CN110388221A - The installation method of the especially big elevator chamber large-tonnage bridge crane of interior shaft - Google Patents

The installation method of the especially big elevator chamber large-tonnage bridge crane of interior shaft Download PDF

Info

Publication number
CN110388221A
CN110388221A CN201910589383.3A CN201910589383A CN110388221A CN 110388221 A CN110388221 A CN 110388221A CN 201910589383 A CN201910589383 A CN 201910589383A CN 110388221 A CN110388221 A CN 110388221A
Authority
CN
China
Prior art keywords
chamber
elevator chamber
elevator
steel
lifting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910589383.3A
Other languages
Chinese (zh)
Other versions
CN110388221B (en
Inventor
李文光
李宇凯
李阳
刘璐
施升涛
张立辉
董泸锴
钱源
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Gold Mining (laizhou) Co Ltd Sanshandao Gold Mine
Original Assignee
Shandong Gold Mining (laizhou) Co Ltd Sanshandao Gold Mine
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Gold Mining (laizhou) Co Ltd Sanshandao Gold Mine filed Critical Shandong Gold Mining (laizhou) Co Ltd Sanshandao Gold Mine
Priority to CN201910589383.3A priority Critical patent/CN110388221B/en
Publication of CN110388221A publication Critical patent/CN110388221A/en
Application granted granted Critical
Publication of CN110388221B publication Critical patent/CN110388221B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C17/00Overhead travelling cranes comprising one or more substantially horizontal girders the ends of which are directly supported by wheels or rollers running on tracks carried by spaced supports
    • B66C17/06Overhead travelling cranes comprising one or more substantially horizontal girders the ends of which are directly supported by wheels or rollers running on tracks carried by spaced supports specially adapted for particular purposes, e.g. in foundries, forges; combined with auxiliary apparatus serving particular purposes
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D13/00Large underground chambers; Methods or apparatus for making them

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Mechanical Engineering (AREA)
  • Lift-Guide Devices, And Elevator Ropes And Cables (AREA)
  • Types And Forms Of Lifts (AREA)

Abstract

The present invention relates to a kind of installation methods of the especially big elevator chamber large-tonnage bridge crane of interior shaft, change before previous earth's surface building binds, using the mounting means of mechanical hoisting large-tonnage bridge crane, utilize elevator chamber, by in stress load center construction drill, be mounted with Lock with double safety guard rope device in drilling chamber, and transfer one steel wire loop to elevator chamber, by main electric chain hoist above mention to top plate abutment location.Large-tonnage bridge crane is lifted to predetermined position in three times using this Lift-on/Lift-off System, is reliable, convenient and fast on theoretical and promotion safety requirements.

Description

The installation method of the especially big elevator chamber large-tonnage bridge crane of interior shaft
Technical field
The present invention relates to the method for lifting underground large-tonnage bridge crane, specifically a kind of especially big elevator caves of interior shaft The installation method of room large-tonnage bridge crane.
Background technique
It is long for the coal mine hoist chamber compared with big cross section, such as San-Shan-Dao Gold Mine mine down-hole elevator chamber 18.7m, width 14.1m, high 15.65m, large-tonnage bridge crane installation difficulty are very big.Driving installation is wanted in elevator chamber It is carried out simultaneously with shaft equipment installation, stable vehicles and sinking headframe cannot all be removed, therefore install operating space and be restricted.Separately On the one hand, chamber top walking dolly and top plate spacing are smaller, such as the San-Shan-Dao Gold Mine mine down-hole elevator chamber, Chamber top walking dolly and top plate spacing only have 2 meters, further limit working space.And the electronic bridge of large-tonnage 60t/10t Formula crane, be self-possessed 38.976t, and tonnage is big;Underground digs chamber and has poured completion, can not implement well using large-tonnage truck crane Lower lifting.
Having a kind of design in the prior art is to realize large-tonnage bridge by alternately lifting in elevator cave indoor construction grillage Formula crane is in the especially big indoor lifting of elevator cave.Although this design can be completed big using elevator chamber inner space Tonnage bridge crane is deposited in the especially big indoor lifting of elevator cave, but due to needing repeated disassembled and assembled grillage and hydraulic jack In the defect that equipment consumption is big and great in constructing amount, construction is cumbersome.
Summary of the invention
The technical problem to be solved by the invention is to provide a kind of especially big elevator chamber large-tonnage overhead traveling cranes of interior shaft The installation method of machine realizes large-tonnage bridge crane in especially big elevator chamber by installing main electric chain hoist upper end Convenient lifting.
Technical scheme is as follows:
A kind of installation method of the especially big elevator chamber large-tonnage bridge crane of interior shaft, it is characterised in that including following step It is rapid:
Step 1: drilling construction, closing well head:
1), in the surface construction drill chamber of elevator chamber;
2), in the top plate of elevator chamber to the stress load center construction drill between drilling machine chamber;It is required that elevator chamber Top plate to drilling machine chamber bottom surface spacing be not less than 12m;
3), pit shaft is closed in the junction position of elevator chamber and guide wheel chamber;
Bis- Walk: construction drill chamber locks rope device:
1), in drilling machine chamber wall side, several anchor poles of constructing, by anchor pole outer end and drilling manganese steel plate welding, as lifting The lock rope card of wirerope the top;
2) lock rope beam, is set up in the surface of the drilling, the fixed guide wheel carrier on lock rope beam is installed in guiding wheel carrier upper end Directive wheel, and wirerope board is installed on lock rope beam;
3) elevator chamber, is set to through drilling decentralization steel cable and connects main electric chain hoist, it will be on main electric chain hoist It mentions to chain sling upper hook and elevator chamber top plate and being adjacent to, wirerope is then fixed on lock rope beam by the wirerope board On, wirerope is located at the part above the board and is fixed on the lock rope card around upper end after directive wheel;
Step 3: lifting operation:
1) it, is arrived first by the assembled driving steel beam lifting to crownblock beam in an elevator drum side with the drawing of secondary electric chain hoist Roller side;
2) it, is drawn on another assembled driving steel beam lifting to crownblock beam again with secondary electric chain hoist to elevator motor side;
3) walking dolly, is finally lifted by crane, stopping when plane has certain interval on walking dolly distance from bottom driving beam orbit is hung to The crane beam of two sides is drawn to walking dolly lower part with secondary electric chain hoist, transfers walking dolly after connecting by lifting.
Preferably, confining bed construction method described in the step 3) of the first step: will be as the I-steel of girder and as pair The channel steel of beam is welded into mutually roof beam structure, and checkered steel plate is welded on roof beam structure as bottom plate, is then laid with sand as buffering, fire prevention Layer.
Preferably, the method for lock rope beam is set up in the step 2 of bis- Walk: pouring pre-buried raw muscle hook in drilling machine chamber bottom surface Two I-steel intervals are welded on raw muscle hook plate by steel plate.
The present invention is constructed in especially big elevator chamber using drilling machine chamber, guide hole, installation lock rope device, by main electric chain hoist It is mounted on the top at elevator chamber stress load center.On the one hand lifting space has effectively been expanded, on the other hand The stress of main electric chain hoist is decomposed into drilling machine machine cave, is more advantageous to protection elevator chamber.Major technique advantage is: with Metallic mineral resources are continually developed, and earth superficial resource gradually decreases, and tends to be depleted, therefore metal mine exploitation is just Constantly develop to deep mining, and scale continues to increase.At present China's metal mine mining depth be more than km more than only There is a few, and it is smaller to exploit scale.In this context, the present invention provides a kind of especially big chamber crane installations in underground New technology solves underground large-scale hoister chamber vault lifting insufficient space, and according to traditional grillage, alternately lifting installation consumes When, effort, consumptive material the drawbacks of.
The present invention is mounted with Lock with double safety guard rope device in drilling chamber, further improves overall security and reliable Property.
Specific embodiment
Method of the invention is further illustrated combined with specific embodiments below.
The blind combined shaft mineshaft diameter 5.5m in San-Shan-Dao Gold Mine mine, the elevation of well -600m, shaft bottom absolute altitude -1240m.Most It is low to serve the middle section -1240m.Combined shaft hole top signal chamber is set in -600m.Elevator chamber is located at -537.3m absolute altitude, chamber Long 18.7m, wide 14.1m, high 15.65m are connected to by big part connecting taxiway with existing ramp.60t/10t electricity is set in winding houses Dynamic bridge crane is installed and is overhauled for equipment and uses.
According to Design of Construction Organization, -537 blind combined shaft winding houses driving installations to be installed with shaft equipment simultaneously into Row, stable vehicles and sinking headframe in winding houses cannot all be removed, and narrow space is caused, according to site operation situation use with Lower mounting means:
1, in a upper segmentation for elevator chamber, using -510m Abandoned Tunnel construction drill chamber, using anti-well drilling machine - Stress load center construction diameter between the top plate (- 521m) of 537m elevator chamber to -510m drilling machine chamber is 108mm's Drilling.
2, in the junction position of elevator chamber and guide wheel chamber, to ensure the operation of shaft equipment personnel safety, closing- 546 pit shafts: be girder 16# channel steel with 32# I-steel being auxiliary girder, and 6mm checkered steel plate is bottom, be then laid with 500mm sand be buffering, Fireprotection layer;The closing of -537 foundation pit mouths is used as operating platform: be girder 16# channel steel with 32# I-steel being auxiliary girder, 6mm checkered steel plate The bottom of for.
3, after the completion of -510m drilling construction, in drilling machine chamber wall side, using inverted cone shape, 5 anchor poles of constructing, Anchor pole outer end is integrally welded, after the manganese steel plate drilling of thickness 40mm, is welded to anchor pole outer end, as lock rope card;- The top of 510m drilling machine chamber bottom plate drilling sets up two, 32 I-steel as lock rope beam, two 32 I-steel spacing 10cm, In Below 32 I-steel, the pre-buried raw muscle hook plate of bottom slab concreting, raw muscle hook plate is welded as a whole with 32 I-steel.On lock rope beam The guiding wheel carrier being longitudinally oriented is welded, directive wheel is installed in guiding wheel carrier upper mounting plate card, and in guiding wheel carrier upper end.
4, from -510 decentralization a piece diameters 40 steel wire loop to -537 elevator chambers, will be mentioned on 20t electric chain hoist to Chain sling upper hook and top plate are adjacent to (driving walking dolly and top plate minimum spacing only have 2 meters), then pass through wirerope described Board is fixed on lock rope beam, is fixed on the lock rope card around upper end after directive wheel.
5, it is 13t that this, which lifts maximum piece weight, and hoisting wirerope uses the wirerope of 4 diameter 28mm.It lifts suitable Sequence: 20t electric chain hoist (as main electric chain hoist) is used in three times: first by the assembled driving girder steel in an elevator drum side On lifting to crownblock beam, 2 3t chain slings (as secondary electric chain hoist) is used to draw to roller side, apart from 10 meters of lifting point (horizontal direction) Position;2 3t chain slings (as secondary electric chain hoist) drawing on another assembled driving steel beam lifting to crownblock beam, will be used to arrive again Elevator motor side, apart from 3 meters of lifting point (horizontal direction) position;It finally lifts by crane walking dolly: being hung to trolley distance from bottom row Stop lifting when plane has the gap 200mm on bicycle beam track, uses 2 3t chain slings (as secondary electric chain hoist) by the crane beam of two sides Forget about it walking dolly lower part, transfers walking dolly after connecting.Complete the installation of above three components.
6, remainder widget erection sequence: lifting electric control part, speed reducer refuels and main power source connects test run.
7, it is installed, removes lifting facility.
The crownblock beam is fixedly connected in the opposite side walls of elevator chamber by fixed forms such as anchor poles.Institute The secondary electric chain hoist stated is located above crownblock beam and to be fixedly connected on elevator chamber by fixed forms such as anchor poles opposite In side walls.Driving girder steel and walking dolly are closed in lifting anteposition in the junction position of elevator chamber and guide wheel chamber On layer.Lifting motor and roller also are located on the junction position confining bed of elevator chamber and guide wheel chamber.Lifting is used Guide wheel is located in the guide wheel chamber below the confining bed.

