CN109948285A - A kind of large size Karst depression ball crown type mechanism central excavation localization method - Google Patents

A kind of large size Karst depression ball crown type mechanism central excavation localization method Download PDF

Info

Publication number
CN109948285A
CN109948285A CN201910251303.3A CN201910251303A CN109948285A CN 109948285 A CN109948285 A CN 109948285A CN 201910251303 A CN201910251303 A CN 201910251303A CN 109948285 A CN109948285 A CN 109948285A
Authority
CN
China
Prior art keywords
central excavation
project
excavation
optimal
total cost
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910251303.3A
Other languages
Chinese (zh)
Inventor
沈志平
朱博勤
吴斌
李颀
姜鹏
付君宜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhengye Engineering & Investment Inc Ltd
National Astronomical Observatories of CAS
Original Assignee
Zhengye Engineering & Investment Inc Ltd
National Astronomical Observatories of CAS
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhengye Engineering & Investment Inc Ltd, National Astronomical Observatories of CAS filed Critical Zhengye Engineering & Investment Inc Ltd
Priority to CN201910251303.3A priority Critical patent/CN109948285A/en
Publication of CN109948285A publication Critical patent/CN109948285A/en
Pending legal-status Critical Current

Links

Landscapes

  • Buildings Adapted To Withstand Abnormal External Influences (AREA)

Abstract

The invention discloses a kind of large-scale Karst depression ball crown type mechanism central excavation localization methods, method includes the following steps: 1) choosing mechanism central excavation candidate region;2) factor for influencing central excavation positioning is determined;3) primary election determines more excellent central excavation point plane coordinates;4) optimal elevation plane is determined;5) it is accurately positioned in optimal elevation plane and obtains optimal mechanism central excavation.Different location of the present invention by simulation ball crown type structures central excavation in large-scale Karst depression, using project total cost as constraint condition, solve position of the ball crown type mechanism center in large-scale Karst depression, it realizes the optimization output of large-scale Karst depression ball crown type mechanism central excavation and is accurately positioned, provided for large-scale Karst depression ball crown type mechanism central excavation positioning a kind of scientific and rational with reference to method.

Description

A kind of large size Karst depression ball crown type mechanism central excavation localization method
Technical field
The present invention relates to a kind of large-scale Karst depression ball crown type mechanism central excavation localization methods.
Background technique
Karst depression be carbonate rock area since corrosion is formed by a kind of negative land form, depression bottom configuration are flat Smooth, diameter is generally by hundreds of meters to thousands of rice etc..For large-scale Karst depression especially large-scale circular Karst depression, It is especially suitable for building ball crown type structures.However, the central excavation position of different ball crown type structures will generate different excavations Effect, such as different centers will generate different excavated volumes, geology endangers control amount.In short, excavation effect should be Under the premise of guaranteeing ball crown type structures safety, meet the installation requirements of ball crown type structures, while considering ball crown type structures Integral constructing cost, to greatest extent reduce excavation project amount.Therefore, in the optimal excavation for how positioning ball crown type structures The heart realizes that the rationalization of large-scale Karst depression is excavated, and large-scale Karst depression ball crown type mechanism must be taken into consideration when building Problem.
Summary of the invention
The technical problem to be solved by the present invention is providing a kind of large-scale Karst depression ball crown type mechanism central excavation positioning Method, to solve in large-scale Karst depression excavation project, since the center of different ball crown type structures will generate difference Excavation effect, need to position the optimal central excavation of ball crown type structures, realize the optimization, rationally of large-scale Karst depression Change Excavation Problems.
The technical scheme adopted by the invention is as follows: a kind of large size Karst depression ball crown type mechanism central excavation localization method, The method steps are as follows:
1) it is waited in the spherical crown structures central excavation that large-scale Karst depression bottom centre position chooses a setting range Favored area;
2) impact factor for influencing central excavation positioning is determined, impact factor includes earthwork evacuation engineering, the molten megalith that collapses Mixture harnessing project, Unstable Rock Treatment engineering, slope project, drainage system and spherical crown structures construction cost;
3) primary election determines more excellent central excavation point plane coordinates: with biggest impact factor earthwork evacuation in candidate region Engineering is computing object, by interactive integral algorithm, calculates earthwork evacuation engineering when central excavation depth is setting value Amount, obtains excavation project amount isogram, primarily determines that the central point of excavated volume isogram is more excellent central excavation point;
4) it determines optimal elevation plane: being the excavation assumed with more excellent central excavation plane coordinates in each elevation plane Center calculates the project total cost of corresponding elevation plane, is with elevation by calculating the corresponding project cost of each impact factor Abscissa, project total cost are ordinate, determine optimal elevation plane;
5) it is accurately positioned in optimal elevation plane: in optimal elevation plane, using more excellent central excavation point as origin, into one Step chooses the region of a setting range, with the spacing being sized, project total cost distribution of contours figure, in setting range In region, according to project total cost isogram, an optimal region being sized further is chosen, in the region Point is encrypted, and to be sized value as spacing, is calculated the corresponding project total cost of each pass point, is obtained in optimal region and add Close coordinate and corresponding engineering total cost table;
6) choose fitting function, to project cost value in closed points coordinate in optimal region and corresponding engineering total cost table into The fitting of row three-dimensional space curved surface, using coordinate points x, y as independent variable, selection project total cost is dependent variable Z, constructs binary function, Seek the minimum of function, it is assumed that function shape is paraboloid, with the method for undetermined coefficients, constructs the binary function about x, y and Z Form is as follows:
Z=Ax2+Bx+Cy2+Dy+Exy+F
In formula, A, B, C, D, E and F are binary function coefficient, and binary function coefficient obtains function such as following formula institute by fitting Show, correlation coefficient r2=0.9786:
Z=90.484x2+459.859x+56.120y2+8.522y-87.460xy+9836.042
In formula: x is horizontal direction, and y is vertical direction, is that optimal mechanism is excavated to the minimum point that binary function is sought Center.
Beneficial effects of the present invention: compared with prior art, the present invention is existed by simulating ball crown type structures central excavation Different location in large-scale Karst depression comprehensively considers earthwork evacuation engineering, the molten megalith mixture harnessing project, crag of collapsing Harnessing project, slope project, drainage system, spherical crown structures construction cost multiple impact factors, by multiple impact factor meters The project total cost of calculation is constraint condition, solves position of the ball crown type mechanism center in large-scale Karst depression, is realized large-scale The optimization of Karst depression ball crown type mechanism central excavation is exported and is accurately positioned, for large-scale Karst depression ball crown type mechanism Central excavation positioning provides a kind of scientific and rational with reference to method.
Detailed description of the invention
Fig. 1 is flow chart of the invention.
Excavation project amount distribution of contours figure when Fig. 2 is primary election.
Project total cost curve (containing each impact factor cost) figure when Fig. 3 determines optimal elevation.
Excavation project total cost isogram when being accurately positioned in the optimal elevation plane of Fig. 4.
Fig. 5 is the central excavation point location drawing finally solved.
Specific embodiment
With reference to the accompanying drawing and the present invention is described further in specific embodiment.
Embodiment 1: as Figure 1-Figure 5, a kind of large size Karst depression ball crown type mechanism central excavation localization method should Method and step is as follows:
1) in depression, bottom centre chooses one 100 meters × 100 meters of square area: intending in a large-scale Karst depression A spherical crown structures are built, bottom center region chooses one 100 meters × 100 meters of candidate region in depression thus, as ball crown type The region that structures center can arbitrarily move.Depression bottom original ground lowest elevation is 841 meters, by qualitative analysis, is determined Cutting depth principle is as follows: the lower limit of central excavation depth is 13 meters, i.e., 828 meters;The upper limit of central excavation depth is 5 meters, i.e., 836 meters.
2) it analyzes and determines impact factor: choosing the factor for influencing the selection of spherical crown structures center, including earthwork evacuation Engineering, the molten megalith mixture harnessing project that collapses, Unstable Rock Treatment engineering, slope project, drainage system, spherical crown structures are built into This.
3) primary election determines more excellent central excavation point plane coordinates: with maximum in 1) described 100 meters × 100 meters candidate regions Impact factor earthwork evacuation engineering is computing object, by interactive integral algorithm, when calculating central excavation depth is 13 meters Earthwork evacuation project amount, obtain excavation project amount isogram, see attached drawing 2, primarily determine in excavated volume isogram Heart point is more excellent central excavation point 1.
4) it determines optimal elevation: being optimization origin with more excellent central excavation point 1 in 828 meters~836 meters elevation planes, Consider all impact factors, i.e. earthwork evacuation engineering, molten megalith mixture harnessing project, Unstable Rock Treatment engineering, the side slope work of collapsing Journey, drainage system, spherical crown structures construction cost increment.The corresponding project cost of each impact factor is calculated, it is total to obtain engineering Cost.Specifically: with 1 meter for ladder, the position of central excavation point 1 is raised step by step, is calculated separately in 828 meters~836 meters elevations The corresponding excavation project total cost of more excellent central excavation point 2 obtains project total cost curve graph (containing each impact factor cost), sees Attached drawing 3.By attached drawing 3 it is found that in the case where comprehensively considering all impact factors, when elevation is 834 meters, project total cost is most It is low, therefore optimal elevation is 834 meters.
5) it is accurately positioned in optimal elevation plane: being origin with more excellent central excavation point 1 in 834 meters of optimal elevation, choosing 20 meters × 20 meters regions 2 are taken to obtain project total cost distribution of contours figure with 2 meters for spacing, see attached drawing 4.
In aforementioned 20 meters × 20 meters regions 2, according to project total cost isogram, one 4 meters × 5 meters are further chosen Optimal region 3, the point in the region is encrypted, with 1 meter for spacing, the corresponding engineering of each pass point is calculated and always makes Valence, as shown in table 1.
Closed points coordinate and corresponding engineering total cost table in 1 optimal region 3 of table
6) fitting function is chosen, three-dimensional space curved surface fitting is carried out to project cost value in table 1.In table 1, since x, y are Independent variable, therefore choosing project total cost is dependent variable Z, constructs binary function, seeks the minimum of function.Assuming that function shape is Paraboloid constructs as follows about the binary function form of x, y and Z with the method for undetermined coefficients:
Z=Ax2+Bx+Cy2+Dy+Exy+F
By fitting, obtains function and be shown below (correlation coefficient r2=0.9786):
Z=90.484x2+459.859x+56.120y2+8.522y-87.460xy+9836.042
In formula: x is horizontal direction, and y is vertical direction.
The minimum that curved surface is sought to above formula, acquiring optimum coordinates value is (- 4.1349, -3.2866), and the value is as optimal Central excavation point 4, locating elevation are 834 meters, see attached drawing 5.
The above description is merely a specific embodiment, but scope of protection of the present invention is not limited thereto, any Those familiar with the art in the technical scope disclosed by the present invention, can easily think of the change or the replacement, and should all contain Within protection scope of the present invention, therefore, protection scope of the present invention should be based on the protection scope of the described claims lid.

Claims (1)

1. a kind of large size Karst depression ball crown type mechanism central excavation localization method, it is characterised in that: the method steps are as follows:
1) the spherical crown structures central excavation candidate regions of a setting range are chosen in large-scale Karst depression bottom centre position Domain;
2) determine that the impact factor for influencing central excavation positioning, impact factor include earthwork evacuation engineering, molten megalith mixing of collapsing Body harnessing project, Unstable Rock Treatment engineering, slope project, drainage system and spherical crown structures construction cost;
3) primary election determines more excellent central excavation point plane coordinates: with biggest impact factor earthwork evacuation engineering in candidate region Earthwork evacuation project amount when central excavation depth is setting value is calculated, is obtained by interactive integral algorithm for computing object To excavation project amount isogram, primarily determine that the central point of excavated volume isogram is more excellent central excavation point;
4) it determines optimal elevation plane: being the central excavation assumed with more excellent central excavation plane coordinates in each elevation plane, By calculating the corresponding project cost of each impact factor, the project total cost of corresponding elevation plane is calculated, with elevation for horizontal seat Mark, project total cost is ordinate, determines optimal elevation plane;
5) it is accurately positioned in optimal elevation plane: in optimal elevation plane, using more excellent central excavation point as origin, further selecting The region of a setting range is taken, with the spacing being sized, project total cost distribution of contours figure, in the region of setting range It is interior, according to project total cost isogram, an optimal region being sized further is chosen, the point in the region is carried out Encryption calculates the corresponding project total cost of each pass point to be sized value as spacing, obtains pass point in optimal region and sits Mark and corresponding engineering total cost table;
6) fitting function is chosen, three are carried out to project cost value in closed points coordinate in optimal region and corresponding engineering total cost table Dimension space surface fitting, using coordinate points x, y as independent variable, selection project total cost is dependent variable Z, constructs binary function, seeks The minimum of function, it is assumed that function shape is paraboloid, with the method for undetermined coefficients, constructs the binary function form about x, y and Z It is as follows:
Z=Ax2+Bx+Cy2+Dy+Exy+F
In formula, A, B, C, D, E and F are binary function coefficient, and binary function coefficient is obtained function and be shown below by fitting, Correlation coefficient r2=0.9786:
Z=90.484x2+459.859x+56.120y2+8.522y-87.460xy+9836.042
In formula: x is horizontal direction, and y is vertical direction, is during optimal mechanism is excavated to the minimum point that binary function is sought The heart.
CN201910251303.3A 2019-03-29 2019-03-29 A kind of large size Karst depression ball crown type mechanism central excavation localization method Pending CN109948285A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910251303.3A CN109948285A (en) 2019-03-29 2019-03-29 A kind of large size Karst depression ball crown type mechanism central excavation localization method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910251303.3A CN109948285A (en) 2019-03-29 2019-03-29 A kind of large size Karst depression ball crown type mechanism central excavation localization method

Publications (1)

Publication Number Publication Date
CN109948285A true CN109948285A (en) 2019-06-28

Family

ID=67013057

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910251303.3A Pending CN109948285A (en) 2019-03-29 2019-03-29 A kind of large size Karst depression ball crown type mechanism central excavation localization method

Country Status (1)

Country Link
CN (1) CN109948285A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110516399A (en) * 2019-09-03 2019-11-29 贵州正业工程技术投资有限公司 A kind of Karst depression ball crown type is peeled off earthwork calculation method
CN110516398A (en) * 2019-09-03 2019-11-29 贵州正业工程技术投资有限公司 A kind of Karst depression ball crown type of spherical coordinates is peeled off earthwork calculation method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101210814A (en) * 2006-12-31 2008-07-02 西安长庆科技工程有限责任公司 Line engineering GPS control network height fitting method
CN103729542A (en) * 2013-10-31 2014-04-16 中国人民解放军空军工程大学 System and method for optimization design of terrain of large multi-track and multi-taxi-track airport
CN106400782A (en) * 2016-06-28 2017-02-15 中铁隧道集团二处有限公司 Construction method for construction of foundation pit support bored secant pile walls with rotary drilling rig

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101210814A (en) * 2006-12-31 2008-07-02 西安长庆科技工程有限责任公司 Line engineering GPS control network height fitting method
CN103729542A (en) * 2013-10-31 2014-04-16 中国人民解放军空军工程大学 System and method for optimization design of terrain of large multi-track and multi-taxi-track airport
CN106400782A (en) * 2016-06-28 2017-02-15 中铁隧道集团二处有限公司 Construction method for construction of foundation pit support bored secant pile walls with rotary drilling rig

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
徐明 等: "FAST 大型岩溶洼地场地岩土治理关键技术研究", 《土木工程学报》 *
潘兵 等: "数字图像相关中亚像素位移测量的曲面拟合法", 《计量学报》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110516399A (en) * 2019-09-03 2019-11-29 贵州正业工程技术投资有限公司 A kind of Karst depression ball crown type is peeled off earthwork calculation method
CN110516398A (en) * 2019-09-03 2019-11-29 贵州正业工程技术投资有限公司 A kind of Karst depression ball crown type of spherical coordinates is peeled off earthwork calculation method
CN110516399B (en) * 2019-09-03 2020-04-14 贵州正业工程技术投资有限公司 Karst depression spherical crown type shelling excavation square amount calculation method

Similar Documents

Publication Publication Date Title
CN103188693B (en) Downtilt based on GIS-Geographic Information System determines method and device
CN109948285A (en) A kind of large size Karst depression ball crown type mechanism central excavation localization method
CN104850682B (en) Location-based Multiple-Point Geostatistics modeling method
CN112419500B (en) Three-dimensional geological model modeling method
CN106446349B (en) A kind of calculation method of the earthwork original place amortization based on revit software
CN1858803A (en) Three dimension uniform model construction method of water conservancy hydropower engineering geological information
CN106202648A (en) Tunnel portal position automatization is than the BIM method for designing of choosing
CN103226847B (en) A kind of meandering river point bar 3-D data volume generation method and device
CN103077558A (en) Method for establishing large-sized karst cave reservoir body distribution model of fractured-vuggy carbonate rock reservoir
CN105528503A (en) Large structure dynamic optimization design method based on structural decomposition
CN106909740B (en) Method and device for calculating total map earthwork amount of oil and gas storage and transportation station
CN107766978B (en) Intelligent optimization method for irregular well pattern
CN108875177A (en) Method based on cruiseway dredging figure under BIM model creation simple beam measuring point
CN112687001B (en) Three-dimensional geological structure model random generation and uncertainty analysis method
CN110348046B (en) Drilling track multi-target optimization method based on fuzzy comprehensive evaluation
CN107481320A (en) A kind of gridless routing of three-dimensional geological modeling
CN103218850B (en) One very three-dimensional mining blasting unit model method for building up
Baltar et al. A generalized multiobjective particle swarm optimization solver for spreadsheet models: application to water quality
CN109977528A (en) Mixed dam BIM universal model design method and application of the gravity dam in conjunction with earth and rockfill dam
CN112772098A (en) Variable irrigation and fertilization zoning method for large-scale sprinkler
CN109829195A (en) Earthwork calculation method based on BIM
CN109918846A (en) A kind of Karst depression central excavation localization method using concentric circles
CN111101941A (en) Boundary optimization-based shallow advanced treatment method for excavation depth pad of high-diving-level coal mining subsidence area
CN113486429B (en) Automatic construction method of space intersection structure based on interpolation algorithm
CN106326588B (en) A kind of method of BIM auxiliary dam storehouse surface design

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190628

RJ01 Rejection of invention patent application after publication