CN108625584A - A kind of tower body equipment temporary platform and its assemble method - Google Patents
A kind of tower body equipment temporary platform and its assemble method Download PDFInfo
- Publication number
- CN108625584A CN108625584A CN201810437462.8A CN201810437462A CN108625584A CN 108625584 A CN108625584 A CN 108625584A CN 201810437462 A CN201810437462 A CN 201810437462A CN 108625584 A CN108625584 A CN 108625584A
- Authority
- CN
- China
- Prior art keywords
- tower body
- support plate
- body equipment
- tripod
- rope
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G3/00—Scaffolds essentially supported by building constructions, e.g. adjustable in height
- E04G3/24—Scaffolds essentially supported by building constructions, e.g. adjustable in height specially adapted for particular parts of buildings or for buildings of particular shape, e.g. chimney stacks or pylons
- E04G3/243—Scaffolds essentially supported by building constructions, e.g. adjustable in height specially adapted for particular parts of buildings or for buildings of particular shape, e.g. chimney stacks or pylons following the outside contour of a building
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G5/00—Component parts or accessories for scaffolds
- E04G5/001—Safety or protective measures against falling down relating to scaffoldings
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The present invention relates to tower body apparatus field more particularly to a kind of tower body equipment temporary platform and its assemble methods.The tower body equipment temporary platform includes the platform unit that several adjoin one another;The platform unit includes support plate, tripod and hook;The support plate is lain on the tripod and the tripod is located at the downside both ends of the support plate, and the hook is fixedly connected in the tower body equipment, the tripod and hook suspension connection;The support plate includes holder and lies in the expanded metal lath on the holder;Upright bar is vertically installed in the support plate, the upright bar is connected with rope each other, and flameproof fabric is provided between the rope and the support plate.The tower body equipment temporary platform has many advantages, such as that making is simple, it is convenient, cost-effective to remove, can be recycled and accelerate construction progress, and the temporary platform is additionally provided with flameproof fabric, can effectively reduce occurrence index, has ensured the life security of staff.
Description
Technical field
The present invention relates to tower body apparatus field more particularly to a kind of tower body equipment temporary platform and its assemble methods.
Background technology
For coking production usually using tower body equipment, equipment region is inflammable and explosive and poisonous and harmful medium is numerous, is easy to happen
Fire generally requires to build temporary platform to tower body equipment to carry out the operation such as assembling to equipment, and existing temporary platform is often
By the way of setting up full hall scaffold, which assembly and disassembly are complicated, time-consuming and laborious and do not prevent fire, these are all these
Field technology personnel do not expect to see.
Invention content
In view of the above problems, the invention discloses a kind of tower body equipment temporary platform, concrete scheme is as follows:
A kind of tower body equipment temporary platform, the tower body equipment temporary platform include the platform list that several adjoin one another
Member;
The platform unit includes support plate, tripod and hook;The support plate is lain on the tripod and institute
The downside both ends that tripod is located at the support plate are stated, the hook is fixedly connected in the tower body equipment, the tripod
It hangs and connects with the hook;
The support plate includes holder and lies in the expanded metal lath on the holder;
Be vertically installed with upright bar in the support plate, the upright bar is connected with rope each other, the rope with it is described
Flameproof fabric is provided between support plate.
Further, it is equipped with asbestos cloth in the support plate.
Further, the upper end, middle part and lower end of the upright bar are both provided with through-hole, for penetrating rope.
Further, the holder and expanded metal lath welding.
Further, the welding hook is in the tower body equipment.
Further, the upright bar is coating steel pipe.
The second aspect of the present invention discloses a kind of method of the above-mentioned tower body equipment temporary platform of assembling, including following step
Suddenly:
S1:The holder and the expanded metal lath are made respectively, and the holder and the expanded metal lath are welded into the plate that is supported;
S2:Lengths of steel pipes is welded to obtain tripod;
S3:Several hooks are made, by the welding hook in the tower body equipment;
S4:The tripod that S2 is obtained is suspended on the hook;
S5:The support plate that S1 is obtained is placed on the tripod that S2 is obtained, is held four of the support plate with iron wire
Angle bundled fixed is on the tripod;
S6:Then upright bar is vertically arranged in the support plate, the upright bar is connected with rope each other, the rope
It is provided with flameproof fabric between the support plate.
Further, in S6, the joint of the rope is fixed with rope card.
Further, in S1, the holder is welded to form by square steel tube, band steel and angle steel.
Further, further include S0 before S1, in S0, the square steel tube is rolled into arc with veneer reeling machine.
Compared with prior art, the invention has the advantages that:
Tower body equipment temporary platform disclosed by the invention is by being arranged platform unit, and with making, simple, dismounting is convenient, saves
About cost, the advantages that can be recycled and accelerating construction progress, and the temporary platform is additionally provided with flameproof fabric, can effectively drop
Low occurrence index has ensured the life security of staff.Invention additionally discloses the assembling tower body equipment temporary platform
Method, this method is simple and practicable, has broad application prospects.
Description of the drawings
Using attached drawing, the invention will be further described, but the embodiment in attached drawing does not constitute any limit to the present invention
System.
Fig. 1 is the structural schematic diagram of holder in the embodiment of the present invention;
Fig. 2 is the structural schematic diagram of light plate net of the embodiment of the present invention;
Fig. 3 is the structural schematic diagram of tripod in the embodiment of the present invention;
Fig. 4 is the schematic diagram linked up in the embodiment of the present invention;
Fig. 5 is the schematic diagram of upright bar in the embodiment of the present invention;
Fig. 6 is the schematic diagram of tower body equipment temporary platform in the embodiment of the present invention;
In figure:
1- holders, 2- square steel tubes, 3- band steels, 4- angle steel, 5- expanded metal laths, 6- tripods, 7- tower body equipment, 8- hooks, 9-
Upright bar, 10- through-holes.
Specific implementation mode
Present invention will be further explained below with reference to specific examples.It should be understood that these embodiments be only used for the present invention without
For limiting the scope of the invention.
Embodiment 1
Present embodiment discloses a kind of tower body equipment temporary platforms, as shown in figs 1 to 6, specifically, the tower body equipment is faced
Shi Pingtai includes the platform unit that several adjoin one another;
Above-mentioned platform unit includes support plate, tripod 6 and hook 8;Support plate is lain on tripod 6 and above-mentioned three foot
Frame 6 is located at the downside both ends of above-mentioned support plate, and above-mentioned hook 8 is fixedly connected in above-mentioned tower body equipment 7,6 He of above-mentioned tripod
8 suspension connection of the hook;
Support plate includes holder 1 and lies in the expanded metal lath 5 on holder 1;
Upright bar 9 is vertically installed in support plate, upright bar 9 is connected with rope, is arranged between rope and support plate each other
There is flameproof fabric.
Holder 1 includes square steel tube 2, band steel 3 and angle steel 4.
Asbestos cloth is equipped in support plate.
Upper end, middle part and the lower end of upright bar are both provided with through-hole 10, for penetrating rope.
Holder 1 and expanded metal lath 5 weld.
Welding hook is in tower body equipment 7.
Upright bar is coating steel pipe.
Tower body equipment temporary platform disclosed in the present embodiment by the way that platform unit is arranged, have make it is simple, remove it is convenient,
Cost-effective, the advantages that can be recycled and accelerating construction progress, and the temporary platform is additionally provided with flameproof fabric, it can be effective
Occurrence index is reduced, has ensured the life security of staff.
Embodiment 2
Present embodiment discloses the methods of the tower body equipment temporary platform described in a kind of assembled embodiment 1, including following step
Suddenly:
S1:Holder and expanded metal lath are made respectively, and holder and expanded metal lath are welded into the plate that is supported;
S2:Lengths of steel pipes is welded to obtain tripod;
S3:Several hooks are made, by welding hook in tower body equipment;
S4:The tripod that S2 is obtained is suspended on hook;
S5:The support plate that S1 is obtained is placed on the tripod that S2 is obtained, is tied four ends angle of support plate with iron wire
It is strapped to be scheduled on tripod;
S6:Then it is vertically arranged upright bar on the supporting plate, upright bar is connected with rope each other, between rope and support plate
It is provided with flameproof fabric.
In S6, the joint of the rope is fixed with rope card.
In S1, the holder is welded to form by square steel tube, band steel and angle steel.
Further include S0 before S1, in S0, the square steel tube is rolled into arc with veneer reeling machine.
Present embodiment discloses the methods for assembling the tower body equipment temporary platform, and this method is simple and practicable, have wide
Application prospect.
Specific embodiments of the present invention are described in detail above, but it is intended only as example, the present invention is simultaneously unlimited
It is formed on particular embodiments described above.To those skilled in the art, it is any to the equivalent modifications that carry out of the present invention and
It substitutes also all among scope of the invention.Therefore, without departing from the spirit and scope of the invention made by impartial conversion and
Modification, all should be contained within the scope of the invention.
Claims (10)
1. a kind of tower body equipment temporary platform, which is characterized in that the tower body equipment temporary platform includes that several adjoin one another
Platform unit;
The platform unit includes support plate, tripod and hook;The support plate is lain on the tripod and described three
Tripod is located at the downside both ends of the support plate, and the hook is fixedly connected in the tower body equipment, the tripod and institute
State hook suspension connection;
The support plate includes holder and lies in the expanded metal lath on the holder;
Upright bar is vertically installed in the support plate, the upright bar is connected with rope each other, the rope and the support
Flameproof fabric is provided between plate.
2. tower body equipment temporary platform according to claim 1, which is characterized in that be equipped with asbestos in the support plate
Cloth.
3. tower body equipment temporary platform according to claim 1, which is characterized in that the upper end of the upright bar, middle part and under
End is both provided with through-hole, for penetrating rope.
4. tower body equipment temporary platform according to claim 1, which is characterized in that the holder and expanded metal lath weldering
It connects.
5. tower body equipment temporary platform according to claim 1, which is characterized in that the hook is welded with the tower body equipment
It connects.
6. tower body equipment temporary platform according to claim 1, which is characterized in that the upright bar is coating steel pipe.
7. the method for the tower body equipment temporary platform described in a kind of any one of assembling claim 1-6, which is characterized in that packet
Include following steps:
S1:The holder and the expanded metal lath are made respectively, and the holder and the expanded metal lath are welded into the plate that is supported;
S2:Lengths of steel pipes is welded to obtain tripod;
S3:Several hooks are made, by the welding hook in the tower body equipment;
S4:The tripod that S2 is obtained is suspended on the hook;
S5:The support plate that S1 is obtained is placed on the tripod that S2 is obtained, is tied four ends angle of the support plate with iron wire
It is strapped to be scheduled on the tripod;
S6:Then upright bar is vertically arranged in the support plate, the upright bar is connected with rope each other, the rope and institute
It states and is provided with flameproof fabric between support plate.
8. the method according to the description of claim 7 is characterized in that in S6, the joint of the rope is fixed with rope card.
9. the method according to the description of claim 7 is characterized in that in S1, the holder is welded by square steel tube, band steel and angle steel
Connect composition.
10. the method according to the description of claim 7 is characterized in that further including S0 before S1, in S0, incited somebody to action with veneer reeling machine
The square steel tube is rolled into arc.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810437462.8A CN108625584A (en) | 2018-05-09 | 2018-05-09 | A kind of tower body equipment temporary platform and its assemble method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810437462.8A CN108625584A (en) | 2018-05-09 | 2018-05-09 | A kind of tower body equipment temporary platform and its assemble method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108625584A true CN108625584A (en) | 2018-10-09 |
Family
ID=63692404
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810437462.8A Pending CN108625584A (en) | 2018-05-09 | 2018-05-09 | A kind of tower body equipment temporary platform and its assemble method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108625584A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113565308A (en) * | 2021-06-29 | 2021-10-29 | 重庆建工第三建设有限责任公司 | Steel structure shaping protection platform with external isolation protection structure |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201778479U (en) * | 2010-07-29 | 2011-03-30 | 中冶天工上海十三冶建设有限公司 | Detachable high-altitude working platform |
CN203373967U (en) * | 2013-05-31 | 2014-01-01 | 中建钢构有限公司 | Operating platform board |
CN204899180U (en) * | 2015-08-26 | 2015-12-23 | 中冶天工集团有限公司 | Steel construction jar body aerial working platform simply sets up device |
-
2018
- 2018-05-09 CN CN201810437462.8A patent/CN108625584A/en active Pending
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201778479U (en) * | 2010-07-29 | 2011-03-30 | 中冶天工上海十三冶建设有限公司 | Detachable high-altitude working platform |
CN203373967U (en) * | 2013-05-31 | 2014-01-01 | 中建钢构有限公司 | Operating platform board |
CN204899180U (en) * | 2015-08-26 | 2015-12-23 | 中冶天工集团有限公司 | Steel construction jar body aerial working platform simply sets up device |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113565308A (en) * | 2021-06-29 | 2021-10-29 | 重庆建工第三建设有限责任公司 | Steel structure shaping protection platform with external isolation protection structure |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP6017083B1 (en) | Floor slab unit, floor slab construction method, and floor construction method | |
CN101592334B (en) | Method for assembling a steam generator | |
JP2007085590A (en) | Scaffold for checking large component for boiler and its construction method | |
CN103643800A (en) | Lifting installation system for buckling restrained supporting member and construction method thereof | |
CN104295077A (en) | Annular hanging platform for mounting stove shell of hot-blast stove, and mounting and dismounting method thereof | |
CN109113369B (en) | Safe demolition method for manual demolition of cylindrical building | |
CN108625584A (en) | A kind of tower body equipment temporary platform and its assemble method | |
CN105952130B (en) | A kind of suspension platform installation method for the construction of building cornice position | |
JP2013113007A (en) | Method and device for temporarily constructing net for steel tower and method and system for repairing steel tower | |
CN108487621A (en) | Assembled movement shield cage and its construction method | |
JP2927321B2 (en) | Dismantling method of large hanging boiler | |
CN212773371U (en) | Limited space steel construction daylighting top cable work platform | |
CN112481437B (en) | Blast furnace Y-shaped downcomer dismounting and replacing method | |
CN211193694U (en) | Rod and tube bundle propeller | |
CN101571003B (en) | Device and method thereof for constructing a large-sized spherical tank construction platform | |
CN209970667U (en) | Roller type photovoltaic glass assembly platform | |
CN112983031A (en) | Movable elevator shaft protection horizontal protection device | |
KR101829662B1 (en) | Split rope apparatus of pendant type scaffoldings for power palnt boiler maintenance and jig for supporting the same | |
CN113550550A (en) | Overhanging unit type scaffold convenient to assemble and disassemble | |
CN201818034U (en) | Movable operation platform | |
CN218642760U (en) | High-altitude installation positioning platform for blast furnace five-way ball and ascending pipe | |
CN216640293U (en) | Assembled high altitude tubular column operation platform | |
CN215291803U (en) | Transformer rail guard and transformer | |
CN217232639U (en) | Temporary up-down device for boiler steel frame | |
CN219034108U (en) | Fire-catching device and operation platform |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20181009 |
|
RJ01 | Rejection of invention patent application after publication |