CN109812002A CN201910061683.4A CN201910061683A CN109812002A CN 109812002 A CN109812002 A CN 109812002A CN 201910061683 A CN201910061683 A CN 201910061683A CN 109812002 A CN109812002 A CN 109812002A
Authority
CN
China
Prior art keywords
boiler
support frame
support
support platform
ash mouth
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910061683.4A
Other languages
Chinese (zh)
Inventor
施吉祥
郭余庆
郭国庆
王读根
季荣华
戴春浩
张凤
孙曙光
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JIANGSU NENGJIAN ELECTROMECHANICAL INDUSTRIAL Co Ltd
Original Assignee
JIANGSU NENGJIAN ELECTROMECHANICAL INDUSTRIAL Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIANGSU NENGJIAN ELECTROMECHANICAL INDUSTRIAL Co Ltd filed Critical JIANGSU NENGJIAN ELECTROMECHANICAL INDUSTRIAL Co Ltd
Priority to CN201910061683.4A priority Critical patent/CN109812002A/en
Publication of CN109812002A publication Critical patent/CN109812002A/en
Pending legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

This case is related to a kind of boiler maintenance ash mouth support platform, it is characterised in that: the support platform is built by several support frames;Support frame as described above includes two vertical poles and several cross bars for being fixedly welded between two vertical poles;The vertical pole both ends of support frame as described above are hinged with other support frames respectively, form continuous support frame chain;For the present invention by the fold combination of support frame chain, composed structure is simple, has higher support strength, can in flexible adaptation boiler Anomalistic space boiler maintenance ash mouth support platform, the support platform globality built is strong, and safety is preferable;Support frame chain etc., which builds material, can easily pass in and out boiler manhole, reduce the material transportation time, and the conveying of material and builds or dismantle and can carry out simultaneously.

Description

For boiler maintenance ash mouth support platform and building method
Technical field
The invention belongs to boiler maintenance technical fields, and in particular to one kind is for boiler maintenance ash mouth support platform and builds Method.
Background technique
Currently, the maintenance of China overwhelming majority heat power plant boiler burner hearth is all made of boiler hearth overhauling platform.Conventional Inspection platform mostly uses scaffolding steel pipe to be built layer by layer, is then being laid with bamboo raft or stationary grid formation operation horizontal above Face, operator moves back and forth between different work surfaces to overhaul.Boiler hearth overhauling platform has easy to use, safety The features such as property is high.
It is very easy in the service work face that the outside of boiler is built using scaffold, and if to be carried out to boiler furnace Maintenance, then overhauled by building scaffold it is then cumbersome, since people or object disengaging boiler will be by diameters about The manhole of 450MM transmits, and transports several tons even tens of tons of scaffolding steel pipe and enters in furnace, then building steel pipe one by one With connect, build several meters even the high hanging working faces of tens of rice, in boiler it is narrow closing, illumination is bad and has more In the environment of prominent sharp portion, this building is time-consuming, laborious and dangerous work, and careless slightly, scaffolding steel pipe falls Or water-cooling wall or other devices in touching boiler, the damage of device in boiler or water-cooling wall just face wear-and corrosion-resistant will be may cause Protective layer is damaged, and operator may cause grievous injury as fallen accidentally.
It is overhauled under environment in such boiler, the scaffold inspection platform for building 600 sides or so cube generally requires 2 days Time, and dismounting also at least needs one day time, and the every blowing out of boiler one day, biggish economy can be all caused to manufacturer Loss;Also, the price for asking construction brigade to build scaffolding steel pipe is equally high.
After the completion of scaffold inspection platform is built, operator moves back and forth in different operational levels carries out maintenance behaviour Make, it is dangerous and inconvenient, due to scaffolding steel pipe block, also will affect spraying abrasion-proof layer, the defect repair welding of service personnel Deng operation;It is mobile in working face because usually having the gap and being uneven between the bamboo raft or screen that are laid on working face Large-scale or compared with heavy equipment when, has no idea smoothly to be moved or be easy to above to be stuck, and operator is when moving above It is also possible to be tripped.
In addition, when building boiler maintenance ash mouth support platform using scaffold, not due to boiler maintenance ash mouth normally shape Rule, it is difficult to smoothly build biggish support platform, if lime-ash is accumulated, boiler maintenance ash mouth support platform but will be increased and built Difficulty.
In view of this, it is necessary to propose that a kind of structure is simple, build rapid, adaptability and safety is good and be examined for boiler Repair grey mouth support platform.
Summary of the invention
The object of the present invention is to provide a kind of structures simply, builds the boiler maintenance ash mouth that is used for rapid, at low cost supports Platform.
It is a further object to provide a kind of included clamp device, safety is good, builds material access manhole side Just be used for boiler maintenance ash mouth support platform and building method.
In order to solve the above-mentioned technical problem, the invention discloses a kind of boiler maintenance ash mouth support platform, the support is flat Platform is built by several support frames;Support frame as described above includes two vertical poles and several cross bars for being fixedly welded between two vertical poles;
The vertical pole both ends of support frame as described above are hinged with other support frames respectively, form continuous support frame chain;
Support frame as described above is equipped with fixation hole and hold-down bars, and the fixation hole includes coaxial limiting section and fixed part, fixed part Under limiting section, and the diameter of fixed part is less than limiting section, and the fixed part is equipped with internal screw thread;
Described hold-down bars one end and support frame are hinged, and the other end is equipped with spherical or cylindrical boss, are equipped with through-hole in the middle part of the boss, Fastening bolt is equipped in through-hole, the through-hole and fastening bolt are threadedly coupled, and the boss diameter matches with the limiting section, The fixed part diameter matches with fastening bolt.
Preferably, the hold-down bars is connected and fixed by fastening bolt and the fixation hole on adjacent supports frame.
Preferably, adjacent two support frame is in 90 ° of angles.
Preferably, support frame as described above width is less than the diameter of boiler manhole.
Preferably, the support platform maximum can bear 250kg/m2Pressure.
Preferably, the every 50-200m of support frame as described above chain is one section.
A kind of building method of boiler maintenance ash mouth support platform, enters boiler from manhole by service personnel, then will branch Support chain is continuously introduced into boiler from manhole, according to space structure in boiler by support frame chain fold be combined into it is several be connected, on The square shaped cells of lower stacking, and the hold-down bars on each support frame is passed through into fastening bolt and consolidating on adjacent supports frame respectively Determine hole to be connected and fixed;To be built into the support platform being spliced by several square shaped cells, at the top of support platform Set up protective net or railing.
Preferably, height and length when the support platform is built need with pot furnace inner space or maintenance and are changed.
Preferably, it when support frame chain being sent into boiler from manhole, to avoid damage to manhole, adds and protects in manhole surrounding Support frame chain is sequentially sent in boiler again after sheath.
It preferably, first will be convex when hold-down bars being connected and fixed by the fixation hole in fastening bolt and adjacent supports frame Platform is docked with the limiting section in fixation hole, then by fastening bolt precession fixed part to install fixation.
Of the invention is used for boiler maintenance ash mouth support platform and building method, has at least the following advantages:
1. by the fold combination of support frame chain, composed structure is simple, has higher support strength, can not be advised in flexible adaptation boiler The then boiler maintenance ash mouth support platform in space, the support platform globality built is strong, and safety is preferable.
2. support frame chain etc., which builds material, can easily pass in and out boiler manhole, reduce the material transportation time, and material Conveying and build or dismantling to carry out simultaneously.
3. when building by hold-down bars can fixation hole be connected and fixed rapidly, only need to be by fastening bolt and fixation hole point when disassembly From it is convenient and rapid to build, and compared with building scaffold inspection platform, holistic conformation and dismounting time are greatly shortened.
4. hold-down bars is connected with support frame, compared with building scaffold inspection platform, reduce fastener carrying, location and installation Trouble, and prevented part and fallen the possibility hurted sb.'s feelings, increased safety coefficient, kept installation more convenient rapidly.
5. fixation hole includes limiting section and fixed part, limiting section can make the rapid alignment and fixation hole of the boss of hold-down bars, side Fastening bolt be tightened, when disassembly, fastening bolt need to only be made to be detached from fixed part, without by fastening bolt completely from It is removed on boss, facilitates disassembly and installation next time.
6. by portable manually or electrically tool, the installation that hold-down bars can be rapidly completed in one or double cooperation is fixed.
Detailed description of the invention
Fig. 1 is a kind of schematic perspective view of support frame.
Fig. 2 is a kind of main view of support frame.
Fig. 3 is a kind of schematic perspective view of support frame chain.
Fig. 4 is a kind of schematic perspective view of square shaped cells being made of support frame.
Fig. 5 is a kind of boiler maintenance ash mouth support platform schematic perspective view being made of square shaped cells.
Specific embodiment
Below by embodiment, the present invention is described in further detail, to enable those skilled in the art referring to specification Text can be implemented accordingly.
Such as " have " it should be appreciated that used herein, "comprising" and " comprising " term are not precluded one or more The presence or addition of a other elements or combinations thereof.
Embodiment 1
As shown in Figs 1-4, a kind of boiler maintenance ash mouth support platform, the support platform are built by several support frames 1;Institute State several cross bars 3 that support frame 1 includes two vertical poles 2 and is fixedly welded between two vertical poles;The length of each support frame 1 is 1m, wide 0.4m。
2 both ends of vertical pole of support frame as described above are hinged with other support frames 1 respectively, form continuous support frame chain A;Every section of branch The length of support chain A is 100m.Support frame chain is continuously introduced into boiler internal by manhole, support platform is greatly reduced and builds Time needed for material conveying.
Support frame as described above is equipped with fixation hole 4 and hold-down bars 5, and the fixation hole 4 includes coaxial limiting section 401 and fixes Portion 402, fixed part 402 are set under limiting section 401, and the diameter of fixed part 402 is less than limiting section 401, and the fixed part is set There is internal screw thread;Hold-down bars 5 is set on support frame, avoids the fastener for fastening being likely to occur when scaffold installation or removal The phenomenon that falling greatly reduces security risk.
Described 5 one end of hold-down bars and support frame are hinged, and the other end is equipped with spherical or cylindrical boss 501, the boss middle part Equipped with through-hole, fastening bolt 502 is equipped in through-hole, the through-hole and fastening bolt are threadedly coupled, 501 diameter of boss and institute It states limiting section 401 to match, 402 diameter of fixed part matches with fastening bolt 502.The boss being mutually matched and limit Portion, fixed part and fastening bolt facilitate the positioning and installation of hold-down bars, substantially reduce the set-up time,
The hold-down bars 5 is connected and fixed by fastening bolt 502 with the fixation hole 4 on adjacent supports frame.
Adjacent two support frame is in 90 ° of angles.
2 width of support frame as described above is less than the diameter of boiler manhole.So as to smoothly access manhole
The support platform maximum can bear 250kg/m2Pressure.Boiler maintenance ash mouth support platform of the invention is by several The square shaped cells B splicing of support composition stacks, and has preferable support strength.And slanting shearing force can be resisted.
The every 50-200m of support frame as described above chain A is one section.If boiler manhole is sufficiently large, support frame chain and inspection can permit Repair personnel while passing through, then can make support frame chain always some be in manhole and be connected with the external world, in this way remove support When platform C, material can be shortened and send out the time.
Embodiment 2
A kind of building method of boiler maintenance ash mouth support platform, enters boiler from manhole by service personnel, then by support frame Chain is continuously introduced into boiler from manhole, and the fold of support frame chain is combined into several connected, upper and lower heaps according to space structure in boiler Folded square shaped cells B, and the hold-down bars on each support frame is passed through into the fixation in fastening bolt and adjacent supports frame respectively Hole is connected and fixed;To be built into the support platform C as shown in Figure 5 being spliced by several square shaped cells, supporting The top shelf of platform C is set up defences protective net or railing.
Height and length when the support platform is built need with pot furnace inner space or maintenance and are changed.
When support frame chain is sent into boiler from manhole, to avoid damage to manhole, after manhole surrounding adds protective layer again Support frame chain A is sequentially sent in boiler.
Support frame chain A as a chain, installation personnel boiler internal either manually or by mechanical-assisted by support frame chain by Section pulls in boiler, while being installed;When disassembly similarly.
When hold-down bars 5 is connected and fixed by the fixation hole 4 in fastening bolt 502 and adjacent supports frame, first by boss 501 It is docked with the limiting section 401 in fixation hole 4, then by 502 precession fixed part 402 of fastening bolt to install fixation.
Embodiment 3
, can be arranged side by side by the single-row support platform B of two row or multi-row when needing wider boiler maintenance ash mouth support platform, side by side Mono-layer propping platform between reinforced by clamp devices such as fasteners, when necessary, slanting support column can be installed additional come offset tiltedly To impact force.
In addition, ideal height and shape, inevitably will appear support frame sometimes in order to obtain in the fold of support frame chain It repeats to turn down, the situation for causing two support frames arranged side by side, it at this time can be by interdependent position aperture on the support frame come solid with hold-down bars It is fixed, the clamp devices such as fastener can also be added additionally to carry out the fastening of two support frames arranged side by side.
Although the embodiments of the present invention have been disclosed as above, but its is not only in the description and the implementation listed With it can be fully applied to various fields suitable for the present invention, for those skilled in the art, can be easily Realize other modification, therefore without departing from the general concept defined in the claims and the equivalent scope, the present invention is simultaneously unlimited In specific details and embodiment shown and described herein.

Claims (10)

1. a kind of boiler maintenance ash mouth support platform, it is characterised in that: the support platform is built by several support frames;Institute State several cross bars that support frame includes two vertical poles and is fixedly welded between two vertical poles;
The vertical pole both ends of support frame as described above are hinged with other support frames respectively, form continuous support frame chain;
Support frame as described above is equipped with fixation hole and hold-down bars, and the fixation hole includes coaxial limiting section and fixed part, fixed part Under limiting section, and the diameter of fixed part is less than limiting section, and the fixed part is equipped with internal screw thread;
Described hold-down bars one end and support frame are hinged, and the other end is equipped with spherical or cylindrical boss, are equipped with through-hole in the middle part of the boss, Fastening bolt is equipped in through-hole, the through-hole and fastening bolt are threadedly coupled, and the boss diameter matches with the limiting section, The fixed part diameter matches with fastening bolt.
2. being used for boiler maintenance ash mouth support platform as described in claim 1, which is characterized in that the hold-down bars passes through fastening Bolt is connected and fixed with the fixation hole on adjacent supports frame.
3. being used for boiler maintenance ash mouth support platform as claimed in claim 2, which is characterized in that adjacent two support frame is in 90 ° of angles.
4. being used for boiler maintenance ash mouth support platform as claimed in claim 3, which is characterized in that support frame as described above width is less than The diameter of boiler manhole.
5. being used for boiler maintenance ash mouth support platform as claimed in claim 4, which is characterized in that the support platform maximum can Bear 250kg/m2Pressure.
6. being used for boiler maintenance ash mouth support platform as claimed in claim 5, which is characterized in that the every 50- of support frame as described above chain 200m is one section.
7. a kind of building method of boiler maintenance ash mouth support platform described in claim 1, it is characterised in that: service personnel from Manhole enters boiler, is then continuously introduced into support frame chain in boiler from manhole, according to space structure in boiler by support frame chain Fold is combined into several connected, stacked on top square shaped cells, and the hold-down bars on each support frame is passed through fastening respectively Bolt is connected and fixed with the fixation hole on adjacent supports frame;To be built into the support being spliced by several square shaped cells Platform is set up defences protective net or railing in the top shelf of support platform.
8. the building method of boiler maintenance ash mouth support platform as claimed in claim 7, which is characterized in that the support platform Height and length when building need with pot furnace inner space or maintenance and are changed.
9. the building method of boiler maintenance ash mouth support platform as claimed in claim 8, which is characterized in that by support frame chain from When manhole is sent into boiler, to avoid damage to manhole, support frame chain is sequentially sent to pot again after manhole surrounding adds protective layer In furnace.
10. the building method of boiler maintenance ash mouth support platform as claimed in claim 9, which is characterized in that lead to hold-down bars When the fixation hole crossed on fastening bolt and adjacent supports frame is connected and fixed, first boss is docked with the limiting section in fixation hole, then By fastening bolt precession fixed part to install fixation.
CN201910061683.4A 2019-01-25 2019-01-25 For boiler maintenance ash mouth support platform and building method Pending CN109812002A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910061683.4A CN109812002A (en) 2019-01-25 2019-01-25 For boiler maintenance ash mouth support platform and building method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910061683.4A CN109812002A (en) 2019-01-25 2019-01-25 For boiler maintenance ash mouth support platform and building method

Publications (1)

Publication Number Publication Date
CN109812002A true CN109812002A (en) 2019-05-28

Family

ID=66604839

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910061683.4A Pending CN109812002A (en) 2019-01-25 2019-01-25 For boiler maintenance ash mouth support platform and building method

Country Status (1)

Country Link
CN (1) CN109812002A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101031697A (en) * 2004-03-31 2007-09-05 萨夫路服务有限公司 Articulating work platform support system, work platform system, and methods of use thereof
US20070240938A1 (en) * 2006-04-17 2007-10-18 Butera Brian A Ladder having improved mobility
CN202273584U (en) * 2011-09-01 2012-06-13 青岛捷马机电设备有限公司 Multifunctional folding ladder
EP2840202A1 (en) * 2013-08-23 2015-02-25 Hitachi Ltd. Working scaffold girder structure for a boiler furnace
CN205314521U (en) * 2016-01-11 2016-06-15 梁军 Quick installation and maintenance platform in boiler stove
CN206569099U (en) * 2017-02-09 2017-10-20 苏州丸石包装材料有限公司 A kind of folding type trolley
CN208168314U (en) * 2018-04-24 2018-11-30 中冶建工集团有限公司 Folding type hanging hanger operation platform

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101031697A (en) * 2004-03-31 2007-09-05 萨夫路服务有限公司 Articulating work platform support system, work platform system, and methods of use thereof
US20070240938A1 (en) * 2006-04-17 2007-10-18 Butera Brian A Ladder having improved mobility
CN202273584U (en) * 2011-09-01 2012-06-13 青岛捷马机电设备有限公司 Multifunctional folding ladder
EP2840202A1 (en) * 2013-08-23 2015-02-25 Hitachi Ltd. Working scaffold girder structure for a boiler furnace
CN205314521U (en) * 2016-01-11 2016-06-15 梁军 Quick installation and maintenance platform in boiler stove
CN206569099U (en) * 2017-02-09 2017-10-20 苏州丸石包装材料有限公司 A kind of folding type trolley
CN208168314U (en) * 2018-04-24 2018-11-30 中冶建工集团有限公司 Folding type hanging hanger operation platform

Similar Documents

Publication Publication Date Title
CN107558723B (en) Method for manufacturing and installing hanging bracket of hanging basket for inclined roof
CN203531493U (en) Heat-engine plant frame type non-metal combined chimney
CN205063308U (en) Outer hanging protection frame and outer hanging protective structure
CN104003287A (en) Umbrella type variable diameter platform device for industry kiln
CN103437283B (en) A kind of hanging basket truss of energy rapid-assembling
CN109812002A (en) For boiler maintenance ash mouth support platform and building method
CN102677912B (en) Temporary supporting device
CN109944422A (en) Inspection platform and building method for boiler second level energy-saving appliance
US20220306431A1 (en) Construction System
CN115520255A (en) Multifunctional multipurpose rotation transportation hoisting device and using method thereof
CN107217912A (en) It is a kind of to be used for the superelevation physical isolation construction method of neighbouring high ferro Business Line construction
CN210369867U (en) Overhanging type outer discharge frame protection device
CN204212444U (en) A kind of safety rope suspension holdfast
CN208862496U (en) A kind of cable tray for the interim transition of level crossing power cable
CN209114841U (en) A kind of building engineering construction scaffold safeguard structure
CN205347456U (en) Protection curtain in workshop is handled to slag
KR101829662B1 (en) Split rope apparatus of pendant type scaffoldings for power palnt boiler maintenance and jig for supporting the same
CN216076209U (en) Adjust nimble outer hanging handling frame of building
CN204627012U (en) A protection canopy that encorbelments of instrument formula for having outer scaffold frame building
CN214942205U (en) Operating platform for pipeline maintenance
CN108625584A (en) A kind of tower body equipment temporary platform and its assemble method
CN109736321A (en) A kind of slope protective device of architectural engineering
CN103927839A (en) Assembling and disassembling device and method of fire alarm detecting device
CN109027557B (en) A mounting platform for air cooler top
CN204782182U (en) Overhaul operation platform of cable conductor on steel pipe pole

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190528