CN110390467B - 一种基于关键场景辨别的虚拟电厂随机自适应鲁棒优化调度方法 - Google Patents

一种基于关键场景辨别的虚拟电厂随机自适应鲁棒优化调度方法 Download PDF

Info

Publication number
CN110390467B
CN110390467B CN201910552920.7A CN201910552920A CN110390467B CN 110390467 B CN110390467 B CN 110390467B CN 201910552920 A CN201910552920 A CN 201910552920A CN 110390467 B CN110390467 B CN 110390467B
Authority
CN
China
Prior art keywords
model
vpp
scene
gas turbine
adaptive robust
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201910552920.7A
Other languages
English (en)
Other versions
CN110390467A (zh
Inventor
孙国强
钱苇航
卫志农
臧海祥
陈�胜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hohai University HHU
Original Assignee
Hohai University HHU
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hohai University HHU filed Critical Hohai University HHU
Priority to CN201910552920.7A priority Critical patent/CN110390467B/zh
Publication of CN110390467A publication Critical patent/CN110390467A/zh
Application granted granted Critical
Publication of CN110390467B publication Critical patent/CN110390467B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/20Design optimisation, verification or simulation
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06312Adjustment or analysis of established resource schedule, e.g. resource or task levelling, or dynamic rescheduling
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06315Needs-based resource requirements planning or analysis
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F2111/00Details relating to CAD techniques
    • G06F2111/04Constraint-based CAD
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Human Resources & Organizations (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Theoretical Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • General Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Tourism & Hospitality (AREA)
  • Marketing (AREA)
  • Game Theory and Decision Science (AREA)
  • Quality & Reliability (AREA)
  • Development Economics (AREA)
  • Health & Medical Sciences (AREA)
  • Educational Administration (AREA)
  • Operations Research (AREA)
  • Evolutionary Computation (AREA)
  • Geometry (AREA)
  • Computer Hardware Design (AREA)
  • General Engineering & Computer Science (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Supply And Distribution Of Alternating Current (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

本发明公开一种基于关键场景辨别的虚拟电厂随机自适应鲁棒优化调度方法,步骤是:根据原始数据构造以虚拟电厂利润最大为优化目标的虚拟电厂确定性模型,构建模型约束条件;采用随机规划法处理市场电价不确定性,采用自适应鲁棒方法处理光伏出力不确定性,建立虚拟电厂随机自适应鲁棒模型;采用关键场景辨别算法求解虚拟电厂随机自适应鲁棒模型;与标准场景算法相比本发明方法极大地削减了场景数量,减少了计算时间,并且能够适应大规模场景下的自适应鲁棒模型求解。

