CN110175736B - Automatic card disassembling and hanging method for power system regulation and control center - Google Patents

Automatic card disassembling and hanging method for power system regulation and control center Download PDF

Info

Publication number
CN110175736B
CN110175736B CN201910276363.0A CN201910276363A CN110175736B CN 110175736 B CN110175736 B CN 110175736B CN 201910276363 A CN201910276363 A CN 201910276363A CN 110175736 B CN110175736 B CN 110175736B
Authority
CN
China
Prior art keywords
task
disassembling
hanging
dismantling
regulation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201910276363.0A
Other languages
Chinese (zh)
Other versions
CN110175736A (en
Inventor
叶茜茜
俞凯
施正钗
杨振
周泰斌
徐伟敏
邱成杰
臧怡宁
陈博
刘梅
朱燕
董辛遥
谢灵峰
姚益剑
徐伟俊
刘津源
虞天昊
吴昊
李军强
袁金腾
瞿合祚
陈旸
陈晓燕
郑达
朱奇伟
谢志云
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wenzhou Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Original Assignee
Wenzhou Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wenzhou Power Supply Co of State Grid Zhejiang Electric Power Co Ltd filed Critical Wenzhou Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Priority to CN201910276363.0A priority Critical patent/CN110175736B/en
Publication of CN110175736A publication Critical patent/CN110175736A/en
Application granted granted Critical
Publication of CN110175736B publication Critical patent/CN110175736B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06312Adjustment or analysis of established resource schedule, e.g. resource or task levelling, or dynamic rescheduling
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Health & Medical Sciences (AREA)
  • Theoretical Computer Science (AREA)
  • Marketing (AREA)
  • General Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • Public Health (AREA)
  • Primary Health Care (AREA)
  • Water Supply & Treatment (AREA)
  • Development Economics (AREA)
  • Educational Administration (AREA)
  • General Health & Medical Sciences (AREA)
  • Game Theory and Decision Science (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Alarm Systems (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The invention discloses an automatic card disassembling and assembling method of an electric power system regulation and control center, which comprises the steps of reading a work task of a regulation and control PMS system, generating a card disassembling and assembling task to be executed, generating a card assembling and assembling task to be executed when the card disassembling and assembling task in an initialization task is matched with an electric power error prevention system task, and starting to execute after receiving a message that both the work task of the PMS and the electric power error prevention system task are completed; when the task is executed, a file with a time sequence is sent to the regulation and control integrated system; reading a power grid pattern file, and when the target state of the execution equipment is inconsistent with the power grid pattern file, reading and storing an operation record of the regulation and control integrated system, and giving an automatic card dismantling failure warning; and when the tasks are consistent, completing the task of automatically disassembling and hanging the cards. The invention has the advantages that: effectively ensures that the automatic card disassembling and hanging operation is in place.

Description

Automatic card disassembling and hanging method for power system regulation and control center
Technical Field
The invention relates to an automatic disassembling and hanging method for a power system regulation and control center.
Background
The regulation and control center is used as an important component in the power system to play roles of unified planning, coordination management, fault treatment and the like on the whole power grid, the work content is wide, the safe and reliable operation of work not only affects the whole power production and transmission quality, but also affects the quality and safety of power consumption. With the continuous development of national economy, the scale of the power grid is continuously enlarged, the number of substations and the operation and maintenance intensity are continuously increased, and the regulation pressure is greatly increased. Therefore, how to effectively and reliably solve the problems of tedious and repeated operation to lighten huge workload from details is needed to be solved.
Through practical investigation, it is found that for a regulator, the license is to be disassembled and hung in the regulation and control integrated system before and after work, the disassembled and hung work content is overlapped with the misoperation prevention system operation work content, and the problem that the disassembling and hung operation is considered to be performed in the regulation and control system in subconscious sense due to the influence of human inertia thought is often caused, and the omission occurs.
Disclosure of Invention
The invention aims to provide an automatic card disassembling and assembling method for a power system regulation and control center, which can effectively solve the problem that regulation and control personnel forget to disassemble and assemble a card.
In order to solve the technical problems, the invention is realized by the following technical scheme: an automatic card disassembling and hanging method for a power system regulation and control center comprises the following steps:
A. reading a work task of the PMS, and initializing and generating a to-be-executed card dismantling task according to a linkage rule base;
B. when the dismantling task in the initialization task is matched with the power error prevention system task, the automatic dismantling and hanging task can be activated to be in a to-be-executed state,
C. when the automatic card-dismantling task is activated, a card-dismantling task to be executed is generated, and after the information that the work task of the PMS and the electric power error-preventing system task are completed is received, the automatic card-dismantling task is started to be executed;
D. when the automatic tear-down and hang-up task is executed, a file with a time sequence is sent to the regulation and control integrated system;
E. reading a power grid pattern file generated by the regulation and control integrated system every minute, and if the target state of the automatic card-dismantling task execution equipment is consistent with the power grid pattern file, reading and storing an operation record of the regulation and control integrated system and giving an automatic card-dismantling failure warning; and when the tasks are consistent, completing the task of automatically disassembling and hanging the cards.
Preferably, when the automatic tear-down task in the step D is executed, the file with the time sequence is sent to the regulation and control integrated system, and meanwhile, the file is reserved for backup.
Preferably, the file in the step D includes the time of disassembling and hanging, the factory station of disassembling and hanging, the equipment of disassembling and hanging, the current state of the equipment of disassembling and hanging, and the content of the target state.
Compared with the prior art, the invention has the advantages that:
1. the safety of automatic card-dismantling of the development regulation system is based on the electric power error-preventing system, and the safety verification mechanism of the electric power error-preventing system is suitable for the automatic card-dismantling system, so that the situations of card-dismantling errors, card-dismantling errors and the like can be avoided, and the safety of automatic card-dismantling is ensured.
2. The task of automatically disassembling and hanging the cards comes from a PMS regulation and control system, and the starting condition of judging the task of automatically disassembling and hanging the cards is that the PMS and the power anti-misoperation system are started, and the disassembling and hanging program can finally act only after the work tasks of the two systems are completed. Based on the linkage discrimination rules and the checking mechanism of the double systems, the execution and rechecking system of the card-dismantling task is ensured, and the automatic card-dismantling task is ensured not to be missed and wrong.
3. The automatic tag-dismantling task is executed in the regulation and control integrated system, and the automatic tag-dismantling task sends an instruction to the regulation and control integrated system according to time sequence tags when the automatic tag-dismantling task is executed. And the regulation and control integrated system receives the instruction and then finishes the disassembling and hanging of the cards according to the time sequence. The communication of the integrated system of disassembling and assembling the card and regulating and controlling is unidirectional file transmission, and the requirement of secondary safety protection of the power system is met.
4. The judgment of the automatic card-dismantling completion condition is carried out by reading the power grid model file generated every minute by the regulation and control integrated system, and when the power grid model state is inconsistent with the card-dismantling target state, the card-dismantling issuing failure alarm reminds a regulator to check and check, so that the automatic card-dismantling operation is effectively ensured to be in place.
5. The automatic card-disassembling program automatically generates a card-disassembling report before the modulator hands over, and the content comprises operation time, task sources, execution conditions and the like, and is used for the modulator to carry out the hand-over condition explanation and hand-over patrol.
Detailed Description
The following detailed description of the embodiments of the invention is intended to be illustrative of the invention and is not to be taken as limiting the invention.
An embodiment of an automatic card disassembling and assembling method for a power system regulation and control center, which comprises the following steps:
A. according to the actual circulation condition of the regulation and control service, the linkage rule among the systems is formulated, and according to the national network information specification, the power grid information discrimination rule library is arranged; an automatic disassembling and hanging program is arranged in a workstation of the regulation and control platform, and is interconnected with a PMS and an electric power error prevention system interface, and the program is started and daemon; reading a work task of the PMS, and initializing and generating a to-be-executed card dismantling task according to a linkage rule base;
B. when the dismantling task in the initialization task is matched with the power error prevention system task, the automatic dismantling and hanging task can be activated to be in a to-be-executed state,
C. when the automatic card-dismantling task is activated, a card-dismantling task to be executed is generated, and after the information that the work task of the PMS and the electric power error-preventing system task are completed is received, the automatic card-dismantling task is started to be executed;
D. when the automatic tear-down task is executed, a file with a time sequence is sent to the regulation and control integrated system, and meanwhile, the file is reserved for backup, and the sent file comprises tear-down time, tear-down stations, tear-down equipment, the current state of the tear-down equipment and the content of a target state;
E. reading a power grid pattern file generated by the regulation and control integrated system every minute, and if the target state of the automatic card-dismantling task execution equipment is consistent with the power grid pattern file, reading and storing an operation record of the regulation and control integrated system and giving an automatic card-dismantling failure warning; and when the tasks are consistent, completing the task of automatically disassembling and hanging the cards.
The regulation and control personnel execute the card disassembling and hanging operation on the regulation and control integrated system, the whole process of executing the operation is consistent with the execution and rechecking whole process of misoperation prevention, the operation belongs to complex heavy labor, and the unnecessary workload is increased. The safe execution of the method is also based on the operation reliability and the safety of the error prevention system.
The task of automatically disassembling and hanging the cards comes from a regulating and controlling PMS system, the task of the PMS system is assembled and controlled in a full-specialized way, a rule base is formulated reasonably, the task of disassembling and hanging the cards can be screened out, omission is avoided, and the rule base can be regulated according to the requirements of users. Meanwhile, the task trigger of the power anti-misoperation system is also very important, the safe and reliable operation can be ensured by the anti-misoperation system task trigger, the task starting time can be definitely operated by the anti-misoperation system task trigger, the execution time of automatic card dismantling can be definitely determined by the PMS and the anti-misoperation system task completion message, and the starting and stopping time of card dismantling by a modulator is summarized at two time points and is stored as a necessary condition of card dismantling events.
Automatic tear-down execution is ultimately accomplished by sending an execution text file to the regulatory integration system. In the text form transmission of the execution file, the automatic tear-down procedure is considered to be in the management information large area of the secondary safety protection of the electric power, and tear-down of the regulation and control integrated system is the control area of the production control large area, namely the safest highest-level area. Compared with other modes, the text transmission has the advantages that the safety protection device has penetrability, and the transverse isolation passing format between the safety areas is arranged, so that the requirement of secondary safety protection transmission of electric power is met, and the effective transmission is realized.
And the regulation and control integrated system reads the tag-dismantling text and carries out tag-dismantling operation according to the requirement. The operation result is recorded in the regulation and control integrated system and can be inquired in real time. And the automatic card-disassembling program judges whether the automatic card-disassembling is successful or not and generates failure warning unsuccessfully by comparing the graphic module information file issued by the regulation and control integrated system every minute with the target state of the card-disassembling task.
The regulator can automatically generate a report for the removal of the cards when the regulator is in shift switching, and the content is set according to the shift switching requirement of the regulator and is used for shift switching condition description and shift switching inspection.
The above embodiments are merely illustrative embodiments of the present invention, but the technical features of the present invention are not limited thereto, and any changes or modifications made by those skilled in the art within the scope of the present invention are included in the scope of the present invention.

Claims (3)

1. An automatic disassembling and hanging method for a power system regulation and control center is characterized in that: the method comprises the following steps:
A. reading a work task of a regulating and controlling PMS system, and initializing and generating an automatic card dismantling and hanging task to be executed according to a linkage rule base;
B. when the dismantling and hanging task in the initialization task is matched with the power error prevention system task, the automatic dismantling and hanging task can be activated to be in a state to be executed;
C. when the automatic card-dismantling task is activated, a card-dismantling task to be executed is generated, and after the information that the work task of the PMS and the electric power error-preventing system task are completed is received, the automatic card-dismantling task is started to be executed;
D. when the automatic tear-down and hang-up task is executed, a file with a time sequence is sent to the regulation and control integrated system;
E. reading a power grid pattern file generated by the regulation and control integrated system every minute, and if the target state of the automatic card-dismantling task execution equipment is consistent with the power grid pattern file, reading and storing an operation record of the regulation and control integrated system and giving an automatic card-dismantling failure warning; and when the tasks are consistent, completing the task of automatically disassembling and hanging the cards.
2. The method for automatically disassembling and assembling a card in a power system control center as claimed in claim 1, wherein: and D, when the automatic tear-down and hang-up task is executed, sending a file with a time sequence to the regulation and control integrated system, and simultaneously, reserving a file for backup.
3. The method for automatically disassembling and assembling a card in a power system control center as claimed in claim 1, wherein: and D, the file in the step comprises the time for disassembling and hanging the cards, the factory station for disassembling and hanging the cards, the equipment for disassembling and hanging the cards, the current state of the equipment for disassembling and hanging the cards and the content of the target state.
CN201910276363.0A 2019-04-08 2019-04-08 Automatic card disassembling and hanging method for power system regulation and control center Active CN110175736B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910276363.0A CN110175736B (en) 2019-04-08 2019-04-08 Automatic card disassembling and hanging method for power system regulation and control center

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910276363.0A CN110175736B (en) 2019-04-08 2019-04-08 Automatic card disassembling and hanging method for power system regulation and control center

Publications (2)

Publication Number Publication Date
CN110175736A CN110175736A (en) 2019-08-27
CN110175736B true CN110175736B (en) 2023-06-23

Family

ID=67689440

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910276363.0A Active CN110175736B (en) 2019-04-08 2019-04-08 Automatic card disassembling and hanging method for power system regulation and control center

Country Status (1)

Country Link
CN (1) CN110175736B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117933949A (en) * 2024-03-22 2024-04-26 广东电网有限责任公司中山供电局 Execution method, device, storage medium and processor for power-supply-protection electric sheet

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20080030587A (en) * 2008-02-05 2008-04-04 (주)모노시스 Signboard information managing system using of a rfid and method of the same
CN104240152A (en) * 2014-09-15 2014-12-24 陈慧超 Power plant equipment on-line state and configuration state management system
CN107657055A (en) * 2017-10-18 2018-02-02 国网福建省电力有限公司 A kind of back-up system method of data synchronization based on distribution main website
CN107704739A (en) * 2017-11-01 2018-02-16 珠海华伟电气科技股份有限公司 Microcomputer anti-error operating system and method, anti-error main frame with listed function, Intelligent key, intelligent lock
KR101827467B1 (en) * 2017-06-01 2018-03-22 주식회사 빛컨 Adaptive iot service system powered by detachable hardware module
WO2018053947A1 (en) * 2016-09-22 2018-03-29 国电南瑞科技股份有限公司 Peer-to-peer mutual backup method suitable for multi-region integrated control of power grid

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103853436A (en) * 2013-12-19 2014-06-11 国家电网公司 Novel method for intelligently hanging and detaching signboard
CN105405073A (en) * 2015-12-23 2016-03-16 国网福建省电力有限公司 Information comparison method based on power distribution automation main station system and GIS system
CN108155717B (en) * 2017-03-16 2020-08-25 国网福建省电力有限公司厦门供电公司 FA anti-error checking method of power distribution main station based on power grid operation data
CN107526768A (en) * 2017-07-04 2017-12-29 国网冀北电力有限公司 A kind of listed assistance system of intelligence and implementation method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20080030587A (en) * 2008-02-05 2008-04-04 (주)모노시스 Signboard information managing system using of a rfid and method of the same
CN104240152A (en) * 2014-09-15 2014-12-24 陈慧超 Power plant equipment on-line state and configuration state management system
WO2018053947A1 (en) * 2016-09-22 2018-03-29 国电南瑞科技股份有限公司 Peer-to-peer mutual backup method suitable for multi-region integrated control of power grid
KR101827467B1 (en) * 2017-06-01 2018-03-22 주식회사 빛컨 Adaptive iot service system powered by detachable hardware module
CN107657055A (en) * 2017-10-18 2018-02-02 国网福建省电力有限公司 A kind of back-up system method of data synchronization based on distribution main website
CN107704739A (en) * 2017-11-01 2018-02-16 珠海华伟电气科技股份有限公司 Microcomputer anti-error operating system and method, anti-error main frame with listed function, Intelligent key, intelligent lock

Also Published As

Publication number Publication date
CN110175736A (en) 2019-08-27

Similar Documents

Publication Publication Date Title
CN111614157B (en) Sequence control system and method for switching operation of transformer substation
CN102361354B (en) The remote intensive managing and control system of unattended substation automated system
CN107611969B (en) Regulation and error prevention system with order regulation and constraint functions and method
CN111723646B (en) Method and device for remotely assisting in maintaining equipment
CN109782724B (en) Control method for preventing misoperation-locking and terminal equipment
CN104750095B (en) Regulation and control center inspection pilot system and method
CN107577223A (en) A kind of nuclear power plant's analog control system digitizes improved checking system
CN109117526A (en) One kind being suitable for mechanical system maintenance of equipment and guides data record and analysis system
CN110175736B (en) Automatic card disassembling and hanging method for power system regulation and control center
CN112529445A (en) Scheduling power failure and recovery condition anti-misoperation method and system based on artificial intelligence
CN106126422B (en) A kind of hydroenergy storage station control software automatic debugging system and method
CN111193968A (en) Verification method, debugging verification host, monitoring host and system of remote signaling information
CN112186739B (en) Sequential control operation order non-power-outage checking method and system
CN105356597A (en) Intensive management and control system for unmanned substation
CN106451788A (en) Method for remotely controlling and operating dispatching automation systems by aid of remote-control safety strategy module
CN113629878B (en) Remote control verification method and system for three-remote switch of power distribution network
CN114691488A (en) Automatic testing system and method for interlocking system
CN114358627A (en) Electric power operation and maintenance management system and operation and maintenance method thereof
CN114977481A (en) Relay protection device control method and system based on block chain technology
CN103647349A (en) Intelligent control method of automation system of centralized control station
CN115001133B (en) Intelligent power-off and power-on switching operation method and system in traction power supply system
CN113806909B (en) Scene selection method and device for nuclear power comprehensive scene verification, and nuclear power comprehensive scene verification method and system
Gao et al. An Edge Computing-Based Paltform of Railway Signalling System On-site Digital Smart Test
CN111092488B (en) Method and system for programmed operation of distribution equipment based on flow
US20240153657A1 (en) Device for controlling a plurality of nuclear reactors

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant