport one by one forms heavy inverted arch steelframe Shipping time, improve the construction efficiency of heavy inverted arch steelframe.
Other features and advantages of the present invention will the following detailed description will be given in the detailed implementation section.
Detailed description of the invention
The drawings are intended to provide a further understanding of the invention, and constitutes part of specification, with following tool Body embodiment is used to explain the present invention together, but is not construed as limiting the invention.In the accompanying drawings:
Fig. 1 be embodiment of the present invention provide tunnel deformation segment again supporting when heavy type inverted arch steelframe construction method Flow chart.
Specific embodiment
Below in conjunction with attached drawing, detailed description of the preferred embodiments.It should be understood that this place is retouched The specific embodiment stated is merely to illustrate and explain the present invention, and is not intended to restrict the invention.
It should be noted that in the absence of conflict, the feature in embodiment and embodiment in the present invention can phase Mutually combination.
In the present invention, in the absence of explanation to the contrary, the noun of locality used such as " upper and lower, top, bottom " is usually needle For direction shown in the drawings either for it is vertical, on vertical or gravity direction for each component mutual alignment relation Word is described.
The present invention will be described in detail below with reference to the accompanying drawings and embodiments.
Embodiment of the present invention provide a kind of tunnel deformation segment again supporting when heavy type inverted arch steelframe construction method, Fig. 1 For tunnel deformation segment again supporting when heavy type inverted arch steelframe construction method flow chart, as shown in Figure 1, the construction method exists Executing after the completion of the arch wall supporting of supporting section for tunnel deformation segment, agrees with the arch wall during the arch wall supporting and is equipped with arch Wall steelframe, the construction method is the following steps are included: S0) in the coagulation of the first given thickness of spray at the beginning of the inverted arch portion of tunnel deformation segment Soil;S1 the inverted arch portion of tunnel deformation segment) is divided into multiple circulation construction sections, and is gone out in each circulation construction section internal labeling Multiple inverted arch installation sites, wherein each inverted arch installation site is correspondingly arranged with the position for being equipped with the arch wall heavy type steelframe; S2) assembled heavy inverted arch steelframe, and the heavy inverted arch steelframe after assembly is hoisted in specified inverted arch installation site, so that peace Heavy inverted arch steelframe in the inverted arch installation site closes cyclization with corresponding arch wall heavy type steelframe;S3) adjacent two Multiple inverted arch connectors are performed between heavy inverted arch steelframe after a assembly, to connect the heavy type after two adjacent assembly Inverted arch steelframe.
Tunnel deformation segment provided by the invention again supporting when heavy type inverted arch steelframe construction method, by by assembled weight Type inverted arch steelframe handling saves the inverted arch steel in the heavy inverted arch steelframe of the composition of handling one by one to specified inverted arch installed position The time of frame section accelerates the installation speed of heavy inverted arch steelframe, improves the construction efficiency of inverted arch construction.
In one embodiment, original supporting is removed in tunnel deformation segment and the tunnel deformation segment for removing original supporting is pressed It is required that being digged, the tunnel deformation segment for completing to dig part to completion after digging performs arch wall supporting again, is digging later Partial tunnel deformation segment performs inverted arch supporting again, is gone when performing inverted arch supporting again using construction method provided by the invention Heavy inverted arch steelframe important in inverted arch supporting is set up, to improve inverted arch construction efficiency;In construction method provided by the present invention The tunnel deformation segment being previously mentioned refer both to complete dig after tunnel deformation segment, wherein for inverted arch portion dig depth reach 5 meters with On inverted arch deep basal pit, when carrying out heavy inverted arch steelframe using the construction method and setting up, first in the inverted arch portion of tunnel deformation segment Just the first given thickness of spray is not less than the concrete of 4cm, later draws the inverted arch portion for completing the just tunnel deformation segment of pneumatically placed concrete Be divided into multiple circulation construction sections, go out inverted arch installation site in each circulation construction section internal labeling, the quantity of inverted arch installation site with The quantity of the corresponding arch wall heavy type steelframe of the circulation construction section is identical, later hangs assembled heavy inverted arch steelframe by single track purlin Handling saves the desired transport of inverted arch steelframe section that lifting back and forth forms heavy inverted arch steelframe to specified inverted arch installation site Time accelerates the installation effectiveness of heavy inverted arch steelframe.
In order to determine the installation site of each heavy inverted arch steelframe, specifically, step S1) in each circulation construction section Internal labeling goes out multiple inverted arch installation sites, wherein each inverted arch installation site and the position pair for being equipped with the arch wall heavy type steelframe It should be arranged, comprising: along the longitudinal to supporting section of tunnel deformation segment, mark in the inverted arch portion of the circulation construction section and applied with the circulation The identical multiple inverted arch camber lines of the corresponding arch wall heavy type steelframe quantity of workshop section so that label each inverted arch camber line with it is described The position of arch wall heavy type steelframe is correspondingly arranged;The multiple inverted arch installation site is determined based on multiple inverted arch camber lines.
In one embodiment, each in the circulation construction multiple inverted arch camber lines of segment mark when determining inverted arch installation site The position of the corresponding arch wall heavy type steelframe of inverted arch camber line, marks the quantity and the quantity phase of arch wall heavy type steelframe of inverted arch camber line Together, after having marked multiple inverted arch camber lines, inverted arch installation site, In are determined according to the size of inverted arch camber line and heavy inverted arch steelframe In practice of construction, the quantity of usual inverted arch installation site is identical as the quantity of arch wall heavy type steelframe, the quantity of arch wall heavy type steelframe It is determined by construction site Surrounding Rock Strength, if construction site Surrounding Rock Strength is weaker, the arch wall heavy type steelframe in designated length Quantity is more, and the spacing between arch wall heavy type steelframe is smaller, and corresponding inverted arch installation site quantity is more, i.e., heavy inverted arch steelframe Quantity also can be corresponding more;If construction site Surrounding Rock Strength is stronger, the quantity of arch wall heavy type steelframe in designated length Less, the quantity of corresponding inverted arch installation site negligible amounts, i.e., heavy inverted arch steelframe also can be reduced accordingly, heavy inverted arch steelframe Lay it is relatively sparse, not only can Enhanced support intensity again not will cause support material waste.
In order to enhance the subsequent inverted arch portion for being cast in tunnel deformation segment concrete anti-crack ability, it is specifically, described to apply Work method further include: after step S2) and before step S3), it is laid with steel mesh in the inverted arch portion of the circulation construction section, And the heavy inverted arch steelframe is fixed with the steel mesh near the heavy type inverted arch steelframe.
After the completion of heavy inverted arch steelframe is set up, guarantee the steady of country rock around inverted arch portion to fix each heavy inverted arch steelframe It is fixed, specifically, the construction method further include: after step S3), to the circulation construction section in inverted arch portion spray again second to Determine the concrete of thickness and performs inverted arch anchor pole in the circulation construction section after the concrete of multiple spray reaches given set strength.Phase It by dowel and connects steelframe between the heavy inverted arch steelframes of adjacent two and is fixedly connected, by every two adjacent heavy type inverted arch After the completion of steelframe connection, pneumatically placed concrete is answered to inverted arch portion, answers the second given thickness of pneumatically placed concrete between 23cm-25cm, so that Multiple groups heavy type inverted arch steelframe is covered by concrete and is fixed, and the inverted arch supporting construction of existing intensity and flexible is formed, in multiple spray Concrete, which reaches, performs inverted arch anchor pole in inverted arch portion after given set strength, to stablize the country rock around inverted arch portion.
In one embodiment, heavy inverted arch steelframe is made of multistage HW200 fashioned iron, and multistage fashioned iron is assembled into and is faced upward The heavy inverted arch steelframe that arch shape is agreed with is hung using single track purlin and assembled heavy inverted arch steelframe is hoisted to specified inverted arch peace Holding position.
For the inverted arch supporting intensity of strengthening subsequent, specifically, the inverted arch anchor pole that performs includes: to construct along the circulation The longitudinal of section marks multiple inverted arch construction lines and on each inverted arch construction line according to given according to given longitudinal pitch Lateral loops spacing determines multiple construction coordinate points;The bolthole of given depth is drilled out on each construction coordinate point;To every Long anchor pole is placed in one bolthole, and by each long anchor pole slip casting into bolthole, until reaching predetermined note Slurry amount stops slip casting.
Specifically, the longitudinal pitch and the lateral loops spacing are between 1.0m-1.3m.
In one embodiment, bolthole is drilled out using TY400 hidden hole drilling, in inverted arch portion boring apertureDrilling Length 12m, longitudinal pitch are set as 1.2m, and lateral loops spacing is set as 1.2m, and long anchor pole is placed into each bolthole, is passed through The long anchor pole injects cement list slurries into country rock, and after grouting amount reaches predetermined grouting amount, slip casting stops, and performs long anchor pole, By long bolt grouting to consolidate country rock around inverted arch portion.
The present invention provide a kind of tunnel deformation segment again supporting when heavy type inverted arch steelframe construction method, which exists It is executed after the completion of arch wall supporting, the inverted arch portion of tunnel deformation segment is divided into multiple circulation construction sections using when the construction method, It constructs in each circulation construction section, in order to ensure the supporting intensity of each circulation construction section, is applied in each circulation one by one The quantity of the quantity of the heavy inverted arch steelframe performed in workshop section arch wall heavy type steelframe corresponding with the circulation construction section is identical, is pacifying When filling heavy inverted arch steelframe, first go out inverted arch installation site in a circulation construction section internal labeling, then the heavy type that assembly is completed is faced upward Arch steelframe is hoisted to specified inverted arch installed position, is hoisted to inverted arch installation site using by assembled heavy inverted arch steelframe Method, when saving transport required when handling one by one forms inverted arch steelframe section in heavy inverted arch steelframe to inverted arch installation site Between, improve the construction efficiency of heavy inverted arch steelframe, will be hoisted to later the heavy inverted arch steelframe of inverted arch installed position with it is right The arch wall heavy type steelframe connection closing cyclization answered, connection heavy inverted arch steelframe per adjacent two reinforce the integer support in tunnel Intensity.
Tunnel deformation segment provided by the invention again supporting when heavy type inverted arch steelframe construction method, by assembly complete weight Type inverted arch steelframe is hoisted to the installation of inverted arch installed position, saves the inverted arch steelframe section that transport one by one forms heavy inverted arch steelframe Shipping time, improve the construction efficiency of heavy inverted arch steelframe.
Other features and advantages of the present invention will the following detailed description will be given in the detailed implementation section.
It is described the prefered embodiments of the present invention in detail above in conjunction with attached drawing, still, the present invention is not limited to above-mentioned realities The detail in mode is applied, within the scope of the technical concept of the present invention, a variety of letters can be carried out to technical solution of the present invention Monotropic type, these simple variants all belong to the scope of protection of the present invention.
It is further to note that specific technical features described in the above specific embodiments, in not lance In the case where shield, can be combined in any appropriate way, in order to avoid unnecessary repetition, the present invention to it is various can No further explanation will be given for the combination of energy.
In addition, various embodiments of the present invention can be combined randomly, as long as it is without prejudice to originally The thought of invention, it should also be regarded as the disclosure of the present invention.

Claims (6)

1. a kind of tunnel deformation segment again supporting when heavy type inverted arch steelframe construction method, the construction method is in tunnel deformation segment Execute after the completion of the arch wall supporting of supporting section, agree with the arch wall during the arch wall supporting and arch wall heavy-duty steel be installed Frame, which is characterized in that the construction method the following steps are included:
S0) in the concrete of the first given thickness of spray at the beginning of the inverted arch portion of tunnel deformation segment;
S1 the inverted arch portion of tunnel deformation segment) is divided into multiple circulation construction sections, and in each circulation construction section internal labeling Multiple inverted arch installation sites out are set wherein each inverted arch installation site is corresponding with the position for being equipped with the arch wall heavy type steelframe It sets;
S2) assembled heavy inverted arch steelframe, and the heavy inverted arch steelframe after assembly is hoisted in specified inverted arch installation site, make The heavy inverted arch steelframe that must be mounted in the inverted arch installation site closes cyclization with corresponding arch wall heavy type steelframe;
S3 multiple inverted arch connectors) are performed between the heavy inverted arch steelframe after two adjacent assembly, it is described adjacent to connect Two assembly after heavy inverted arch steelframe.
2. construction method according to claim 1, which is characterized in that step S1) in each circulation construction section internal standard Remember multiple inverted arch installation sites out, is set wherein each inverted arch installation site is corresponding with the position for being equipped with the arch wall heavy type steelframe It sets, comprising:
It is corresponding with the circulation construction section in the inverted arch portion label of the circulation construction section along the longitudinal to supporting section of tunnel deformation segment The identical multiple inverted arch camber lines of arch wall heavy type steelframe quantity so that each inverted arch camber line and the arch wall of label are heavy The position of steelframe is correspondingly arranged;
The multiple inverted arch installation site is determined based on multiple inverted arch camber lines.
3. construction method according to claim 1, which is characterized in that the construction method further include: after step S2) And before step S3), be laid with steel mesh in the inverted arch portion of the circulation construction section, and by the heavy inverted arch steelframe near The steel mesh of the nearly heavy type inverted arch steelframe is fixed.
4. construction method according to claim 1, which is characterized in that the construction method further include: step S3) it Afterwards, it sprays the concrete of the second given thickness again to the circulation construction section in inverted arch portion, and reaches given in the concrete of multiple spray Inverted arch anchor pole is performed in the circulation construction section after set strength.
5. construction method according to claim 4, which is characterized in that the inverted arch anchor pole that performs includes:
Along the longitudinal according to the multiple inverted arch construction lines of given longitudinal pitch label and in each inverted arch of the circulation construction section Multiple construction coordinate points are determined according to given lateral loops spacing on construction line;
The bolthole of given depth is drilled out on each construction coordinate point;
Long anchor pole is placed into bolthole described in each, and passes through each long anchor pole slip casting into bolthole, Zhi Daoda To predetermined grouting amount, stop slip casting.
6. construction method according to claim 5, which is characterized in that the longitudinal pitch and the lateral loops spacing are situated between In 1.0m-1.3m.
CN201910719995.XA 2019-08-06 2019-08-06 Tunnel deformation segment again supporting when heavy type inverted arch steelframe construction method Pending CN110410101A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910719995.XA CN110410101A (en) 2019-08-06 2019-08-06 Tunnel deformation segment again supporting when heavy type inverted arch steelframe construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910719995.XA CN110410101A (en) 2019-08-06 2019-08-06 Tunnel deformation segment again supporting when heavy type inverted arch steelframe construction method

Publications (1)

Publication Number Publication Date
CN110410101A true CN110410101A (en) 2019-11-05

Family

ID=68366007

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910719995.XA Pending CN110410101A (en) 2019-08-06 2019-08-06 Tunnel deformation segment again supporting when heavy type inverted arch steelframe construction method

Country Status (1)

Country Link
CN (1) CN110410101A (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002097898A (en) * 2000-09-26 2002-04-05 Ishikawajima Constr Materials Co Ltd Arch tunnel, and construction method and bottom slab block for the same
CN107387117A (en) * 2017-07-07 2017-11-24 中国铁道科学研究院铁道建筑研究所 A kind of prefabricated assembled tunnel structure in tunnel bottom and its construction method
CN107387119A (en) * 2017-07-07 2017-11-24 中国铁道科学研究院铁道建筑研究所 Prefabricated assembled tunnel inverted arch, tunnel structure and its construction method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002097898A (en) * 2000-09-26 2002-04-05 Ishikawajima Constr Materials Co Ltd Arch tunnel, and construction method and bottom slab block for the same
CN107387117A (en) * 2017-07-07 2017-11-24 中国铁道科学研究院铁道建筑研究所 A kind of prefabricated assembled tunnel structure in tunnel bottom and its construction method
CN107387119A (en) * 2017-07-07 2017-11-24 中国铁道科学研究院铁道建筑研究所 Prefabricated assembled tunnel inverted arch, tunnel structure and its construction method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
罗雨: "隧道全断面支护拆换设备配置方案讨论", 《建材与装饰》 *

Similar Documents

Publication Publication Date Title
CN104612698B (en) A kind of shallow-depth-excavation tunnel top bar interval wall construction method
CN101614125B (en) Construction method of V-level surrounding rock tunnel
CN101864963B (en) Large-section loess tunnel construction method
CN106194196B (en) A kind of large-scale karst cave treatment crossing tunnel trunk and excavation method
CN106761769A (en) A kind of construction technology of big cross section large-deformation tunnel in soft rock
CN110017144B (en) Loess tunnel three-step construction method considering substrate reinforcement treatment
CN105696602A (en) Composite pile-anchor supporting method and structure for deepening excavation
CN103615273A (en) Square steel confined concrete arch center wall back filling bolting-grouting support system and construction method
CN104405399A (en) Construction method for excavating support body in tunnel by crossing quicksand stratum
CN102587922A (en) Oblique-crossing inclined shaft upper arc guide top brushing construction method for soft crushed rock layer
CN205712137U (en) Foundation pit supporting construction
CN108103939A (en) Oblique section steel trestle construction composite reinforcement mode and construction technology
CN106246192A (en) Large-scale karst cave treatment under a kind of tunnel basis and base plate and tunnel excavation method
CN106245931A (en) The underpinning device of load bearing wall and construction method in brick mix structure
CN109403985A (en) The gate-type of pole weak broken wall rock layer is caunched engineering method
CN104294769B (en) A kind of piling and the construction method increasing the built bridge abutment structure of platform cap composite reinforcement
CN110242305A (en) A kind of inclined shaft applies the construction technique in main hole into single side heading method
CN109113757A (en) Tunnel cross mouth rapid constructing method
CN208267862U (en) A kind of bracing means at tunnel road surface crack
CN109898521A (en) A kind of anchored pile supporting and construction method for foundation pit external corner
CN110486034A (en) Subway station and construction method based on pile foundation in four pilot tunnel of single layer and middle drift
CN206408630U (en) Anchor head is placed in the Pile-Anchor Supporting for Deep Excavation system of pile body
CN111140248A (en) Bias tunnel structure applying prestress to pilot tunnel and construction method thereof
CN108397202B (en) Freeze the leading excavation method of base tunnel in multi-step under advance support
CN204097889U (en) A kind of piling and the built bridge abutment structure of increase platform cap composite reinforcement

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20191105

RJ01 Rejection of invention patent application after publication