CN109973130A - Once draw construction system and method in place in a kind of main cable strand realization narrow space of Super Long Tunnel anchor - Google Patents
Once draw construction system and method in place in a kind of main cable strand realization narrow space of Super Long Tunnel anchor Download PDFInfo
- Publication number
- CN109973130A CN109973130A CN201910342163.0A CN201910342163A CN109973130A CN 109973130 A CN109973130 A CN 109973130A CN 201910342163 A CN201910342163 A CN 201910342163A CN 109973130 A CN109973130 A CN 109973130A
- Authority
- CN
- China
- Prior art keywords
- conversion equipment
- strand
- traction
- door frame
- main cable
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000010276 construction Methods 0.000 title claims abstract description 18
- 238000000034 method Methods 0.000 title claims abstract description 16
- 238000006243 chemical reaction Methods 0.000 claims abstract description 113
- 241000282326 Felis catus Species 0.000 claims description 15
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 claims description 10
- 239000000203 mixture Substances 0.000 claims description 9
- 241001347978 Major minor Species 0.000 claims description 8
- 229910000831 Steel Inorganic materials 0.000 claims description 7
- 239000010959 steel Substances 0.000 claims description 7
- 238000004873 anchoring Methods 0.000 claims description 6
- 229910052742 iron Inorganic materials 0.000 claims description 5
- 241000219122 Cucurbita Species 0.000 claims description 3
- 235000009852 Cucurbita pepo Nutrition 0.000 claims description 3
- 238000007796 conventional method Methods 0.000 claims description 3
- 230000008569 process Effects 0.000 claims description 3
- 239000004744 fabric Substances 0.000 claims 1
- 230000008901 benefit Effects 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 239000000725 suspension Substances 0.000 description 2
- 230000008859 change Effects 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 230000006872 improvement Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 230000001141 propulsive effect Effects 0.000 description 1
- 230000005641 tunneling Effects 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/40—Devices or apparatus specially adapted for handling or placing units of linings or supporting units for tunnels or galleries
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D20/00—Setting anchoring-bolts
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
The invention discloses a kind of main cable strands to realize that construction system and method in place are once drawn in the narrow space of Super Long Tunnel anchor using trailer system conversion equipment;The construction system has trailer system and conversion equipment;The following steps are included: the arrangement of (1) trailer system when operation;(2) arrangement of conversion equipment;(3) method is made in conversion: 1. strand traction rope conversion front haulage;2. first conversion equipment worries messenger;3. second conversion equipment is separated with traction rope;4. second conversion equipment worries messenger;5. third conversion equipment is separated with traction rope;6. third conversion equipment worries messenger.Be suitable for longer tunnel anchorage length, narrow space, the gradient it is larger when, using be arranged in dissipate cable saddle door frame on conversion equipment can efficiently, safety main cable strand once be drawn in place.
Description
Technical field
The present invention relates to civil engineering suspension bridge construction fields, and in particular to realizes that a kind of main cable strand utilizes trailer system
Conversion equipment realizes that construction system and method in place are once drawn in the narrow space of Super Long Tunnel anchor.
Background technique
Main rope of suspension bridge strand is drawn when dissipating cable saddle to tunnel anchorage, due to slope change, narrow space, heavy mechanical equipment
Can not start tunneling, primary traction cannot achieve in place using conventional main cable strand traction technique, led at this time using this system
It crosses device and simply converts and can achieve primary traction in place, improve propulsive efficiency.
Summary of the invention
Therefore, in order to solve above-mentioned deficiency, the present invention provides a kind of main cable strand realization narrow space of Super Long Tunnel anchor herein
Primary construction system and the method drawn in place efficient, safety can once draw main push-towing rope in place.
It is once drawn in place the invention is realized in this way constructing a kind of main cable strand realization narrow space of Super Long Tunnel anchor
Construction system, it is characterised in that: the construction system has trailer system and conversion equipment;
Wherein, the composition of trailer system structure mainly includes dissipating cable saddle door frame, chain block, cat road door frame, cat road door frame guide wheel
Group, major-minor rack winch, hauling rope, pull device, cat road bottom plate is led, horizontal guide sheave, anchoring steel pipe;It will be led by pulling device
Hauling rope connection on secondary rack winch ultimately forms trailer system;Cat road door frame guide wheel group is mounted on cat road door frame, water
On anchoring steel pipe, conversion equipment, which is arranged in tunnel anchorage, to be dissipated in cable saddle door frame for flat directive wheel setting, and 3 are arranged on coaxial line,
At the beginning of being fixed on tunnel anchorage by chain block on branch arch ring fashioned iron;It pulls device to be arranged on hauling rope, hauling rope passes through 3 conversions
Horizontal guide sheave is connected to after bypassing the directive wheel of bottom after the corresponding rotating wheel of device.
Once draw construction method in place in a kind of main cable strand realization narrow space of Super Long Tunnel anchor, it is characterised in that: press
It is realized according to such as under type;
Step 1: the arrangement of trailer system: the composition of trailer system structure specifically includes that scattered cable saddle buttress door frame, tunnel anchorage hole
Mouth door frame, tower top arc guide wheel group, rack winch (major and minor), hauling rope, pulls device, cat road door frame, Mao Dao at tower top portal
The compositions such as door frame guide wheel group, each position carrying roller, and related directive wheel;By pulling device for the hauling rope on major-minor rack winch
Connection ultimately forms trailer system;
Step 2: the arrangement of conversion equipment: conversion equipment, which is arranged in tunnel anchorage, to be dissipated in cable saddle door frame, and 3 are arranged on coaxial line,
At the beginning of being fixed on tunnel anchorage by chain block on branch arch ring fashioned iron;
Step 3: conversion operation method:
1. strand traction rope converts front haulage;Main cable strand, which is drawn using conventional method to tunnel anchorage, dissipates cable saddle front end and by the
One conversion equipment, this process are the height effectively raised tunnel anchorage and dissipate traction rope at cable saddle, traction rope must be hung on to second, the
In three conversion equipment rotating wheel races, and its height is controlled by chain block;
2. first conversion equipment worries messenger: when the traction of main cable strand anchor head is close to first conversion equipment, controlling and reduce
Hauling speed stops traction when strand anchor head is more than first conversion equipment 50cm, by pulling at first conversion equipment
Cucurbit decentralization, gourd hook are hung on conversion equipment, and the traction rope of trailer system is hung on first conversion equipment rotating wheel wheel
In slot, since the limitation of spatial altitude slowly promotes chain block, make strand anchor head promoted certain altitude not with ground face contact;
3. second conversion equipment is separated with traction rope: continuing to draw main cable strand, when from second conversion equipment of strand anchor head
Stop traction when 50cm, second conversion equipment is separated with traction rope, and continuing traction passes through the traction of strand anchor head
Second conversion equipment;
4. second conversion equipment worries messenger: stopping traction after strand anchor head passes through second conversion equipment, by traction rope
It is hung in second conversion equipment rotating wheel race, is promoted traction rope to maximum height using chain block, and continue to draw
Main cable strand;
5. third conversion equipment is separated with traction rope: when strand anchor head is drawn to from third conversion equipment 50cm, utilizing
One or two conversion equipment is separated as fulcrum, by third conversion equipment with traction rope, and continues to draw;
6. third conversion equipment worries messenger: after strand anchor head passes through third conversion equipment, due to by spatial altitude
Limitation can contact generation friction with scattered cable saddle pier cap concrete and damage main cable strand, therefore just pass through the if continuing to draw strand
Stop traction after three conversion equipments, traction rope is hung in third conversion equipment rotating wheel race, it will using chain block
Main cable strand improves, and continues primary traction in place.
Surpass the present invention has the advantage that being realized the invention discloses a kind of main cable strand using trailer system conversion equipment
Once draw construction system and method in place in the narrow space of long tunnel anchor;The construction system has trailer system and conversion equipment;
The following steps are included: the arrangement of (1) trailer system when operation;(2) arrangement of conversion equipment;(3) method is made in conversion: 1. strand is led
Messenger converts front haulage;2. first conversion equipment worries messenger;3. second conversion equipment is separated with traction rope;4. second
Conversion equipment worries messenger;5. third conversion equipment is separated with traction rope;6. third conversion equipment worries messenger.It is suitable for
When tunnel anchorage length is longer, narrow space, the gradient are larger, using be arranged in dissipate conversion equipment on cable saddle door frame can efficiently, peace
Complete once draws main cable strand in place.
Detailed description of the invention
Fig. 1 is trailer system and conversion equipment layout drawing;
Fig. 2 is conversion equipment arrangement schematic diagram;
Fig. 3 is conversion equipment schematic diagram.
Specific embodiment
Below in conjunction with attached drawing 1- Fig. 3, the present invention is described in detail, technical solution in the embodiment of the present invention into
Row clearly and completely describes, it is clear that described embodiments are only a part of the embodiments of the present invention, rather than whole realities
Apply example.Based on the embodiments of the present invention, those of ordinary skill in the art are obtained without making creative work
Every other embodiment, shall fall within the protection scope of the present invention.
The present invention provides a kind of main cable strand realization narrow space of Super Long Tunnel anchor by improvement herein and once draws in place
Construction system, it is characterised in that: the construction system has trailer system and conversion equipment;
The composition of trailer system structure mainly includes dissipating cable saddle door frame 1, chain block 2, cat road door frame 3, cat road door frame guide wheel group
4, major-minor rack winch, hauling rope 5, pull device 6, cat road bottom plate leads 7, horizontal guide sheave 8, anchoring steel pipe 9;By pulling device
Hauling rope connection on major-minor rack winch is ultimately formed trailer system by 6;Cat road door frame guide wheel group 4 is mounted on cat road door frame
On 3, the setting of horizontal guide sheave 8 is on anchoring steel pipe 9, and conversion equipment 10, which is arranged in tunnel anchorage, to be dissipated in cable saddle door frame 1, coaxial line
Upper arrangement 3, at the beginning of being fixed on tunnel anchorage by chain block 2 on branch arch ring fashioned iron;It pulls device 6 to be arranged on hauling rope 5, traction
Rope 5 is connected to horizontal guide sheave 8 after the directive wheel 11 of bottom after 3 corresponding rotating wheels of conversion equipment 10.
Construction method in place is once drawn in a kind of main cable strand realization narrow space of Super Long Tunnel anchor, real as follows
It is existing;
Step 1: the arrangement of trailer system: the composition of trailer system structure specifically includes that scattered cable saddle buttress door frame, tunnel anchorage hole
Mouth door frame, tower top arc guide wheel group, rack winch (major and minor), hauling rope, pulls device, cat road door frame, Mao Dao at tower top portal
The compositions such as door frame guide wheel group, each position carrying roller, and related directive wheel;By pulling device for the hauling rope on major-minor rack winch
Connection ultimately forms trailer system;
Step 2: the arrangement of conversion equipment: conversion equipment, which is arranged in tunnel anchorage, to be dissipated in cable saddle door frame, and 3 are arranged on coaxial line,
At the beginning of being fixed on tunnel anchorage by chain block on branch arch ring fashioned iron;
Step 3: conversion operation method:
1. strand traction rope converts front haulage;Main cable strand, which is drawn using conventional method to tunnel anchorage, dissipates cable saddle front end and by the
One conversion equipment, this process are the height effectively raised tunnel anchorage and dissipate traction rope at cable saddle, traction rope must be hung on to second, the
In three conversion equipment rotating wheel races, and its height is controlled by chain block;
2. first conversion equipment worries messenger: when the traction of main cable strand anchor head is close to first conversion equipment, controlling and reduce
Hauling speed stops traction when strand anchor head is more than first conversion equipment 50cm, by pulling at first conversion equipment
Cucurbit decentralization, gourd hook are hung on conversion equipment, and the traction rope of trailer system is hung on first conversion equipment rotating wheel wheel
In slot, since the limitation of spatial altitude slowly promotes chain block, make strand anchor head promoted certain altitude not with ground face contact;
3. second conversion equipment is separated with traction rope: continuing to draw main cable strand, when from second conversion equipment of strand anchor head
Stop traction when 50cm, second conversion equipment is separated with traction rope, and continuing traction passes through the traction of strand anchor head
Second conversion equipment;
4. second conversion equipment worries messenger: stopping traction after strand anchor head passes through second conversion equipment, by traction rope
It is hung in second conversion equipment rotating wheel race, is promoted traction rope to maximum height using chain block, and continue to draw
Main cable strand;
5. third conversion equipment is separated with traction rope: when strand anchor head is drawn to from third conversion equipment 50cm, utilizing
One or two conversion equipment is separated as fulcrum, by third conversion equipment with traction rope, and continues to draw;
6. third conversion equipment worries messenger: after strand anchor head passes through third conversion equipment, due to by spatial altitude
Limitation can contact generation friction with scattered cable saddle pier cap concrete and damage main cable strand, therefore just pass through the if continuing to draw strand
Stop traction after three conversion equipments, traction rope is hung in third conversion equipment rotating wheel race, it will using chain block
Main cable strand improves, and continues primary traction in place.
The present invention has the advantages that
1, this system not only can solve under Super Long Tunnel anchor narrow space, can not once draw problem in place, be by this
System also solves effective conversion of different gradient in Super Long Tunnel anchor, inclination angle situation, and primary traction in place, simplifies numerous complicated
Link, the safety for improving efficiency, ensure that construction.
2, system can be repeated, be recycled, at low cost, easy to operate to save manually.
The foregoing description of the disclosed embodiments enables those skilled in the art to implement or use the present invention.
Various modifications to these embodiments will be readily apparent to those skilled in the art, as defined herein
General Principle can be realized in other embodiments without departing from the spirit or scope of the present invention.Therefore, of the invention
It is not intended to be limited to the embodiments shown herein, and is to fit to and the principles and novel features disclosed herein phase one
The widest scope of cause.
Claims (2)
1. a kind of main cable strand realizes that construction system in place is once drawn in the narrow space of Super Long Tunnel anchor, it is characterised in that: this is applied
Work system has trailer system and conversion equipment;
The composition of trailer system structure mainly includes dissipating cable saddle door frame (1), chain block (2), cat road door frame (3), cat road door frame
Guide wheel group (4), major-minor rack winch, hauling rope (5), pull device (6), cat road bottom plate lead (7), horizontal guide sheave (8), anchoring
Steel pipe (9);The hauling rope connection on major-minor rack winch is ultimately formed into trailer system by pulling device (6);Cat road door frame
Guide wheel group (4) is mounted on cat road door frame (3), and horizontal guide sheave (8) setting is in anchoring steel pipe (9), conversion equipment (10) cloth
It sets and is dissipated in cable saddle door frame (1) in tunnel anchorage, 3 are arranged on coaxial line, tunnel anchorage just branch arch is fixed on by chain block (2)
On ring steel;It pulls device (6) to be arranged on hauling rope (5), hauling rope (5) passes through the corresponding rotating wheel of 3 conversion equipments (10)
Horizontal guide sheave (8) are connected to after bypassing the directive wheel (11) of bottom afterwards.
2. a kind of main cable strand realizes that construction method in place is once drawn in the narrow space of Super Long Tunnel anchor, it is characterised in that: according to
As under type is realized;
Step 1: the arrangement of trailer system: the composition of trailer system structure specifically includes that scattered cable saddle buttress door frame, tunnel anchorage hole
Mouth door frame, tower top arc guide wheel group, rack winch (major and minor), hauling rope, pulls device, cat road door frame, Mao Dao at tower top portal
The compositions such as door frame guide wheel group, each position carrying roller, and related directive wheel;By pulling device for the hauling rope on major-minor rack winch
Connection ultimately forms trailer system;
Step 2: the arrangement of conversion equipment: conversion equipment, which is arranged in tunnel anchorage, to be dissipated in cable saddle door frame, and 3 are arranged on coaxial line,
At the beginning of being fixed on tunnel anchorage by chain block on branch arch ring fashioned iron;
Step 3: conversion operation method:
1. strand traction rope converts front haulage;Main cable strand, which is drawn using conventional method to tunnel anchorage, dissipates cable saddle front end and by the
One conversion equipment, this process are the height effectively raised tunnel anchorage and dissipate traction rope at cable saddle, traction rope must be hung on to second, the
In three conversion equipment rotating wheel races, and its height is controlled by chain block;
2. first conversion equipment worries messenger: when the traction of main cable strand anchor head is close to first conversion equipment, controlling and reduce
Hauling speed stops traction when strand anchor head is more than first conversion equipment 50cm, by pulling at first conversion equipment
Cucurbit decentralization, gourd hook are hung on conversion equipment, and the traction rope of trailer system is hung on first conversion equipment rotating wheel wheel
In slot, since the limitation of spatial altitude slowly promotes chain block, make strand anchor head promoted certain altitude not with ground face contact;
3. second conversion equipment is separated with traction rope: continuing to draw main cable strand, when from second conversion equipment of strand anchor head
Stop traction when 50cm, second conversion equipment is separated with traction rope, and continuing traction passes through the traction of strand anchor head
Second conversion equipment;
4. second conversion equipment worries messenger: stopping traction after strand anchor head passes through second conversion equipment, by traction rope
It is hung in second conversion equipment rotating wheel race, is promoted traction rope to maximum height using chain block, and continue to draw
Main cable strand;
5. third conversion equipment is separated with traction rope: when strand anchor head is drawn to from third conversion equipment 50cm, utilizing
One or two conversion equipment is separated as fulcrum, by third conversion equipment with traction rope, and continues to draw;
6. third conversion equipment worries messenger: after strand anchor head passes through third conversion equipment, due to by spatial altitude
Limitation can contact generation friction with scattered cable saddle pier cap concrete and damage main cable strand, therefore just pass through the if continuing to draw strand
Stop traction after three conversion equipments, traction rope is hung in third conversion equipment rotating wheel race, it will using chain block
Main cable strand improves, and continues primary traction in place.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910342163.0A CN109973130B (en) | 2019-04-26 | 2019-04-26 | Construction system and method for realizing one-time traction of extra-long tunnel anchor narrow space by main cable strand |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910342163.0A CN109973130B (en) | 2019-04-26 | 2019-04-26 | Construction system and method for realizing one-time traction of extra-long tunnel anchor narrow space by main cable strand |
Publications (2)
Publication Number | Publication Date |
---|---|
CN109973130A true CN109973130A (en) | 2019-07-05 |
CN109973130B CN109973130B (en) | 2023-09-08 |
Family
ID=67086451
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910342163.0A Active CN109973130B (en) | 2019-04-26 | 2019-04-26 | Construction system and method for realizing one-time traction of extra-long tunnel anchor narrow space by main cable strand |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109973130B (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111877176A (en) * | 2020-07-31 | 2020-11-03 | 中交武汉港湾工程设计研究院有限公司 | Anchor structure for spreading anchor cable into anchor of guide tunnel and construction method |
CN112176871A (en) * | 2020-09-15 | 2021-01-05 | 中交二公局第二工程有限公司 | Method for erecting suspension bridge main cable with tunnel type anchors at two sides |
CN113830111A (en) * | 2021-10-30 | 2021-12-24 | 浙江天弘机器人科技有限公司 | Low-carbon cableway for power transmission line construction and working method thereof |
CN114108480A (en) * | 2021-12-01 | 2022-03-01 | 中交第二航务工程局有限公司 | Full-section downward-sliding erection structure of suspension bridge catwalk and construction method thereof |
Citations (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH05256019A (en) * | 1992-03-11 | 1993-10-05 | Fujii Denko Co Ltd | Work scaffolding for deep foundation |
JPH083922A (en) * | 1994-06-21 | 1996-01-09 | Hazama Gumi Ltd | Suspension bridge anchor and construction method |
CN202543805U (en) * | 2011-12-01 | 2012-11-21 | 中交二公局第二工程有限公司 | Rear anchor lifting device for erection of major strand of suspension bridge in PPWS (precast parallel wire strand) construction |
CN104631320A (en) * | 2014-12-29 | 2015-05-20 | 大连理工大学 | Tunnel anchor of single-hole double-anchor system |
US20150211205A1 (en) * | 2014-01-29 | 2015-07-30 | Guangzhou Jishi Construction Group Co., Ltd. | Construction system for subway station |
CN105888706A (en) * | 2016-06-13 | 2016-08-24 | 中国葛洲坝集团基础工程有限公司 | Multifunctional steel trolley capable of being moved and lifted and method for mounting top arch arc plate steel cover |
CN106012855A (en) * | 2016-06-22 | 2016-10-12 | 四川路桥华东建设有限责任公司 | System for fast mounting steel pull rod in ultra-long and large-dip-angle tunnel anchorage and operation method |
CN107119572A (en) * | 2017-06-22 | 2017-09-01 | 四川路桥华东建设有限责任公司 | A kind of main rope of suspension bridge strand second traction enters the construction method of tunnel anchorage |
CN107313786A (en) * | 2017-06-30 | 2017-11-03 | 云南公投建设集团隧道工程有限公司 | Chassis trailer system |
CN108468554A (en) * | 2018-06-08 | 2018-08-31 | 涪特智能装备(重庆)有限公司 | The mechanical laying method of tunnel trolley and earth water-proof plate and two lining longitudinal reinforcements |
CN108708756A (en) * | 2018-08-31 | 2018-10-26 | 四川路桥华东建设有限责任公司 | A kind of tunnel anchorage is interior to utilize the construction system and method that dissipate cable saddle buttress anchoring cat road head-rope |
CN109137758A (en) * | 2018-11-23 | 2019-01-04 | 中交第三航务工程局有限公司 | A kind of self-anchored suspension bridge cable construction technology |
CN210003305U (en) * | 2019-04-26 | 2020-01-31 | 四川路桥华东建设有限责任公司 | Construction system for achieving traction in place in narrow anchor space of ultra-long tunnel in modes |
-
2019
- 2019-04-26 CN CN201910342163.0A patent/CN109973130B/en active Active
Patent Citations (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH05256019A (en) * | 1992-03-11 | 1993-10-05 | Fujii Denko Co Ltd | Work scaffolding for deep foundation |
JPH083922A (en) * | 1994-06-21 | 1996-01-09 | Hazama Gumi Ltd | Suspension bridge anchor and construction method |
CN202543805U (en) * | 2011-12-01 | 2012-11-21 | 中交二公局第二工程有限公司 | Rear anchor lifting device for erection of major strand of suspension bridge in PPWS (precast parallel wire strand) construction |
US20150211205A1 (en) * | 2014-01-29 | 2015-07-30 | Guangzhou Jishi Construction Group Co., Ltd. | Construction system for subway station |
CN104631320A (en) * | 2014-12-29 | 2015-05-20 | 大连理工大学 | Tunnel anchor of single-hole double-anchor system |
CN105888706A (en) * | 2016-06-13 | 2016-08-24 | 中国葛洲坝集团基础工程有限公司 | Multifunctional steel trolley capable of being moved and lifted and method for mounting top arch arc plate steel cover |
CN106012855A (en) * | 2016-06-22 | 2016-10-12 | 四川路桥华东建设有限责任公司 | System for fast mounting steel pull rod in ultra-long and large-dip-angle tunnel anchorage and operation method |
CN107119572A (en) * | 2017-06-22 | 2017-09-01 | 四川路桥华东建设有限责任公司 | A kind of main rope of suspension bridge strand second traction enters the construction method of tunnel anchorage |
CN107313786A (en) * | 2017-06-30 | 2017-11-03 | 云南公投建设集团隧道工程有限公司 | Chassis trailer system |
CN108468554A (en) * | 2018-06-08 | 2018-08-31 | 涪特智能装备(重庆)有限公司 | The mechanical laying method of tunnel trolley and earth water-proof plate and two lining longitudinal reinforcements |
CN108708756A (en) * | 2018-08-31 | 2018-10-26 | 四川路桥华东建设有限责任公司 | A kind of tunnel anchorage is interior to utilize the construction system and method that dissipate cable saddle buttress anchoring cat road head-rope |
CN109137758A (en) * | 2018-11-23 | 2019-01-04 | 中交第三航务工程局有限公司 | A kind of self-anchored suspension bridge cable construction technology |
CN210003305U (en) * | 2019-04-26 | 2020-01-31 | 四川路桥华东建设有限责任公司 | Construction system for achieving traction in place in narrow anchor space of ultra-long tunnel in modes |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111877176A (en) * | 2020-07-31 | 2020-11-03 | 中交武汉港湾工程设计研究院有限公司 | Anchor structure for spreading anchor cable into anchor of guide tunnel and construction method |
CN111877176B (en) * | 2020-07-31 | 2021-12-31 | 中交武汉港湾工程设计研究院有限公司 | Anchor structure for spreading anchor cable into anchor of guide tunnel and construction method |
CN112176871A (en) * | 2020-09-15 | 2021-01-05 | 中交二公局第二工程有限公司 | Method for erecting suspension bridge main cable with tunnel type anchors at two sides |
CN113830111A (en) * | 2021-10-30 | 2021-12-24 | 浙江天弘机器人科技有限公司 | Low-carbon cableway for power transmission line construction and working method thereof |
CN113830111B (en) * | 2021-10-30 | 2022-08-02 | 浙江天弘机器人科技有限公司 | Low-carbon cableway for power transmission line construction and working method thereof |
CN114108480A (en) * | 2021-12-01 | 2022-03-01 | 中交第二航务工程局有限公司 | Full-section downward-sliding erection structure of suspension bridge catwalk and construction method thereof |
CN114108480B (en) * | 2021-12-01 | 2023-05-26 | 中交第二航务工程局有限公司 | Suspension bridge catwalk full-section lower sliding frame arrangement structure and construction method thereof |
Also Published As
Publication number | Publication date |
---|---|
CN109973130B (en) | 2023-09-08 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109973130A (en) | Once draw construction system and method in place in a kind of main cable strand realization narrow space of Super Long Tunnel anchor | |
CN102444086B (en) | Cable hanging system for inclined stay cable of bridge and cable hanging method for inclined stay cable of bridge | |
CN201209090Y (en) | Ropeway cable crane using single machine traction and lifting at steep terrain | |
CN101967796B (en) | Method for arranging parallel steel wire stay cable | |
CN210003305U (en) | Construction system for achieving traction in place in narrow anchor space of ultra-long tunnel in modes | |
CN201272942Y (en) | Mounting angle regulation apparatus for stay cable column end of stayed-cable bridge | |
CN107119572A (en) | A kind of main rope of suspension bridge strand second traction enters the construction method of tunnel anchorage | |
CN109610922B (en) | Typical topography iron tower assemblage construction equipment | |
CN102815627A (en) | Automatic traction system for large-scale tower-type crane standard-knot removal and installation | |
CN109944166B (en) | Ultra-long large-dip-angle tunnel anchor large-tonnage cable saddle sliding and mounting system and operation method | |
CN109853393A (en) | A kind of the hanging cable construction system and its construction method of king-tower vertical transfer cable-stayed bridge | |
CN212670303U (en) | Stay cable beam end mounting structure | |
CN212025936U (en) | Equipment for mounting continuous steel strand stay cable at tower end of cable-stayed bridge | |
CN204958233U (en) | Tower crane plays to rise wire rope and holds in palm rope device | |
CN216235734U (en) | Vertical transportation hoisting structure for curtain wall unit plate | |
CN107344697A (en) | Cable boom hoisting | |
CN206986731U (en) | A kind of suspension cable lashing trailer system | |
CN106044579B (en) | Cable machine walking dolly auxiliary traction carrying rope crosses river structure and method | |
CN210178366U (en) | Scattered cable saddle portal system of narrow space tunnel anchor of super large inclination | |
CN209955996U (en) | Inclined shaft sports car protector | |
CN205916922U (en) | Cable machine walking dolly is supplementary to be pull ropeway carrying -rope and crosses river structure | |
CN209836818U (en) | Large-tonnage cable saddle gliding and mounting system for ultra-long large-inclination-angle tunnel anchor | |
CN104386602A (en) | Inclined roadway trackless auxiliary transportation method and device | |
CN107178044A (en) | A kind of method that I-shaped gooseneck is worn under during jacking bridge and culvert track strengthening | |
CN204750193U (en) | Automatic decoupling device device in sub -inclined shaft pittop |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |