CN110130922A - A kind of construction method of line tunnel portal - Google Patents

A kind of construction method of line tunnel portal Download PDF

Info

Publication number
CN110130922A
CN110130922A CN201910546808.2A CN201910546808A CN110130922A CN 110130922 A CN110130922 A CN 110130922A CN 201910546808 A CN201910546808 A CN 201910546808A CN 110130922 A CN110130922 A CN 110130922A
Authority
CN
China
Prior art keywords
construction
portal
hole
tunnel
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910546808.2A
Other languages
Chinese (zh)
Inventor
李凤远
杨延栋
韩伟锋
陈馈
张兵
杨振兴
张合沛
高会中
褚长海
许华国
任颖莹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Key Laboratory of Shield Machine and Boring Technology
China Railway Tunnel Group Co Ltd CRTG
Original Assignee
State Key Laboratory of Shield Machine and Boring Technology
China Railway Tunnel Group Co Ltd CRTG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Key Laboratory of Shield Machine and Boring Technology, China Railway Tunnel Group Co Ltd CRTG filed Critical State Key Laboratory of Shield Machine and Boring Technology
Priority to CN201910546808.2A priority Critical patent/CN110130922A/en
Publication of CN110130922A publication Critical patent/CN110130922A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/14Layout of tunnels or galleries; Constructional features of tunnels or galleries, not otherwise provided for, e.g. portals, day-light attenuation at tunnel openings
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/23Dune restoration or creation; Cliff stabilisation

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Civil Engineering (AREA)
  • Architecture (AREA)
  • Geology (AREA)
  • General Engineering & Computer Science (AREA)
  • Paleontology (AREA)
  • Environmental & Geological Engineering (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention discloses a kind of construction methods of line tunnel portal, comprising the following steps: carries out stage excavation to hole using excavator in the face-upward slope peripheral hardware intercepting ditch at construction hole and gutter;Open cut tunnel and portal section are from top to bottom carried out using hand fit's excavator;When excavating absolute altitude corresponding to dark hole advance support, advance support construction is carried out immediately;Before start tunneling, route two sides set reinforcing pile respectively at the upright excavation face of light and shade boundary;Portal construction is carried out after the completion of open cut tunnel or lining of tunnel portal section.In the construction method, first in construction hole face-upward slope peripheral hardware intercepting ditch, gutter, washing away to avoid side slope causes Falling Rocks, unstability to collapse.In the construction process, it carries out slope surface spray concrete protective layer to be connected with former slope surface, prevents slope surface weathering, cause soil erosion.

Description

A kind of construction method of line tunnel portal
Technical field
The present invention relates to Shield Construction Technique fields, more particularly, to a kind of construction method of line tunnel portal.
Background technique
Shield is a kind of advanced engineering machinery quickly built for tunnel, with the continuous increasing of domestic Metro Tunnel Add, the operating condition of shield-tunneling construction becomes increasingly complex.
In geology construction, it can be related to constructing to the stratum of different geological conditions, shield-tunneling construction is usually according to ground The hardness of layer divides, including ground consisting of hard rock boring mode and soft rock strata boring mode.
During constructing tunnel, entrance construction is particularly important, and rainwater washes away hole, is easy to cause Falling Rocks, loses It is steady to collapse.With the weathering of hole slope surface, water and soil stream is easily caused.
The above-mentioned accident for how avoiding hole is those skilled in the art's technical problem urgently to be solved.
Summary of the invention
In order to solve the above technical problems, the object of the present invention is to provide a kind of construction methods of line tunnel portal.
The application provides a kind of construction method of line tunnel portal, comprising the following steps:
S1: face-upward slope peripheral hardware intercepting ditch and gutter at construction hole;
S2: stage excavation is carried out to hole using excavator;
S3: open cut tunnel and portal section are from top to bottom carried out using hand fit's excavator;
S4: when excavating absolute altitude corresponding to dark hole advance support, advance support construction is carried out immediately;
S5: before start tunneling, route two sides set reinforcing pile respectively at the upright excavation face of light and shade boundary;
S6: portal construction is carried out after the completion of open cut tunnel or lining of tunnel portal section.
Optionally, in step S4, in conjunction with side slope landform, slope surface anchor pole, steel mesh spray concrete as provisional protection;Bian Yang Slope brush slope is layered progress from top to bottom, carries out anchoring stock net-spraying supporting.
Optionally, in step S5, hole earthwork evacuation, which reaches, forms step at tunnel mileage, performs dark hole set arch and peace Leading truck is filled, lead pipe-shed support is performed on step, tunnel cutting is carried out after the completion of Shed-pipe Advanced Support performs.
Optionally, it in step S5, is excavated into hole section and keeps short drilling depth, weak blast, strong supporting, just sprayed concrete after excavation, use Steel arch-shelf assembling machine erects steelframe, sprays concrete again after installation system anchor pole, linked network.
Optionally, in step S3, open cut tunnel carries out base treatment after the completion of excavating, and after base bearing capacity reaches predetermined value, applies Make inverted arch, after inverted arch concrete final set, fills concrete.
Optionally, in step S6, portal headwall and aileron concrete placing use bracket and custom built forms, and pumping concrete enters mould;Hole After the completion of door, hole waterproof and water drainage system is performed.
Technical solution of the present invention has the advantage that compared with prior art
In the construction method, first in construction hole face-upward slope peripheral hardware intercepting ditch, gutter, washing away to avoid side slope leads to side Slope falling rocks, unstability are collapsed.In the construction process, it carries out slope surface spray concrete protective layer to be connected with former slope surface, prevents slope surface weathering, cause Soil erosion.
Specific embodiment
It is described in detail below in conjunction with specific embodiment.It should be understood that specific embodiment party described herein Formula is merely to illustrate and explain the present invention, and is not intended to restrict the invention.
In a kind of specific embodiment, the present invention provides a kind of construction method of line tunnel portal, including it is following Step:
Step S1: face-upward slope peripheral hardware intercepting ditch and gutter at construction hole;
Step S2: stage excavation is carried out to hole using excavator;
Step S3: open cut tunnel and portal section are from top to bottom carried out using hand fit's excavator;
Step S4: when excavating absolute altitude corresponding to dark hole advance support, advance support construction is carried out immediately;
Step S5: before start tunneling, route two sides set reinforcing pile respectively at the upright excavation face of light and shade boundary;
Step S6: portal construction is carried out after the completion of open cut tunnel or lining of tunnel portal section.
In the construction method, first in construction hole face-upward slope peripheral hardware intercepting ditch, gutter, washes away and lead to avoid side slope Falling Rocks, unstability are caused to collapse.In the construction process, it carries out slope surface spray concrete protective layer to be connected with former slope surface, prevents slope surface weathering, Cause soil erosion.
In a kind of specific embodiment, in step S4, in conjunction with side slope landform, slope surface anchor pole, steel mesh, spray concrete as Provisional protection;Face-upward slope brush slope is layered progress from top to bottom, carries out anchoring stock net-spraying supporting.
In conjunction with side slope landform degree of stability, slope surface anchor pole, steel mesh, spray concrete are as provisional protection, to ensure peace of constructing Entirely.
Face-upward slope brush slope is layered progress from top to bottom, and every 2~3m of layer height carries out anchoring stock net-spraying supporting with excavating in time. It carries out slope surface spray concrete protective layer to be connected with former slope surface, prevents slope surface weathering, cause soil erosion, side slope protection is caused to be damaged It is bad.Cut-and-cover tunnel, portal excavate, and avoid carrying out in the rainy day.
In another specific embodiment, in step S5, hole earthwork evacuation, which reaches, forms step at tunnel mileage, Dark hole set arch and installation leading truck are performed, lead pipe-shed support is performed on step, hole is carried out after the completion of Shed-pipe Advanced Support performs Body excavates.
Further, it in step S5, is excavated into hole section and keeps short drilling depth, weak blast, strong supporting, just sprayed concrete after excavation, adopt Steelframe is erected with steel arch-shelf assembling machine, sprays concrete again after installation system anchor pole, linked network.
It is excavated into hole section and keeps short drilling depth, weak blast, strong supporting, quick-fried using manually boring using operation platform, excavator is matched It attaches together carrier aircraft and digs dress, spray concrete carries out in two times, that is, just spray after excavating erects steelframe, installation system anchor using steel arch-shelf assembling machine It sprays after bar, linked network, closes in time again, guarantee supporting quality.
In above-mentioned each specific embodiment, in step S3, open cut tunnel carries out base treatment, base bearing capacity after the completion of excavating After reaching predetermined value, inverted arch is applied, after inverted arch concrete final set, fills concrete.
Open cut tunnel lining cutting is after the completion of inverted arch is filled from light and shade hole intersection to the lining cutting of tunnel portal direction.Open cut tunnel arch wall lining cutting It is all made of formwork jumbo and makees internal model, combined steel makees external mold, disposable form.Open cut tunnel lining cutting and tunnel portal construction terminate The backfill construction of hole top is carried out afterwards.Open cut tunnel backfills placement in layers after the completion of waterproof layer applies, and left and right alternating is symmetrical to backfill.
Specifically, portal headwall and aileron concrete placing use bracket and custom built forms, and pumping concrete enters mould in step S6;Hole After the completion of door, hole waterproof and water drainage system is performed.
Portal construction carries out after the completion of open cut tunnel or lining of tunnel portal section;Portal headwall and aileron concrete placing using bracket and are determined Pallet, concrete are pumped into mould, poker vibrator vibrates, and presses using automatic gauge blending station production outside hole, the transport of concrete transport vehicle It is required that carrying out the maintenance work of bricklaying.
A kind of specific embodiment is as follows:
Hole cubic metre of earth uses excavator stage excavation, and dump truck is transported to spoil disposal area;The cubic meter of stone controls weak blast using shallow bore hole, excavates Machine or loading machine dress quarrel, dump truck are transported to spoil disposal area.
Cut-and-cover tunnel, portal excavate before, first construction hole face-upward slope outside cut, gutter, washed away to avoid side slope, Falling Rocks, unstability are caused to collapse.Open cut tunnel and portal section are excavated from top to bottom to be carried out using hand fit's excavator.Meet individually compared with Big boulder or a small amount of hard rock, air drill drilling, micro- dose disintegrate, and pneumatic pick repairs chisel profile or non-electric control photoface exploision, must not disturb Dynamic side slope, influences stability of slope.Loading machine or excavator dress quarrel, dump truck transport directly to required location and unload quarrel.Side slope is opened It digs the gradient and presses design drawing slope, when excavating absolute altitude corresponding to dark hole advance support, carry out advance support construction immediately.In conjunction with side Hillside fields shape degree of stability, slope surface anchor pole, steel mesh, spray concrete are as provisional protection, to ensure construction safety.
Face-upward slope brush slope is layered progress from top to bottom, and every 2~3m of layer height carries out anchoring stock net-spraying supporting with excavating in time. It carries out slope surface spray concrete protective layer to be connected with former slope surface, prevents slope surface weathering, cause soil erosion, side slope protection is caused to be damaged It is bad.Cut-and-cover tunnel, portal excavate, and avoid carrying out in the rainy day.
Before start tunneling, stablize to ensure that slope is faced upward in outlet, route two sides set No. 1 respectively at the upright excavation face of light and shade boundary With No. 2 pre-reinforcement stakes, No. 1 stake diameter 3.0m × 3.0m, No. 2 stake diameter 3.5m × 2.5m, long stake is 26m, has been performed to hole stake Finish and hole excavation construction can be carried out after reaching design strength.
Hole earthwork evacuation, which reaches, forms step at tunnel mileage, dark hole set arch and installation leading truck are performed, in step On perform lead pipe-shed support, tunnel cutting is carried out after the completion of Shed-pipe Advanced Support performs.
It is excavated into hole section and keeps short drilling depth, weak blast, strong supporting, quick-fried using manually boring using operation platform, excavator is matched It attaches together carrier aircraft and digs dress, spray concrete carries out in two times, that is, just spray after excavating erects steelframe, installation system anchor using steel arch-shelf assembling machine It sprays after bar, linked network, closes in time again, guarantee supporting quality.
Open cut tunnel carries out base treatment after the completion of excavating, base bearing capacity can apply inverted arch, filling concrete after reaching requirement, fill out Concrete placings are filled to carry out after inverted arch concrete final set.
Open cut tunnel lining cutting is after the completion of inverted arch is filled from light and shade hole intersection to the lining cutting of tunnel portal direction.Open cut tunnel arch wall lining cutting It is all made of formwork jumbo and makees internal model, combined steel makees external mold, disposable form.Open cut tunnel lining cutting and tunnel portal construction terminate The backfill construction of hole top is carried out afterwards.Open cut tunnel backfills placement in layers after the completion of waterproof layer applies, and left and right alternating is symmetrical to backfill.
Portal construction carries out after the completion of open cut tunnel or lining of tunnel portal section;Portal headwall and aileron concrete placing using bracket and are determined Pallet, concrete are pumped into mould, poker vibrator vibrates, and presses using automatic gauge blending station production outside hole, the transport of concrete transport vehicle It is required that carrying out the maintenance work of bricklaying.After the completion of portal, hole waterproof and water drainage system is performed in time.
The construction method of line tunnel portal provided by the present invention is described in detail above.Tool used herein Principle and implementation of the present invention are described for body example, the above embodiments are only used to help understand this hair Bright method and its core concept.It should be pointed out that for those skilled in the art, not departing from the present invention , can be with several improvements and modifications are made to the present invention under the premise of principle, these improvement and modification also fall into right of the present invention It is required that protection scope in.

Claims (6)

1. a kind of construction method of line tunnel portal, which comprises the following steps:
S1: face-upward slope peripheral hardware intercepting ditch and gutter at construction hole;
S2: stage excavation is carried out to hole using excavator;
S3: open cut tunnel and portal section are from top to bottom carried out using hand fit's excavator;
S4: when excavating absolute altitude corresponding to dark hole advance support, advance support construction is carried out immediately;
S5: before start tunneling, route two sides set reinforcing pile respectively at the upright excavation face of light and shade boundary;
S6: portal construction is carried out after the completion of open cut tunnel or lining of tunnel portal section.
2. the construction method of line tunnel portal as described in claim 1, which is characterized in that in step S4, in conjunction with side slope landform, Slope surface anchor pole, steel mesh spray concrete as provisional protection;Face-upward slope brush slope is layered progress from top to bottom, carries out anchoring stock net-spraying branch Shield.
3. the construction method of line tunnel portal as claimed in claim 2, which is characterized in that in step S5, the hole cubic metre of earth and stone is opened It digs to reach and forms step at tunnel mileage, perform dark hole set arch and installation leading truck, lead pipe-shed support is performed on step, Shed-pipe Advanced Support carries out tunnel cutting after the completion of performing.
4. the construction method of the line tunnel portal as described in claim 3, which is characterized in that in step S5, excavated into hole section It keeps short drilling depth, weak blast, strong supporting, concrete is just sprayed after excavation, steelframe is erected using steel arch-shelf assembling machine, installation system anchor pole, Concrete is sprayed after linked network again.
5. such as the construction method of the described in any item line tunnel portals of Claims 1-4, which is characterized in that in step S3, open cut tunnel Base treatment is carried out after the completion of excavating, after base bearing capacity reaches predetermined value, applies inverted arch, after inverted arch concrete final set, fills concrete.
6. the construction method of the line tunnel portal as described in claim 5, which is characterized in that in step S6, portal headwall and Aileron concrete placing uses bracket and custom built forms, and pumping concrete enters mould;After the completion of portal, hole waterproof and water drainage system is performed.
CN201910546808.2A 2019-06-24 2019-06-24 A kind of construction method of line tunnel portal Pending CN110130922A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910546808.2A CN110130922A (en) 2019-06-24 2019-06-24 A kind of construction method of line tunnel portal

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910546808.2A CN110130922A (en) 2019-06-24 2019-06-24 A kind of construction method of line tunnel portal

Publications (1)

Publication Number Publication Date
CN110130922A true CN110130922A (en) 2019-08-16

Family

ID=67578974

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910546808.2A Pending CN110130922A (en) 2019-06-24 2019-06-24 A kind of construction method of line tunnel portal

Country Status (1)

Country Link
CN (1) CN110130922A (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110424460A (en) * 2019-08-22 2019-11-08 中铁隧道集团三处有限公司 A kind of tunnel open excavation construction technology
CN110645003A (en) * 2019-10-17 2020-01-03 中铁二局集团有限公司 Completely weathered granite bias steep slope tunnel entry construction method
CN110863838A (en) * 2019-12-11 2020-03-06 湖北省路桥集团有限公司 Complex weak surrounding rock tunnel entry structure and construction method
CN110939455A (en) * 2019-12-18 2020-03-31 浙江大学城市学院 Construction method of tunnel portal structure
CN111472811A (en) * 2020-04-17 2020-07-31 中国人民解放军63921部队 Assembled integral GFRP-framework concrete mouth lining structure for rapid repair of tunnel mouth and rapid repair method
CN111926856A (en) * 2020-07-01 2020-11-13 中铁二院重庆勘察设计研究院有限责任公司 Tunnel entering construction method based on longitudinal anti-skid open cut tunnel structure
CN112901204A (en) * 2021-02-25 2021-06-04 中铁二十五局集团第五工程有限公司 Safe construction method for cliff tunnel
CN114086969A (en) * 2021-11-30 2022-02-25 广西路桥工程集团有限公司 Tunnel entering construction method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104278993A (en) * 2013-07-11 2015-01-14 福州市规划设计研究院 Construction method of unsymmetrical loading tunnel heterotropic hole
CN105156121A (en) * 2015-10-08 2015-12-16 中铁二十五局集团第五工程有限公司 Construction method of large-cross section loess tunnel cave entering shallow buried section
CN207598248U (en) * 2017-12-11 2018-07-10 中铁二院成都勘察设计研究院有限责任公司 A kind of Mountainous high speed railway tunnel protects bridge open-cut tunnel structure

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104278993A (en) * 2013-07-11 2015-01-14 福州市规划设计研究院 Construction method of unsymmetrical loading tunnel heterotropic hole
CN105156121A (en) * 2015-10-08 2015-12-16 中铁二十五局集团第五工程有限公司 Construction method of large-cross section loess tunnel cave entering shallow buried section
CN207598248U (en) * 2017-12-11 2018-07-10 中铁二院成都勘察设计研究院有限责任公司 A kind of Mountainous high speed railway tunnel protects bridge open-cut tunnel structure

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110424460A (en) * 2019-08-22 2019-11-08 中铁隧道集团三处有限公司 A kind of tunnel open excavation construction technology
CN110645003A (en) * 2019-10-17 2020-01-03 中铁二局集团有限公司 Completely weathered granite bias steep slope tunnel entry construction method
CN110863838A (en) * 2019-12-11 2020-03-06 湖北省路桥集团有限公司 Complex weak surrounding rock tunnel entry structure and construction method
CN110863838B (en) * 2019-12-11 2021-08-20 湖北省路桥集团有限公司 Complex weak surrounding rock tunnel entry structure and construction method
CN110939455A (en) * 2019-12-18 2020-03-31 浙江大学城市学院 Construction method of tunnel portal structure
CN111472811A (en) * 2020-04-17 2020-07-31 中国人民解放军63921部队 Assembled integral GFRP-framework concrete mouth lining structure for rapid repair of tunnel mouth and rapid repair method
CN111472811B (en) * 2020-04-17 2021-06-01 中国人民解放军63921部队 Assembled integral GFRP-framework concrete mouth lining structure for rapid repair of tunnel mouth and rapid repair method
CN111926856A (en) * 2020-07-01 2020-11-13 中铁二院重庆勘察设计研究院有限责任公司 Tunnel entering construction method based on longitudinal anti-skid open cut tunnel structure
CN112901204A (en) * 2021-02-25 2021-06-04 中铁二十五局集团第五工程有限公司 Safe construction method for cliff tunnel
CN114086969A (en) * 2021-11-30 2022-02-25 广西路桥工程集团有限公司 Tunnel entering construction method
CN114086969B (en) * 2021-11-30 2024-02-20 广西路桥工程集团有限公司 Tunnel entering construction method

Similar Documents

Publication Publication Date Title
CN110130922A (en) A kind of construction method of line tunnel portal
CN102606162B (en) Quick construction method for weak surrounding rock shallowly-buried easily-collapsed area of tunnel
CN109594564A (en) A kind of anti-collapse construction method of Metro Deep Excavation open cut
CN101864960A (en) Carst region double-arch road tunnel construction method
CN108005660A (en) A kind of Optimization of Expressway Tunnel Construction method
CN107842368A (en) The non-quick-fried excavation technology of city tunnel Drilling milling mechanical combination
CN110107310A (en) A kind of construction method at tunnel slope hole
CN107023300A (en) A kind of use canopy, which is defended the doctrine, builds the construction method of subway station
CN109322330A (en) A kind of light and dark digging combination Metro Station Structure avoiding housing demolition and its construction method
CN111101540B (en) Construction method for passing existing electric power tunnel on open cut tunnel
CN109778869A (en) Foundation ditch construction method
CN105239598A (en) Integral sinking construction method for well-type full-automatic stereo garage
CN102505704A (en) Large open caisson construction method in soft geological shaft
CN108316339A (en) A kind of construction method of water penetration geology large size arch bridge base
CN111206937A (en) Pile group construction method for removing intruding main body structure in shield interval
CN109736827A (en) The method that city underground ground consisting of hard rock service channel high pressure gas expansion fracturing is excavated
CN107503755A (en) A kind of construction method for exempting from button arch flat-top cavern-pile method construction subway station
CN108625879A (en) Mountain Tunnels half-open and half-hidden structure and its construction method
CN109488313A (en) V-level surrounding rock micro-step excavation construction process
CN110284885A (en) Shield inspection-pit construction method
CN110259490A (en) A kind of Underground Subway Station construction method
CN106121659A (en) The narrow-bore tunnel excavation method of major urban arterial highway upper-soft lower-hard ground is worn under one
CN110847929B (en) Tunnel portal section pre-reinforcing and excavating construction method based on partition blasting
CN102808627A (en) Underground excavation construction method of steel pipe shed
CN110821500B (en) Large-section tunnel excavation and support construction method for penetrating through earth-rock boundary stratum

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190816