Description

一种基于关键场景辨别的虚拟电厂随机自适应鲁棒优化调度 方法
技术领域
本发明属于电力***电源调度领域,特别涉及一种基于关键场景辨别的虚拟电厂随机自适应鲁棒优化调度方法。
背景技术
我国能源结构正向清洁、低碳方向转变,而可再生能源具有地理位置分散、随机性强、波动性大、可控性较弱等特点,随着接入电网的总规模不断扩大,对电网的安全、可靠、经济运行提出了新挑战。虚拟电厂(virtual power plant,VPP)通过先进的通信、计量和控制技术聚合可再生能源、储能、需求响应(demand response,DR)等多种分布式能源,作为一个整体参与电网运行,能够减小分布式能源单独并网对公网造成的冲击,并提高其市场竞争力。
VPP在优化调度过程中会受到可再生能源出力以及市场电价等不确定性因素的影响。目前,自适应鲁棒方法已被应用于处理不确定性因素,其中机组启停决策为第一阶段,经济调度决策为第二阶段。求解算法有标准场景算法、Benders算法以及列约束生成算法(column and comstraint generaion,CCG)。Benders和CCG算法均不可避免地引入了非线性项,都需要采用Big-M法对非线性项进行线性化处理,因此增加了边界参数和二进制变量,导致在问题规模较大时模型求解复杂。标准场景算法通过列举不确定集的顶点将自适应鲁棒模型由三层优化模型转化为单层模型,但是计算效率较低,在求解大规模问题时甚至可能出现模型不可解的情况。
发明内容
发明目的:针对以上问题,本发明提出一种基于关键场景辨别的虚拟电厂随机自适应鲁棒优化调度方法,极大地削减了求解所需的场景数量,从而提高了算法的求解效率。
技术方案:为实现本发明的目的,本发明所采用的技术方案是:一种基于关键场景辨别的虚拟电厂随机自适应鲁棒优化调度方法,包括如下步骤:
步骤1,根据原始数据构建以虚拟电厂(virtual power plant,VPP)利润最大化为目标的VPP确定性模型;构建模型约束条件;所述原始数据包括:日前能量市场(day-aheadenergy market,DAM)、实时能量市场(real-time energy market,RTM)数据以及VPP各聚合单元的参数;所述约束条件包括:燃气轮机约束、ESS约束、可中断负荷约束、DAM/RTM交易量约束、功率平衡约束;
步骤2,由于市场电价和光伏出力的不确定性以及不平衡惩罚的存在,VPP目标利润与实际利润之间存在偏差,为了提高整体收益,降低不平衡惩罚,VPP的优化调度需要考虑不确定性的影响;因此,在VPP确定性模型的基础上,采用随机规划法处理市场电价的不确定性,采用自适应鲁棒方法处理光伏出力的不确定性,从而建立VPP随机自适应鲁棒模型;
步骤3,为提高计算效率,采用关键场景辨别算法求解虚拟电厂(VPP)随机自适应鲁棒模型,输出最优调度结果。
采用软件GAMS24.4以及Matlab对基于关键场景辨别算法的VPP随机自适应鲁棒模型进行联合编程求解,结果表明:关键场景辨别算法极大地削减了场景数量,减少了计算时间,并且随着场景集规模的增加,计算时间增长缓慢,能够适应大规模场景下的自适应鲁棒模型求解。
进一步,所述步骤1建立了VPP确定性模型,包括以下步骤:
步骤1.1:VPP所有者的优化目标是最大化累计盈利,包括参与DAM和RTM所获得的收入、燃气轮机的运行成本、中断负荷成本,其目标函数表示为:
Figure BDA0002106035650000021
其中,T为一天的总时段数,取值为24;λt DA、λt RT分别为DAM和RTM电价;Pt DA
Figure BDA0002106035650000022
为VPP在DAM的购售电量;Pt RT
Figure BDA00021060356500000213
为VPP在RTM的购售电量;kp为购电系数,表示购电价格与售电价格之比;
Figure BDA0002106035650000023
为燃气轮机的运行成本;
Figure BDA0002106035650000024
为中断负荷成本;
采用分段线性函数描述燃气轮机的运行成本:
Figure BDA0002106035650000025
Figure BDA0002106035650000026
其中,a为燃气轮机的固定成本;布尔变量
Figure BDA00021060356500000212
表示燃气轮机是否工作;Kl为燃气轮机第l段发电成本斜率;gl,t为燃气轮机第l段出力;Nl为燃气轮机成本曲线的线性分段数;λsu、λsd分别为燃气轮机启停成本;布尔变量
Figure BDA0002106035650000027
分别表示燃气轮机是否启动、停止;
Figure BDA0002106035650000028
为燃气轮机总出力;
可中断负荷成本为VPP向用户支付的中断负荷补偿费用,由于不同中断程度对用户的影响程度不同,因此根据中断负荷的等级对用户进行补偿,中断负荷成本表示为:
Figure BDA0002106035650000029
其中,nm为中断等级数;
Figure BDA00021060356500000210
为第m级中断负荷的补偿价格;
Figure BDA00021060356500000211
为t时段第m级负荷中断量;
步骤1.2:构建VPP确定性模型的约束条件,所述约束条件包括:
(1)燃气轮机约束条件:
Figure BDA0002106035650000031
Figure BDA0002106035650000032
Figure BDA0002106035650000033
Figure BDA0002106035650000034
Figure BDA0002106035650000035
Figure BDA0002106035650000036
Figure BDA0002106035650000037
Figure BDA0002106035650000038
Figure BDA0002106035650000039
其中,gGT,max、gGT,min分别为燃气轮机的最大、最小输出功率;rU、rD为燃气轮机的向上、向下爬坡率;
Figure BDA00021060356500000310
为燃气轮机第l段出力上限;tsu、tsd分别为燃气轮机的最小开关机时间;tsu,0、tsd,0分别为燃气轮机的初始开关机时间;
Figure BDA00021060356500000311
分别为t时段和t-1时段燃气轮机的总出力;布尔变量
Figure BDA00021060356500000312
表示燃气轮机在t时段和t-1时段是否工作;
(2)电储能***(ESS)约束条件:
Figure BDA00021060356500000313
Figure BDA00021060356500000314
Figure BDA00021060356500000315
Figure BDA00021060356500000316
其中,
Figure BDA00021060356500000317
分别为电储能***(electric energy storage system,ESS)t时段和t-1时段的蓄电量;ηc、ηd分别为ESS的充放电效率;
Figure BDA00021060356500000318
分别为ESS的充放电量;Ses ,max、Ses,min分别为ESS蓄电量的上下限;gesc,max、gesd,max分别为ESS的最大充放电功率;
(3)可中断负荷约束条件:
Figure BDA0002106035650000041
Figure BDA0002106035650000042
Figure BDA0002106035650000043
其中,
Figure BDA0002106035650000044
为第m级负荷中断系数;
Figure BDA0002106035650000045
为t时段第m级负荷中断量;
Figure BDA0002106035650000046
为t时段电负荷;
Figure BDA0002106035650000047
分别为t时段和t-1时段的负荷中断量;Lcurt,max为连续时间内的最大负荷中断量,避免了连续时间内负荷中断量过大导致的用户满意度下降问题;
(4)DAM/RTM交易量约束条件:
Figure BDA0002106035650000048
Figure BDA0002106035650000049
Figure BDA00021060356500000410
0≤Pt RT≤PRT,max (24)
其中,Pt DA
Figure BDA00021060356500000411
分别为t时段VPP在DAM的购售电量;Pt RT
Figure BDA00021060356500000412
分别为t时段VPP在RTM的购售电量;PDA,max、SDA,max为VPP在DAM的最大购售电量;PRT,max、SRT,max为VPP在RTM的最大购售电量;
(5)功率平衡约束条件:
Figure BDA00021060356500000413
其中,Pt RES为光伏电站出力。
进一步,所述步骤2采用随机规划法处理市场电价不确定性,采用自适应鲁棒方法处理光伏出力不确定性,建立虚拟电厂随机自适应鲁棒模型,包括以下步骤:
步骤2.1:考虑VPP同时参与DAM和RTM的情况。在DAM阶段,VPP在光伏不确定参数实现之前进行决策;在RTM阶段,VPP在光伏不确定参数和日前市场决策实现后进行决策。因此,虚拟电厂随机自适应鲁棒模型可以采用三层结构max-min-max形式,由两阶段组成,其目标函数表示为:
Figure BDA00021060356500000414
其中,np为电价场景数;π(p)为电价场景概率;下标p、s分别表示第p组电价场景和第s组光伏出力场景;Ω为原始光伏场景集;
步骤2.2:与确定性模型相比,随机自适应鲁棒模型在DAM阶段考虑了电价场景,日前决策变量特征为均含有下标p、t,下标p表示第p组电价场景,下标t表示t时段;在RTM阶段考虑了电价场景和光伏场景,实时决策变量特征为均含有下标p、t、s,下标s表示第s组光伏出力场景;所述随机自适应鲁棒模型的约束条件为:
(1)日前运行约束条件:
Figure BDA0002106035650000051
Figure BDA0002106035650000052
Figure BDA0002106035650000053
Figure BDA0002106035650000054
Figure BDA0002106035650000055
Figure BDA0002106035650000056
Figure BDA0002106035650000057
Figure BDA0002106035650000058
(2)实时运行约束条件:
Figure BDA0002106035650000059
Figure BDA00021060356500000510
Figure BDA00021060356500000511
Figure BDA00021060356500000512
Figure BDA00021060356500000513
Figure BDA00021060356500000514
Figure BDA00021060356500000515
Figure BDA0002106035650000061
Figure BDA0002106035650000062
Figure BDA0002106035650000063
Figure BDA0002106035650000064
Figure BDA0002106035650000065
Figure BDA0002106035650000066
Figure BDA0002106035650000067
Figure BDA0002106035650000068
Figure BDA0002106035650000069
进一步,所述步骤3为提高计算效率,采用关键场景辨别算法求解虚拟电厂随机自适应鲁棒模型,该算法将原虚拟电厂随机自适应鲁棒模型分解为主模型和子模型进行迭代求解,主模型为关键场景集下的VPP单层优化模型,子模型则用来辨别关键场景集,包括以下步骤:
步骤3.1:引入辅助变量τMP代替随机自适应鲁棒模型第二阶段的min-max问题,表示VPP在RTM所获得的最低利润,从而将原三层优化模型转化为单层优化模型,即模型目标函数由式(26)转化为式(51),所述单层优化模型即为分解后的主模型,具体模型如下:
(1)所述主模型的目标函数为:
Figure BDA00021060356500000610
Figure BDA00021060356500000611
其中,ΩMP为关键场景集;
(2)日前运行约束条件:式(27)~(34);
(3)实时运行约束条件:式(35)~(50);
步骤3.2:引入辅助变量
Figure BDA00021060356500000612
表示光伏场景集Ω\ΩMP下VPP在RTM所获得的利润,Ω\ΩMP表示剔除关键场景集的原始光伏场景集,τSP表示最恶劣情况下的
Figure BDA00021060356500000613
所述最恶劣情况指的是虚拟电厂利润最低的情况,对应的场景即为关键场景,从而将三层优化模型即式(26)中第二阶段的min-max问题转化为单层优化模型即式(53),所述单层优化模型即为分解后的子模型,具体模型如下:
