CN110304588A - A kind of gate construction method for hanging under narrow working space - Google Patents

A kind of gate construction method for hanging under narrow working space Download PDF

Info

Publication number
CN110304588A
CN110304588A CN201910605597.5A CN201910605597A CN110304588A CN 110304588 A CN110304588 A CN 110304588A CN 201910605597 A CN201910605597 A CN 201910605597A CN 110304588 A CN110304588 A CN 110304588A
Authority
CN
China
Prior art keywords
segment
gate
suspension centre
section
upper cavity
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910605597.5A
Other languages
Chinese (zh)
Other versions
CN110304588B (en
Inventor
王桂玉
丁华丽
郝二峰
杨艳
吴金永
甘银钢
岳胜利
李艳
常莉
李辉
李国兴
侯郑郑
王磊
王鹏
王昶磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan Water Conservancy No2 Engineering Bureau
Original Assignee
Henan Water Conservancy No2 Engineering Bureau
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan Water Conservancy No2 Engineering Bureau filed Critical Henan Water Conservancy No2 Engineering Bureau
Priority to CN201910605597.5A priority Critical patent/CN110304588B/en
Publication of CN110304588A publication Critical patent/CN110304588A/en
Application granted granted Critical
Publication of CN110304588B publication Critical patent/CN110304588B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66FHOISTING, LIFTING, HAULING OR PUSHING, NOT OTHERWISE PROVIDED FOR, e.g. DEVICES WHICH APPLY A LIFTING OR PUSHING FORCE DIRECTLY TO THE SURFACE OF A LOAD
    • B66F11/00Lifting devices specially adapted for particular uses not otherwise provided for
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B7/00Barrages or weirs; Layout, construction, methods of, or devices for, making same
    • E02B7/20Movable barrages; Lock or dry-dock gates

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Barrages (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

For the gate installation under narrow working space, using gate upper cavity as the space of rotator construction, first lift gate first segment, second section, it is lifted using short side, at the upstream or downstream for placing it in gate slot after upper cavity swivel, the installation space of reserved gate slot, short side lifts third segment later, after being turned in upper cavity to third segment, it transfers to gate slot, second section is successively sling later, first segment, and it is placed sequentially in gate slot, realize the assembled forming of segment gate, the narrow space on gate slot top can be made full use of, improve operating efficiency.

Description

A kind of gate construction method for hanging under narrow working space
Technical field
The present invention relates to the gate construction method for hanging of hydraulic engineering, and in particular to a kind of under narrow working space Gate construction method for hanging.
Background technique
Gate is the main structural components that water blocking, water storage project are carried out in hydraulic engineering, and common gate form includes flat Plate gate, gates of segmental shape or flap gate etc., are typically mounted in gate slot, mostly use lifting method to hang in practice It is assembled after gate is hung in gate slot, after can choose section assembling or overall package according to lifting space or lifting force Lifting.Above-mentioned operation mode needs biggish working space, it is desirable that has corresponding lifting space above gate slot, and often needs Want fixed hoisting equipment.
In gate architecture construction, headstock gear, headstock gear bottom plate and gate slot have often been built in gate slot top Top constitutes gate upper cavity, and headstock gear often uses steel and concrete structure, considers construction period, if gates lifting is waited to complete Afterwards, building for headstock gear is just carried out, the duration can be wasted;If building headstock gear in advance, the space that will cause gate lifting is narrow Narrow, general lifting operation method can not achieve, how after the completion of headstock gear is built or gate top is provided with building When, the lifting operation of gate is carried out using the narrow upper section cavity of gate, is the Practical Project technical problem for needing to solve.
Summary of the invention
The present invention in view of the above technical problems, proposes a kind of gate lifting construction side under narrow working space Method can effectively solve gate top setting building, lifting problem when barrier.
The present invention provides a kind of gate construction method for hanging under narrow working space, which utilizes gate Upper cavity carries out gate lifting, narrow to adapt to for the narrow space construction after the completion of pouring at the top of gate upper cavity Working space, gate use segment lifting, and gate is lifted from gate slot, lifted by crane using short side, turned in gate upper cavity Body carries out the lifting construction of gate, specifically includes following construction procedure:
S1: processing gate segment, the gate includes the first segment being arranged from top to bottom, second section and third segment, institute It states and is provided with several suspension centres on first segment, second section and third segment;
S2: when binding at the top of gate upper cavity, main suspension centre is set on top plate, is respectively arranged with a left side in the main suspension centre two sides One auxiliary suspension centre, the second from left auxiliary suspension centre and the right side one assist suspension centre and the right side two to assist suspension centre;
S3: the second section is transported by flat car to gate slot, and flat car wheel hub uses steel wheel hub, wheel hub bottom peace Track is filled, flat car carries out tethered sliding using hoist engine;
S4: carrying out the lifting of second section using main suspension centre using gate slot, and lifting utilizes main suspension centre, cooperates steel using hoist engine Cord is lifted by crane, and second section is lifted into gate upper cavity;
S5: in the gate upper cavity, rotator construction is carried out to second section, wherein the first from left auxiliary suspension centre, the right side one assist Suspension centre connects the left suspension centre and right suspension centre of second section transverse direction by wirerope respectively, and the second from left assists suspension centre, the right side two to assist suspension centre Lower suspension centre and upper suspension centre on the right side of second section are connected by wirerope respectively, assist suspension centre, a right auxiliary hanging in described the first from left Point, the second from left auxiliary suspension centre, the right side two assist that hoist engine is arranged respectively at suspension centre, realize second section using hoist engine cooperation wirerope Rotator construction, the friendship of the side wall and gate grooved top plate in the upper cavity upstream or downstream is placed on after second section is turned At boundary;
S6: the hanging method in installation steps S3-S5 lifts first segment, and first segment is placed on the second section The temporary locking of first segment and second section is realized on top using junction steel plate pre-buried in upper cavity;
S7: according to the hanging method in step S3-S4, third segment is lifted into the upper cavity;
S8: realize that the rotator construction of third segment, the rotator construction specifically comprise the following steps: in upper cavity
S81: I-steel is laid in upper cavity bottom and then steel plate, erection construction platform drop down onto third segment on platform;
S82: main rope is set in main suspension centre, it is laterally intermediate that main rope suspension hook installation steel cable is fixed on third segment On main suspension centre, jack is installed again, it is firm that jack one end is connect with the vertical right side suspension centre in third segment on suspension hook;
S83: jack is installed using the second from left auxiliary suspension centre, it is firm that jack one end is connect with third segment left lower suspension centre, connection Third segment is sling using main suspension centre cooperation hoist engine after fixed;
S84: left hydraulic device and right hydraulic device is respectively set on the left side wall and right-side wall of the upper cavity;
S85: cooperating main suspension centre and the second from left to assist the hoist engine and wirerope of suspension centre using left hydraulic device, right hydraulic device, Realize the rotator construction of third segment;Cooperate after turning it with gate separation;
S9: the third segment in step S8 after swivel directly being lifted into gate slot, and is lifted downwards to design position, Temporary locking is carried out, third segment is fixed in gate slot;
S10: first segment is sling on upper cavity top using the first from left auxiliary suspension centre, is hung second section using main suspension centre It rises, second section is lifted to gate slot upper space and after being aligned, second section is lifted downwards to third segment, is used Second section and third segment are fixed temporary locking device;
S11: first segment is sling using main suspension centre to design position, first segment is lifted to gate by decentralization first segment Slot upper space and after being aligned, lifting downwards is in second section, using temporary locking device by first segment and second section It is fixed;
S12: it is assembled to welding is carried out between first segment, second section, third segment, hanging device is removed, construction is completed.
Preferably, the specific hanging method in step S4 are as follows: gate second section main rope suspension hook installs a steel Cord is fixed on gate transverse direction suspension centre, installs the jack of a 50t, jack one end and the vertical right side suspension centre of gate on suspension hook again It is firm to connect, and gate is made to be in equilibrium state.
Preferably, first segment is first lifted in step S3-S5, and it is rear in step S6 to lift second section, by second section As for the first segment top;The second section that top is directly sling in the step S10 is transferred after being turned to third Remaining first segment is directly sling in step S11 in segment top, after being turned in decentralization to second section.
The advantages and beneficial effects of the present invention are:
1) it makes full use of the narrow cavity on gate top to carry out lifting operation, gate upper cavity may be implemented and place obstacles object, Large-scale Hoisting equipment can not carry out the technical problem of operation;It is arranged on the top plate of gate upper cavity due to lifting point, utilizes The operations such as swivel, lifting, installation can be realized in hoist engine, compared to traditional large size lifting, engineering cost have been saved, relative to people Work less important work mode, improves operating efficiency;
2) the upstream and downstream space for utilizing gate slot, carries out the placement of gate segment, the comprehensive utilization of three-dimensional space may be implemented, make The first segment and second section first lifted by crane first are placed on the upstream or downstream of gate slot, do not influence hanging for subsequent third segment Dress, swivel and gate slot decentralization, improve operating efficiency;
3) traditional gate hoisting is overcome, can be the construction for carrying out headstock gear before gate installation, it can be simultaneously The synchronous construction for realizing gate concrete works and headstock gear concrete works can greatly improve construction efficiency and structure Globality recycles the hanging method to carry out the installation of gate, can shorten the construction period after the completion of headstock gear construction;
4) for the lifting problem of similar narrow working space, the thinking solved the problems, such as is provided, i.e., is matched using three-dimensional space It closes and segment lifting using small-sized hanging device can both realize the lifting of complex large-sized component, skill can be provided for similar engineering Art reference.
Detailed description of the invention:
Fig. 1 is gate first segment structural schematic diagram;
Fig. 2 is gate second section structural schematic diagram;
Fig. 3 is gate third bay structural schematic diagram;
Fig. 4 is gate second section transport diagram;
Fig. 5 is gate second section short side lifting schematic diagram;
Fig. 6 is gate second section rotator construction schematic diagram;
Fig. 7 is that gate second section places schematic diagram;
Fig. 8 is that gate first segment and second section place schematic diagram;
Fig. 9 is gate third segment lifting schematic diagram;
Figure 10 is that schematic diagram is transferred in gate third segment;
Figure 11 is that gate second section slings schematic diagram;
Figure 12 is that gate second section transfers schematic diagram;
Figure 13 is that gate first segment transfers schematic diagram;
Figure 14 is gate third segment rotator construction (one) schematic diagram;
Figure 15 is gate third segment rotator construction (two) schematic diagram;
Figure 16 is gate third segment rotator construction (three) schematic diagram;
Figure 17 is gate third segment rotator construction (four) schematic diagram;
Figure 18 is gate third segment rotator construction (five) schematic diagram.
Specific embodiment: the structure that the present invention limits specifically is explained below for Figure of description content Explanation.
The present invention provides a kind of gate construction method for hanging under narrow working space, which utilizes gate Upper cavity carries out gate lifting, narrow to adapt to for the narrow space construction after the completion of pouring at the top of gate upper cavity Working space, gate use segment lifting, and gate is lifted from gate slot, lifted by crane using short side, turned in gate upper cavity Body carries out the lifting construction of gate, specifically includes following construction procedure:
S1: processing gate segment, the gate includes the first segment 1, second section 2 and third segment 3 being arranged from top to bottom, Several suspension centres are provided on the first segment 1, second section 2 and third segment 3;
S2: when binding at the top of gate upper cavity, main suspension centre 5 is set on the top plate 4, is respectively set in main 5 two sides of suspension centre There are the first from left auxiliary suspension centre 7, the second from left auxiliary suspension centre 6 and the right side one that suspension centre 8 and the right side two is assisted to assist suspension centre 9;
S3: the second section 2 is transported by flat car to gate slot, and flat car wheel hub uses steel wheel hub, wheel hub bottom Attachment rail, flat car carry out tethered sliding using hoist engine;
S4: carrying out the lifting of second section 2 using main suspension centre 5 using gate slot, and lifting is utilized main suspension centre 5, matched using hoist engine It closes wirerope to be lifted by crane, by the lifting of second section 2 into gate upper cavity;
S5: in the gate upper cavity, rotator construction is carried out to second section 2, wherein the first from left auxiliary suspension centre 7, the right side one are auxiliary Suspension centre 8 is helped to connect the lateral left suspension centre and right suspension centre of second section 2 by wirerope respectively, the second from left assists suspension centre 6, the right side two to assist Suspension centre 9 connects the lower suspension centre and upper suspension centre on 2 right side of second section by wirerope respectively, assists suspension centre 7, the right side one in described the first from left Auxiliary suspension centre 8, the second from left auxiliary suspension centre 6, the right side two assist that hoist engine is respectively set at suspension centre 9, real using hoist engine cooperation wirerope The rotator construction of existing second section 2, is placed on the side wall and lock in the upper cavity upstream or downstream after second section 2 is turned The intersection of gate slot top plate;
S6: the hanging method in installation steps S3-S5 lifts first segment 1, and first segment 1 is placed on second section 2 tops of section, the temporary locking of first segment 1 and second section 2 is realized using junction steel plate pre-buried in upper cavity;
S7: according to the hanging method in step S3-S4, third segment 3 is lifted into the upper cavity;
S8: realize that the rotator construction of third segment 3, the rotator construction specifically comprise the following steps: in upper cavity
S81: I-steel is laid in upper cavity bottom and then third segment 3 is dropped down onto platform by steel plate, erection construction platform On;
S82: main rope is set in main suspension centre 5, main rope suspension hook installation steel cable is fixed in 3 transverse direction of third segment Between on main suspension centre 5, jack is installed again, it is firm that jack one end is connect with the vertical right side suspension centre in third segment 3 on suspension hook;
S83: jack is installed using the second from left auxiliary suspension centre 6, it is firm that jack one end is connect with 3 left lower suspension centre of third segment, even Fixed utilization afterwards main suspension centre 5 cooperation hoist engine is connect to sling third segment 3;
S84: left hydraulic device 10 and right hydraulic device 11 are respectively set on the left side wall and right-side wall of the upper cavity;
S85: main suspension centre 5 and the second from left is cooperated to assist the hoist engine and steel of suspension centre 6 using left hydraulic device 10, right hydraulic device 11 Cord realizes the rotator construction of third segment 3;Cooperate after turning it with gate separation;
S9: the third segment 3 in step S8 after swivel is directly lifted into gate slot, and the extremely design position of lifting downwards It sets, carries out temporary locking, third segment 3 is fixed in gate slot;
S10: being sling first segment 1 on upper cavity top using the first from left auxiliary suspension centre 7, using main suspension centre 5 by second section 2 It slings, after the lifting of second section 2 to gate slot upper space and being aligned, by the lifting downwards of second section 2 to third segment 3 On, second section 2 and third segment 3 are fixed using temporary locking device;
S11: decentralization first segment 1 to design position is sling first segment 1 using main suspension centre 5, extremely by the lifting of first segment 1 Gate slot upper space and after being aligned, lifting downwards is in second section 2, using temporary locking device by first segment 1 and the Two segments 2 are fixed;
S12: it is assembled to welding is carried out between first segment 1, second section 2, third segment 3, hanging device is removed, completes to apply Work.
Preferably, the specific hanging method in step S4 are as follows: 2 main rope suspension hook of gate second section installs a steel Cord is fixed on gate transverse direction suspension centre, installs the jack of a 50t, jack one end and the vertical right side suspension centre of gate on suspension hook again It is firm to connect, and gate is made to be in equilibrium state.
Preferably, first segment 1 is first lifted in step S3-S5, and it is rear in step S6 to lift second section 2, by the second section Section 2 is as 1 top of first segment;The second section 2 that top is directly sling in the step S10, is transferred after being turned To 3 top of third segment, remaining first segment 1 is directly sling in step S11, after being turned in decentralization to second section 2.
After second section 2 is lifted into upper cavity, the placement of second section 2 is located at gate slot upstream or downstream, reserves The gate slot installation space of third segment 3, the short side of preferred second section are placed vertically out, and long side is horizontal positioned, and long side It is arranged in parallel with two gate slots;When operation, it is preferable that the operation mode of second section 2 is wirerope applied force shown in attached drawing 6 Direction, i.e., the second from left auxiliary suspension centre 6, the right side two assist the upward applied force of suspension centre 9, the first from left assist suspension centre 7 and the right side one assist 8 steel of suspension centre Cord moves down, for realize second section 2 upstream or downstream is placed, preferred the first from left auxiliary suspension centre 7, the second from left are auxiliary Suspension centre 6 and the right side one is helped to assist suspension centre 8 and the right side two that suspension centre 9 is assisted to realize that upstream and downstream is staggeredly arranged;Or second section 2 upstream Or when the placement of downstream, using human assistance operation, realize that second section 2 is being vacillated up and down using incremental launching device or hydraulic device It is dynamic;
As concrete engineering example, emergency repair gate is arranged in certain flood-relief channel intake tower, and intake tower bulkhead gate groove elevation is 360m~407m.Since bulkhead gate producer is undressed when flood discharging tunnel top surface platform binds, can not be installed before binding, Therefore it can only lift and install from gate slot at present.Gate widths 8.22m, gate slot left and right banks direction width 8.5m, therefore gate lifts When can only be lifted by short side, lifting to 407m platform to be turned in upper plenum.
When headstock gear binds, the lifting of later period gate is considered, in each embedded auxiliary suspension centre in rolling open and close machine two sides, carry out Auxiliary lifts and cooperates rotator construction.
First segment is first lifted by crane, and is temporarily fixed on 407m elevation maintenance door cavity upstream end, second section is hung in recurrence, is set In in first segment, when using casting concrete pre-buried steel plate suspension centre by first segment and second section when fix.
Third segment is finally lifted by crane, directly enters gate slot after complete overturning in 90 °, is transferred to formulating position, then by second It is hung on third segment after the swivel of segment, finally first segment is hung in second section, carry out welding and complete whole splicing.
The above embodiment is only the preferred embodiment of the present invention, and protection scope of the present invention is not construed as only limiting In the concrete form that embodiment is stated, protection scope of the present invention also includes that those skilled in the art conceive institute according to the present invention It is conceivable that equivalent technologies mean.

Claims (3)

1. a kind of gate construction method for hanging under narrow working space, which is carried out using gate upper cavity Gate lifting, for the narrow space construction after the completion of being poured at the top of gate upper cavity, to adapt to narrow working space, gate Using segment lifting, gate is lifted from gate slot, is lifted by crane using short side, turned in gate upper cavity, carry out gate Lifting construction, it is characterised in that: specifically include following construction procedure:
S1: processing gate segment, the gate includes the first segment being arranged from top to bottom, second section and third segment, institute It states and is provided with several suspension centres on first segment, second section and third segment;
S2: when binding at the top of gate upper cavity, main suspension centre is set on top plate, is respectively arranged with a left side in the main suspension centre two sides One auxiliary suspension centre, the second from left auxiliary suspension centre and the right side one assist suspension centre and the right side two to assist suspension centre;
S3: the second section is transported by flat car to gate slot, and flat car wheel hub uses steel wheel hub, wheel hub bottom peace Track is filled, flat car carries out tethered sliding using hoist engine;
S4: carrying out the lifting of second section using main suspension centre using gate slot, and lifting utilizes main suspension centre, cooperates steel using hoist engine Cord is lifted by crane, and second section is lifted into gate upper cavity;
S5: in the gate upper cavity, rotator construction is carried out to second section, wherein the first from left auxiliary suspension centre, the right side one assist Suspension centre connects the left suspension centre and right suspension centre of second section transverse direction by wirerope respectively, and the second from left assists suspension centre, the right side two to assist suspension centre Lower suspension centre and upper suspension centre on the right side of second section are connected by wirerope respectively, assist suspension centre, a right auxiliary hanging in described the first from left Point, the second from left auxiliary suspension centre, the right side two assist that hoist engine is arranged respectively at suspension centre, realize second section using hoist engine cooperation wirerope Rotator construction, the friendship of the side wall and gate grooved top plate in the upper cavity upstream or downstream is placed on after second section is turned At boundary;
S6: the hanging method in installation steps S3-S5 lifts first segment, and first segment is placed on the second section The temporary locking of first segment and second section is realized on top using junction steel plate pre-buried in upper cavity;
S7: according to the hanging method in step S3-S4, third segment is lifted into the upper cavity;
S8: realize that the rotator construction of third segment, the rotator construction specifically comprise the following steps: in upper cavity
S81: I-steel is laid in upper cavity bottom and then steel plate, erection construction platform drop down onto third segment on platform;
S82: main rope is set in main suspension centre, it is laterally intermediate that main rope suspension hook installation steel cable is fixed on third segment On main suspension centre, jack is installed again, it is firm that jack one end is connect with the vertical right side suspension centre in third segment on suspension hook;
S83: jack is installed using the second from left auxiliary suspension centre, it is firm that jack one end is connect with third segment left lower suspension centre, connection Third segment is sling using main suspension centre cooperation hoist engine after fixed;
S84: left hydraulic device and right hydraulic device is respectively set on the left side wall and right-side wall of the upper cavity;
S85: cooperating main suspension centre and the second from left to assist the hoist engine and wirerope of suspension centre using left hydraulic device, right hydraulic device, Realize the rotator construction of third segment;Cooperate after turning it with gate separation;
S9: the third segment in step S8 after swivel directly being lifted into gate slot, and is lifted downwards to design position, Temporary locking is carried out, third segment is fixed in gate slot;
S10: first segment is sling on upper cavity top using the first from left auxiliary suspension centre, is hung second section using main suspension centre It rises, second section is lifted to gate slot upper space and after being aligned, second section is lifted downwards to third segment, is used Second section and third segment are fixed temporary locking device;
S11: first segment is sling using main suspension centre to design position, first segment is lifted to gate by decentralization first segment Slot upper space and after being aligned, lifting downwards is in second section, using temporary locking device by first segment and second section It is fixed;
S12: it is assembled to welding is carried out between first segment, second section, third segment, hanging device is removed, construction is completed.
2. a kind of gate construction method for hanging under narrow working space as described in claim 1, it is characterised in that: step Specific hanging method in rapid S4 are as follows: gate second section main rope suspension hook installation steel cable is fixed on gate and laterally hangs On point, the jack of a 50t is installed again on suspension hook, it is firm that jack one end is connect with the vertical right side suspension centre of gate, is in gate Equilibrium state.
3. a kind of gate construction method for hanging under narrow working space as described in claim 1, it is characterised in that: step First segment, rear lifting second section in step S6, by second section as in the first segment are first lifted in rapid S3-S5 Portion;The second section that top is directly sling in the step S10, decentralization is to third segment top after being turned, in step S11 Remaining first segment is directly sling, after being turned in decentralization to second section.
CN201910605597.5A 2019-07-05 2019-07-05 Gate hoisting construction method used in narrow operation space Active CN110304588B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910605597.5A CN110304588B (en) 2019-07-05 2019-07-05 Gate hoisting construction method used in narrow operation space

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910605597.5A CN110304588B (en) 2019-07-05 2019-07-05 Gate hoisting construction method used in narrow operation space

Publications (2)

Publication Number Publication Date
CN110304588A true CN110304588A (en) 2019-10-08
CN110304588B CN110304588B (en) 2020-07-24

Family

ID=68078188

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910605597.5A Active CN110304588B (en) 2019-07-05 2019-07-05 Gate hoisting construction method used in narrow operation space

Country Status (1)

Country Link
CN (1) CN110304588B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110984611A (en) * 2019-11-29 2020-04-10 中国二十二冶集团有限公司 Narrow space steel column installation method
CN111119133A (en) * 2020-01-16 2020-05-08 董传强 Hydropower station gate protection construction equipment and construction method thereof
CN113605346A (en) * 2021-08-04 2021-11-05 中交三航局第二工程有限公司 Non-navigation-stop maintenance method for large drain valve

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS60192013A (en) * 1984-03-09 1985-09-30 Hitachi Zosen Corp Gate checking and repairing device
JPH07233518A (en) * 1994-02-22 1995-09-05 Ishigaki Mech Ind Co Easily inspectable gate pump
CN103074872A (en) * 2013-01-18 2013-05-01 成都阿朗科技有限责任公司 Gate slot construction method and device for gate
CN103469771A (en) * 2013-09-26 2013-12-25 江苏省水利机械制造有限公司 Segmented mounting method for large-sized goggles gate
US20140140770A1 (en) * 2011-05-20 2014-05-22 Hitachi Zosen Corporation Floating flap gate
CN205557471U (en) * 2016-01-29 2016-09-07 常州市武进第一水利机械有限公司 Plane gate liftes vertically
CN105951683A (en) * 2016-05-19 2016-09-21 中国葛洲坝集团第工程有限公司 Construction method for corbel steel reinforcements of gate pier
CN106120664A (en) * 2016-06-24 2016-11-16 中国长江三峡集团公司 Ship lift tail-bay main gate construction method

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS60192013A (en) * 1984-03-09 1985-09-30 Hitachi Zosen Corp Gate checking and repairing device
JPH07233518A (en) * 1994-02-22 1995-09-05 Ishigaki Mech Ind Co Easily inspectable gate pump
US20140140770A1 (en) * 2011-05-20 2014-05-22 Hitachi Zosen Corporation Floating flap gate
CN103074872A (en) * 2013-01-18 2013-05-01 成都阿朗科技有限责任公司 Gate slot construction method and device for gate
CN103469771A (en) * 2013-09-26 2013-12-25 江苏省水利机械制造有限公司 Segmented mounting method for large-sized goggles gate
CN205557471U (en) * 2016-01-29 2016-09-07 常州市武进第一水利机械有限公司 Plane gate liftes vertically
CN105951683A (en) * 2016-05-19 2016-09-21 中国葛洲坝集团第工程有限公司 Construction method for corbel steel reinforcements of gate pier
CN106120664A (en) * 2016-06-24 2016-11-16 中国长江三峡集团公司 Ship lift tail-bay main gate construction method

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110984611A (en) * 2019-11-29 2020-04-10 中国二十二冶集团有限公司 Narrow space steel column installation method
CN111119133A (en) * 2020-01-16 2020-05-08 董传强 Hydropower station gate protection construction equipment and construction method thereof
CN111119133B (en) * 2020-01-16 2021-07-06 董传强 Hydropower station gate protection construction equipment and construction method thereof
CN113605346A (en) * 2021-08-04 2021-11-05 中交三航局第二工程有限公司 Non-navigation-stop maintenance method for large drain valve
CN113605346B (en) * 2021-08-04 2022-08-12 中交三航局第二工程有限公司 Non-navigation-stop maintenance method for large drain valve

Also Published As

Publication number Publication date
CN110304588B (en) 2020-07-24

Similar Documents

Publication Publication Date Title
CN110304588A (en) A kind of gate construction method for hanging under narrow working space
CN203412327U (en) Rotary lift type stereo garage
CN103711301A (en) Construction method and device for two-track movable electric basket and lifting hoist
CN102877637B (en) Method for implementing operating platform in bottom wall construction of cantilever beam
CN104343263A (en) Rotary lifting type three-dimensional garage
CN110407078A (en) A kind of gate segment swivel construction method for hanging of more suspension centres
CN203794498U (en) Built-in self-elevating tower crane device
CN101509229B (en) Method for constructing side span beam section without joist bracket of large-span steel box girder cable-stayed bridge
CN111778857B (en) Process for synchronously erecting upper and lower beams of double-layer overhead bridge of urban public rail
CN110258352A (en) The steel reinforced concrete combined bridge construction method that two bridgings are done
CN113335475B (en) Deck bottom fixed pulley sliding platform dismantling process
CN108147295A (en) A kind of cable crane and its lifting trailer system in suspension bridge construction
CN105421239B (en) Hoisting method for large-span highway-railway dual-purpose steel truss girder bridge deck slab
CN111350523B (en) Construction method and device for dismantling negative ring in limited space
CN207419264U (en) A kind of cable hoisting and rotator construction system
CN205241086U (en) Template hoist and mount and ann gun carriage of disassembling and using
CN202989702U (en) Track switch hoisting transportation operation device
CN110344334A (en) Steel reinforced concrete combined bridge construction method is done using two bridgings of dorsal funciculus formula Bridge Erector
CN107720652B (en) A kind of construction method for hanging of frame structure large scale equipment
CN113235460B (en) Prefabricated segment swinging method for bridge cantilever assembly
CN215291562U (en) Device for high-rise building construction by adopting cantilever crane
CN113322819B (en) Method for erecting first-span T beam at tunnel outlet
CN112627882B (en) Transferring machine tool for large shield tunnel mid-board and mounting method
CN205775849U (en) A kind of automatic-lifting type is opened the navigation or air flight heavy-duty steel trestle temporarily
CN210763974U (en) Be suitable for reverse construction method to get soil mouthful and pass suspension type electric hoist for material

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant