CN110258231A - The construction method on cast-in-place assembling concrete road surface - Google Patents

The construction method on cast-in-place assembling concrete road surface Download PDF

Info

Publication number
CN110258231A
CN110258231A CN201910366666.1A CN201910366666A CN110258231A CN 110258231 A CN110258231 A CN 110258231A CN 201910366666 A CN201910366666 A CN 201910366666A CN 110258231 A CN110258231 A CN 110258231A
Authority
CN
China
Prior art keywords
road surface
concrete
cast
construction method
place
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910366666.1A
Other languages
Chinese (zh)
Inventor
杨永伟
于成波
刘秉辉
徐世文
王源全
谷金鑫
赵大军
***
王志远
郑焘
惠志明
娄英奎
李世有
孙锐
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 9 Group Co Ltd
Second Engineering Co Ltd of China Railway No 9 Group Co Ltd
Original Assignee
China Railway No 9 Group Co Ltd
Second Engineering Co Ltd of China Railway No 9 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway No 9 Group Co Ltd, Second Engineering Co Ltd of China Railway No 9 Group Co Ltd filed Critical China Railway No 9 Group Co Ltd
Priority to CN201910366666.1A priority Critical patent/CN110258231A/en
Publication of CN110258231A publication Critical patent/CN110258231A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C11/00Details of pavings
    • E01C11/02Arrangement or construction of joints; Methods of making joints; Packing for joints
    • E01C11/04Arrangement or construction of joints; Methods of making joints; Packing for joints for cement concrete paving
    • E01C11/12Packing of metal and plastic or elastic materials
    • E01C11/126Joints with only metal and prefabricated packing or filling
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C11/00Details of pavings
    • E01C11/02Arrangement or construction of joints; Methods of making joints; Packing for joints
    • E01C11/04Arrangement or construction of joints; Methods of making joints; Packing for joints for cement concrete paving
    • E01C11/14Dowel assembly ; Design or construction of reinforcements in the area of joints
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C7/00Coherent pavings made in situ
    • E01C7/08Coherent pavings made in situ made of road-metal and binders
    • E01C7/10Coherent pavings made in situ made of road-metal and binders of road-metal and cement or like binders
    • E01C7/14Concrete paving

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Paving Structures (AREA)

Abstract

The construction method on cast-in-place assembling concrete road surface, belong to construction engineering technical field, including the clear table of roadbed, original ground it is smooth roll, 5% Cement Soil base treatment, concrete construction (binding of road surface reinforcing bar, the installation of channel steel template, installation built-in fitting, casting concrete), road surface press polish, surface galling, watering health cover water-saving curing film, installation shed, installation polyethylene foam sheet (10mm) and are transferred to lower whorl construction.Cast in situs is taken to complete the automatic assembling for the first time on road surface in assembled road surface by the present invention, reduce high freight, and the circulation difficulty and expense of a series of lifting large scale equipments of bring, reduce the miscellaneous work task high due to on-site consolidation bring base processing accuracy, reduce the longer duration required for on-site consolidation, reaches time saving, laborsaving, efficient effect.

Description

The construction method on cast-in-place assembling concrete road surface
Technical field
The invention belongs to construction engineering technical fields, especially relate to a kind of construction method on pin-connected panel road surface.
Background technique
With the enhancing of global environmental consciousness, unnecessary pollution and waste are avoided, existing construction building site is general Recyclable assembled road surface is mostly used, in conjunction with the development on assembled road surface, first is that is mainly used at present is all Prefabrication, forms chain block structure according to each size and shapes such as similar A, B, C to realize the assembly on road surface, work progress by Factory carries out the prefabricated and health of assembled block;Second is that transporting specified job location using flat car after intensity meets;Third is that By after the completion of base treatment, lifting is completed with crane or large scale equipment and is laid in scene in advance;Fourth is that piece processing is to complete to face When assembled road surface construction.Since working procedure is cumbersome, and assembled road surface unit weight is all in 6t or more, transit link Expense is high, four lifting points is arranged in roads plate, and the reinforcing bar for needing to lift sleeve and road deck is welded.From cost The loss of many man power and materials all is brought to enterprise on upper and working procedure, therefore needs a kind of new skill in the prior art Art scheme solves the problems, such as this.
Summary of the invention
The technical problems to be solved by the present invention are: providing the construction method on cast-in-place assembling concrete road surface, will assemble Cast in situs is taken to complete the automatic assembling for the first time on road surface in formula road surface, reduces high freight and hanging belt A series of large scale equipments circulation difficulty and expense, reduce due to high many and diverse of on-site consolidation bring base processing accuracy Task reduces the longer duration required for on-site consolidation, has reached time saving, laborsaving, efficient effect.
The construction method on cast-in-place assembling concrete road surface, it is characterized in that: include the following steps, and following steps sequentially into Row,
Step 1: road surface base treatment
The clear list processing of substrate is carried out using excavator on construction road surface, surface dust is manually cleared up to smooth, measurement assembled The base profile on road surface is rolled repeatedly using road roller, until carrying out 5% cement after foundation bearing capacity meets 200Kpa and changing The base treatment of good soil;
Step 2: concrete construction
By step 1 treated the included reinforced mesh in concrete road surface, assembling reinforcement and embedded sleeve barrel, steel mesh Piece is fixed using quincunx spacer bar, formwork, and using road surface combined steel formwork, template inside coating release agent, template outside is adopted Formwork reinforcement is carried out with reinforcing bar, ground is protruded into reinforcing bar one end, and the other end is exposed, and absolute altitude is marked on the inside of template, pours cast-in-place mixed Solidifying soil, vibrates, and completes concrete construction;
Step 3: road surface press polish and maintenance
Concrete press polish is carried out using electric concrete finisher and receives face, attached plastic film health 72h or more removes plastics Film after carrying out plucking slicing using napper, covers concrete surface after facing concrete compression strength reaches 35mpa The maintenance of lid water-saving moist keeping maintenance film;
So far, a kind of construction method on cast-in-place assembling concrete road surface is completed.
The clear table of clear list processing uses 20t road roller, rolling layer 5 with a thickness of 30cm, road roller in the step 1 It is secondary.
The diameter of reinforced mesh is 6mm, spacing 100mm in the step 2.
Before formwork is completed in reinforcing bar binding in the step 2, each portion's size of template is checked, is laid with two cloth, one film of 200g/ ㎡ Geotextiles are isolated by concrete section with bottom substrate structure.
The reinforcing bar for carrying out formwork reinforcement in the step 2 on the outside of template is 16 reinforcing bar of Φ, and reinforcing bar protrudes into ground 20cm, outside Dew length is 30cm, bar spacing 40cm.
The sequence that cast-in-place concrete is poured in the step 2 is that left width and right width staggeredly pour.
After template is fixedly mounted in the step 2, installation of embedded parts, the pre-buried length in one end are carried out before pouring cast-in-place concrete 150mm, internal diameter 30mm steel bushing, the pre-buried length of the other end are 200mm, and diameter 25mm rod iron, spacing 500mm setting is together.
The concrete prefabricated unit obtained after the completion of the step 2 concrete construction is that structure snd size are consistent logical Use prefabricated unit.
Through the above design, the present invention can be brought the following benefits: be applied on cast-in-place assembling concrete road surface The working procedure on current most of pin-connected panel road surface is simplified and has been carried out to prefabricated unit thorough excellent by work method Change, pin-connected panel road surface need both overcome existing precast splice type by that can will be poured in place after the completion of base treatment All multi-process on road surface are omitted transport, lifting link, greatly save cost.
Detailed description of the invention
Below in conjunction with the drawings and specific embodiments, the present invention is further illustrated:
Fig. 1 is the construction method schematic process flow diagram on the cast-in-place assembling concrete road surface of the present invention.
Fig. 2 is the concrete prefabricated cellular construction schematic diagram of construction method on the cast-in-place assembling concrete road surface of the present invention.
Fig. 3 is the construction method installation of embedded parts structural schematic diagram on the cast-in-place assembling concrete road surface of the present invention.
1- steel bushing, 2- rod iron, the concrete prefabricated unit of 3-, 4- thick steel plate, 5- polyethylene foam sheet in figure.
Specific embodiment
The construction method on cast-in-place assembling concrete road surface, as shown in Figure 1, include the following steps,
Step 1: carrying out the clear list processing of substrate using excavator on construction road surface, clear table will manually float with a thickness of 30cm Soil cleaning is smooth, measures the base profile on assembled road surface, is rolled repeatedly using 20t road roller, and first quiet rear vibration rolls 5 Time, until foundation bearing capacity meets 200Kpa, using road roller vibroroller cmpacting without obvious wheelmark as criterion of acceptability, carry out 5% cement and change The base treatment of good soil;
Step 2: two step of 200g/ ㎡, one film geotextiles are laid with, by concrete section and lower part base after the completion of substrate construction Layer structure isolation, the included reinforced mesh in concrete road surface, reinforced mesh use bar diameter for 6mm, spacing 100mm, steel mesh Piece is fixed using quincunx spacer bar, it is ensured that protective layer thickness and size;Assembling reinforcement, steel bar meter are tied up using scene processing The mode of bundle, reinforcing bar are 50mm away from concrete outer rim protective layer;Embedded sleeve barrel, as shown in figure 3, to pour preceding one end pre- for concrete slab Burying long 150mm, internal diameter 30mm steel bushing 1, pre-buried length is 200mm on one side, diameter 25mm rod iron 2, spacing 500mm setting 1, To guarantee that height 240mm is arranged in accurate positioning sleeve side concrete slab interface, length is one of the 3mm thick steel plate 4 of 4000mm, ∠ 30*30*4mm angle steel together, is laid with one of 10mm thick polyethylene cystosepiment 5 on the outside of steel plate using double-sided adhesive tape, size and steel plate It is identical.Sleeve and pre-buried rod iron are fixed using pre-embedded steel slab and binding reinforcement mesh sheet and to drawing reinforcing bar;Formwork is flat using surface Whole, the straight road surface 24mm combined steel formwork, template inside coating release agent are convenient for demoulding, are stretched on the outside of template using 16 reinforcing bar of Φ Enter ground 20cm, protruded length 30cm, bar spacing 40cm, carry out formwork reinforcement, prevents the phenomenon that running mould;In template Side marks absolute altitude, pours cast-in-place concrete, pours sequence as shown in Fig. 2, wherein A is right width, and B is left width, pours sequence as a left side Width and right width staggeredly pour, and such as first pour left width, turn to pour right width after completing 100m;Cooperate plug-in type using three axis road surface spreaders Vibrator vibrates, and vibrator inserts evenly distributed, 1.5 times of distance no more than vibrating head operating radius, completion casting concrete;
Step 3: using electric concrete finisher progress concrete press polish receipts face, attached plastic film health 72h or more, Plastic film is removed, after facing concrete compression strength reaches 35mpa, plucking slicing is carried out using napper, napper opens It to advance in strict accordance with the line of ink marker when dynamic, averagely promote 18m~22m per minute, and observe tool bit abrasion degree, planing depth control , will uniformly to napper operating pressure during plucking in 8mm~10mm, the streakline of pull-out is straight, uniform, depth is big, together When concrete road surface thickness it is more uniform, it is ensured that for napper during plucking, groove depth, uniform groove width are consistent, and plucking slicing is complete Finish and clear up immediately, carries out next road slicing after completing together;It sprinkles water after slicing to concrete surface, covering water-saving moisturizing is supported Cuticula maintenance, curing time are 7 days, complete pouring for concrete road surface.
The construction method on cast-in-place assembling concrete road surface of the invention, takes cast in situs for assembled road surface to complete The automatic assembling for the first time on road surface reduces high freight, and a series of turnover of lifting large scale equipments of bring is stranded Difficult and expense, reduces the miscellaneous work task high due to on-site consolidation bring base processing accuracy, reduces on-site consolidation The required longer duration has reached time saving, laborsaving, efficient effect.

Claims (8)

1. the construction method on cast-in-place assembling concrete road surface, it is characterized in that: include the following steps, and following steps sequentially into Row,
Step 1: road surface base treatment
The clear list processing of substrate is carried out using excavator on construction road surface, surface dust is manually cleared up to smooth, measurement assembled road surface Base profile, rolled repeatedly using road roller, until after foundation bearing capacity meets 200Kpa, carry out 5% Cement Soil Base treatment;
Step 2: concrete construction
It is adopted by step 1 treated the included reinforced mesh in concrete road surface, assembling reinforcement and embedded sleeve barrel, reinforced mesh It is fixed with quincunx spacer bar, formwork, using road surface combined steel formwork, template inside coating release agent, template outside uses steel Muscle carries out formwork reinforcement, and ground is protruded into reinforcing bar one end, and the other end is exposed, and absolute altitude is marked on the inside of template, pours cast-in-place concrete, After vibrating, casting concrete is completed;
Step 3: road surface press polish and maintenance
Concrete press polish is carried out using electric concrete finisher and receives face, it is thin to remove plastics by attached plastic film health 72h or more Film after carrying out plucking slicing using napper, covers concrete surface after facing concrete compression strength reaches 35mpa Water-saving moist keeping maintenance film maintenance;
So far, a kind of construction method on cast-in-place assembling concrete road surface is completed.
2. the construction method on cast-in-place assembling concrete road surface according to claim 1, it is characterized in that: in the step 1 For the clear table of clear list processing with a thickness of 30cm, road roller uses 20t road roller, and rolling layer is 5 times.
3. the construction method on cast-in-place assembling concrete road surface according to claim 1, it is characterized in that: the step 2 In, the diameter of reinforced mesh is 6mm, spacing 100mm.
4. the construction method on cast-in-place assembling concrete road surface according to claim 1, it is characterized in that: in the step 2 Before formwork is completed in reinforcing bar binding, each portion's size of template is checked, two cloth, the one film geotextiles of 200g/ ㎡ are laid with, by concrete section It is isolated with bottom substrate structure.
5. the construction method on cast-in-place assembling concrete road surface according to claim 1, it is characterized in that: in the step 2 The reinforcing bar that formwork reinforcement is carried out on the outside of template is 16 reinforcing bar of Φ, and reinforcing bar protrudes into ground 20cm, protruded length 30cm, bar spacing For 40cm.
6. the construction method on cast-in-place assembling concrete road surface according to claim 1, it is characterized in that: in the step 2 The sequence for pouring cast-in-place concrete is that left width and right width staggeredly pour.
7. the construction method on cast-in-place assembling concrete road surface according to claim 1, it is characterized in that: in the step 2 After template is fixedly mounted, installation of embedded parts, the pre-buried long 150mm in one end, internal diameter 30mm steel bushing are carried out before pouring cast-in-place concrete (1), the pre-buried length of the other end is 200mm, and diameter 25mm rod iron (2), spacing 500mm setting is together.
8. the construction method on cast-in-place assembling concrete road surface according to claim 1, it is characterized in that: the step 2 is mixed The concrete prefabricated unit (3) obtained after the completion of solidifying soil construction is the consistent general prefabricated unit of structure snd size.
CN201910366666.1A 2019-05-05 2019-05-05 The construction method on cast-in-place assembling concrete road surface Pending CN110258231A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910366666.1A CN110258231A (en) 2019-05-05 2019-05-05 The construction method on cast-in-place assembling concrete road surface

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910366666.1A CN110258231A (en) 2019-05-05 2019-05-05 The construction method on cast-in-place assembling concrete road surface

Publications (1)

Publication Number Publication Date
CN110258231A true CN110258231A (en) 2019-09-20

Family

ID=67914149

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910366666.1A Pending CN110258231A (en) 2019-05-05 2019-05-05 The construction method on cast-in-place assembling concrete road surface

Country Status (1)

Country Link
CN (1) CN110258231A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111021176A (en) * 2019-12-16 2020-04-17 范拓 Garden road construction method
CN112962377A (en) * 2021-02-03 2021-06-15 四川吉凯瑞建设工程有限公司 Detachable cast-in-place concrete pavement and pouring method
CN114737430A (en) * 2022-05-13 2022-07-12 中国建筑第二工程局有限公司 High fill roadbed filling construction method
RU2777627C1 (en) * 2021-12-28 2022-08-08 Николай Николаевич Кириллов Method for constructing a pavement based on reinforced concrete blocks with prismatic elements on the lower surfaces
CN115012430A (en) * 2021-12-27 2022-09-06 德州市公路工程总公司 Prestressed anchor cable frame type protective structure and construction method thereof

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1145431A (en) * 1996-03-12 1997-03-19 西南工学院 Novel road and construction method thereof
CN101748674A (en) * 2008-12-03 2010-06-23 上海通用汽车有限公司 Road construction method
CN103590299A (en) * 2013-11-18 2014-02-19 北京中建建筑科学研究院有限公司 Construction method of reusable temporary road plate
CN207091859U (en) * 2017-08-11 2018-03-13 上海市城市建设设计研究总院(集团)有限公司 The precast assembly pavement structure integrated with pipe gallery
CN109024135A (en) * 2018-08-15 2018-12-18 江西博慧工程技术服务有限公司 A kind of concrete road surface green upgradeable architecture and remodeling method
CN109295827A (en) * 2018-11-14 2019-02-01 中国建筑第八工程局有限公司 Removable existing pouring type concrete road surface and method of construction
CN109610312A (en) * 2018-12-26 2019-04-12 北京工业大学 Prefabrication and assembly construction floorings based on the connection of X-type presstressed reinforcing steel

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1145431A (en) * 1996-03-12 1997-03-19 西南工学院 Novel road and construction method thereof
CN101748674A (en) * 2008-12-03 2010-06-23 上海通用汽车有限公司 Road construction method
CN103590299A (en) * 2013-11-18 2014-02-19 北京中建建筑科学研究院有限公司 Construction method of reusable temporary road plate
CN207091859U (en) * 2017-08-11 2018-03-13 上海市城市建设设计研究总院(集团)有限公司 The precast assembly pavement structure integrated with pipe gallery
CN109024135A (en) * 2018-08-15 2018-12-18 江西博慧工程技术服务有限公司 A kind of concrete road surface green upgradeable architecture and remodeling method
CN109295827A (en) * 2018-11-14 2019-02-01 中国建筑第八工程局有限公司 Removable existing pouring type concrete road surface and method of construction
CN109610312A (en) * 2018-12-26 2019-04-12 北京工业大学 Prefabrication and assembly construction floorings based on the connection of X-type presstressed reinforcing steel

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111021176A (en) * 2019-12-16 2020-04-17 范拓 Garden road construction method
CN111021176B (en) * 2019-12-16 2021-07-27 江西古蒽建筑工程有限公司 Garden road construction method
CN112962377A (en) * 2021-02-03 2021-06-15 四川吉凯瑞建设工程有限公司 Detachable cast-in-place concrete pavement and pouring method
CN115012430A (en) * 2021-12-27 2022-09-06 德州市公路工程总公司 Prestressed anchor cable frame type protective structure and construction method thereof
CN115012430B (en) * 2021-12-27 2024-03-01 德州市公路工程总公司 Prestressed anchor cable frame type protective structure and construction method thereof
RU2777627C1 (en) * 2021-12-28 2022-08-08 Николай Николаевич Кириллов Method for constructing a pavement based on reinforced concrete blocks with prismatic elements on the lower surfaces
CN114737430A (en) * 2022-05-13 2022-07-12 中国建筑第二工程局有限公司 High fill roadbed filling construction method

Similar Documents

Publication Publication Date Title
CN110258231A (en) The construction method on cast-in-place assembling concrete road surface
CN107905254B (en) Construction method of comprehensive pipe gallery formwork supporting integrated hydraulic internal formwork trolley
CN106592426B (en) The construction method of transverse prestress overall with reinforced concrete bridge deck plate prefab-form system
CN106346595A (en) Vertical molding mold and system and application method for concrete utility tunnel
CN103615053B (en) Monolithic reinforced concrete structure post empiricism engineering method
CN104453229B (en) Large-span load-bearing prestress double-T plate construction method
CN105563640A (en) Manufacturing process for environment-friendly construction modularization tool type temporary road plate block
CN108193608A (en) The cast-in-place road gully of mobile moldbase and construction method
CN105350559B (en) A kind of construction method of diamond dust structural floor suitable for large-sized workshop
CN107574762A (en) A kind of construction method for strengthening Cast-in-situ Beam 0# block construction qualities
CN108457243B (en) Construction method of assembled concrete breakwater
CN106182359A (en) The concrete list storehouse horizontal mould of pipe gallery, system and piping lane molding methods
CN206374015U (en) Concrete pipe gallery vertical-forming die and system
CN111074950B (en) Pre-closed advanced water stop post-cast strip for basement outer wall and construction method
CN105951842A (en) Raft lower reversed beam polystyrene board caul construction method
CN106284789B (en) Construction technology for controlling cast-in-situ floor Forming Quality
CN107386246A (en) A kind of lock chamber wall Construction Through Form on Traveler method
CN104594654B (en) A kind of concrete structure reinforcement scheme generation method
CN213296440U (en) Water stop structure for post-cast strip of underground chamber bottom plate
CN204418691U (en) A kind of for cast-in-place vertical member and horizontal member junction concrete blocking apparatus
CN112832149B (en) Culvert construction equipment and construction method
CN114457846A (en) Road station main body structure construction method
CN114182756A (en) Construction method for simply and movably pouring cable trench by using internal mold support system
CN210712595U (en) Cement member crossing road
CN113833003A (en) Construction method of raft plate of oversized clean workshop

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190920

RJ01 Rejection of invention patent application after publication