(1)所述子模型的目标函数为:
Figure BDA0002106035650000071
Figure BDA0002106035650000072
(2)实时运行约束条件:式(35)~(50);
步骤3.3:主模型用来求解关键场景集ΩMP下的VPP最大利润,子模型用来辨别关键场景ssp并将其添加到关键场景集ΩMP中,根据分解后的主模型和子模型进行迭代求解,方法如下:
(1)定义初始关键场景集ΩMP={s0},其中s0为初始光伏场景;
(2)求解关键场景集ΩMP下的主模型,将主模型求得的第一阶段决策变量
Figure BDA0002106035650000073
Figure BDA0002106035650000074
表示为zMP
(3)将zMP代入子模型求解,计算出光伏场景集Ω\ΩMP下的
Figure BDA0002106035650000075
根据式(54)辨别出τSP对应的关键场景ssp,即选出使虚拟电厂利润最小的场景;
(4)比较主模型中τMP与子模型中τSP的大小,若τMP≤τSP,则说明关键场景集中的关键场景已经包含所有场景的不确定性信息,转至步骤(5);否则将关键场景ssp添加到关键场景集ΩMP中,即ΩMP={ΩMP、sSP},同时,式(35)~(50)中各变量的下标光伏出力场景s也增加1,下标s每加1,即在主模型中增加一组实时运行约束条件,转至步骤(2),继续迭代;
(5)输出步骤(2)中求解主模型所得的最优调度结果,即决策变量
Figure BDA0002106035650000076
Figure BDA0002106035650000077
有益效果:与现有技术相比,本发明的技术方案具有以下有益的技术效果:本发明基于关键场景辨别的虚拟电厂随机自适应鲁棒优化调度方法,极大地削减了求解模型所需的场景数量,从而提高了算法的求解效率。
附图说明
图1是VPP一天内的负荷需求量图;
图2是光伏机组出力数据图;
图3是DAM电价和RTM电价场景图;
图4是VPP利润以及辅助变量τMP、τSP的历次迭代结果图;
图5是算例Case 3、Case 8-12的优化结果比较图;
图6是基于关键场景辨别的自适应鲁棒算法流程图;
图7是本发明的流程图。
具体实施方式
下面结合附图和实施例对本发明的技术方案作进一步的说明。
本发明所述的一种基于关键场景辨别的虚拟电厂随机自适应鲁棒优化调度方法,如图7所示,包括以下步骤:
步骤1,根据原始数据构建以虚拟电厂(virtual power plant,VPP)利润最大化为目标的VPP确定性模型;构建模型约束条件;所述原始数据包括:日前能量市场(day-aheadenergy market,DAM)、实时能量市场(real-time energy market,RTM)数据以及VPP各聚合单元的参数;所述约束条件包括:燃气轮机约束、ESS约束、可中断负荷约束、DAM/RTM交易量约束、功率平衡约束;
步骤2,由于市场电价和光伏出力的不确定性以及不平衡惩罚的存在,VPP目标利润与实际利润之间存在偏差,为了提高整体收益,降低不平衡惩罚,VPP的优化调度需要考虑不确定性的影响;因此,在VPP确定性模型的基础上,采用随机规划法处理市场电价的不确定性,采用自适应鲁棒方法处理光伏出力的不确定性,从而建立VPP随机自适应鲁棒模型;
步骤3,为提高计算效率,采用关键场景辨别算法求解虚拟电厂(VPP)随机自适应鲁棒模型,输出最优调度结果。
采用软件GAMS24.4以及Matlab对基于关键场景辨别算法的VPP随机自适应鲁棒模型进行联合编程求解,结果表明:关键场景辨别算法极大地削减了场景数量,减少了计算时间,并且随着场景集规模的增加,计算时间增长缓慢,能够适应大规模场景下的自适应鲁棒模型求解。
所述步骤1建立了VPP确定性模型,包括以下步骤:
步骤1.1:VPP所有者的优化目标是最大化累计盈利,包括参与DAM和RTM所获得的收入、燃气轮机的运行成本、中断负荷成本,其目标函数表示为:
Figure BDA0002106035650000081
其中,T为一天的总时段数,取值为24;
Figure BDA0002106035650000082
分别为DAM和RTM电价;Pt DA
Figure BDA0002106035650000083
为VPP在DAM的购售电量;Pt RT
Figure BDA0002106035650000084
为VPP在RTM的购售电量;kp为购电系数,表示购电价格与售电价格之比;
Figure BDA0002106035650000085
为燃气轮机的运行成本;
Figure BDA0002106035650000086
为中断负荷成本;
采用分段线性函数描述燃气轮机的运行成本:
Figure BDA0002106035650000087
Figure BDA0002106035650000091
其中,a为燃气轮机的固定成本;布尔变量
Figure BDA0002106035650000092
表示燃气轮机是否工作;Kl为燃气轮机第l段发电成本斜率;gl,t为燃气轮机第l段出力;Nl为燃气轮机成本曲线的线性分段数;λsu、λsd分别为燃气轮机启停成本;布尔变量
Figure BDA0002106035650000093
分别表示燃气轮机是否启动、停止;
Figure BDA0002106035650000094
为燃气轮机总出力;
可中断负荷成本为VPP向用户支付的中断负荷补偿费用,由于不同中断程度对用户的影响程度不同,因此根据中断负荷的等级对用户进行补偿,中断负荷成本表示为:
Figure BDA0002106035650000095
其中,nm为中断等级数;
Figure BDA0002106035650000096
为第m级中断负荷的补偿价格;
Figure BDA0002106035650000097
为t时段第m级负荷中断量;
步骤1.2:构建VPP确定性模型的约束条件,所述约束条件包括:
(1)燃气轮机约束条件:
Figure BDA0002106035650000098
Figure BDA0002106035650000099
Figure BDA00021060356500000910
Figure BDA00021060356500000911
Figure BDA00021060356500000912
Figure BDA00021060356500000913
Figure BDA00021060356500000914
Figure BDA00021060356500000915
Figure BDA00021060356500000916
其中,gGT,max、gGT,min分别为燃气轮机的最大、最小输出功率;rU、rD为燃气轮机的向上、向下爬坡率;
Figure BDA00021060356500000917
为燃气轮机第l段出力上限;tsu、tsd分别为燃气轮机的最小开关机时间;tsu,0、tsd,0分别为燃气轮机的初始开关机时间;
Figure BDA0002106035650000101
分别为t时段和t-1时段燃气轮机的总出力;布尔变量
Figure BDA0002106035650000102
表示燃气轮机在t时段和t-1时段是否工作;
(2)电储能***(ESS)约束条件:
Figure BDA0002106035650000103
Figure BDA0002106035650000104
Figure BDA0002106035650000105
Figure BDA0002106035650000106
其中,
Figure BDA0002106035650000107
分别为电储能***(electric energy storage system,ESS)t时段和t-1时段的蓄电量;ηc、ηd分别为ESS的充放电效率;
Figure BDA0002106035650000108
分别为ESS的充放电量;Ses ,max、Ses,min分别为ESS蓄电量的上下限;gesc,max、gesd,max分别为ESS的最大充放电功率;
(3)可中断负荷约束条件:
Figure BDA0002106035650000109
Figure BDA00021060356500001010
Figure BDA00021060356500001011
其中,
Figure BDA00021060356500001012
为第m级负荷中断系数;
Figure BDA00021060356500001013
为t时段第m级负荷中断量;
Figure BDA00021060356500001014
为t时段电负荷;
Figure BDA00021060356500001015
分别为t时段和t-1时段的负荷中断量;Lcurt,max为连续时间内的最大负荷中断量,避免了连续时间内负荷中断量过大导致的用户满意度下降问题;
(4)DAM/RTM交易量约束条件:
Figure BDA00021060356500001016
0≤Pt DA≤PDA,max (22)
Figure BDA00021060356500001017
0≤Pt RT≤PRT,max (24)
其中,Pt DA
Figure BDA00021060356500001018
分别为t时段VPP在DAM的购售电量;Pt RT
Figure BDA00021060356500001020
分别为t时段VPP在RTM的购售电量;PDA,max、SDA,max为VPP在DAM的最大购售电量;PRT,max、SRT,max为VPP在RTM的最大购售电量;
(5)功率平衡约束条件:
Figure BDA00021060356500001019
其中,Pt RES为光伏电站出力。
所述步骤2采用随机规划法处理市场电价不确定性,采用自适应鲁棒方法处理光伏出力不确定性,建立虚拟电厂随机自适应鲁棒模型,包括以下步骤:
步骤2.1:考虑VPP同时参与DAM和RTM的情况。在DAM阶段,VPP在光伏不确定参数实现之前进行决策;在RTM阶段,VPP在光伏不确定参数和日前市场决策实现后进行决策。因此,虚拟电厂随机自适应鲁棒模型可以采用三层结构max-min-max形式,由两阶段组成,其目标函数表示为:
Figure BDA0002106035650000111
其中,np为电价场景数;π(p)为电价场景概率;下标p、s分别表示第p组电价场景和第s组光伏出力场景;Ω为原始光伏场景集;
步骤2.2:与确定性模型相比,随机自适应鲁棒模型在DAM阶段考虑了电价场景,日前决策变量特征为均含有下标p、t,下标p表示第p组电价场景,下标t表示t时段;在RTM阶段考虑了电价场景和光伏场景,实时决策变量特征为均含有下标p、t、s,下标s表示第s组光伏出力场景;所述随机自适应鲁棒模型的约束条件为:
(1)日前运行约束条件:
Figure BDA0002106035650000112
Figure BDA0002106035650000113
Figure BDA0002106035650000114
Figure BDA0002106035650000115
Figure BDA0002106035650000116
Figure BDA0002106035650000117
Figure BDA0002106035650000118
Figure BDA0002106035650000119
(2)实时运行约束条件:
Figure BDA0002106035650000121
Figure BDA0002106035650000122
Figure BDA0002106035650000123
Figure BDA0002106035650000124
Figure BDA0002106035650000125
Figure BDA0002106035650000126
Figure BDA0002106035650000127
Figure BDA0002106035650000128
Figure BDA0002106035650000129
Figure BDA00021060356500001210
Figure BDA00021060356500001211
Figure BDA00021060356500001212
Figure BDA00021060356500001213
Figure BDA00021060356500001214
Figure BDA00021060356500001215
Figure BDA00021060356500001216
所述步骤3为提高计算效率,采用关键场景辨别算法求解虚拟电厂随机自适应鲁棒模型,该算法将原虚拟电厂随机自适应鲁棒模型分解为主模型和子模型进行迭代求解,主模型为关键场景集下的VPP单层优化模型,子模型则用来辨别关键场景集,包括以下步骤:
步骤3.1:引入辅助变量τMP代替随机自适应鲁棒模型第二阶段的min-max问题,表示VPP在RTM所获得的最低利润,从而将原三层优化模型转化为单层优化模型,即模型目标函数由式(26)转化为式(51),所述单层优化模型即为分解后的主模型,具体模型如下:
(1)所述主模型的目标函数为:
Figure BDA0002106035650000131
Figure BDA0002106035650000132
其中,ΩMP为关键场景集;
(2)日前运行约束条件:式(27)~(34);
(3)实时运行约束条件:式(35)~(50);
步骤3.2:引入辅助变量
Figure BDA0002106035650000133
表示光伏场景集Ω\ΩMP下VPP在RTM所获得的利润,Ω\ΩMP表示剔除关键场景集的原始光伏场景集,τSP表示最恶劣情况下的
Figure BDA0002106035650000134
所述最恶劣情况指的是虚拟电厂利润最低的情况,对应的场景即为关键场景,从而将三层优化模型即式(26)中第二阶段的min-max问题转化为单层优化模型即式(53),所述单层优化模型即为分解后的子模型,具体模型如下:
(1)所述子模型的目标函数为:
Figure BDA0002106035650000135
Figure BDA0002106035650000136
(2)实时运行约束条件:式(35)~(50);
步骤3.3:主模型用来求解关键场景集ΩMP下的VPP最大利润,子模型用来辨别关键场景ssp并将其添加到关键场景集ΩMP中,根据分解后的主模型和子模型进行迭代求解,方法如下:
(1)定义初始关键场景集ΩMP={s0},其中s0为初始光伏场景;
(2)求解关键场景集ΩMP下的主模型,将主模型求得的第一阶段决策变量
Figure BDA0002106035650000137
Figure BDA0002106035650000138
表示为zMP
(3)将zMP代入子模型求解,计算出光伏场景集Ω\ΩMP下的
Figure BDA0002106035650000139
根据式(54)辨别出τSP对应的关键场景ssp,即选出使虚拟电厂利润最小的场景;
(4)比较主模型中τMP与子模型中τSP的大小,若τMP≤τSP,则说明关键场景集中的关键场景已经包含所有场景的不确定性信息,转至步骤(5);否则将关键场景ssp添加到关键场景集ΩMP中,即ΩMP={ΩMP、sSP},同时,式(35)~(50)中各变量的下标光伏出力场景s也增加1,下标s每加1,即在主模型中增加一组实时运行约束条件,转至步骤(2),继续迭代;
(5)输出步骤(2)中求解主模型所得的最优调度结果,即决策变量
Figure BDA0002106035650000141
Figure BDA0002106035650000142
本实施例以燃气轮机机组、光伏机组、ESS、以及可中断负荷构成VPP。考虑VPP参与DAM、RTM的情况,调度周期设置为1天,分为24个时段。
燃气轮机采用TAU5670型号,具体参数见表1,电储能***的具体参数见表2,VPP一天内的负荷需求见图1,可中断负荷分为3级,均设为总负荷的10%,每级补偿价格分别为40€/MWh、45€/MWh、50€/MWh。光伏机组出力历史数据见图2,采用蒙特卡罗法随机生成50组光伏场景;DAM电价和RTM电价见图3。
表1 TAU5670燃气轮机参数
Figure BDA0002106035650000143
表2电储能***参数
Figure BDA0002106035650000144
图4给出了采用关键场景辨别算法求解虚拟电厂随机自适应鲁棒模型时,VPP利润以及辅助变量τMP、τSP的历次迭代结果。
由图4可知,基于关键场景辨别的自适应鲁棒求解算法需要经过4次迭代得到最优调度结果。在迭代过程中,主模型的目标函数即VPP的利润随着迭代次数的增加不断减小,这是由于每经过一次迭代,子模型从光伏场景集中辨别出一个关键场景,并将其添加到关键场景集中。相应地,主模型中需要增加一组实时约束条件及其变量,从而使得主模型受到的约束不断增强。
经过子模型的关键场景辨别后,光伏场景数量由初始的50组削减到4组,其中关键场景集ΩMP=[s1,s23,s49,s6]。但是需证明剩余的46组场景为非关键场景,即对优化结果无影响,接下来引入3个不同场景数量的算例进行分析。
Case1:考虑子问题辨别出的4组关键场景+剩余的46组非关键场景。
Case2:考虑子问题辨别出的4组关键场景+任意21组非关键场景。
Case3:仅考虑子问题辨别出的4组关键场景。
表2给出了采用标准场景算法对Case1-3进行求解时,优化结果和运行时间。
表2不同场景集下的优化结果比较
Figure BDA0002106035650000145
Figure BDA0002106035650000151
由表2可知,Case1-3的优化结果完全相同,这表明非关键场景对优化结果没有影响。比较结果显示了仅考虑关键场景集的Case3不仅能够准确的替代考虑50个初始光伏场景的Case1,并且由于削减了大量的非关键场景,Case3与Case2、Case1相比节省了大量计算时间,当场景集规模增大时尤为明显。
为了验证关键场景辨别算法在计算效率上的优越性,引入算例Case4-7,随机生成光伏场景,场景数量依次增加。
表3分别给出了采用关键场景辨别算法和标准场景算法求解VPP随机自适应鲁棒模型的比较结果。
表3两种算法的运行效率比较
Figure BDA0002106035650000152
由表3可知,两种求解算法下的VPP利润均一致。经过3~4次迭代,关键场景辨别算法即可找到所有的关键场景。随着场景集规模的增加,标准场景算法的计算时间急剧增加,当采用大规模场景集时,自适应鲁棒模型甚至将不可解。而关键场景辨别算法极大地削减了场景数量,减少了计算时间,并且随着场景集规模的增加,计算时间增长缓慢,能够适应大规模场景下的自适应鲁棒模型求解,提高了计算效率。
此外,关键场景辨别算法也可以作为一种场景削减手段。采用基于概率距离的快速前代削减方法对初始的50组光伏场景进行场景削减,所得算例Case 8-12如表4所示。
表4 case8-12的场景数
Figure BDA0002106035650000153
Figure BDA0002106035650000161
图5对算例Case 3、Case 8-12的优化结果进行了比较。
由图5可知,从Case 8-12,VPP的利润不断降低,这是由于Case 8-12削减后的场景数量逐渐增加,包含的不确定信息逐渐完善,从而模型所受到的约束不断增强。而Case 3虽然只包含关键场景辨别得到的4组场景,但是VPP的利润却低于Case 8-12,并且与考虑所有场景情况的Case 1一致,不确定性信息保留完整。传统的场景削减方法为了提高计算效率牺牲了准确性,而关键场景辨别算法能够在减少场景数量的同时完整地保留不确定性信息,从而保证了计算结果的准确性。
以上仿真结果验证了本发明的有效性和实用性。该发明能极大地削减了场景数量,减少了计算时间,并且随着场景集规模的增加,计算时间增长缓慢,能够适应大规模场景下的VPP随机自适应鲁棒模型求解。
以上实施例仅为说明本发明的技术思想,不能以此限定本发明的保护范围,凡是按照本发明提出的技术思想,在技术方案基础上所做的任何改动,均落入本发明保护范围之内。

Claims (1)

1.一种基于关键场景辨别的虚拟电厂随机自适应鲁棒优化调度方法,其特征在于:该方法包括以下步骤:
步骤1,根据原始数据构建以虚拟电厂(virtual power plant,VPP)利润最大化为目标的VPP确定性模型;构建模型约束条件;所述原始数据包括:日前能量市场(day-aheadenergy market,DAM)、实时能量市场(real-time energy market,RTM)数据以及VPP各聚合单元的参数;所述约束条件包括:燃气轮机约束、ESS约束、可中断负荷约束、DAM/RTM交易量约束、功率平衡约束;
步骤2,VPP的优化调度需要考虑不确定性的影响;在VPP确定性模型的基础上,采用随机规划法处理市场电价的不确定性,采用自适应鲁棒方法处理光伏出力的不确定性,从而建立VPP随机自适应鲁棒模型;
步骤3,采用关键场景辨别算法求解虚拟电厂(VPP)随机自适应鲁棒模型,输出最优调度结果;
所述步骤1建立了VPP确定性模型,包括以下步骤:
步骤1.1:VPP所有者的优化目标是最大化累计盈利,包括参与DAM和RTM所获得的收入、燃气轮机的运行成本、中断负荷成本,其目标函数表示为:
Figure FDA0003718502650000011
其中,T为一天的总时段数;λt DA、λt RT分别为DAM和RTM电价;Pt DA、St DA为VPP在DAM的购售电量;Pt RT
Figure FDA0003718502650000012
为VPP在RTM的购售电量;kp为购电系数,表示购电价格与售电价格之比;
Figure FDA0003718502650000013
为燃气轮机的运行成本;
Figure FDA0003718502650000014
为中断负荷成本;
采用分段线性函数描述燃气轮机的运行成本:
Figure FDA0003718502650000015
Figure FDA0003718502650000016
其中,a为燃气轮机的固定成本;布尔变量
Figure FDA0003718502650000017
表示燃气轮机是否工作;Kl为燃气轮机第l段发电成本斜率;gl,t为燃气轮机第l段出力;Nl为燃气轮机成本曲线的线性分段数;λsu、λsd分别为燃气轮机启停成本;布尔变量
Figure FDA0003718502650000018
分别表示燃气轮机是否启动、停止;
Figure FDA0003718502650000019
为燃气轮机总出力;
可中断负荷成本为VPP向用户支付的中断负荷补偿费用,根据中断负荷的等级对用户进行补偿,中断负荷成本表示为:
Figure FDA0003718502650000021
其中,nm为中断等级数;
Figure FDA0003718502650000022
为第m级中断负荷的补偿价格;
Figure FDA0003718502650000023
为t时段第m级负荷中断量;
步骤1.2:构建VPP确定性模型的约束条件,所述约束条件包括:
(1)燃气轮机约束条件:
Figure FDA0003718502650000024
Figure FDA0003718502650000025
Figure FDA0003718502650000026
Figure FDA0003718502650000027
Figure FDA0003718502650000028
Figure FDA0003718502650000029
Figure FDA00037185026500000210
Figure FDA00037185026500000211
Figure FDA00037185026500000212
其中,gGT,max、gGT,min分别为燃气轮机的最大、最小输出功率;rU、rD为燃气轮机的向上、向下爬坡率;
Figure FDA00037185026500000213
为燃气轮机第l段出力上限;tsu、tsd分别为燃气轮机的最小开关机时间;tsu ,0、tsd,0分别为燃气轮机的初始开关机时间;
Figure FDA00037185026500000214
分别为t时段和t-1时段燃气轮机的总出力;布尔变量
Figure FDA00037185026500000215
表示燃气轮机在t时段和t-1时段是否工作;
(2)电储能***(ESS)约束条件:
Figure FDA00037185026500000216
Figure FDA00037185026500000217
Figure FDA00037185026500000218
Figure FDA00037185026500000219
其中,
Figure FDA0003718502650000031
分别为电储能***(electric energy storage system,ESS)t时段和t-1时段的蓄电量;ηc、ηd分别为ESS的充放电效率;
Figure FDA0003718502650000032
分别为ESS的充放电量;Ses,max、Ses ,min分别为ESS蓄电量的上下限;gesc,max、gesd,max分别为ESS的最大充放电功率;
(3)可中断负荷约束条件:
Figure FDA0003718502650000033
Figure FDA0003718502650000034
Figure FDA0003718502650000035
其中,
Figure FDA0003718502650000036
为第m级负荷中断系数;
Figure FDA0003718502650000037
为t时段电负荷;
Figure FDA0003718502650000038
分别为t时段和t-1时段的负荷中断量;Lcurt,max为连续时间内的最大负荷中断量;
(4)DAM/RTM交易量约束条件:
Figure FDA0003718502650000039
0≤Pt DA≤PDA,max (22)
Figure FDA00037185026500000310
0≤Pt RT≤PRT,max (24)
其中,Pt DA
Figure FDA00037185026500000311
分别为t时段VPP在DAM的购售电量;Pt RT
Figure FDA00037185026500000312
分别为t时段VPP在RTM的购售电量;PDA,max、SDA,max为VPP在DAM的最大购售电量;PRT,max、SRT,max为VPP在RTM的最大购售电量;
(5)功率平衡约束条件:
Figure FDA00037185026500000313
其中,Pt RES为光伏电站出力;
所述步骤2采用随机规划法处理市场电价不确定性,采用自适应鲁棒方法处理光伏出力不确定性,建立虚拟电厂随机自适应鲁棒模型,包括以下步骤:
步骤2.1:考虑VPP同时参与DAM和RTM的情况;在DAM阶段,VPP在光伏不确定参数实现之前进行决策;在RTM阶段,VPP在光伏不确定参数和日前市场决策实现后进行决策;虚拟电厂随机自适应鲁棒模型的目标函数表示为:
Figure FDA00037185026500000314
其中,np为电价场景数;π(p)为电价场景概率;下标p、s分别表示第p组电价场景和第s组光伏出力场景;Ω为原始光伏场景集;
步骤2.2:随机自适应鲁棒模型在DAM阶段考虑了电价场景,日前决策变量特征为均含有下标p、t,下标p表示第p组电价场景,下标t表示t时段;在RTM阶段考虑了电价场景和光伏场景,实时决策变量特征为均含有下标p、t、s,下标s表示第s组光伏出力场景;所述随机自适应鲁棒模型的约束条件为:
(1)日前运行约束条件:
Figure FDA0003718502650000041
Figure FDA0003718502650000042
Figure FDA0003718502650000043
Figure FDA0003718502650000044
Figure FDA0003718502650000045
Figure FDA0003718502650000046
Figure FDA0003718502650000047
Figure FDA0003718502650000048
(2)实时运行约束条件:
Figure FDA0003718502650000049
Figure FDA00037185026500000410
Figure FDA00037185026500000411
Figure FDA00037185026500000412
Figure FDA00037185026500000413
Figure FDA00037185026500000414
Figure FDA0003718502650000051
Figure FDA0003718502650000052
Figure FDA0003718502650000053
Figure FDA0003718502650000054
Figure FDA0003718502650000055
Figure FDA0003718502650000056
Figure FDA0003718502650000057
Figure FDA0003718502650000058
Figure FDA0003718502650000059
Figure FDA00037185026500000510
所述步骤3采用关键场景辨别算法求解虚拟电厂随机自适应鲁棒模型;该算法将原虚拟电厂随机自适应鲁棒模型分解为主模型和子模型进行迭代求解,主模型为关键场景集下的VPP单层优化模型,子模型则用来辨别关键场景集;包括以下步骤:
步骤3.1:引入辅助变量τMP代替随机自适应鲁棒模型第二阶段的min-max问题,表示VPP在RTM所获得的最低利润,将原三层优化模型转化为单层优化模型,即模型目标函数由式(26)转化为式(51),所述单层优化模型即为分解后的主模型,具体模型如下:
(1)所述主模型的目标函数为:
Figure FDA00037185026500000511
Figure FDA00037185026500000512
其中,ΩMP为关键场景集;
(2)日前运行约束条件:式(27)~(34);
(3)实时运行约束条件:式(35)~(50);
步骤3.2:引入辅助变量
Figure FDA00037185026500000513
表示光伏场景集Ω\ΩMP下VPP在RTM所获得的利润,Ω\ΩMP表示剔除关键场景集的原始光伏场景集,τSP表示最恶劣情况下的
Figure FDA00037185026500000514
所述最恶劣情况指的是虚拟电厂利润最低的情况,对应的场景即为关键场景,从而将原三层优化模型即式(26)中第二阶段的min-max问题转化为单层优化模型,所述单层优化模型即为分解后的子模型,具体模型如下:
(1)所述子模型的目标函数为:
Figure FDA0003718502650000061
Figure FDA0003718502650000062
(2)实时运行约束条件:式(35)~(50);
步骤3.3:主模型用来求解关键场景集ΩMP下的VPP最大利润,子模型用来辨别关键场景ssp并将其添加到关键场景集ΩMP中,根据分解后的主模型和子模型进行迭代求解,输出所得最优调度结果;
根据分解后的主模型和子模型进行迭代求解,方法如下:
(1)定义初始关键场景集ΩMP={s0},其中s0为初始光伏场景;
(2)求解关键场景集ΩMP下的主模型,将主模型求得的第一阶段决策变量
Figure FDA0003718502650000063
Figure FDA0003718502650000064
表示为zMP
(3)将zMP代入子模型求解,计算出光伏场景集Ω\ΩMP下的
Figure FDA0003718502650000065
根据式(54)辨别出τSP对应的关键场景ssp,即选出使虚拟电厂利润最小的场景;
(4)比较主模型中τMP与子模型中τSP的大小,若τMP≤τSP,则说明关键场景集中的关键场景已经包含所有场景的不确定性信息,转至步骤(5);否则将关键场景ssp添加到关键场景集ΩMP中,即ΩMP={ΩMP、sSP},同时,式(35)~(50)中各变量的下标光伏出力场景s也增加1,下标s每加1,即在主模型中增加一组实时运行约束条件,转至步骤(2),继续迭代;
(5)输出步骤(2)中求解主模型所得的最优调度结果,即决策变量
Figure FDA0003718502650000066
Figure FDA0003718502650000067
CN201910552920.7A 2019-06-25 2019-06-25 一种基于关键场景辨别的虚拟电厂随机自适应鲁棒优化调度方法 Active CN110390467B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910552920.7A CN110390467B (zh) 2019-06-25 2019-06-25 一种基于关键场景辨别的虚拟电厂随机自适应鲁棒优化调度方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910552920.7A CN110390467B (zh) 2019-06-25 2019-06-25 一种基于关键场景辨别的虚拟电厂随机自适应鲁棒优化调度方法

Publications (2)

Publication Number Publication Date
CN110390467A CN110390467A (zh) 2019-10-29
CN110390467B true CN110390467B (zh) 2022-08-19

Family

ID=68285752

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910552920.7A Active CN110390467B (zh) 2019-06-25 2019-06-25 一种基于关键场景辨别的虚拟电厂随机自适应鲁棒优化调度方法

Country Status (1)

Country Link
CN (1) CN110390467B (zh)

Families Citing this family (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111342450B (zh) * 2020-03-07 2022-08-23 西南交通大学 考虑不确定光伏与负荷的牵引供电***鲁棒能量管理方法
CN111931331B (zh) * 2020-06-23 2021-06-22 河海大学 一种适用于配电网机组组合的分布鲁棒优化方法
CN111682536B (zh) * 2020-06-24 2023-08-18 上海电力大学 虚拟电厂参与日前双重市场的随机-鲁棒优化运行方法
CN112215641B (zh) * 2020-10-10 2024-06-07 国网上海市电力公司 智能楼宇型虚拟电厂参与能量调频的控制方法及***
CN112465320A (zh) * 2020-11-18 2021-03-09 国网江苏省电力有限公司盐城供电分公司 一种基于区块链技术的虚拟电厂交易管理方法
CN112465208B (zh) * 2020-11-20 2022-09-30 国网江苏省电力有限公司盐城供电分公司 计及区块链技术的虚拟电厂随机自适应鲁棒优化调度方法
CN113270895B (zh) * 2021-07-20 2021-10-15 中国电力科学研究院有限公司 一种电能与辅助服务市场的日前鲁棒联合优化方法及***
CN114444851A (zh) * 2021-12-16 2022-05-06 国网江苏省电力有限公司经济技术研究院 一种计及旋转备用服务的虚拟电厂优化调度方法及***
CN116415740B (zh) * 2023-06-06 2023-09-12 国网浙江省电力有限公司金华供电公司 一种基于鞍论不确定性的虚拟电厂两阶段鲁棒优化方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103824134A (zh) * 2014-03-06 2014-05-28 河海大学 一种用于虚拟电厂的两阶段优化调度方法
CN106127389A (zh) * 2016-06-24 2016-11-16 河海大学 一种虚拟电厂热电联合调度鲁棒优化模型
CN106447216A (zh) * 2016-10-12 2017-02-22 国网宁夏电力公司 一种计及不确定性的虚拟电厂竞标的优化方法
CN108388973A (zh) * 2018-01-11 2018-08-10 河海大学 一种虚拟电厂自适应鲁棒调度优化方法
CN108960510A (zh) * 2018-07-04 2018-12-07 四川大学 一种基于两阶段随机规划的虚拟电厂优化交易策略模型

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103824134A (zh) * 2014-03-06 2014-05-28 河海大学 一种用于虚拟电厂的两阶段优化调度方法
CN106127389A (zh) * 2016-06-24 2016-11-16 河海大学 一种虚拟电厂热电联合调度鲁棒优化模型
CN106447216A (zh) * 2016-10-12 2017-02-22 国网宁夏电力公司 一种计及不确定性的虚拟电厂竞标的优化方法
CN108388973A (zh) * 2018-01-11 2018-08-10 河海大学 一种虚拟电厂自适应鲁棒调度优化方法
CN108960510A (zh) * 2018-07-04 2018-12-07 四川大学 一种基于两阶段随机规划的虚拟电厂优化交易策略模型

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
含电动汽车的虚拟电厂鲁棒随机优化调度;孙国强等;《电力***自动化》;20170325(第06期);全文 *
基于技术型虚拟电厂的配电网阻塞管理;周宇等;《全球能源互联网》;20190523(第03期);全文 *

Also Published As

Publication number Publication date
CN110390467A (zh) 2019-10-29

Similar Documents

Publication Publication Date Title
CN110390467B (zh) 一种基于关键场景辨别的虚拟电厂随机自适应鲁棒优化调度方法
CN112465208B (zh) 计及区块链技术的虚拟电厂随机自适应鲁棒优化调度方法
Moradi-Sepahvand et al. Integrated expansion planning of electric energy generation, transmission, and storage for handling high shares of wind and solar power generation
CN109787261B (zh) 电网侧及用户侧储能***容量优化配置方法
Zhou et al. Boosting hydropower output of mega cascade reservoirs using an evolutionary algorithm with successive approximation
CN109146320B (zh) 一种考虑配电网安全性的虚拟电厂优化调度方法
Cheng et al. Stochastic short-term scheduling of a wind-solar-hydro complementary system considering both the day-ahead market bidding and bilateral contracts decomposition
CN112952807B (zh) 考虑风电不确定性与需求响应的多目标优化调度方法
CN112529249B (zh) 一种计及绿证交易的虚拟电厂优化调度及交易管理方法
CN105356465B (zh) 一种经济性与安全性协调的输电网规划平台及应用
CN114897346A (zh) 计及不确定性和需求响应的虚拟电厂鲁棒优化调度方法
CN110165698B (zh) 一种实现前瞻性误差资产转换的风电场平滑并网方法
CN114256882B (zh) 一种基于风险控制的风储联合***调度方法及***
CN113592133A (zh) 一种能量枢纽优化配置方法及***
CN115375344A (zh) 计及阶梯碳交易机制的微电网两阶段鲁棒优化低碳经济调度方法
CN114792201B (zh) 电力***低碳经济调度方法及装置
CN111654045A (zh) 一种电力现货市场下储能***充放电优化方法
CN111047093A (zh) 一种电动汽车典型快充站优化运行配置方法
CN117559563B (zh) 一种风光储充一体化微网运行方案的优化方法及***
Zeng et al. Day-ahead interval scheduling strategy of power systems based on improved adaptive diffusion kernel density estimation
CN113723823A (zh) 电网运营的模拟装置及方法
CN114358378A (zh) 一种用于考虑需量管理的用户侧储能优化配置***及方法
CN112670982B (zh) 一种基于奖励机制的微电网有功调度控制方法及***
CN112510690B (zh) 考虑风火储联合和需求响应奖惩的优化调度方法及***
CN104009464B (zh) 一种计及电阻的内嵌网损双层经济优化调度方法

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant