CN110070343A - A kind of prospecting project management system and method - Google Patents

A kind of prospecting project management system and method Download PDF

Info

Publication number
CN110070343A
CN110070343A CN201910333237.4A CN201910333237A CN110070343A CN 110070343 A CN110070343 A CN 110070343A CN 201910333237 A CN201910333237 A CN 201910333237A CN 110070343 A CN110070343 A CN 110070343A
Authority
CN
China
Prior art keywords
project
data
prospecting
submodule
module
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910333237.4A
Other languages
Chinese (zh)
Inventor
黄佳铭
刘伟
张庆华
楼康明
周志远
朱晓强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
GUANGZHOU INSTITUTE OF GEOLOGICAL SURVEY
Original Assignee
Guangzhou Urban Planning Survey and Design Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Urban Planning Survey and Design Institute filed Critical Guangzhou Urban Planning Survey and Design Institute
Priority to CN201910333237.4A priority Critical patent/CN110070343A/en
Publication of CN110070343A publication Critical patent/CN110070343A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/109Time management, e.g. calendars, reminders, meetings or time accounting

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Operations Research (AREA)
  • Economics (AREA)
  • Marketing (AREA)
  • Data Mining & Analysis (AREA)
  • Quality & Reliability (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a kind of prospecting project management systems, are applied to Construction Technology field, including project establishes module, data inquiry module and Schedule monitoring module;The project establishes module, establishes prospecting project for obtaining the Project Management Information of prospecting project, and according to the Project Management Information;The data inquiry module is fed back for the data query to user;The Schedule monitoring module, feeds back for the progress queries to user;It is also used to obtain project data, and according to the project data, updates current project progress;It is also used to be calculated according to the project data, obtains the project actual construction time, and according to the project actual construction time and the project plan duration, generate and issue duration abnormity prompt.The invention also discloses a kind of prospecting project management methods, are able to achieve the informationization of prospecting project management, can effectively improve project management efficiency and work quality, accelerate project process.

Description

A kind of prospecting project management system and method
Technical field
The present invention relates to Construction Technology field more particularly to a kind of prospecting project management systems and method.
Background technique
With the needs of social development, engineering construction cause is constantly developing, in order to guarantee the smooth head of engineering construction First need to carry out is exactly geotechnical engineering investigation.
In geotechnical engineering investigation project management process, project process fully understands that project performance provides for manager Most direct information, at present generally by relevant staff voluntarily statistical work situation, after obtaining its job schedule, mouth Head is reported and notifies project manager, project manager again to the job schedule got carry out collect statistics obtain project into Degree.
Inventor has found in the practice of the invention, in existing geotechnical engineering investigation project management process, by It in artificial statistical work progress and project process, is influenced vulnerable to people's subjective consciousness, is easy error, and geotechnical engineering investigation project It is related to cross-region construction, and work post is various, and oral report may result in information transmitting and omit and not in time, so as to cause project The efficiency of management and work quality reduce, and influence project process.
Summary of the invention
The embodiment of the present invention provides a kind of prospecting project management system and method, is able to achieve the information of prospecting project management Change, project management efficiency and work quality can be effectively improved, accelerates project process.
To achieve the above object, the embodiment of the invention provides a kind of prospecting project management systems, including project to establish mould Block, data inquiry module and Schedule monitoring module;
The project establishes module, believes for obtaining the Project Management Information of prospecting project, and according to the project management Breath establishes prospecting project;Wherein, the Project Management Information includes the project plan duration, and the project plan duration includes field operation Plan time is write in plan time, data processing plan time and report;
The data inquiry module is fed back for the data query to user;
The Schedule monitoring module, feeds back for the progress queries to user;It is also used to obtain project data, and root According to the project data, current project progress is updated;It is also used to be calculated according to the project data, obtains the practical work of project Phase, and according to the project actual construction time and the project plan duration, it generates and issues duration abnormity prompt;Wherein, described Project data includes field data, interior industry data and exploration report, and the project process includes field operation progress, data processing Progress is write in progress and report, and the project actual construction time includes field operation actual construction time, data processing actual construction time and report Announcement writes the actual construction time.
As an improvement of the above scheme, the Project Management Information further includes prospecting project information, exploratory techniques requirement, people Member and facility information and prospecting project work amount.
As an improvement of the above scheme, the data inquiry module is specifically used for obtaining the data query instruction of user, and It is inquired according to data query instruction, obtains and show corresponding project data;Wherein, the data query instruction packet Including field data inquiry instruction, the instruction of interior industry data query and exploration report inquiry instruction, the project data includes field operation number According to, interior industry data and exploration report.
As an improvement of the above scheme, the Schedule monitoring module includes that project process inquires submodule, project process more New submodule, actual construction time acquisition submodule and duration abnormity prompt submodule;
The project process inquires submodule, and the progress queries for obtaining user instruct, and according to the progress queries Instruction is inquired, and is obtained and is shown corresponding project process;Wherein, the progress queries instruction includes that field operation progress queries refer to It enables, progress inquiry instruction is write in the instruction of data processing progress queries and report;
The project process updates submodule, for obtaining project data, and according to the project data, updates currentitem Mesh progress;
The actual construction time acquisition submodule obtains the project actual construction time for being calculated according to the project data;
The duration abnormity prompt submodule, for comparing the project actual construction time and the project plan duration It is right, when detecting that the project actual construction time is greater than the project plan duration, generates and issue duration abnormity prompt.
As an improvement of the above scheme, the system also includes Data storage modules and data check module;
The Data storage module carries out filing processing for the project achievement to prospecting project;
The data check module, it is one or more in the project achievement for obtaining and showing;It is also used to download The project achievement it is one or more.
As an improvement of the above scheme, the system also includes user management modules and user log-in block;
The user management module, for managing the registration and unregistration of user account;Be also used to the user account into The distribution of row permission;
The user log-in block is verified for obtaining the log-on message of user, and to the log-on message.
As an improvement of the above scheme, the system also includes opinion interactive modules;
The opinion interactive module, including school examine submodule and reply submodule;
Submodule is examined in the school, for obtaining the authority information of listed user account, when the power of the user account It when limit information meets preset authority information, obtains school and examines information, information is examined according to the school, generate school and examine opinion, and send To corresponding user account;
The answer submodule, for obtaining and showing that opinion is examined in school relevant to listed user account;It is also used to Reply message is obtained, according to the reply message, opinion is generated and replies, and be sent to corresponding user account;
Submodule is examined in the school, is also used to obtain and show that opinion relevant to listed user account replies.
As an improvement of the above scheme, the system also includes work grading modules;
The work grading module, for obtaining the authority information of listed user account, when the user account When authority information meets preset authority information, score information is obtained, and according to institute's scoring information, generates commenting for prospecting project Divide result.
As an improvement of the above scheme, the system also includes locating and monitoring modules;
The locating and monitoring module includes personnel positioning submodule, locating query submodule and attendance monitoring submodule;
The personnel positioning submodule, for obtaining the location information of each specified user account in real time;
The locating query submodule, the locating query for obtaining user are instructed, are instructed according to the locating query, The real-time position information of corresponding user account is shown on electronic map;
The attendance monitoring submodule, for monitoring whether current time is within the scope of the predetermined time, when monitoring to work as When the preceding moment is in preset time range, judge whether the real-time position information of each specified user account is in preset In position range, if it is not, then generating the attendance abnormity prompt of the user account, and it is sent to pre-set user account.
The embodiment of the invention also provides a kind of prospecting project management methods, are applied to described in any item prospecting items as above Mesh management system, comprising:
The Project Management Information that module obtains prospecting project is established by project, and is established according to the Project Management Information Prospecting project;Wherein, the Project Management Information includes the project plan duration, and the project plan duration includes field operation plan work Plan time is write in phase, data processing plan time and report;
It is fed back by data query of the data inquiry module to user;
It is fed back by progress queries of the Schedule monitoring module to user;
Project data is obtained by the Schedule monitoring module, and according to the project data, updates current project progress; Wherein, the project data includes field data, interior industry data and exploration report, and the project process includes field operation progress, interior Progress is write in industry data processing progress and report;
It is calculated by the Schedule monitoring module according to the project data, obtains the project actual construction time, and according to It the project actual construction time and the project plan duration, generates and issues duration abnormity prompt;Wherein, the practical work of the project Phase includes that the actual construction time is write in field operation actual construction time, data processing actual construction time and report.
Compared with prior art, a kind of prospecting project management system and method disclosed by the invention, establish mould by project Block obtains the Project Management Information of prospecting project, and establishes prospecting project according to the Project Management Information;Pass through data query Module feeds back the data query of user;It is fed back by progress queries of the Schedule monitoring module to user;Pass through institute It states Schedule monitoring module and obtains project data, and according to the project data, update current project progress;It is supervised by the progress Control module is calculated according to the project data, obtains the project actual construction time, and according to project actual construction time and described The project plan duration generates and issues duration abnormity prompt, the informationization of prospecting project management is able to achieve, so that project manager Member can inquire to obtain project data and project process at any time, while can automatically update project according to the project data got Progress avoids artificial statistical work progress and project process, avoids causing project process to be united due to being influenced by people's subjective consciousness Meter error the case where, avoid the information as caused by oral report transmitting omit and not in time the case where, and it is possible to automatically Duration abnormity prompt is generated and issued, project manager is allowed to understand the abnormal conditions of project process, control item in time Mesh progress accelerates project process to effectively improve project management efficiency and work quality.
Detailed description of the invention
Fig. 1 is a kind of structural schematic diagram for prospecting project management system that the embodiment of the present invention 1 provides.
Fig. 2 is a kind of structural schematic diagram for prospecting project management system that the embodiment of the present invention 2 provides.
Fig. 3 is a kind of structural schematic diagram for prospecting project management system that the embodiment of the present invention 3 provides.
Fig. 4 is a kind of flow diagram for prospecting project management method that the embodiment of the present invention 4 provides.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
It is a kind of structural schematic diagram for prospecting project management system that the embodiment of the present invention 1 provides referring to Fig. 1.The system 100 include that project establishes module 110, data inquiry module 120 and Schedule monitoring module 130.
It should be noted that the system 100 can run on desktop computer, notebook computer, Android smartphone, peace Tall and erect Intelligent flat and web terminal are associated with independent cloud server from the background, and server mounts large database, support internet It is wirelessly connected with 4G/5G, realizes data sharing.
The project establishes module 110, for obtaining the Project Management Information of prospecting project, and according to the project management Information establishes prospecting project;Wherein, the Project Management Information includes the project plan duration, and the project plan duration includes outer Plan time is write in industry plan time, data processing plan time and report.
It should be noted that by taking the running equipment of the system is mobile phone as an example, in the prospecting project's earlier stage stage, project pipe Reason personnel can be through Project Management Informations such as the touch screen cuit plan times of mobile phone, and it is logical that project establishes module 110 The Project Management Information that touch screen obtains prospecting project is crossed, and establishes prospecting item automatically according to the Project Management Information got Mesh, the Project Management Information got will be uploaded to cloud server by internet or 4G/5G.
Preferably, the Project Management Information further includes prospecting project information, exploratory techniques requirement, personnel and facility information With prospecting project work amount.
It should be noted that the prospecting project information includes but is not limited to reconnoitre project name, project number, project position It sets, scale of the project and architecture structure form.The exploration technique requires to include but is not limited to the whole hole requirement of drilling, samples and want It asks, in-situ test requirement and stratigraphic description template.The personnel and facility information include but is not limited to specific implementation personnel, march into the arena Drilling machine quantity, measurement and in-situ test number of devices and logistics supply vehicle.The prospecting project work amount includes but is not limited to Drill hole information typing and achievement quantitative requirement.
The data inquiry module 120, feeds back for the data query to user.
It should be noted that work is write in the field data collecting work of prospecting project, data processing work and report After the completion of work, relevant project data is uploaded and is stored in the associated database of the system 100, and project manager can be with It is that the project datas such as field data, interior industry data and exploration report are inquired by data inquiry module 120.Work as project manager When needing to inquire data, project manager's trigger data enquiry module 120, to carry out the data query of prospecting project, data Enquiry module 120 transfers the data of the prospecting project from database to feed back to project manager.
The Schedule monitoring module 130, feeds back for the progress queries to user;It is also used to obtain project data, And according to the project data, current project progress is updated;It is also used to be calculated according to the project data, obtains project reality The border duration, and according to the project actual construction time and the project plan duration, it generates and issues duration abnormity prompt;Wherein, The project data includes field data, interior industry data and exploration report, and the project process includes field operation progress, interior industry data Progress is write in processing progress and report, and the project actual construction time includes field operation actual construction time, data processing actual construction time The actual construction time is write with report.
It should be noted that work is write in the field data collecting work of prospecting project, data processing work and report After the completion of work, relevant data be stored in in the associated database of the system 100, outside 130 real-time perfoming of Schedule monitoring module The acquisition of the project datas such as industry data, interior industry data and exploration report, if Schedule monitoring module 130 is available to corresponding number According to, then it represents that corresponding work is completed, for example, 130 real-time perfoming field data of Schedule monitoring module obtains, and from database In obtain field data, then it represents that field data collecting work is completed, at this point, the field operation progress in renewal item progress be It completes, in another example industry data acquisition in 130 real-time perfoming of Schedule monitoring module, but industry in complete can not be obtained from database Data, then it represents that interior industry data are not yet uploaded to database, and data processing work does not complete, at this time in renewal item progress Data processing progress be unfinished.When project manager needs queried for items progress, project manager's triggering Schedule monitoring module 130, to carry out the inquiry of project process, Schedule monitoring module 130 obtains current project progress to feed back to Project manager.In addition, Schedule monitoring module 130 is calculated also according to the project data acquired, obtain corresponding The project actual construction time, also, the project plan duration that while establishing to project actual construction time and prospecting project sets is compared, and it is raw At and issue duration abnormity prompt, to remind project manager to manage, the item that is acquired with Schedule monitoring module 130 Mesh number is according to for for field data, Schedule monitoring module 130 obtains the daily completion that drills according to the field data acquired Situation calculates the estimated time for completing all drillings according to the daily performance of drilling, will be outer using as the field operation actual construction time The field operation plan time that the industry actual construction time determines with early period compares, when the field operation actual construction time exceeding field operation plan time, It then indicates that field process is unsatisfactory for construction period, automatically generate and issues corresponding duration abnormity prompt.
A kind of prospecting project management system provided by the embodiment of the present invention 1 establishes module by project and obtains prospecting item Purpose Project Management Information, and prospecting project is established according to the Project Management Information;By data inquiry module to user's Data query is fed back;It is fed back by progress queries of the Schedule monitoring module to user;Pass through the Schedule monitoring mould Block obtains project data, and according to the project data, updates current project progress;By the Schedule monitoring module according to institute It states project data to be calculated, obtains the project actual construction time, and according to the project actual construction time and the project plan duration, Duration abnormity prompt is generated and issued, the informationization of prospecting project management is able to achieve, project manager is looked at any time Inquiry obtains project data and project process, while can automatically update project process according to the project data got, avoids people Work statistical work progress and project process avoid the feelings for causing project process statistics to malfunction due to being influenced by people's subjective consciousness Condition, avoid the information as caused by oral report transmitting omit and not in time the case where, and it is possible to automatically generate and issue Duration abnormity prompt allows project manager to understand the abnormal conditions of project process in time, control project process, thus Project management efficiency and work quality are effectively improved, project process is accelerated.
In a preferred embodiment, the data inquiry module 120 is specifically used for obtaining the data query instruction of user, And inquired according to data query instruction, it obtains and shows corresponding project data;Wherein, the data query instruction It include field operation including field data inquiry instruction, the instruction of interior industry data query and exploration report inquiry instruction, the project data Data, interior industry data and exploration report.
It should be noted that project manager's trigger data inquires mould when project manager needs to inquire data Block 120 issues data query instruction by handset touch panel, and data inquiry module 120 receives the data query instruction, and root It is inquired according to data query instruction, is field data inquiry instruction when the data query instructs, inquires and show phase The field data of project should be reconnoitred;It is that interior industry data query instructs when the data query instructs, inquires and show corresponding prospecting The interior industry data of project;It is exploration report inquiry instruction when the data query instructs, inquires and show corresponding prospecting project Exploration report.By taking project manager needs to inquire field data as an example, project manager's trigger data enquiry module 120, And field data inquiry instruction is issued by the touch screen of mobile phone, data inquiry module 120 obtains field data inquiry instruction, and According to the field data inquiry instruction, relevant field data is transferred from database, and acquisition is shown on handset touch panel The field data arrived.In the present embodiment, data inquiry module 120 can carry out the data query of single kind, optimize item The query process of mesh number evidence, improves data-handling efficiency.
In a further advantageous embodiment, the Schedule monitoring module 130 include project process inquiry submodule, project into Degree updates submodule, actual construction time acquisition submodule and duration abnormity prompt submodule.
The project process inquires submodule, and the progress queries for obtaining user instruct, and according to the progress queries Instruction is inquired, and is obtained and is shown corresponding project process;Wherein, the progress queries instruction includes that field operation progress queries refer to It enables, progress inquiry instruction is write in the instruction of data processing progress queries and report.
It should be noted that when project manager needs queried for items progress, project manager trigger project into Degree inquiry submodule, and progress queries instruction is issued by handset touch panel, project process inquires submodule and receives the progress Inquiry instruction, and according to the progress queries instructions query and show current project progress, to feed back to project manager, tool Body, when progress queries instruction is the instruction of field operation progress queries, current field operation progress is obtained, and be shown in mobile phone touching It touches on screen;When progress queries instruction is the instruction of data processing progress queries, current data processing is obtained Progress, and be shown on handset touch panel;When progress queries instruction writes progress inquiry instruction for report, obtain current Report write progress, and be shown on handset touch panel.
The project process updates submodule, for obtaining project data, and according to the project data, updates currentitem Mesh progress.
It should be noted that project process updates submodule real-time perfoming field data, interior industry data and exploration report etc. The acquisition of project data, if project process updates, submodule is available to arrive corresponding data, then it represents that corresponding work is complete At being obtained for example, project process updates submodule real-time perfoming field data, and obtain field data from database, then table Show that field data collecting work is completed, at this point, the field operation progress in renewal item progress is to be completed, in another example project process Industry data acquisition in submodule real-time perfoming is updated, but industry data in complete can not be obtained from database, then it represents that interior industry Data are not yet uploaded to database, and data processing work does not complete, at this time the data processing in renewal item progress Progress is unfinished.
The actual construction time acquisition submodule obtains the project actual construction time for being calculated according to the project data.
It should be noted that actual construction time acquisition submodule is calculated according to project data, it is real to obtain corresponding project The border duration, within industry data instance, actual construction time acquisition submodule is according to the upload of all data of the interior industry data got Time calculates the estimated time for completing all interior industry data, using as the data processing actual construction time.
The duration abnormity prompt submodule, for comparing the project actual construction time and the project plan duration It is right, when detecting that the project actual construction time is greater than the project plan duration, generates and issue duration abnormity prompt.
It should be noted that the item that duration abnormity prompt submodule is set when establishing project actual construction time and prospecting project Mesh plan time is compared, and when detecting that the project actual construction time is greater than the project plan duration, generates and issues Duration abnormity prompt, to remind project manager to manage.Using the project actual construction time as data processing reality For duration, the data processing plan that data processing actual construction time and early period is determining of duration abnormity prompt submodule Duration compares, when the data processing actual construction time exceeding data processing plan time, then it represents that interior industry data Job dissatisfaction foot construction period is handled, automatically generates and issues corresponding duration abnormity prompt.
In the present embodiment, Schedule monitoring module 130 can carry out the project process inquiry of single kind, optimize project Inquiry, update and the abnormity prompt process of progress, improve data-handling efficiency.
It referring to fig. 2, is a kind of structural schematic diagram for prospecting project management system that the embodiment of the present invention 2 provides.The system System 100 further includes Data storage module 140 and data check module 150;
The Data storage module 140 carries out filing processing for the project achievement to prospecting project;
The data check module 150, it is one or more in the project achievement for obtaining and showing;It is also used to down Carry the one or more of the project achievement.
It should be noted that the project achievement of the prospecting project includes all with the prospecting project phase in the system 100 The data of pass, the classification of the project achievement include but is not limited to exploration report, field data and interior industry data.Data storage mould Block 140 saves the project achievement for the project of reconnoitring to database according to file format classification, to complete electronic filing processing.? Mesh achievement filing processing after, project manager can be by data check module 150 have access to in download items achievement One or more contents.
A kind of prospecting project management system provided by the embodiment of the present invention 2 realizes project by Data storage module 140 The electronic filing of achievement avoids manual sort's Consolidation Project achievement, realizes with no paper at all with informationization, reduces paper waste, be convenient for Data save and inquiry, also, by data check module 150 have access to download items achievement, avoid manually search needed for Project achievement content further improves the working efficiency and work quality of prospecting project management, to further speed up project Progress.
It is a kind of structural schematic diagram for prospecting project management system that the embodiment of the present invention 3 provides referring to Fig. 3.The system System 100 further includes user management module 160 and user log-in block 170;
The user management module 160, for managing the registration and unregistration of user account;It is also used to the user account Carry out the distribution of permission;
The user log-in block 170 is verified for obtaining the log-on message of user, and to the log-on message.
It should be noted that administrative staff can register new user account by user management module 160, nullify existing User account, and according to different posies to existing user account carry out permission distribution, different permissions, can be used Function it is also different, for example, the account of project manager possess typing and push Project Management Information permission so that project Management information typing can be uploaded to cloud server by internet or 4G/5G after completing and push to project correlation in real time Personnel's account, the account of outdoor workers possess the permission of the information and requirement that obtain prospecting project, and outdoor workers pass through in system Log in the account number cipher of oneself, the information and requirement of available prospecting project, to implement field data acquisition work as requested Make.Each personnel are used using the input for carrying out the log-on messages such as account and password by user log-in block 170 is needed before the system Family login module 170 verifies the log-on message of user account, to complete the login of user account.
A kind of prospecting project management system provided by the embodiment of the present invention 3 is logged in by user management module and user Module realizes one account system of a people to personnel, and different permissions is arranged according to post difference, needs to carry out account and password before use It inputs, so that the distribution of prospecting task is clear, precisely distributes to individual, one account of a people, task when avoiding reconnoitring the project implementation Distribution is fuzzy, and the implementation of certain tasks is caused the case where evading mutually occur.
In a preferred embodiment, the system also includes opinion interactive modules;
The opinion interactive module, including school examine submodule and reply submodule;
Submodule is examined in the school, for obtaining the authority information of listed user account, when the power of the user account It when limit information meets preset authority information, obtains school and examines information, information is examined according to the school, generate school and examine opinion, and send To corresponding user account;
The answer submodule, for obtaining and showing that opinion is examined in school relevant to listed user account;It is also used to Reply message is obtained, according to the reply message, opinion is generated and replies, and be sent to corresponding user account;
Submodule is examined in the school, is also used to obtain and show that opinion relevant to listed user account replies.
It should be noted that after project manager is by prospecting project management system real time review project data, discovery There are problems that correct, school can be triggered and examine submodule, and include that opinion and relevant people are examined in school by handset touch panel input Information is examined in the school of member, and the authority information that submodule obtains currently logged user account is examined in school, when the power of the user account It when limit information is project manager's permission, obtains school and examines information, information is examined according to the school, generate school and examine opinion, and send To the user account of specified related personnel, can be consulted and its account phase by replying submodule after related personnel's login account Opinion is examined in the school of pass, and inputs reply message by handset touch panel, is replied submodule and is obtained the reply message, and according to institute It states reply message and generates opinion answer, be sent at the account of corresponding project manager, project manager is examined by school The opinion that submodule can consult related personnel replies, and opinion interactive process will save filing as Project Process file.
By taking field data is examined in project manager school as an example, project manager passes through the ground that uploads in real time to outdoor workers Layer description information, sample information, core photo carry out consulting school when examining, and discovery there are problems that correct, can be in real time in school It examines submodule publication school and examines opinion, field operation technical staff need to reply opinion by replying submodule, field operation technical staff Field operation encounter technical problem can also be attached to photo by replying submodule Online release or the problem of alternative document illustrates or It is required that project manager, to Solve on site, project manager need to examine submodule by school and reply problem, field operation meaning See that interactive process will save filing as Project Process file.In addition, surveyor and project manager can hand in opinion Mutual module real-time communication, is not limited by time and place, and communication process will be saved as procedure file, also, project pipe Reason personnel can real time review exploration report, online by opinion interactive module carry out school examine work, school audits and compliance record will be used as process File is retained.
In the present embodiment, it realizes that the real-time school of project data is examined and works by opinion interactive module to link up, reduce The number of site inspection allows project manager to manage multiple projects simultaneously, to further increase project management effect Rate and work quality accelerate project process.
In a further advantageous embodiment, the system also includes work grading modules;
The work grading module, for obtaining the authority information of listed user account, when the user account When authority information meets preset authority information, score information is obtained, and according to institute's scoring information, generates commenting for prospecting project Divide result.
It should be noted that project manager after logging in its account, can trigger work grading module, work scoring Module obtains the authority information of listed user account, when the authority information of the user account is project manager's permission When, project manager is commented by handset touch panel input for early period of entire prospecting project, field operation, interior industry work in every Divide information, work grading module obtains the score information of input, and according to institute's scoring information, generates the scoring knot of prospecting project Fruit simultaneously saves to database.
In a further preferred embodiment, the system also includes locating and monitoring modules.
The locating and monitoring module includes personnel positioning submodule, locating query submodule and attendance monitoring submodule.
The personnel positioning submodule, for obtaining the location information of each specified user account in real time.
It should be noted that project manager can set the use for needing to carry out locating and monitoring personnel in system in advance The GPS function of family account, the handheld device of each designated person can upload its location information in real time, and personnel positioning submodule is real-time Obtain the location information of each user account for being set to need to carry out locating and monitoring personnel.
The locating query submodule, the locating query for obtaining user are instructed, are instructed according to the locating query, The real-time position information of corresponding user account is shown on electronic map.
It should be noted that project manager can trigger locating query submodule, and issued by handset touch panel Locating query instruction relevant to the user account being queried, locating query submodule receives locating query instruction, according to described Locating query instruction, obtains the real-time position information for the user account being queried, such as Baidu map, Amap or Tencent The real-time position information for the user account being queried is shown on the electronic maps such as figure.
The attendance monitoring submodule, for monitoring whether current time is within the scope of the predetermined time, when monitoring to work as When the preceding moment is in preset time range, judge whether the real-time position information of each specified user account is in preset In position range, if it is not, then generating the attendance abnormity prompt of the user account, and it is sent to pre-set user account.
It should be noted that the predetermined time range, the preset position range and the pre-set user account can To be set according to the actual situation, beneficial effects of the present invention are not influenced.Using the predetermined time range as 9 points of morning To at 6 points in afternoon, current time be 10 points of morning and the pre-set user account is attendance for project manager's account Monitoring submodule real-time monitors current time and is in preset time range, at this point, obtaining each specified user account Real-time position information, and judge whether the real-time position information of each specified user account is in preset position range, If it is not, then generating the attendance abnormity prompt of the user account, and it is sent to project manager's account end, so as to project quality pipe Reason personnel realize that the attendance to staff monitors.
It is to be appreciated that above-described embodiment can in any combination, to constitute more preferred embodiment.
It referring to fig. 4, is a kind of flow diagram for prospecting project management method that the embodiment of the present invention 4 provides.The side Method is applied to prospecting project management acquisition system described in any embodiment as above, comprising steps of
S1, the Project Management Information that module obtains prospecting project is established by project, and according to the Project Management Information Establish prospecting project;Wherein, the Project Management Information includes the project plan duration, and the project plan duration includes field operation meter It draws duration, data processing plan time and report and writes plan time;
S2, it is fed back by data query of the data inquiry module to user;
S3, it is fed back by progress queries of the Schedule monitoring module to user;
S4, project data is obtained by the Schedule monitoring module, and according to the project data, update current project into Degree;Wherein, the project data includes field data, interior industry data and exploration report, the project process include field operation progress, Progress is write in data processing progress and report;
S5, it is calculated by the Schedule monitoring module according to the project data, obtains project actual construction time, and root According to the project actual construction time and the project plan duration, generates and issue duration abnormity prompt;Wherein, the project is practical Duration includes that the actual construction time is write in field operation actual construction time, data processing actual construction time and report.
A kind of prospecting project management method that the embodiment of the present invention 4 provides establishes module by project and obtains prospecting project Project Management Information, and prospecting project is established according to the Project Management Information;By data inquiry module to the number of user It is fed back it is investigated that asking;It is fed back by progress queries of the Schedule monitoring module to user;Pass through the Schedule monitoring module Project data is obtained, and according to the project data, updates current project progress;Through the Schedule monitoring module according to Project data is calculated, and obtains the project actual construction time, and according to the project actual construction time and the project plan duration, raw At and issue duration abnormity prompt, be able to achieve prospecting project management informationization, project manager is inquired at any time Project data and project process are obtained, while project process can be automatically updated according to the project data got, is avoided artificial Statistical work progress and project process avoid causing project process to count the case where malfunctioning due to being influenced by people's subjective consciousness, Avoid the information as caused by oral report transmitting omit and not in time the case where, and it is possible to automatically generate and issue work Phase abnormity prompt allows project manager to understand the abnormal conditions of project process, control project process, to have in time Effect improves project management efficiency and work quality, accelerates project process.
The above is a preferred embodiment of the present invention, it is noted that for those skilled in the art For, various improvements and modifications may be made without departing from the principle of the present invention, these improvements and modifications are also considered as Protection scope of the present invention.

Claims (10)

1. a kind of prospecting project management system, which is characterized in that establish module, data inquiry module and Schedule monitoring including project Module;
The project establishes module, builds for obtaining the Project Management Information of prospecting project, and according to the Project Management Information Vertical prospecting project;Wherein, the Project Management Information includes the project plan duration, and the project plan duration includes field operation plan Plan time is write in duration, data processing plan time and report;
The data inquiry module is fed back for the data query to user;
The Schedule monitoring module, feeds back for the progress queries to user;It is also used to obtain project data, and according to institute Project data is stated, current project progress is updated;It is also used to be calculated according to the project data, obtains the project actual construction time, And according to the project actual construction time and the project plan duration, generates and issue duration abnormity prompt;Wherein, the project Data include field data, interior industry data and exploration report, and the project process includes field operation progress, data processing progress Progress is write with report, the project actual construction time includes that field operation actual construction time, data processing actual construction time and report are compiled Write the actual construction time.
2. prospecting project management system as described in claim 1, which is characterized in that the Project Management Information further includes prospecting Project information, exploratory techniques requirement, personnel and facility information and prospecting project work amount.
3. prospecting project management system as described in claim 1, which is characterized in that the data inquiry module is specifically used for obtaining The data query instruction at family is taken, and is inquired according to data query instruction, obtains and shows corresponding project data; Wherein, the data query instruction includes field data inquiry instruction, interior industry data query instructs and exploration report inquiry instruction, The project data includes field data, interior industry data and exploration report.
4. prospecting project management system as described in claim 1, which is characterized in that the Schedule monitoring module include project into Degree inquiry submodule, project process update submodule, actual construction time acquisition submodule and duration abnormity prompt submodule;
The project process inquires submodule, and the progress queries for obtaining user instruct, and are instructed according to the progress queries It is inquired, obtained and shows corresponding project process;Wherein, progress queries instruction include the instruction of field operation progress queries, Progress inquiry instruction is write in the instruction of data processing progress queries and report;
The project process updates submodule, for obtaining project data, and according to the project data, update current project into Degree;
The actual construction time acquisition submodule obtains the project actual construction time for being calculated according to the project data;
The duration abnormity prompt submodule, for the project actual construction time to be compared with the project plan duration, When detecting that the project actual construction time is greater than the project plan duration, generates and issue duration abnormity prompt.
5. prospecting project management system as described in claim 1, which is characterized in that the system also includes Data storage modules With data check module;
The Data storage module carries out filing processing for the project achievement to prospecting project;
The data check module, it is one or more in the project achievement for obtaining and showing;It is also used to download described Project achievement it is one or more.
6. prospecting project management system as described in claim 1, which is characterized in that the system also includes user management modules And user log-in block;
The user management module, for managing the registration and unregistration of user account;It is also used to weigh the user account The distribution of limit;
The user log-in block is verified for obtaining the log-on message of user, and to the log-on message.
7. prospecting project management system as claimed in claim 6, which is characterized in that the system also includes opinion interaction moulds Block;
The opinion interactive module, including school examine submodule and reply submodule;
Submodule is examined in the school, for obtaining the authority information of listed user account, when the permission of the user account is believed It when breath meets preset authority information, obtains school and examines information, information is examined according to the school, generate school and examine opinion, and be sent to phase The user account answered;
The answer submodule, for obtaining and showing that opinion is examined in school relevant to listed user account;It is also used to obtain Reply message generates opinion and replies according to the reply message, and is sent to corresponding user account;
Submodule is examined in the school, is also used to obtain and show that opinion relevant to listed user account replies.
8. prospecting project management system as claimed in claim 6, which is characterized in that the system also includes work scoring moulds Block;
The work grading module, for obtaining the authority information of listed user account, when the permission of the user account When information meets preset authority information, score information is obtained, and according to institute's scoring information, generates the scoring knot of prospecting project Fruit.
9. prospecting project management system as claimed in claim 6, which is characterized in that the system also includes locating and monitoring moulds Block;
The locating and monitoring module includes personnel positioning submodule, locating query submodule and attendance monitoring submodule;
The personnel positioning submodule, for obtaining the location information of each specified user account in real time;
The locating query submodule, the locating query for obtaining user are instructed, are instructed according to the locating query, in electronics The real-time position information of corresponding user account is shown on map;
The attendance monitoring submodule, for monitoring whether current time is within the scope of the predetermined time, when monitoring current When carving in preset time range, judge whether the real-time position information of each specified user account is in preset position In range, if it is not, then generating the attendance abnormity prompt of the user account, and it is sent to pre-set user account.
10. a kind of prospecting project management method is applied to prospecting project management system as described in any one of claim 1 to 9, It is characterised by comprising:
The Project Management Information that module obtains prospecting project is established by project, and is established and is reconnoitred according to the Project Management Information Project;Wherein, the Project Management Information includes the project plan duration, the project plan duration include field operation plan time, Plan time is write in data processing plan time and report;
It is fed back by data query of the data inquiry module to user;
It is fed back by progress queries of the Schedule monitoring module to user;
Project data is obtained by the Schedule monitoring module, and according to the project data, updates current project progress;Its In, the project data includes field data, interior industry data and exploration report, and the project process includes field operation progress, interior industry Progress is write in data processing progress and report;
It is calculated by the Schedule monitoring module according to the project data, obtains the project actual construction time, and according to described It project actual construction time and the project plan duration, generates and issues duration abnormity prompt;Wherein, the project actual construction time packet It includes field operation actual construction time, data processing actual construction time and report and writes the actual construction time.
CN201910333237.4A 2019-04-24 2019-04-24 A kind of prospecting project management system and method Pending CN110070343A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910333237.4A CN110070343A (en) 2019-04-24 2019-04-24 A kind of prospecting project management system and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910333237.4A CN110070343A (en) 2019-04-24 2019-04-24 A kind of prospecting project management system and method

Publications (1)

Publication Number Publication Date
CN110070343A true CN110070343A (en) 2019-07-30

Family

ID=67368663

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910333237.4A Pending CN110070343A (en) 2019-04-24 2019-04-24 A kind of prospecting project management system and method

Country Status (1)

Country Link
CN (1) CN110070343A (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111160761A (en) * 2019-12-27 2020-05-15 中国航空工业集团公司西安飞机设计研究所 Software development quality control method
CN111950845A (en) * 2020-07-02 2020-11-17 广东邦鑫数据科技股份有限公司 Processing method, system, device and medium for surveying and measuring engineering data
CN112116318A (en) * 2020-09-04 2020-12-22 北京安锐卓越信息技术股份有限公司 Method, device and storage medium for tracking project progress
CN112184177A (en) * 2020-10-13 2021-01-05 广东天衡工程建设咨询管理有限公司 Project supervision method, device and storage medium
CN112465457A (en) * 2020-11-27 2021-03-09 重庆康盛监理咨询有限公司 Supervision project management method, system, device and computer storage medium
CN113095612A (en) * 2019-12-23 2021-07-09 中国石油天然气股份有限公司 Method and device for monitoring oil field exploration progress and storage medium
CN113256131A (en) * 2021-06-01 2021-08-13 安徽鑫洋信息工程有限公司 Intelligent coordination construction system of prefabricated building
CN113344513A (en) * 2021-05-31 2021-09-03 珠海大横琴科技发展有限公司 Project information management method and device, electronic equipment and storage medium
CN113836083A (en) * 2021-09-15 2021-12-24 云南建投第一勘察设计有限公司 Geological material library collecting and arranging system and method
CN113933482A (en) * 2021-11-16 2022-01-14 中航勘察设计研究院有限公司 Civil engineering test internal and external industry management system and method
CN117114625A (en) * 2023-09-25 2023-11-24 武汉市勘察设计有限公司 Geotechnical engineering investigation full life cycle integrated operation management platform and method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20100198648A1 (en) * 2009-02-05 2010-08-05 International Business Machines Corporation Dynamic meeting group organizer
CN102096849A (en) * 2009-12-15 2011-06-15 苏州铭星软件科技有限公司 Flow management design method based on network program
CN107169747A (en) * 2017-06-19 2017-09-15 郑州航空工业管理学院 A kind of management system of various engineering of civil construction
CN107590601A (en) * 2017-09-10 2018-01-16 沈阳市电信规划设计院股份有限公司 Communication scheme produces accessory system

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20100198648A1 (en) * 2009-02-05 2010-08-05 International Business Machines Corporation Dynamic meeting group organizer
CN102096849A (en) * 2009-12-15 2011-06-15 苏州铭星软件科技有限公司 Flow management design method based on network program
CN107169747A (en) * 2017-06-19 2017-09-15 郑州航空工业管理学院 A kind of management system of various engineering of civil construction
CN107590601A (en) * 2017-09-10 2018-01-16 沈阳市电信规划设计院股份有限公司 Communication scheme produces accessory system

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
钟春来: "面向工程勘察设计院的PDM项目管理***", 《中国优秀博硕士学位论文全文数据库(硕士) 信息科技辑》 *
黄燕鹏: "工程项目调度管理信息***的研究与开发", 《中国优秀博硕士学位论文全文数据库(硕士) 信息科技辑》 *

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113095612A (en) * 2019-12-23 2021-07-09 中国石油天然气股份有限公司 Method and device for monitoring oil field exploration progress and storage medium
CN113095612B (en) * 2019-12-23 2024-03-29 中国石油天然气股份有限公司 Monitoring method and device for oilfield exploration progress and storage medium
CN111160761A (en) * 2019-12-27 2020-05-15 中国航空工业集团公司西安飞机设计研究所 Software development quality control method
CN111950845A (en) * 2020-07-02 2020-11-17 广东邦鑫数据科技股份有限公司 Processing method, system, device and medium for surveying and measuring engineering data
CN112116318A (en) * 2020-09-04 2020-12-22 北京安锐卓越信息技术股份有限公司 Method, device and storage medium for tracking project progress
CN112184177B (en) * 2020-10-13 2023-11-24 广东天衡工程建设咨询管理有限公司 Project supervision method, equipment and storage medium
CN112184177A (en) * 2020-10-13 2021-01-05 广东天衡工程建设咨询管理有限公司 Project supervision method, device and storage medium
CN112465457A (en) * 2020-11-27 2021-03-09 重庆康盛监理咨询有限公司 Supervision project management method, system, device and computer storage medium
CN112465457B (en) * 2020-11-27 2024-05-24 重庆康盛监理咨询有限公司 Method, system, device and computer storage medium for managing supervision project
CN113344513A (en) * 2021-05-31 2021-09-03 珠海大横琴科技发展有限公司 Project information management method and device, electronic equipment and storage medium
CN113256131B (en) * 2021-06-01 2024-02-02 安徽鑫洋信息工程有限公司 Intelligent coordination construction system of assembled building
CN113256131A (en) * 2021-06-01 2021-08-13 安徽鑫洋信息工程有限公司 Intelligent coordination construction system of prefabricated building
CN113836083A (en) * 2021-09-15 2021-12-24 云南建投第一勘察设计有限公司 Geological material library collecting and arranging system and method
CN113933482A (en) * 2021-11-16 2022-01-14 中航勘察设计研究院有限公司 Civil engineering test internal and external industry management system and method
CN113933482B (en) * 2021-11-16 2024-04-30 中航勘察设计研究院有限公司 Geotechnical test inner and outer industry management system and geotechnical test inner and outer industry management method
CN117114625A (en) * 2023-09-25 2023-11-24 武汉市勘察设计有限公司 Geotechnical engineering investigation full life cycle integrated operation management platform and method

Similar Documents

Publication Publication Date Title
CN110070343A (en) A kind of prospecting project management system and method
CN102693183B (en) Method and system for realizing automatic software testing
CN105956672A (en) Power line inspection real-time monitoring management system
CN105989443A (en) Intelligent-mobile-terminal-based communication line inspection system
CN107977820B (en) Intelligent logistics express delivery method
CN108960456A (en) Private clound secure, integral operation platform
US10832189B2 (en) Systems and methods for dynamically scheduling tasks across an enterprise
US11087285B2 (en) Systems and methods for providing message templates in an enterprise system
JP6689852B2 (en) Survey results framework
CN106251092A (en) Field operation managing and control system based on operation template
CN111582729A (en) System and method for acquiring field data of soil mass and geological survey
US20180322439A1 (en) Systems and methods for generating activities across an enterprise
EP3091487A1 (en) Network deployment for cellular, backhaul, fiber optic and other network infrastructure
CN110991886A (en) Community task processing method, device, equipment and medium
CN110490559A (en) A kind of mobile law enforcement inspection method, device, system and server
CN114111706A (en) Leveling method integrating interior and exterior industry and quality inspection and data acquisition system
CN110570097A (en) business personnel risk identification method and device based on big data and storage medium
CN101819660A (en) Compulsory verification measuring instrument filing and dynamic management method and system thereof
CN107527148A (en) The building site project management system of power network wisdom building site control platform
CN112085225A (en) Operation and maintenance system and method for user side power equipment
CN110956444A (en) Infrastructure distribution network engineering data management mobile system
CN107422293A (en) A kind of electric energy meter field intellectuality verification system and method
CN112150112A (en) Site environment survey internal and external work overall process management system and method
CN107612744B (en) Intelligent transportation equipment operation and maintenance system based on mobile platform
CN109688181A (en) A kind of data prospecting processing method, server, terminal and system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Guo Yu

Inventor after: Yu Gemiao

Inventor after: Huang Jiaming

Inventor after: Liu Wei

Inventor after: Zhang Qinghua

Inventor after: Lou Kangming

Inventor after: Zhou Zhiyuan

Inventor after: Zhu Xiaoqiang

Inventor before: Huang Jiaming

Inventor before: Liu Wei

Inventor before: Zhang Qinghua

Inventor before: Lou Kangming

Inventor before: Zhou Zhiyuan

Inventor before: Zhu Xiaoqiang

CB03 Change of inventor or designer information
TA01 Transfer of patent application right

Effective date of registration: 20220303

Address after: 510000 200 Tanling Road, Jiaheyuan, Baiyun District, Guangzhou City, Guangdong Province

Applicant after: GUANGZHOU INSTITUTE OF GEOLOGICAL SURVEY

Address before: No.10 Jianshe Avenue, Yuexiu District, Guangzhou, Guangdong Province 510060

Applicant before: GUANGZHOU URBAN PLANNING & DESIGN SURVEY Research Institute

TA01 Transfer of patent application right
RJ01 Rejection of invention patent application after publication

Application publication date: 20190730

RJ01 Rejection of invention patent application after publication