Claims (3)

1. a kind of installation method of the especially big elevator chamber large-tonnage bridge crane of interior shaft, it is characterised in that including following step It is rapid:
Step 1: drilling construction, closing well head:
1), in the surface construction drill chamber of elevator chamber;
2), in the top plate of elevator chamber to the stress load center construction drill between drilling machine chamber;It is required that elevator chamber Top plate to drilling machine chamber bottom surface spacing be not less than 12m;
3), pit shaft is closed in the junction position of elevator chamber and guide wheel chamber;
Bis- Walk: construction drill chamber locks rope device:
1), in drilling machine chamber wall side, several anchor poles of constructing, by anchor pole outer end and drilling manganese steel plate welding, as lifting The lock rope card of wirerope the top;
2) lock rope beam, is set up in the surface of the drilling, the fixed guide wheel carrier on lock rope beam is installed in guiding wheel carrier upper end Directive wheel, and wirerope board is installed on lock rope beam;
3) elevator chamber, is set to through drilling decentralization steel cable and connects main electric chain hoist, it will be on main electric chain hoist It mentions to chain sling upper hook and elevator chamber top plate and being adjacent to, wirerope is then fixed on lock rope beam by the wirerope board On, wirerope is located at the part above the board and is fixed on the lock rope card around upper end after directive wheel;
Step 3: lifting operation:
1) it, is arrived first by the assembled driving steel beam lifting to crownblock beam in an elevator drum side with the drawing of secondary electric chain hoist Roller side;
2) it, is drawn on another assembled driving steel beam lifting to crownblock beam again with secondary electric chain hoist to elevator motor side;
3) walking dolly, is finally lifted by crane, stopping when plane has certain interval on walking dolly distance from bottom driving beam orbit is hung to The crane beam of two sides is drawn to walking dolly lower part with secondary electric chain hoist, transfers walking dolly after connecting by lifting.
2. the installation method of the especially big elevator chamber large-tonnage bridge crane of interior shaft as described in claim 1, feature It is confining bed construction method described in the step 3) of the first step: the I-steel as girder and the channel steel as auxiliary girder is mutual It is welded into roof beam structure, checkered steel plate is welded on roof beam structure as bottom plate, is then laid with sand as buffering, fireprotection layer.
3. the installation method of the especially big elevator chamber large-tonnage bridge crane of interior shaft as described in claim 1 goods 2, special Sign is the method that lock rope beam is set up in the step 2 of bis- Walk: pre-buried raw muscle hook plate is poured in drilling machine chamber bottom surface, by two Root I-steel interval is welded on raw muscle hook plate.
CN201910589383.3A 2019-07-02 2019-07-02 Mounting method of large-tonnage bridge crane in blind shaft super-large elevator chamber Active CN110388221B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910589383.3A CN110388221B (en) 2019-07-02 2019-07-02 Mounting method of large-tonnage bridge crane in blind shaft super-large elevator chamber

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910589383.3A CN110388221B (en) 2019-07-02 2019-07-02 Mounting method of large-tonnage bridge crane in blind shaft super-large elevator chamber

Publications (2)

Publication Number Publication Date
CN110388221A true CN110388221A (en) 2019-10-29
CN110388221B CN110388221B (en) 2020-10-02

Family

ID=68286026

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910589383.3A Active CN110388221B (en) 2019-07-02 2019-07-02 Mounting method of large-tonnage bridge crane in blind shaft super-large elevator chamber

Country Status (1)

Country Link
CN (1) CN110388221B (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4951924A (en) * 1988-02-01 1990-08-28 Mcdermott International, Inc. Deepwater subsea lowering/lifting system
JPH09328292A (en) * 1996-06-10 1997-12-22 Tokyo Gas Co Ltd Crane for truck
CN203441517U (en) * 2013-05-10 2014-02-19 玉溪大红山矿业有限公司 Ventilation device capable of effectively reducing poisonous air in mine transporting tunnel
CN103964285A (en) * 2014-05-07 2014-08-06 中钢集团马鞍山矿山研究院有限公司 Interior shaft hoisting system on-line improvement method for changing multi-rope floor type into tower type

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4951924A (en) * 1988-02-01 1990-08-28 Mcdermott International, Inc. Deepwater subsea lowering/lifting system
JPH09328292A (en) * 1996-06-10 1997-12-22 Tokyo Gas Co Ltd Crane for truck
CN203441517U (en) * 2013-05-10 2014-02-19 玉溪大红山矿业有限公司 Ventilation device capable of effectively reducing poisonous air in mine transporting tunnel
CN103964285A (en) * 2014-05-07 2014-08-06 中钢集团马鞍山矿山研究院有限公司 Interior shaft hoisting system on-line improvement method for changing multi-rope floor type into tower type

Also Published As

Publication number Publication date
CN110388221B (en) 2020-10-02

Similar Documents

Publication Publication Date Title
CN103266192B (en) Hoisting method for replacing cooling wall in overhauling of blast furnace
CN103696774B (en) Aboveground down-hole parallel construction staple shaft frame development method
CN109296374B (en) TBM hoisting and translation method for deep well enclosed space
CN202690063U (en) Derrick-free shaft-sinking construction device for mine shaft
CN210214612U (en) Radiant cable crane hoisting system in tunnel anchor
CN103964285B (en) A kind of many rope floor types change tower interior shaft elevator system non-stop production reformation method
CN202391104U (en) Portable rail slip form
CN103964284B (en) Frictional geared promotes interior shaft elevator system non-stop production reformation method
CN212503680U (en) Hoisting system for large-scale bridge crane heavy workpiece
CN106246187B (en) Multiple spot arranges a kind of self well digging construction method of interior shaft sinking shaft facility
CN208150862U (en) A kind of lifting platform for the construction of large-scale deep shaft
CN110388221A (en) The installation method of the especially big elevator chamber large-tonnage bridge crane of interior shaft
CN107288640A (en) A kind of steady rope self-supporting modularization vertical shaft driving and masonry construction device of nothing
CN105040592B (en) A kind of horizontal drawing cable bridge and its erection method
CN106050260A (en) Non-stop production reconstruction method for tower-type external shaft hoisting system
CN107720652B (en) A kind of construction method for hanging of frame structure large scale equipment
CN205591926U (en) Do not have self -supporting modularization shaft of surely restricting and dig step construction equipment
CN106012854B (en) The transporting equipment of prefabricated assembled overpass bridge plate
CN111284282B (en) Single rope lifting and counterweight method for middle and small mine inclined shaft automobile
CN201241729Y (en) Simple automatic slag-discharging apparatus of deep large drilled shaft
CN112125238B (en) Construction and installation method of steel beam in shaft
CN212837943U (en) Double-hole separately-repaired tunnel construction production vertical shaft bottom trackless transport vehicle yard structure
CN209337920U (en) It is a kind of for drop shaft, the interim lift headframe of ore storage bin
CN206384699U (en) A kind of tower bright shaft hoisting system of non-stop production reformation
CN206288833U (en) A kind of take electric block as the intelligent loading elevator for driving main frame

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant