CN109797765A - It is a kind of to carry out the construction method that cushion cap is connect with pile foundation by attachment device - Google Patents
It is a kind of to carry out the construction method that cushion cap is connect with pile foundation by attachment device Download PDFInfo
- Publication number
- CN109797765A CN109797765A CN201811593772.5A CN201811593772A CN109797765A CN 109797765 A CN109797765 A CN 109797765A CN 201811593772 A CN201811593772 A CN 201811593772A CN 109797765 A CN109797765 A CN 109797765A
- Authority
- CN
- China
- Prior art keywords
- cushion cap
- prefabricated
- pile
- steel plate
- connect
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Piles And Underground Anchors (AREA)
Abstract
The construction method that cushion cap is connect with pile foundation is carried out by attachment device the present invention provides a kind of, comprising the following steps: S1, excavation pit are laid with the steel plate for being reserved with pile hole, weld guide pile at the angle of four ends on the steel plate;S2, inserting piling prefabricated pile, bored concrete pile inner concrete, and prefabricated pile and steel plate are welded;S3 makes prefabricated cushion cap in factory, includes grout hole, extravasating hole and casing on the prefabricated cushion cap, there are location holes for prefabricated cushion cap four positions for holding angle to correspond to steel plate guide pile according to the position of inserting piling prefabricated pile;S4 makes prefabricated cushion cap in factory according to the cushion cap size of design;S5, the prefabricated cushion cap of in-site installation;Docking location between construction method component of the present invention is more accurate, and cushion cap reduces site operation link, greatly reduce the construction time in factory's pre-production.
Description
Technical field
The present invention relates to the realm of building construction, and in particular to a kind of to carry out what cushion cap was connect with pile foundation by attachment device
Construction method.
Background technique
(explanation: fabricated construction is the various components of engineering in factory's pre-production to fabricated construction, and construct Shi Xian
Field carries out assembly connection, and the process for not needing in-site pouring cement shortens the construction time, guarantees construction quality) it is cast-in-place with tradition
(explanation: being traditional arrangement and method for construction to structure, needs to make the processes such as template, reinforcing bar and carries out cement grouting, construction time
Long, work surface is big) it compares, the emphasis of quality control is the processing of each primary structure member connecting node.Currently, municipal bridge work
Connection between journey superstructure, between superstructure and pier stud comparative maturity, and for pile foundation and prefabricated cushion cap
Connection, is related to less, especially under the complex environment of city, how around avoiding pipeline, Rapid Implementation pile foundation
It is always difficult point and hot spot in engineering with the connection of prefabricated cushion cap.The present invention has devised small straight specifically for city overline bridge
The conversion equipment that diameter pile foundation is connect with prefabricated cushion cap realizes the quick connection on Small Diameter Pile basis and prefabricated cushion cap.
Summary of the invention
In view of the deficiencies of the prior art, carry out what cushion cap was connect with pile foundation by attachment device the present invention provides a kind of
Construction method is effectively shielded from complicated underground utilities using Small Diameter Pile, avoids the case where destroying underground pipeline system hair
It is raw, cushion cap is carried out using connection transfer device and is connect with pile foundation, can solve the cause of the position deviation as caused by construction of prefabricated piles
Stake is set to dock difficult problem with cushion cap reserving hole, it is only necessary to according to the size of cushion cap, make conversion equipment, not need to examine
The position for considering prefabricated pile is conducive to the standardization batch production of cushion cap, and cushion cap is in factory's pre-production, cushion cap and pile foundation
After connecting by converter device, the age of concrete is withouted waiting for, the installation of day pier column can be carried out at once, subtracted significantly
Few construction time.
To achieve the above object, the present invention adopts the following technical scheme:
It is a kind of to carry out the construction method that cushion cap is connect with pile foundation by attachment device, comprising the following steps:
S1 carries out construction by machinery and excavates foundation pit, and the depth of foundation pit is depending on the height of cushion cap, the depth of foundation pit
Less than or equal to cushion cap height, after foundation pit excavates, in the bottom surface placing concrete bed course of foundation pit, in the pad of foundation pit
Layer surface is laid with the steel plate outline border prefabricated according to cushion cap length and width dimensions, and cushion cap is welded to connect at four ends angle of steel plate outline border
Steel pipe;
S2 carries out inserting piling prefabricated pile using static pressure force method, prefabricated stake is squeezed by machinery, prefabricated pile reserves
The certain length in ground (generally 600-800mm);
S3, after placing the prefabricated steel plate outline border for having welded joint steel pipe, with prefabricated steel plate and each stake top, company
Connect the steel-pipe welding of cushion cap, the prefabricated steel plate size is consistent with cushion cap top surface size, aperture on the steel plate, orifice position with
The distributing position of stake and steel pipe matches, and the size of aperture is matched respectively at stake diameter size, the size of joint steel pipe diameter.
S4 makes prefabricated cushion cap in factory according to the cushion cap size of design, prefabricated cushion cap include grout hole, extravasating hole and
Grouting Pipe, there are location holes for prefabricated cushion cap four positions for holding angle to be correspondingly connected with steel pipe, position pore size and joint steel pipe size
It is adapted;
S5, the prefabricated cushion cap of in-site installation, the location hole of prefabricated cushion cap entangle joint steel pipe outstanding, from default grout hole
It is quickly connected by Grouting Pipe grouting.
The case where further, the prefabricated pile is Small Diameter Pile, is explored in inserting piling prefabricated pile according to address early period,
The distributing position and overline bridge load of pipeline determine the position of inserting piling pile.
Further, the height that the height of the steel plate outline border reserves ground with prefabricated pile matches.
Further, in the step S3, after the steel plate welding of the steel plate outline border provided with joint steel pipe and aperture, shape
The conversion equipment being connect at cushion cap with stake.
Further, comprising the following specific steps prefabricated cushion cap is sling in the step S5, prefabricated cushion cap is reserved
The part of the prominent steel plate of aligned joint steel pipe, the decline of prefabricated cushion cap the joint steel pipe of protrusion cover completely
In reserved hole, then carries out grouting construction and prefabricated cushion cap and prefabricated pile are linked into an integrated entity.
Further, the steel pipe that cushion cap is welded to connect at four ends angle of steel plate outline border, length should compare prefabricated pile
Reserve the long 300-500mm of length on ground.
A kind of beneficial effect carrying out the construction method that cushion cap is connect with pile foundation by attachment device provided by the invention exists
In: it is effectively shielded from complicated underground utilities and carries out pitching pile, avoid the case where destroying underground pipeline system generation;It is suitable for
The bridge underground construction of current city is built;Cushion cap is carried out using connection transfer device to connect with pile foundation, can solve due to pre-
Position deviation caused by pile driving construction processed causes stake to dock difficult problem with cushion cap reserving hole, it is only necessary to according to the big of cushion cap
It is small, conversion equipment is made, without the concern for the position of prefabricated pile, is conducive to the standardization batch production of cushion cap, cushion cap exists
Factory's pre-production after cushion cap is connect with pile foundation by converter device, withouts waiting for the age of concrete, can at once into
The installation of row day pier column, greatly reduces the construction time.
Detailed description of the invention
Fig. 1 is step S1 schematic diagram of the invention;
Fig. 2 is step S2 schematic diagram of the invention;
Fig. 3 is step S3 schematic diagram of the invention;
Fig. 4 is step S5 schematic diagram of the invention.
In figure: 1, foundation pit;2, concrete cushion;3, prefabricated pile;4, steel plate;5, joint steel pipe;6, prefabricated cushion cap;7, it overflows
Starch hole;8, preformed hole;9, grout hole.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete
Whole description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.Ability
Domain ordinary person every other embodiment obtained without making creative work, belongs to guarantor of the invention
Protect range.
Embodiment: a kind of to carry out the construction method that cushion cap is connect with pile foundation by attachment device.
Embodiment 1, it is a kind of to carry out the construction method that cushion cap is connect with pile foundation by attachment device, comprising the following steps:
S1 carries out construction by machinery and excavates foundation pit, and the depth of foundation pit is depending on the height of cushion cap, the depth of foundation pit
Equal to cushion cap height, after foundation pit excavates, in the bottom surface placing concrete bed course of foundation pit, in the mat surface of foundation pit
It is laid with the steel plate outline border prefabricated according to cushion cap length and width dimensions, the steel pipe of cushion cap is welded to connect at four ends angle of steel plate outline border;
S2 carries out inserting piling prefabricated pile using static pressure force method, and the prefabricated pile is steel-pipe pile and is Small Diameter Pile, in inserting piling
The case where being explored when steel-pipe pile according to address early period, the distributing position of pipeline and overline bridge load determine the position of inserting piling pile,
Prefabricated steel-pipe pile is driven underground by machinery, prefabricated pile reserves the certain length in ground, is 600mm;
S3, after placing the prefabricated steel plate outline border for having welded joint steel pipe, with prefabricated steel plate and each stake top, company
Connect the steel-pipe welding of cushion cap, the prefabricated steel plate size is consistent with cushion cap top surface size, aperture on the steel plate, orifice position with
The distributing position of stake and steel pipe matches, and the size of aperture is matched respectively at stake diameter size, the size of joint steel pipe diameter.
S4 makes prefabricated cushion cap in factory according to the cushion cap size of design, prefabricated cushion cap include grout hole, extravasating hole and
Grouting Pipe, there are location holes for prefabricated cushion cap four positions for holding angle to be correspondingly connected with steel pipe, position pore size and joint steel pipe size
It is adapted;
S5, the prefabricated cushion cap of in-site installation, the reserving hole of prefabricated cushion cap entangle joint steel pipe outstanding, from default grouting
Hole is quickly connected by Grouting Pipe grouting.Specific steps include: that prefabricated cushion cap is sling, the reserving hole of prefabricated cushion cap
It is directed at the part of the prominent steel plate of joint steel pipe, the decline of prefabricated cushion cap is covered completely the joint steel pipe of protrusion reserved
Hole in, then carry out grouting construction prefabricated cushion cap and prefabricated pile are linked into an integrated entity.
Embodiment 2, it is a kind of to carry out the construction method that cushion cap is connect with pile foundation by attachment device, comprising the following steps:
S1 carries out construction by machinery and excavates foundation pit, and the depth of foundation pit is depending on the height of cushion cap, the depth of foundation pit
Less than cushion cap height, after foundation pit excavates, in the bottom surface placing concrete bed course of foundation pit, in the mat surface of foundation pit
It is laid with the steel plate outline border prefabricated according to cushion cap length and width dimensions, the steel pipe of cushion cap is welded to connect at four ends angle of steel plate outline border;
S2 carries out inserting piling prefabricated pile using vibratory drilling method, and the prefabricated pile is steel-pipe pile and is Small Diameter Pile, in inserting piling steel
The case where being explored when tubular pole according to address early period, the distributing position of pipeline and overline bridge load determine the position of inserting piling pile,
Prefabricated steel-pipe pile is driven underground by machinery, and prefabricated pile reserves the certain length 800mm in ground;
S3, after placing the prefabricated steel plate outline border for having welded joint steel pipe, with prefabricated steel plate and each stake top, company
Connect the steel-pipe welding of cushion cap, the prefabricated steel plate size is consistent with cushion cap top surface size, aperture on the steel plate, orifice position with
The distributing position of stake and steel pipe matches, and the size of aperture is matched respectively at stake diameter size, the size of joint steel pipe diameter.
S4 makes prefabricated cushion cap, prefabricated cushion cap reserving hole and cushion cap top surface in factory according to the cushion cap size of design
Connection, there are location holes for prefabricated cushion cap four positions for holding angle to be correspondingly connected with steel pipe, position pore size and joint steel pipe size phase
Adaptation;
S5, the prefabricated cushion cap of in-site installation, the reserving hole of prefabricated cushion cap entangles joint steel pipe outstanding, from reserving hole
Grouting is quickly connected.Specific steps include: that prefabricated cushion cap is sling, and the reserving hole of prefabricated cushion cap is directed at joint steel pipe
The part of prominent steel plate completely covers the decline of prefabricated cushion cap the joint steel pipe of protrusion in reserved hole, then
Grouting construction is carried out to link into an integrated entity prefabricated cushion cap and prefabricated pile.
The above is presently preferred embodiments of the present invention, but the present invention should not be limited to the embodiment and attached drawing institute
Disclosure both falls within guarantor of the present invention so all do not depart from the lower equivalent or modification completed of spirit disclosed in this invention
The range of shield.
Claims (6)
1. a kind of carry out the construction method that cushion cap is connect with pile foundation by attachment device, which comprises the following steps:
S1, by machinery carry out construction excavate foundation pit, the depth of foundation pit depending on the height of cushion cap, the depth of foundation pit be less than or
Equal to cushion cap height, after foundation pit excavates, in the bottom surface placing concrete bed course of foundation pit, spread in the mat surface of foundation pit
If being welded to connect the steel pipe of cushion cap at four ends angle of steel plate outline border according to the steel plate outline border that cushion cap length and width dimensions are prefabricated;
S2 carries out inserting piling prefabricated pile using static pressure force method, prefabricated stake is driven underground by machinery, prefabricated pile reserves ground
The certain length in face;
S3 after placing the prefabricated steel plate outline border for having welded joint steel pipe, with prefabricated steel plate and each stake top, connect cushion cap
Steel-pipe welding, the prefabricated steel plate size is consistent with cushion cap top surface size, aperture on the steel plate, orifice position and stake and steel pipe
Distributing position match, the size of aperture is matched respectively at stake diameter size, the size of joint steel pipe diameter;
S4 makes prefabricated cushion cap in factory, prefabricated cushion cap includes grout hole, extravasating hole and slip casting according to the cushion cap size of design
Pipe, prefabricated cushion cap four ends angle are correspondingly connected with the position of steel pipe there are location hole, and positioning pore size is mutually fitted with joint steel pipe size
Match;
S5, the prefabricated cushion cap of in-site installation, the location hole of prefabricated cushion cap entangle joint steel pipe outstanding, pass through note from default grout hole
Slurry pipe grouting is quickly connected.
2. as described in claim 1 carry out the construction method that cushion cap is connect with pile foundation by attachment device, it is characterised in that: institute
State prefabricated pile be Small Diameter Pile, in inserting piling prefabricated pile according to address early period explore the case where, pipeline distributing position and day
Axle load carries the position for determining inserting piling pile.
3. as described in claim 1 carry out the construction method that cushion cap is connect with pile foundation by attachment device, it is characterised in that: institute
The height for stating steel plate outline border and the height that prefabricated pile reserves ground match.
4. as described in claim 1 carry out the construction method that cushion cap is connect with pile foundation by attachment device, it is characterised in that: institute
It states in step S3, after the steel plate welding of the steel plate outline border provided with joint steel pipe and aperture, forms the conversion that cushion cap is connect with stake
Device.
5. as described in claim 1 carry out the construction method that cushion cap is connect with pile foundation by attachment device, it is characterised in that: institute
It states in step S5 comprising the following specific steps prefabricated cushion cap is sling, the reserving hole alignment joint steel pipe of prefabricated cushion cap is prominent
The part of steel plate completely covers the decline of prefabricated cushion cap the joint steel pipe of protrusion in reserved hole, then carries out
Grouting construction links into an integrated entity prefabricated cushion cap and prefabricated pile.
6. as described in claim 1 carry out the construction method that cushion cap is connect with pile foundation by attachment device, it is characterised in that: institute
The steel pipe that cushion cap is welded to connect at four ends angle of steel plate outline border is stated, length is 300- longer than the length that prefabricated pile reserves ground
500mm。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811593772.5A CN109797765B (en) | 2018-12-25 | 2018-12-25 | It is a kind of to carry out the construction method that cushion cap is connect with pile foundation by attachment device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811593772.5A CN109797765B (en) | 2018-12-25 | 2018-12-25 | It is a kind of to carry out the construction method that cushion cap is connect with pile foundation by attachment device |
Publications (2)
Publication Number | Publication Date |
---|---|
CN109797765A true CN109797765A (en) | 2019-05-24 |
CN109797765B CN109797765B (en) | 2019-11-22 |
Family
ID=66557568
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811593772.5A Active CN109797765B (en) | 2018-12-25 | 2018-12-25 | It is a kind of to carry out the construction method that cushion cap is connect with pile foundation by attachment device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109797765B (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110904986A (en) * | 2019-10-28 | 2020-03-24 | 国网福建省电力有限公司 | Precast pile-bearing platform assembly type foundation tenon type flange connection structure and construction method |
CN111255482A (en) * | 2020-01-16 | 2020-06-09 | 广东省建筑构件工程有限公司 | Underpinning structure on subway tunnel and construction method thereof |
CN111560940A (en) * | 2020-05-09 | 2020-08-21 | 中铁二十局集团第三工程有限公司 | Treatment method of karst tunnel |
CN114277780A (en) * | 2021-12-25 | 2022-04-05 | 深圳市蛇口招商港湾工程有限公司 | Construction method of marine soft soil foundation structure |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2005290898A (en) * | 2004-04-02 | 2005-10-20 | Yamakawa Kensetsu Kk | Bridge pier construction method and bridge pier |
CN201704699U (en) * | 2010-07-08 | 2011-01-12 | 宝钢工程技术集团有限公司 | Steel structure foundation system of offshore fan |
JP2013224535A (en) * | 2012-04-20 | 2013-10-31 | Shimizu Corp | Insulation/separation type joint structure for pile foundation |
CN104631489A (en) * | 2014-12-31 | 2015-05-20 | 云南建工基础工程有限责任公司 | Bridge cushion cap force underpinning technology in underneath pass open trench tunnel construction |
CN105672347A (en) * | 2016-01-25 | 2016-06-15 | 济南轨道交通集团有限公司 | Structure of prefabricated pile-plate brackets for underpinning existing pile foundations through shield tunneling and construction method |
CN105970993A (en) * | 2016-06-30 | 2016-09-28 | 上海勘测设计研究院有限公司 | Underwater connection structure for precast piles and precast bearing platform, and construction method thereof |
CN107059774A (en) * | 2017-05-27 | 2017-08-18 | 中交第三航务工程勘察设计院有限公司 | A kind of assembled high-rise pile cap revetment structure and construction method |
CN206706804U (en) * | 2017-03-21 | 2017-12-05 | 沈阳建筑大学 | A kind of bridge pier column structure |
CN108797628A (en) * | 2018-07-03 | 2018-11-13 | 上海市城市建设设计研究总院(集团)有限公司 | Lift-off formula subtracts shock insulation pile foundation construction |
-
2018
- 2018-12-25 CN CN201811593772.5A patent/CN109797765B/en active Active
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2005290898A (en) * | 2004-04-02 | 2005-10-20 | Yamakawa Kensetsu Kk | Bridge pier construction method and bridge pier |
CN201704699U (en) * | 2010-07-08 | 2011-01-12 | 宝钢工程技术集团有限公司 | Steel structure foundation system of offshore fan |
JP2013224535A (en) * | 2012-04-20 | 2013-10-31 | Shimizu Corp | Insulation/separation type joint structure for pile foundation |
CN104631489A (en) * | 2014-12-31 | 2015-05-20 | 云南建工基础工程有限责任公司 | Bridge cushion cap force underpinning technology in underneath pass open trench tunnel construction |
CN105672347A (en) * | 2016-01-25 | 2016-06-15 | 济南轨道交通集团有限公司 | Structure of prefabricated pile-plate brackets for underpinning existing pile foundations through shield tunneling and construction method |
CN105970993A (en) * | 2016-06-30 | 2016-09-28 | 上海勘测设计研究院有限公司 | Underwater connection structure for precast piles and precast bearing platform, and construction method thereof |
CN206706804U (en) * | 2017-03-21 | 2017-12-05 | 沈阳建筑大学 | A kind of bridge pier column structure |
CN107059774A (en) * | 2017-05-27 | 2017-08-18 | 中交第三航务工程勘察设计院有限公司 | A kind of assembled high-rise pile cap revetment structure and construction method |
CN108797628A (en) * | 2018-07-03 | 2018-11-13 | 上海市城市建设设计研究总院(集团)有限公司 | Lift-off formula subtracts shock insulation pile foundation construction |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110904986A (en) * | 2019-10-28 | 2020-03-24 | 国网福建省电力有限公司 | Precast pile-bearing platform assembly type foundation tenon type flange connection structure and construction method |
CN110904986B (en) * | 2019-10-28 | 2021-06-22 | 国网福建省电力有限公司 | Precast pile-bearing platform assembly type foundation tenon type flange connection structure and construction method |
CN111255482A (en) * | 2020-01-16 | 2020-06-09 | 广东省建筑构件工程有限公司 | Underpinning structure on subway tunnel and construction method thereof |
CN111560940A (en) * | 2020-05-09 | 2020-08-21 | 中铁二十局集团第三工程有限公司 | Treatment method of karst tunnel |
CN114277780A (en) * | 2021-12-25 | 2022-04-05 | 深圳市蛇口招商港湾工程有限公司 | Construction method of marine soft soil foundation structure |
Also Published As
Publication number | Publication date |
---|---|
CN109797765B (en) | 2019-11-22 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109797765B (en) | It is a kind of to carry out the construction method that cushion cap is connect with pile foundation by attachment device | |
CN104120647B (en) | It is suitable for section assembling concrete frame bridge pier system and the construction method of rapid construction | |
CN103669866B (en) | The construction method of basement reinforced concrete post node connecting structure | |
CN104264902A (en) | Steel pipe column disc positioning device and structure for connecting concrete filled steel tubular column with pile foundation | |
CN104612120B (en) | A kind of integral construction method setting up platform about steel-pipe pile in water | |
CN110331727A (en) | The supporting construction and construction method that bored concrete pile and diaphram wall combine | |
CN109356169A (en) | A kind of foundation pit campshed support system and its construction method | |
KR102162125B1 (en) | Pile and Coping for Bridge Construction | |
CN102410031A (en) | Underground space structure constructed by pile wall construction method | |
CN208517810U (en) | A kind of temporary trestle bridge for deep big foundation pit excavation construction | |
CN209508992U (en) | A kind of underwater embedding rock steel sheet pile cofferdam structure | |
CN209179021U (en) | A kind of foundation pit campshed support system | |
CN108978680B (en) | Mucky soil elevator foundation pit supporting construction device and method | |
CN101392521A (en) | Rock-socketed steel dock structure and construction method thereof | |
CN107338799B (en) | Large span foundation pit supporting construction | |
CN113027463B (en) | Suspension type reverse wall working well supporting structure and construction method | |
CN202247942U (en) | Overhanging type lifter foundation | |
CN109577322A (en) | A kind of constructing device for inside soil body existing pile foundation pile extension | |
CN202969333U (en) | Steel truss rock-socketed wharf structure | |
CN212054725U (en) | Cast-in-place reinforced concrete arch-covering formwork system | |
CN208884535U (en) | A kind of distortion-free Larsen steel sheet pile supporting construction | |
CN109797767A (en) | A kind of pinpoint cushion cap and pile foundation connection method | |
CN105178356A (en) | Setting-up construction method for vertical joint bars of columns in reverse building method | |
CN210658324U (en) | Rigid connection structure of prefabricated tubular pile and prefabricated foundation | |
CN211080280U (en) | Large-diameter pile foundation enclosure miniature pile group |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |