CN109723081A - Subway station lattice column construction method - Google Patents

Subway station lattice column construction method Download PDF

Info

Publication number
CN109723081A
CN109723081A CN201811622500.3A CN201811622500A CN109723081A CN 109723081 A CN109723081 A CN 109723081A CN 201811622500 A CN201811622500 A CN 201811622500A CN 109723081 A CN109723081 A CN 109723081A
Authority
CN
China
Prior art keywords
lattice column
column
reinforcement cage
steel reinforcement
lattice
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811622500.3A
Other languages
Chinese (zh)
Inventor
蒋亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuxi Fast Deer Metro Steel Structure Manufacturing Co Ltd
Original Assignee
Wuxi Fast Deer Metro Steel Structure Manufacturing Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuxi Fast Deer Metro Steel Structure Manufacturing Co Ltd filed Critical Wuxi Fast Deer Metro Steel Structure Manufacturing Co Ltd
Priority to CN201811622500.3A priority Critical patent/CN109723081A/en
Publication of CN109723081A publication Critical patent/CN109723081A/en
Pending legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)
  • Foundations (AREA)

Abstract

The invention discloses a kind of subway station lattice column construction methods, comprise the following steps: a, lattice column preparation, a1, lattice column arrangement, a2, welding batten plate, a3, field joint are welded;B, b2, column pile driving construction, b1, boring positioning excavate pore-forming, b3, borehole cleaning simultaneously place steel reinforcement cage;C, lattice column is constructed, and c1, is determined anchor point, c2, is placed lattice column, c3, lattice column and steel reinforcement cage weld, c4, casting concrete.Through the above way, subway station lattice column construction method of the present invention has ensured the main body intensity of lattice column, avoid lattice column main body stress deformation, it ensure that the installation effect of lattice column main body, there is enough spaces simultaneously to place lattice column and steel reinforcement cage, guarantee that lattice column and steel reinforcement cage are placed straight and horizontal, promote the work progress stable and continuous of stand column pile and lattice column, construction cost is reduced, construction efficiency is improved.

Description

Subway station lattice column construction method
Technical field
The present invention relates to subway work technical fields, more particularly to a kind of subway station lattice column construction method.
Background technique
With the fast development of China's economic, ground traffic is no longer satisfied the needs of going out of people, and occurs more next More modes of transportation, such as overpass, subway etc..The appearance of subway alleviates the pressure of going out of people significantly.Underground is continuous Wall is as important building enclosure form a kind of in deep-foundation pit engineering, and in China, each metropolitan railway traffic engineering was built in recent years If having obtained extensive reference in field.
With the expansion of rail vehicle stage space, structure type is become more complicated, and difficulty of construction gradually increases, underground The function of diaphragm wall is also gradually sent out to the direction of permanent building enclosure and main structure longitudinal support structure from interim building enclosure Exhibition.The wherein important component of lattice column longitudinal bracing can guarantee enhancing component strength performance under the conditions of same axial drag.
At present during subway work, it is easy to happen the situations such as inclination in the installation process of lattice column, leads to lattice column Workability be affected, influence the construction speed of subway station, increase construction cost.
Summary of the invention
The invention mainly solves the technical problem of providing a kind of subway station lattice column construction method, lattice column main body intensity Height avoids lattice column main body stress deformation, ensure that the installation effect of lattice column main body, while having enough spaces to put It sets lattice column and steel reinforcement cage, guarantees that lattice column and steel reinforcement cage are placed straight and horizontal, promote applying for stand column pile and lattice column Work process stable and continuous, reduces construction cost, improves construction efficiency.
In order to solve the above technical problems, one technical scheme adopted by the invention is that: a kind of subway station lattice column is provided and is applied Work method, comprises the following steps: a, lattice column preparation;B, column pile driving construction;C, lattice column is constructed;
Wherein lattice column includes four angle steel and multiple batten plates, and lattice column preparation includes the following steps:
A1, lattice column arrangement: it is arranged symmetrically two-by-two using four angle steel, Formation cross-section is rectangular-shaped column structure, from column The top of structure to bottom interval is disposed with multiple batten plates and forms lattice column main body;
A2, welding batten plate: batten plate is soldered to top, last block batten plate of top and column structure along the bottom of column structure Top distance is adjustable;
A3, field joint are welded: transport to scene after the processing of lattice column main body merogenesis docked, it is single when welding at the scene For lattice column welding line joint no more than two, weld seam uses groove welding, and single angle steel connector will be staggeredly arranged, and section connector rate is not It can exceed that 50%, the distance that is staggered is greater than 500mm;
Column pile driving construction includes the following steps:
B1, boring positioning: according to setting position, timber fixed point is directly pinpointed or squeezes into, then by " crossing method " in wood The surrounding of stake fixed point carries out fender pile point;
B2, excavate pore-forming: ensuring that drilled pile is not tilted, do not moved, it is ensured that the verticality of drilling and pile position deviation meet design with Code requirement, drilling diameter are 20cm at least bigger than design aperture, and depth of pore forming need to be greater than not less than design hole depth, sediment thickness 10cm;
B3, borehole cleaning simultaneously place steel reinforcement cage: placing steel reinforcement cage in cleaning hole after sediment, arrange a positioning every 2 ~ 5m on steel reinforcement cage Gusset, the symmetrically placed four positioning gusset of per pass section, is fixed when steel reinforcement cage falls to orifice position with fashioned iron;
Lattice column construction includes the following steps:
C1, it determines anchor point: after the completion of stand column pile drilling, borehole circumference mud, soil etc. being cleaned out, surveyor calculates lattice Four four coordinate points of side midpoint extended line of structure column, then carry out unwrapping wire, and deviations are less than 50mm;
C2, it places lattice column: lattice column being sling and is slowly put into steel reinforcement cage, while being in reinforcement connection using fashioned iron;
C3, lattice column and steel reinforcement cage weld: welding two pegs on every side of lattice column, the longitudinal pitch of peg is not less than 200mm often shows five, peg and steel reinforcement cage is locked, and is located at lattice column among steel reinforcement cage;
C4, casting concrete: oppose the progress concreting of stanchion bottom, after stand column pile concrete casting complete, carries out stake holes in time Backfill.
In a preferred embodiment of the present invention, the contact area of batten plate and angle steel is at least batten plate area on lattice column Half.
In a preferred embodiment of the present invention, in lattice column preparation process top batten plate and lattice column body top away from From 600mm is not more than, two batten plates are at least arranged for every meter on single lattice column.
In a preferred embodiment of the present invention, lattice column uses Q235B steel, and welding rod uses E43XX, and weld seam is 10 ~ 20mm。
In a preferred embodiment of the present invention, steel reinforcement cage includes longitudinally arranged main supporting rib and the main supporting rib of connection Steel ring, be fixed between the two using welding manner.
In a preferred embodiment of the present invention, the positioning gusset in column pile driving construction on steel reinforcement cage uses welding by both sides, fixed The diameter of section of position gusset is at least 15mm.
In a preferred embodiment of the present invention, the position deviation range of lattice column is when lattice column is hung in steel reinforcement cage ± 25 ~ 38mm, perpendicularity deviation≤L/250, lattice column corner≤2 ° ~ 5 °.
In a preferred embodiment of the present invention, the section catercorner length in lattice column insertion steel reinforcement cage is less than steel reinforcement cage Diameter.
In a preferred embodiment of the present invention, stand column pile lower concrete at least pours in three times, pours height for the first time Degree is at least 1/5th of stand column pile height, pours the half that height is at least stand column pile height for the second time, and third time is completed The concreting of residual altitude, pour each time after the completion of need to backfill it is closely knit after poured next time again.
The beneficial effects of the present invention are: the overall structure of lattice column main body is strong in subway station lattice column construction method of the present invention Degree is high, avoids lattice column main body stress deformation, ensure that the installation effect of lattice column main body, while there is enough spaces to come Lattice column and steel reinforcement cage are placed, guarantees that lattice column and steel reinforcement cage are placed straight and horizontal, promote stand column pile and lattice column Work progress stable and continuous, reduces construction cost, improves construction efficiency.
Detailed description of the invention
To describe the technical solutions in the embodiments of the present invention more clearly, make required in being described below to embodiment Attached drawing is briefly described, it should be apparent that, drawings in the following description are only some embodiments of the invention, for For those of ordinary skill in the art, without creative efforts, it can also be obtained according to these attached drawings other Attached drawing, in which:
Fig. 1 is the structural schematic diagram of subway station lattice column construction of the invention;
The components in the drawings are labeled as follows: 100, lattice column, 101, angle steel, 102, batten plate, 200, stand column pile, 300, reinforcing bar Cage, 301, supporting rib, 302, steel ring, 303, positioning gusset.
Specific embodiment
The technical scheme in the embodiments of the invention will be clearly and completely described below, it is clear that described implementation Example is only a part of the embodiments of the present invention, instead of all the embodiments.Based on the embodiments of the present invention, this field is common Technical staff's all other embodiment obtained without making creative work belongs to the model that the present invention protects It encloses.
Referring to Fig. 1, the embodiment of the present invention includes:
Embodiment one
A kind of subway station lattice column construction method, including following preparation section: prepared by lattice column 100, the construction of stand column pile 200 and lattice The construction of structure column.
Wherein lattice column 100 includes four angle steel 101 and multiple batten plates 102, and lattice column preparation includes the following steps:
A1, lattice column 100 are arranged: it is arranged symmetrically two-by-two using four angle steel 101, Formation cross-section is rectangular-shaped column structure, Multiple batten plates 102, which are disposed with, from the top of column structure to bottom interval forms lattice column main body, batten plate 102 and angle on lattice column The contact area of steel 101 is at least the half of batten plate area.
A2, welding batten plate 102: batten plate 102 is soldered to top, last block batten plate of top along the bottom of column structure 102 is adjustable with column structure top distance.
Top batten plate 102 is 600mm at a distance from lattice column body top in lattice column preparation process, on single lattice column Every meter is at least arranged two batten plates 102.
A3, field joint are welded: transport to scene after the processing of lattice column main body merogenesis being docked, when welding at the scene For single lattice column welding line joint no more than two, weld seam uses groove welding, and single 101 connector of angle steel will be staggeredly arranged, section Connector rate is 35%, and the distance that is staggered is 560mm.
Lattice column uses Q235B steel in lattice column preparation process, and welding rod uses E43XX, and weld seam is 10mm.
Column pile driving construction includes the following steps:
B1, boring positioning: according to setting position, timber fixed point is directly pinpointed or squeezes into, then by " crossing method " in wood The surrounding of stake fixed point carries out fender pile point, guarantees the firm of boring procedure and safety, it is ensured that drilling it is straight and horizontal.
B2, it excavates pore-forming: ensuring that drilled pile is not tilted, do not moved, it is ensured that the verticality of drilling is set with pile position deviation satisfaction Meter and code requirement, drilling diameter are 20cm at least bigger than design aperture, and depth of pore forming needs big not less than design hole depth, sediment thickness In 10cm, it is ensured that there are enough spaces to be used to place steel reinforcement cage, guarantee that steel reinforcement cage is placed straight and horizontal.
B3, borehole cleaning simultaneously place steel reinforcement cage 300: placing steel reinforcement cage 300 in cleaning hole after sediment, steel reinforcement cage 300 includes longitudinal The main supporting rib 301 of arrangement and the steel ring 302 of the main supporting rib 301 of connection, are fixed using welding manner between the two.
On steel reinforcement cage 300 every 2m arrange a positioning gusset 303, the symmetrically placed four positioning gusset 303 of per pass section, It is fixed when steel reinforcement cage 300 falls to orifice position with fashioned iron.Wherein the positioning gusset 303 on steel reinforcement cage 300 is using two-sided Weldering, the diameter of section of positioning gusset 303 are 15mm, it is ensured that the intensity of steel reinforcement cage 300.
Lattice column construction includes the following steps:
C1, it determines anchor point: after the completion of stand column pile drilling, borehole circumference mud, soil etc. being cleaned out, surveyor calculates lattice Four four coordinate points of side midpoint extended line of structure column, then carry out unwrapping wire, deviations 48mm.
C2, place lattice column 100: lattice column 100 is sling and is slowly put into steel reinforcement cage 300, at the same use fashioned iron into Row reinforces connection, and the position deviation range that lattice column 100 hangs lattice column when in steel reinforcement cage 300 is ± 25mm, and verticality is inclined Difference is L/250, and lattice column corner is 2.
The section catercorner length that lattice column 100 is inserted into steel reinforcement cage 300 is less than the diameter of steel reinforcement cage 300, it is ensured that lattice Column is smoothly smoothly placed, improve lattice column place stability, it is ensured that construction it is reliable and stable.
C3, lattice column 100 and steel reinforcement cage 300 weld: welding two pegs on every side of lattice column 100, peg is indulged It is 200mm to spacing, often shows five, peg and steel reinforcement cage are locked, be located at lattice column among steel reinforcement cage.
C4, casting concrete: oppose the progress concreting of stanchion bottom, after stand column pile concrete casting complete, carries out in time Stake holes backfill.
Stand column pile lower concrete at least pours in three times, pour for the first time height be at least stand column pile height five/ One, the half that height is at least stand column pile height is poured for the second time, and third time completes the concreting of residual altitude.
On the one hand fully ensured that in this way concrete to pour secret room secured, on the other hand steel reinforcement cage can be carried out good Fastening, avoid rising of steel cage.
Need to backfill after the completion of pouring each time it is closely knit after poured next time again, stake holes is backfilled using coarse sand, is backfilled When from lattice column periphery and it is intermediate uniformly carry out, avoid squeezing inclined.
Embodiment two
A kind of subway station lattice column construction method, including following preparation section: prepared by lattice column 100, the construction of stand column pile 200 and lattice The construction of structure column.
Wherein lattice column 100 includes four angle steel 101 and multiple batten plates 102, and lattice column preparation includes the following steps:
A1, lattice column 100 are arranged: it is arranged symmetrically two-by-two using four angle steel 101, Formation cross-section is rectangular-shaped column structure, Multiple batten plates 102, which are disposed with, from the top of column structure to bottom interval forms lattice column main body, batten plate 102 and angle on lattice column The contact area of steel 101 is at least the half of batten plate area.
A2, welding batten plate 102: batten plate 102 is soldered to top, last block batten plate of top along the bottom of column structure 102 is adjustable with column structure top distance.
Top batten plate 102 is 500mm at a distance from lattice column body top in lattice column preparation process, on single lattice column Every meter is at least arranged two batten plates 102.
A3, field joint are welded: transport to scene after the processing of lattice column main body merogenesis being docked, when welding at the scene For single lattice column welding line joint no more than two, weld seam uses groove welding, and single 101 connector of angle steel will be staggeredly arranged, section Connector rate is 40%, and the distance that is staggered is 600mm.
Lattice column uses Q235B steel in lattice column preparation process, and welding rod uses E43XX, and weld seam is 12mm.
Column pile driving construction includes the following steps:
B1, boring positioning: according to setting position, timber fixed point is directly pinpointed or squeezes into, then by " crossing method " in wood The surrounding of stake fixed point carries out fender pile point, guarantees the firm of boring procedure and safety, it is ensured that drilling it is straight and horizontal.
B2, it excavates pore-forming: ensuring that drilled pile is not tilted, do not moved, it is ensured that the verticality of drilling is set with pile position deviation satisfaction Meter and code requirement, drilling diameter are 20cm at least bigger than design aperture, and depth of pore forming needs big not less than design hole depth, sediment thickness In 10cm, it is ensured that there are enough spaces to be used to place steel reinforcement cage, guarantee that steel reinforcement cage is placed straight and horizontal.
B3, borehole cleaning simultaneously place steel reinforcement cage 300: placing steel reinforcement cage 300 in cleaning hole after sediment, steel reinforcement cage 300 includes longitudinal The main supporting rib 301 of arrangement and the steel ring 302 of the main supporting rib 301 of connection, are fixed using welding manner between the two.
On steel reinforcement cage 300 every 5m arrange a positioning gusset 303, the symmetrically placed four positioning gusset 303 of per pass section, It is fixed when steel reinforcement cage 300 falls to orifice position with fashioned iron.Wherein the positioning gusset 303 on steel reinforcement cage 300 is using two-sided Weldering, the diameter of section of positioning gusset 303 are 18mm, it is ensured that the intensity of steel reinforcement cage 300.
Lattice column construction includes the following steps:
C1, it determines anchor point: after the completion of stand column pile drilling, borehole circumference mud, soil etc. being cleaned out, surveyor calculates lattice Four four coordinate points of side midpoint extended line of structure column, then carry out unwrapping wire, deviations 45mm.
C2, place lattice column 100: lattice column 100 is sling and is slowly put into steel reinforcement cage 300, at the same use fashioned iron into Row reinforces connection, and the position deviation range that lattice column 100 hangs lattice column when in steel reinforcement cage 300 is ± 30mm, and verticality is inclined Difference≤L/300, lattice column corner≤5 °.
The section catercorner length that lattice column 100 is inserted into steel reinforcement cage 300 is less than the diameter of steel reinforcement cage 300, it is ensured that lattice Column is smoothly smoothly placed, improve lattice column place stability, it is ensured that construction it is reliable and stable.
C3, lattice column 100 and steel reinforcement cage 300 weld: welding two pegs on every side of lattice column 100, peg is indulged It is 240mm to spacing, often shows five, peg and steel reinforcement cage are locked, be located at lattice column among steel reinforcement cage.
C4, casting concrete: oppose the progress concreting of stanchion bottom, after stand column pile concrete casting complete, carries out in time Stake holes backfill.
Stand column pile lower concrete at least pours in three times, pour for the first time height be at least stand column pile height five/ One, the half that height is at least stand column pile height is poured for the second time, and third time completes the concreting of residual altitude.
It has on the one hand fully ensured that pouring for concrete is closely knit secured in this way, on the other hand steel reinforcement cage can have been carried out good Fastening, avoid rising of steel cage.
Need to backfill after the completion of pouring each time it is closely knit after poured next time again, stake holes is backfilled using coarse sand, is backfilled When from lattice column periphery and it is intermediate uniformly carry out, avoid squeezing inclined.
The beneficial effect of subway station lattice column construction method of the present invention is:
The overall structural strength of lattice column main body is high, avoids lattice column main body stress deformation, ensure that the installation of lattice column main body Effect;
Lattice column and steel reinforcement cage are placed with enough spaces, guarantee that lattice column and steel reinforcement cage place straight and horizontal, rush Into the work progress stable and continuous of stand column pile and lattice column, construction cost is reduced, construction efficiency is improved.
The above description is only an embodiment of the present invention, is not intended to limit the scope of the invention, all to utilize this hair Equivalent structure or equivalent flow shift made by bright description is applied directly or indirectly in other relevant technology necks Domain is included within the scope of the present invention.

Claims (9)

1. a kind of subway station lattice column construction method, which is characterized in that comprise the following steps: a, lattice column preparation;B, stand column pile Construction;C, lattice column is constructed;
Wherein lattice column includes four angle steel and multiple batten plates, and lattice column preparation includes the following steps:
A1, lattice column arrangement: it is arranged symmetrically two-by-two using four angle steel, Formation cross-section is rectangular-shaped column structure, from column The top of structure to bottom interval is disposed with multiple batten plates and forms lattice column main body;
A2, welding batten plate: batten plate is soldered to top, last block batten plate of top and column structure along the bottom of column structure Top distance is adjustable;
A3, field joint are welded: transport to scene after the processing of lattice column main body merogenesis docked, it is single when welding at the scene For lattice column welding line joint no more than two, weld seam uses groove welding, and single angle steel connector will be staggeredly arranged, and section connector rate is not It can exceed that 50%, the distance that is staggered is greater than 500mm;
Column pile driving construction includes the following steps:
B1, boring positioning: according to setting position, timber fixed point is directly pinpointed or squeezes into, then by " crossing method " in wood The surrounding of stake fixed point carries out fender pile point;
B2, excavate pore-forming: ensuring that drilled pile is not tilted, do not moved, it is ensured that the verticality of drilling and pile position deviation meet design with Code requirement, drilling diameter are 20cm at least bigger than design aperture, and depth of pore forming need to be greater than not less than design hole depth, sediment thickness 10cm;
B3, borehole cleaning simultaneously place steel reinforcement cage: placing steel reinforcement cage in cleaning hole after sediment, arrange a positioning every 2 ~ 5m on steel reinforcement cage Gusset, the symmetrically placed four positioning gusset of per pass section, is fixed when steel reinforcement cage falls to orifice position with fashioned iron;
Lattice column construction includes the following steps:
C1, it determines anchor point: after the completion of stand column pile drilling, borehole circumference mud, soil etc. being cleaned out, surveyor calculates lattice Four four coordinate points of side midpoint extended line of structure column, then carry out unwrapping wire, and deviations are less than 50mm;
C2, it places lattice column: lattice column being sling and is slowly put into steel reinforcement cage, while being in reinforcement connection using fashioned iron;
C3, lattice column and steel reinforcement cage weld: welding two pegs on every side of lattice column, the longitudinal pitch of peg is not less than 200mm often shows five, peg and steel reinforcement cage is locked, and is located at lattice column among steel reinforcement cage;
C4, casting concrete: oppose the progress concreting of stanchion bottom, after stand column pile concrete casting complete, carries out stake holes in time Backfill.
2. subway station lattice column construction method according to claim 1, which is characterized in that batten plate and angle steel on lattice column Contact area is at least the half of batten plate area.
3. subway station lattice column construction method according to claim 1, which is characterized in that top in lattice column preparation process Batten plate is not more than 600mm at a distance from lattice column body top, at least arranges two batten plates for every meter on single lattice column.
4. subway station lattice column construction method according to claim 1, which is characterized in that lattice column uses Q235B steel, weldering Item uses E43XX, and weld seam is 10 ~ 20mm.
5. subway station lattice column construction method according to claim 1, which is characterized in that steel reinforcement cage includes longitudinally arranged The steel ring of main supporting rib and the main supporting rib of connection, is fixed using welding manner between the two.
6. subway station lattice column construction method according to claim 1, which is characterized in that in column pile driving construction on steel reinforcement cage Positioning gusset use welding by both sides, the diameter of section for positioning gusset is at least 15mm.
7. subway station lattice column construction method according to claim 1, which is characterized in that lattice column is hung in steel reinforcement cage When lattice column position deviation range be ± 25 ~ 38mm, perpendicularity deviation≤L/250, lattice column corner≤2 ° ~ 5 °.
8. subway station lattice column construction method according to claim 1, which is characterized in that lattice column is inserted into steel reinforcement cage Section catercorner length is less than the diameter of steel reinforcement cage.
9. subway station lattice column construction method according to claim 1, which is characterized in that stand column pile lower concrete is at least It pours in three times, pours height is at least stand column pile height 1/5th for the first time, pour height for the second time and be at least column Stake height half, third time complete residual altitude concreting, pour each time after the completion of need to backfill it is closely knit after again It is poured next time.
CN201811622500.3A 2018-12-28 2018-12-28 Subway station lattice column construction method Pending CN109723081A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811622500.3A CN109723081A (en) 2018-12-28 2018-12-28 Subway station lattice column construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811622500.3A CN109723081A (en) 2018-12-28 2018-12-28 Subway station lattice column construction method

Publications (1)

Publication Number Publication Date
CN109723081A true CN109723081A (en) 2019-05-07

Family

ID=66296554

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811622500.3A Pending CN109723081A (en) 2018-12-28 2018-12-28 Subway station lattice column construction method

Country Status (1)

Country Link
CN (1) CN109723081A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110411430A (en) * 2019-07-30 2019-11-05 中铁十二局集团有限公司 The survey of forced centering observation pier sets Construction Method of Metro Station
CN110685295A (en) * 2019-09-16 2020-01-14 中国二十冶集团有限公司 Bored concrete pile shaped steel combination assembled tower crane basis
CN112012222A (en) * 2020-08-27 2020-12-01 中交隧道工程局有限公司 Construction system and construction method for hard rock stratum upright post pile in urban sensitive area

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
张茸: "浅谈格构柱安装施工质量控制", 《四川水泥》 *
陈克济等: "《地铁工程施工技术》", 30 June 2014, 中国铁道出版社 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110411430A (en) * 2019-07-30 2019-11-05 中铁十二局集团有限公司 The survey of forced centering observation pier sets Construction Method of Metro Station
CN110685295A (en) * 2019-09-16 2020-01-14 中国二十冶集团有限公司 Bored concrete pile shaped steel combination assembled tower crane basis
CN112012222A (en) * 2020-08-27 2020-12-01 中交隧道工程局有限公司 Construction system and construction method for hard rock stratum upright post pile in urban sensitive area

Similar Documents

Publication Publication Date Title
CN104895092B (en) The method that a kind of interim lattice column of inner support is used as permanent structure post
CN105201532B (en) The Ring Cutting construction method of underground Long span spherical crown shape dome under weak surrounding rock
CN106930271A (en) It is a kind of to excavate the continuous side wall supporting and retaining system protective construction in underground and its construction method without fertile groove
CN109723081A (en) Subway station lattice column construction method
CN105587320B (en) Rich water sand-pebble layer abnormal shape deep shaft structural system and its construction method
CN103510540B (en) Mortar flag stone retaining wall reinforcement construction method and structure thereof
CN108643192A (en) Brace in Deep Footing Groove supporting ultralong steel tube column pile construction method
CN103306289A (en) Foundation pit piled anchor dado concrete anchor cable top beam structure and construction method thereof
CN104746892B (en) Construction method that joist demolishes walls device and joist is demolished walls
CN107435335A (en) Brick retaining wall steel bar girder hardened system and method on foundation pit enclosure top beam
CN110777802A (en) Deep foundation pit high-low span supporting structure and construction method thereof
CN104131566B (en) A kind of basement is without the construction method of horizontal support foundation ditch
CN205077499U (en) Double row pile supporting construction with transverse connection component
CN110439025A (en) Portal type building pile foundation underpinning structure in narrow space and construction method
CN106758759A (en) A kind of trestle pile foundation and its anchoring process for deep water drift net riverbed
CN206800370U (en) It is a kind of to excavate the continuous side wall supporting and retaining system protective construction in underground without fertile groove
CN105274997B (en) Muscle formula bracket and the method for pushing up road steel pipe support and top board using bracket construction
CN108951655A (en) Basement construction method for supporting in the case of prestressed stretch-draw
CN108797607B (en) Construction method for double-pipe inclined strut support deep foundation pit
CN113339014B (en) Back hole side wall steel rail pipe curtain method and structure for protecting rock clamping in ultra-small clear distance tunnel
CN206036408U (en) Span pipeline normal position of foundation ditch and suspend protection architecture in midair
CN206477240U (en) A kind of trestle pile foundation for deep water drift net riverbed
CN109797753A (en) Suitable for the stand column pile of high scar place foundation pit and the construction method of lattice column
CN108193695A (en) A kind of enclosure structure of foundation pit of subway station support and construction method
CN207862947U (en) A kind of enclosure structure of foundation pit of subway station support

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190507

RJ01 Rejection of invention patent application after publication