CN110107310A - A kind of construction method at tunnel slope hole - Google Patents

A kind of construction method at tunnel slope hole Download PDF

Info

Publication number
CN110107310A
CN110107310A CN201910369051.4A CN201910369051A CN110107310A CN 110107310 A CN110107310 A CN 110107310A CN 201910369051 A CN201910369051 A CN 201910369051A CN 110107310 A CN110107310 A CN 110107310A
Authority
CN
China
Prior art keywords
hole
ductule
slope
tunnel
carrying
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910369051.4A
Other languages
Chinese (zh)
Inventor
陈继
林晓
高国庆
陈航博
曾思杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
In Sanhang (xiamen) Engineering Co Ltd
China Construction Third Engineering Bureau Co Ltd
CCCC Third Harbor Engineering Co Ltd Xiamen Branch
Original Assignee
In Sanhang (xiamen) Engineering Co Ltd
China Construction Third Engineering Bureau Co Ltd
CCCC Third Harbor Engineering Co Ltd Xiamen Branch
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by In Sanhang (xiamen) Engineering Co Ltd, China Construction Third Engineering Bureau Co Ltd, CCCC Third Harbor Engineering Co Ltd Xiamen Branch filed Critical In Sanhang (xiamen) Engineering Co Ltd
Priority to CN201910369051.4A priority Critical patent/CN110107310A/en
Publication of CN110107310A publication Critical patent/CN110107310A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B5/00Artificial water canals, e.g. irrigation canals
    • E02B5/02Making or lining canals
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/14Layout of tunnels or galleries; Constructional features of tunnels or galleries, not otherwise provided for, e.g. portals, day-light attenuation at tunnel openings

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • General Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Paleontology (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The invention discloses a kind of construction methods at tunnel slope hole, including following below scheme: intercepting ditch excavation is pushed up in hole, hole is excavated, hole side slope protection and hole advance support are constructed.When carrying out hole top intercepting ditch and excavating process, hoist excavation section by section and masonry from lower.When carrying out hole excavation process, hole cubic metre of earth is excavated using excavator cooperation dumper along excavation line, and manual amendment face-upward slope, hole face-upward slope face is excavated by design grade, carries out brush slope by design grade from top to bottom.Hole side slope protection process should carry out behind face-upward slope brush slope;When carrying out hole advance support construction process, using advanced tubule supporting and the following steps are included: ductule production, drilling, ductule jacking and slip casting.Construction method of the invention can create favorable conditions for constructing tunnel, it is ensured that construction safety shortens the constructing tunnel duration, reduces construction cost.

Description

A kind of construction method at tunnel slope hole
Technical field
The present invention relates to a kind of construction methods at tunnel slope hole.
Background technique
The highway, high speed railway construction in China flourish in recent years, generate a large amount of Tunnel Engineering therewith, and big Most highways, railway are generally routed along cheuch, therefore Unevenly-pressured shallow tunnel occupies sizable specific gravity in these Tunnel Engineering.Partially Pressure tunnel portal excavate be all the time geotechnical engineering industry a great problem, especially show that landform, geological environment are complicated Weak surrounding rock area, rock matter weakness, low bearing capacity, developmental joint fissure, structure are broken, and massif stability itself is poor, bias Tunnel portal section buried depth is extremely shallow, is disturbed when excavation to massif big, it is likely that cause tunnel side slopes slump, Tunnel Landslide, lining The problems such as building crack and tunnel overall offset threatens the safety of tunnel excavation personnel, influences the normal operation in tunnel, raw to the people Life property safety brings hidden trouble.Tunnel portal construction is the most important construction part in tunnel, and working procedure is more.Tunnel is logical It is often both ends, to increase working face and solving construction ventilation and construction transportation problem, usually at the intermediate position of major long tunnel An inclined shaft is cut as service gallery.Inclined shaft generally requires constructs in advance, creates conditions for construction.
Summary of the invention
A kind of construction method at tunnel slope hole is provided it is an object of the invention to overcome the deficiencies of existing technologies, it It can create favorable conditions for constructing tunnel, shorten the constructing tunnel duration, reduce construction cost.
The object of the present invention is achieved like this: a kind of construction method at tunnel slope hole, including following below scheme: hole top Intercepting ditch excavates;Hole is excavated, hole side slope protection and the construction of hole advance support;Wherein,
When carrying out the hole top intercepting ditch excavation process, hole top is applied in advance other than away from hole excavation line horizontal distance 5m Intercepting ditch, using hand excavation and it is artificial build, hoist and excavation section by section and built using M7.5 mortar flag stone from lower;It is cutting The gradient in ditch, which is greater than at 20%, is arranged chute, and the substrate of chute sets a platform every 2m;When chute is very long, using point Section is built, 5~10 meters of every segment length, joint waterproof material joint filling;
When carrying out the hole excavation process, hole cubic metre of earth is opened using excavator cooperation dumper along excavation line It digs, manual amendment face-upward slope, hole face-upward slope face is excavated by design grade, carries out brush slope by design grade from top to bottom; The open cut tunnel section cubic meter of stone is excavated using standing is weakened, and is excavated into after hole, timely 5~8m of lining cutting hole sections of open cut tunnel, concrete It is formed using tunneling boring one-time-concreting, arch is bent using fashioned iron, and abutment wall reinforces support using the lumps of wood, and template uses tunnel Special combination punching block, concrete are manually turned over and are shoveled into mould, with poker vibrator vibration compacting by interim blending station mixing;
When carrying out the hole side slope protection process, should immediately side, face upward slope brush slope after carry out;The side slope at hole uses Slope is excavated, slope ratio is 1:0.5;More than backfill face rattan protection is climbed using plantation, uses bolting and shotcreting with wire mesh below backfill face, spray anchor Net supporting parameter: injection C20 concrete with a thickness of 10cm, using 25 hollow grouting anchor of φ, rock-bolt length L=4m, anchor pole Arrangement spacing is 1.2m × 1.2m;The size of mesh opening of 8 steel mesh of φ is 20cm × 20cm;Construction finishes to be conserved in time;
When carrying out advance support construction process, using advanced tubule supporting and the following steps are included: ductule production, brill Hole, ductule jacking and slip casting;
When carrying out ductule making step, the length of ductule is 3.5m~6m, and the front end of ductule is made into sharp cone distal, tail Portion's welding φ 8mm reinforcing bar is put more energy into hoop, bores extravasating hole every 10~20cm on the tube wall of ductule, and the spacing of extravasating hole is 15cm, And be in quincunx interlaced arrangement, the diameter of extravasating hole is 6~8mm, and tail length is stayed not less than 30cm as not boring extravasating hole Only starch section;
When carrying out drill process, the position of surveying and locating pilot hole, when drill hole, strictly presses the outer limb that setting-out carries out pilot hole Degree is 5 °~15 °, and for pilot hole in 120 ° of tunnel arch range arrangement, the circumferential spacing of pilot hole is 40cm;The aperture ratio of pilot hole is small to lead Big 10~the 20mm or more of the diameter of pipe, the drilling deviation of pilot hole are not more than 10cm, and the depth of pilot hole is greater than the length of ductule;
When carrying out ductule jacking step, the sundries in pilot hole first is blown out with blower, then ductule is headed into air drill In pilot hole, the tail end protruded length of ductule is not less than 30cm, and tail portion welds together with steelframe;Ductule is along tunnel longitudinal direction The lap of splice is more than or equal to 1.0m;Conduit tail twines cotton yarn, so that ductule is fitted closely with pilot hole, and is blocked up aperture with cotton yarn Tightly;Jet thickness is around the concrete enclosing ductule of 5~8cm after ductule installation;
When carrying out slip casting step, cement grout pressure injection is entered by ductule using grouting pump;It is first rinsed in ductule before slip casting Deposit, from the bottom to top sequence carry out;Single hole grouting pressure reaches design requirement value, continue slip casting 10min and into slurry speed Slip casting terminates when to start to reach 80% or more of design grout absorption into 1/4 or grout absorption of slurry speed;The small of slurry has been infused to lead Pipe will block aperture immediately, prevent slurries from outflowing.
The construction method at above-mentioned tunnel slope hole, wherein the bolting and shotcreting with wire mesh is the following steps are included: set up branch Frame, drilling, slip casting, applies anchor pole, installation steel mesh, installation expansion joint divider, gunite concrete, conserves, takes cleaning slope surface Expansion joint divider, construction expansion joint out.
The construction method at above-mentioned tunnel slope hole, wherein right when carrying out the hole side, facing upward slope protection process The inadequate substrate of bearing capacity is changed using C15 concrete and is filled out.
The construction method at above-mentioned tunnel slope hole, wherein when carrying out the slip casting step of advance support construction process, Grouting parameter is as follows:
1) the water ash weight ratio of cement grout is 1:1;
2) grouting pressure: 0.5~1.0MPa.
The construction method at tunnel slope hole of the invention, simple process is quick, easy to operate, can be by constructing tunnel mistake Security risk in journey minimizes, and time effects are reduced to most short;It can create favorable conditions for constructing tunnel, it is ensured that construction peace Entirely, shorten the constructing tunnel duration, reduce construction cost.
Detailed description of the invention
Fig. 1 is the safeguard structure figure that uses in the construction method at tunnel slope hole of the invention;
Fig. 2 is the advance support section layout drawing that uses in the construction method at tunnel slope hole of the invention.
Specific embodiment
The present invention will be further described with reference to the accompanying drawings.
Please refer to Fig. 1 and Fig. 2, a kind of construction method at tunnel slope hole of the invention, including following below scheme: hole top is cut It excavates in ditch;Hole is excavated, and slope protection and the construction of hole advance support are faced upward in hole side.
When carrying out hole top intercepting ditch excavation process, applies hole top in advance other than away from hole excavation line horizontal distance 5m and intercept water Ditch, using hand excavation and it is artificial build, hoist and excavation section by section and built using M7.5 mortar flag stone from lower;It is cut on hole top The gradient in ditch, which is greater than at 20%, is arranged chute, and the substrate of chute sets a platform every 2m;When chute is very long, using point Section is built, 5~10 meters of every segment length, joint waterproof material joint filling;The downstream of hole top intercepting ditch connects with roadbed gutter, shape At good drainage system
When carrying out hole excavation process, hole cubic metre of earth is excavated using excavator cooperation dumper along excavation line, people Work modifies face-upward slope, and hole face-upward slope face is excavated by design grade, carries out brush slope, every excavation by design grade from top to bottom One layer should apply supporting according to design in time, prevent rain drop erosion from causing to come down;The open cut tunnel section cubic meter of stone is using decrease standing It is excavated, is excavated into after hole, timely 5~8m of lining cutting hole sections of open cut tunnel, concrete is formed using tunneling boring one-time-concreting, arch It is bent using fashioned iron, abutment wall reinforces support using the lumps of wood, and template uses tunnel special combination punching block, and concrete is by temporarily mixing With station mixing, manually turns over and shovel into mould, with poker vibrator vibration compacting;
Carry out hole side, face upward slope protection process when, should immediately side, face upward slope brush slope after carry out;The side slope at hole is used and is opened Slope is dug, slope ratio is 1:0.5;More than backfill face rattan protection is climbed using plantation, uses bolting and shotcreting with wire mesh, shot anchor net below backfill face Supporting parameter: injection C20 concrete with a thickness of 10cm, using 25 hollow grouting anchor 10 of φ, rock-bolt length L=4m, anchor pole Arrangement spacing is 1.2m × 1.2m;The size of mesh opening of 8 steel mesh 20 of φ is 20cm × 20cm;Construction finishes to be conserved in time; The substrate inadequate to bearing capacity is changed using C15 concrete and is filled out (see Fig. 1);
Bolting and shotcreting with wire mesh is the following steps are included: setting up bracket, cleaning slope surface, drilling, slip casting, applying anchor pole, installation reinforcing bar Net, gunite concrete, maintenance, takes out expansion joint divider, construction expansion joint at installation expansion joint divider.
When carrying out advance support construction process, using advanced tubule supporting and the following steps are included: ductule production, brill Hole, ductule jacking and slip casting;
When carrying out ductule making step, the length of ductule is 3.5m~6m, and the front end of ductule is made into sharp cone distal, tail Portion's welding φ 8mm reinforcing bar is put more energy into hoop, bores extravasating hole every 10~20cm on the tube wall of ductule, and in quincunx interlaced arrangement, The diameter of extravasating hole is 6~8mm, and tail length is stayed not less than 30cm as the only slurry section for not boring extravasating hole;
When carrying out drill process, the position of surveying and locating pilot hole, when drill hole, strictly presses the outer limb that setting-out carries out pilot hole Degree is 5 °~15 °, and for pilot hole in 120 ° of tunnel arch range arrangement, the circumferential space D of pilot hole is 40cm;The aperture ratio of pilot hole is small to lead Big 10~the 20mm or more of the diameter of pipe, the drilling deviation of pilot hole are not more than 10cm, and the depth of pilot hole is greater than the length of ductule;
When carrying out ductule jacking step, the sundries in pilot hole first is blown out with blower, then ductule is headed into air drill In pilot hole, the tail end protruded length of ductule is not less than 30cm, and to connect aperture valve and pipeline, tail portion is welded on steelframe Together;The lap of splice of the ductule along tunnel longitudinal direction is more than or equal to 1.0m;Ductule tail portion twines cotton yarn, so that ductule and pilot hole It fits closely, and with cotton yarn that aperture is stifled tight;The concrete enclosing ductule that jet thickness is 5~8cm after ductule installation Around;
When carrying out slip casting step, cement grout pressure injection is entered by ductule using grouting pump;Grouting parameter is as follows:
1) the water ash weight ratio of cement grout is 1:1;
2) grouting pressure: 0.5~1.0MPa;
The deposit in ductule is first rinsed before slip casting, sequence carries out from the bottom to top;Single hole grouting pressure, which reaches design, to be wanted Evaluation, continue slip casting 10min and into slurry speed be start into slurry speed 1/4 or grout absorption reach design grout absorption 80% and Slip casting terminates when above;The ductule for having infused slurry will block aperture immediately, prevent slurries from outflowing.
Above embodiments are used for illustrative purposes only, rather than limitation of the present invention, the technology people in relation to technical field Member, without departing from the spirit and scope of the present invention, can also make various transformation or modification, therefore all equivalent Technical solution also should belong to scope of the invention, should be limited by each claim.

Claims (4)

1. a kind of construction method at tunnel slope hole, including following below scheme: pushing up intercepting ditch and excavate in hole;Hole is excavated, hole side Face upward slope protection and the construction of hole advance support;It is characterized in that,
When carrying out the hole top intercepting ditch excavation process, applies hole top in advance other than away from hole excavation line horizontal distance 5m and intercept water Ditch, using hand excavation and it is artificial build, hoist and excavation section by section and built using M7.5 mortar flag stone from lower;In intercepting ditch The gradient be greater than at 20% chute be set, the substrate of chute sets a platform every 2m;When chute is very long, built using segmentation It builds, 5~10 meters of every segment length, joint waterproof material joint filling;
When carrying out the hole excavation process, hole cubic metre of earth is excavated using excavator cooperation dumper along excavation line, people Work modifies face-upward slope, and hole face-upward slope face is excavated by design grade, carries out brush slope by design grade from top to bottom;Open cut tunnel section The cubic meter of stone is excavated using standing is weakened, and is excavated into after hole, timely 5~8m of lining cutting hole sections of open cut tunnel, and concrete is using complete The molding of section one-time-concreting, arch are bent using fashioned iron, and abutment wall reinforces support using the lumps of wood, and template uses tunnel dedicated set Punching block is closed, concrete is manually turned over and shoveled into mould, with poker vibrator vibration compacting by interim blending station mixing;
When carrying out the hole side slope protection process, should immediately side, face upward slope brush slope after carry out;The side slope at hole is using excavation Slope, slope ratio are 1:0.5;More than backfill face rattan protection is climbed using plantation, uses bolting and shotcreting with wire mesh, shot anchor net branch below backfill face Protect parameter: injection C20 concrete with a thickness of 10cm, using 25 hollow grouting anchor of φ, rock-bolt length L=4m, anchor pole arrangement Spacing is 1.2m × 1.2m;The size of mesh opening of 8 steel mesh of φ is 20cm × 20cm;Construction finishes to be conserved in time;
Carry out advance support construction process when, using advanced tubule supporting and the following steps are included: ductule production, drilling, Ductule jacking and slip casting;
When carrying out ductule making step, the length of ductule is 3.5m~6m, and the front end of ductule is made into sharp cone distal, tail portion weldering It connects φ 8mm reinforcing bar to put more energy into hoop, bores extravasating hole every 10~20cm on the tube wall of ductule, the spacing of extravasating hole is 15cm, and is in Quincunx interlaced arrangement, the diameter of extravasating hole are 6~8mm, and tail length is stayed not less than 30cm as the only slurry for not boring extravasating hole Section;
When carrying out drill process, the position of surveying and locating pilot hole is strictly by the extrapolation angle that setting-out carries out pilot hole when drill hole 5 °~15 °, for pilot hole in 120 ° of tunnel arch range arrangement, the circumferential spacing of pilot hole is 40cm;The aperture ratio ductule of pilot hole Big 10~the 20mm or more of diameter, the drilling deviation of pilot hole are not more than 10cm, and the depth of pilot hole is greater than the length of ductule;
When carrying out ductule jacking step, the sundries in pilot hole first is blown out with blower, then ductule is headed into pilot hole with air drill In, the tail end protruded length of ductule is not less than 30cm, and tail portion welds together with steelframe;Overlap joint of the ductule along tunnel longitudinal direction Length is more than or equal to 1.0m;Conduit tail twines cotton yarn, so that ductule is fitted closely with pilot hole, and with cotton yarn that aperture is stifled tight;It is small Jet thickness is around the concrete enclosing ductule of 5~8cm after conduit installation;
When carrying out slip casting step, cement grout pressure injection is entered by ductule using grouting pump;It is heavy in ductule first to rinse before slip casting Product object, sequence carries out from the bottom to top;Single hole grouting pressure reaches design requirement value, continues slip casting 10min and is to open into speed is starched Slip casting terminates when beginning to reach 80% or more of design grout absorption into 1/4 or grout absorption of slurry speed;The ductule for having infused slurry is wanted Aperture is blocked immediately, prevents slurries from outflowing.
2. the construction method at tunnel slope hole according to claim 1, which is characterized in that the bolting and shotcreting with wire mesh includes Following steps: it sets up bracket, cleaning slope surface, drilling, slip casting, apply anchor pole, installation steel mesh, installation expansion joint divider, spray It penetrates concrete, maintenance, take out expansion joint divider, construction expansion joint.
3. the construction method at tunnel slope hole according to claim 1, which is characterized in that carry out the hole side, When facing upward slope protection process, the substrate inadequate to bearing capacity is changed using C15 concrete and is filled out.
4. the construction method at tunnel slope hole according to claim 1, which is characterized in that carrying out advance support construction When the slip casting step of process, grouting parameter is as follows:
1) the water ash weight ratio of cement grout is 1:1;
2) grouting pressure: 0.5~1.0MPa.
CN201910369051.4A 2019-05-05 2019-05-05 A kind of construction method at tunnel slope hole Pending CN110107310A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910369051.4A CN110107310A (en) 2019-05-05 2019-05-05 A kind of construction method at tunnel slope hole

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910369051.4A CN110107310A (en) 2019-05-05 2019-05-05 A kind of construction method at tunnel slope hole

Publications (1)

Publication Number Publication Date
CN110107310A true CN110107310A (en) 2019-08-09

Family

ID=67488223

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910369051.4A Pending CN110107310A (en) 2019-05-05 2019-05-05 A kind of construction method at tunnel slope hole

Country Status (1)

Country Link
CN (1) CN110107310A (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110778334A (en) * 2019-10-28 2020-02-11 湖北建科国际工程有限公司 Construction method of bias tunnel portal excavation protection structure
CN110939455A (en) * 2019-12-18 2020-03-31 浙江大学城市学院 Construction method of tunnel portal structure
CN111350512A (en) * 2020-04-16 2020-06-30 青岛市青排市政工程有限公司 Transverse hole underground excavation process method
CN111424483A (en) * 2020-04-29 2020-07-17 四川省交通勘察设计研究院有限公司 Short roadbed transition section structure between highway bridges and tunnels and construction method thereof
CN111577330A (en) * 2020-05-08 2020-08-25 平煤神马建工集团有限公司 Construction method for open channel section of large-section inclined shaft and high-strength combined template thereof
CN111608701A (en) * 2020-06-02 2020-09-01 中铁隧道局集团有限公司 Method for treating roof collapse of shallow tunnel entrance section
CN111648790A (en) * 2020-06-12 2020-09-11 安徽省公路桥梁工程有限公司 Shallow-buried bias tunnel entry structure and construction method
CN111663543A (en) * 2020-05-18 2020-09-15 中铁二院贵阳勘察设计研究院有限责任公司 Ear wall formula open cut tunnel structure of stake board formula
CN112127900A (en) * 2020-09-07 2020-12-25 中国水利水电第十四工程局有限公司 Construction method for hidden half-wall and half-arch protection structure of exposed arch of shallow-buried bias tunnel penetrating through accumulation body
CN113847038A (en) * 2021-09-18 2021-12-28 中电建铁路建设投资集团有限公司 Single-row steel pipe advanced grouting reinforcement method
CN111424483B (en) * 2020-04-29 2024-07-02 四川省交通勘察设计研究院有限公司 Short-circuit base transition section structure between expressway bridge tunnels and construction method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101260806A (en) * 2008-04-24 2008-09-10 重庆交通科研设计院 Preposition type opening construction method
CN102787844A (en) * 2012-07-19 2012-11-21 中铁十三局集团有限公司 Tunnel building method for heading pilot tunnel and inclined shaft on super long tunnel with small-diameter heading machine
CN103883328A (en) * 2014-03-20 2014-06-25 福州大学 Semi-covering semi-darkened construction method for separated tunnels downwards penetrating through high and steep V-shaped gully eccentric compression section
CN104818991A (en) * 2015-03-30 2015-08-05 中铁二十四局集团福建铁路建设有限公司 Construction method of residual slope wash tunnel with shallow cover and unsymmetrical pressure
CN107327308A (en) * 2017-07-13 2017-11-07 高军 A kind of Railway Tunnel waterproof method
KR20180007972A (en) * 2016-07-15 2018-01-24 박재현 Construction method for closed parallel tunnel and closed parallel tunnel using the same

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101260806A (en) * 2008-04-24 2008-09-10 重庆交通科研设计院 Preposition type opening construction method
CN102787844A (en) * 2012-07-19 2012-11-21 中铁十三局集团有限公司 Tunnel building method for heading pilot tunnel and inclined shaft on super long tunnel with small-diameter heading machine
CN103883328A (en) * 2014-03-20 2014-06-25 福州大学 Semi-covering semi-darkened construction method for separated tunnels downwards penetrating through high and steep V-shaped gully eccentric compression section
CN104818991A (en) * 2015-03-30 2015-08-05 中铁二十四局集团福建铁路建设有限公司 Construction method of residual slope wash tunnel with shallow cover and unsymmetrical pressure
KR20180007972A (en) * 2016-07-15 2018-01-24 박재현 Construction method for closed parallel tunnel and closed parallel tunnel using the same
CN107327308A (en) * 2017-07-13 2017-11-07 高军 A kind of Railway Tunnel waterproof method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
中铁一局五公司蒙河铁路工程项目经理部: "《屏边隧道斜井洞口施工方案》", 30 June 2018 *

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110778334A (en) * 2019-10-28 2020-02-11 湖北建科国际工程有限公司 Construction method of bias tunnel portal excavation protection structure
CN110939455A (en) * 2019-12-18 2020-03-31 浙江大学城市学院 Construction method of tunnel portal structure
CN111350512A (en) * 2020-04-16 2020-06-30 青岛市青排市政工程有限公司 Transverse hole underground excavation process method
CN111424483A (en) * 2020-04-29 2020-07-17 四川省交通勘察设计研究院有限公司 Short roadbed transition section structure between highway bridges and tunnels and construction method thereof
CN111424483B (en) * 2020-04-29 2024-07-02 四川省交通勘察设计研究院有限公司 Short-circuit base transition section structure between expressway bridge tunnels and construction method thereof
CN111577330A (en) * 2020-05-08 2020-08-25 平煤神马建工集团有限公司 Construction method for open channel section of large-section inclined shaft and high-strength combined template thereof
CN111663543A (en) * 2020-05-18 2020-09-15 中铁二院贵阳勘察设计研究院有限责任公司 Ear wall formula open cut tunnel structure of stake board formula
CN111608701B (en) * 2020-06-02 2022-04-26 中铁隧道局集团有限公司 Method for treating roof collapse of shallow tunnel entrance section
CN111608701A (en) * 2020-06-02 2020-09-01 中铁隧道局集团有限公司 Method for treating roof collapse of shallow tunnel entrance section
CN111648790A (en) * 2020-06-12 2020-09-11 安徽省公路桥梁工程有限公司 Shallow-buried bias tunnel entry structure and construction method
CN111648790B (en) * 2020-06-12 2023-03-14 安徽省公路桥梁工程有限公司 Shallow-buried bias tunnel entry structure and construction method
CN112127900A (en) * 2020-09-07 2020-12-25 中国水利水电第十四工程局有限公司 Construction method for hidden half-wall and half-arch protection structure of exposed arch of shallow-buried bias tunnel penetrating through accumulation body
CN113847038A (en) * 2021-09-18 2021-12-28 中电建铁路建设投资集团有限公司 Single-row steel pipe advanced grouting reinforcement method
CN113847038B (en) * 2021-09-18 2024-04-02 中电建铁路建设投资集团有限公司 Single-row steel pipe advanced grouting reinforcement method

Similar Documents

Publication Publication Date Title
CN110107310A (en) A kind of construction method at tunnel slope hole
CN104032758B (en) Extra-high reinforced construction method in discarded pit
WO2021223573A1 (en) Construction structure for communication and connection between newly added mined channel and existing station hall layer
CN104500077B (en) A kind of shallow-depth-excavation tunnel passes through cottage area construction method
CN105257301B (en) A kind of shallow-depth-excavation tunnel weak surrounding rock landslide reinforcing and processing method
CN110056369A (en) A kind of construction method at tunnel's entrance and exit hole
CN101408106B (en) Small tube shed pre-grouting method
CN105839643A (en) Tunnel in-hole construction method adopting foundation pit support
CN108005660A (en) A kind of Optimization of Expressway Tunnel Construction method
CN109736827B (en) Method for excavating urban subway hard rock stratum communication channel by high-pressure gas expansion fracturing
CN105715296A (en) Blowing sand backfill and grouting construction method of tunnel crossing coal mine goaf
CN102505704A (en) Large open caisson construction method in soft geological shaft
CN103758123A (en) Method for constructing protecting wall lining of cast-in-place manual hole digging pile
CN106049195A (en) Method for strengthening subgrade basement of existing high speed railway line
CN107023300A (en) A kind of use canopy, which is defended the doctrine, builds the construction method of subway station
CN102400694A (en) Reinforcement method for combined part of shield tunnel and mining-method tunnel
CN104763435A (en) Construction method of shallow-buried excavation type large cross section of tunnel in tail slag filling area
CN110284885A (en) Shield inspection-pit construction method
CN110259490A (en) A kind of Underground Subway Station construction method
CN206888992U (en) A kind of water-bed mine shield tunnel combination docking structure form
CN115539048A (en) Construction method for shallow-buried bias tunnel portal
CN107514266A (en) Shield export & import bolt anchorage soil body construction method
CN107165641B (en) High inclination-angle ladder way opposite direction excavating construction method in thin layer breaking up hard rock stratum
CN109630157A (en) A kind of regulator control system of Tunnel Engineering and ground water regime
CN104453915A (en) Large-section vertical shaft pre-grouting reinforcement quick excavation method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190809