CN109681206A - 一种采煤填充控制地表沉降的方法 - Google Patents

一种采煤填充控制地表沉降的方法 Download PDF

Info

Publication number
CN109681206A
CN109681206A CN201810947745.7A CN201810947745A CN109681206A CN 109681206 A CN109681206 A CN 109681206A CN 201810947745 A CN201810947745 A CN 201810947745A CN 109681206 A CN109681206 A CN 109681206A
Authority
CN
China
Prior art keywords
filling
band
mining
caving
coal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810947745.7A
Other languages
English (en)
Inventor
程志恒
王建伟
王公达
韩小冰
刘光文
李鹏
赵灿
鲍世超
姜黎明
汪昕
余德杰
李文刚
尚俊业
张允光
徐海亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
North China Institute of Science and Technology
Original Assignee
North China Institute of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by North China Institute of Science and Technology filed Critical North China Institute of Science and Technology
Priority to CN201810947745.7A priority Critical patent/CN109681206A/zh
Publication of CN109681206A publication Critical patent/CN109681206A/zh
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21CMINING OR QUARRYING
    • E21C41/00Methods of underground or surface mining; Layouts therefor
    • E21C41/16Methods of underground mining; Layouts therefor
    • E21C41/18Methods of underground mining; Layouts therefor for brown or hard coal
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F15/00Methods or devices for placing filling-up materials in underground workings

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Remote Sensing (AREA)
  • Processing Of Solid Wastes (AREA)

Abstract

本发明公开了一种采煤填充控制地表沉降的方法,该方法包含:根据矿井岩层的物理力学性质,计算各岩层的荷载,若岩层的荷载小于其下层岩层的荷载,则该岩层作为关键层,找出所有的关键层;煤层的侧面作为采煤工作面,在该采煤工作面上设置有:充填支架,在采煤时,采煤工作面每向前推进一距离,沿推进方向构筑矸石充填条带,并通过垮落法形成垮落顶板条带,且矸石充填条带与垮落顶板条带间隔设置;在垮落时,形成离层空间;将高水材料填充入离层空间内,形成高水充填体,实现充填条带与高水充填体的联合支撑体系。本发明的采煤填充控制地表沉降的方法通过联合矸石充填和高水材料充填,以控制地表沉降,不仅提高了支撑效果,而且降低了成本。

Description

一种采煤填充控制地表沉降的方法
技术领域
本发明属于煤矿充填技术领域,具体涉及一种采煤填充控制地表沉降的方法。
背景技术
我国煤矿开采历史悠久,开发范围广阔,特别是山西等重点产煤省份,开发强度较大,历史遗留采空区面积广,采空区地表塌陷破坏严重。长壁工作面是我国最常见的采煤工作面之一,具有采煤效率高,巷道掘进少等优点。
近年来,随着煤矿充填机械的进步,特别是综采充填一体化专用支架的研制成功,又出现了采用综合机械化进行矸石充填的技术,即综合机械化矸石充填。
综合机械化矸石充填集“减沉”和“减排”于一体,其所用的专门充填支架前部为普通综采支架,支架后部在顶梁上悬吊了一部刮板输送机以输送矸石充填材料。工作面先采煤后充填,采空区随采随充,确保采空区的大部分空间及时为矸石所充填,并以矸石充填体来限制煤层上覆岩层的移动,从而实现控制地表沉陷的目的。该技术采用的充填体为矸石粉煤灰混合体,具有抗变形能力强、长期稳定等优点,且可以消除矿山上普遍存在的矸石山等,是一种较为理想的充填材料。
但是,综合机械化矸石充填存在用量太大,材料来源较少,又成本较高等缺点,达到了增加吨煤成本70-80元,不能大规模采用。矸石充填的成本成为了限制其大规模应用的主要问题。此外,综合机械化矸石充填还存在采煤效率过低的缺点,工作面年均产煤量不超过100万吨。
因此,通过减少矸石用量以缩小成本,以及提高工作面采煤效率是今后矸石充填的发展方向。高水材料充填是采用水体积比超过90%的高水材料进行充填的一种新技术,其主要优点在于材料来源不受限制,成本也较低,高水材料可以通过管道或钻孔输送至充填区域,但存在需要在采空区构筑专用的模板体系,材料的泌水性(指水泥浆体所含水分从浆体中析出的难易程度)及长期稳定性差等缺点。
发明内容
本发明的目的是提供一种采煤填充控制地表沉降的方法,该方法解决了现有矸石充填用量大成本高的问题,通过矸石充填条带与高水充填体的联合支撑,具有很好的支撑效果,实现对地表沉降的控制。
为了达到上述目的,本发明提供了一种采煤填充控制地表沉降的方法,该方法包含:
(S1)煤层的侧面作为采煤工作面,在该采煤工作面上设置有:充填支架,在采煤时,所述的采煤工作面每向前推进一距离,沿推进方向构筑矸石充填条带,并通过垮落法形成垮落顶板条带,且所述的矸石充填条带与所述的垮落顶板条带间隔设置;
(S2)根据矿井岩层的物理力学性质,计算各岩层的荷载(qi)1,i=1……n,若岩层i+1的荷载(qi)1小于其下层岩层i的荷载(qi-1)1,则岩层i+1作为关键层,找出所有的关键层;
(S3)在垮落时,在所述的垮落顶板条带上方的各关键层和其下层岩层之间形成离层空间;
(S4)在所述离层空间上的关键层钻孔形成注浆通道,所述的离层空间与注浆通道相通,高水材料通过该注浆通道从下至上依次填充入所述的离层空间内,形成高水充填体,实现矸石充填条带与高水充填体的联合支撑体系,以支撑岩层及表土层。
优选地,在所述的步骤(S2)中,所述的物理力学性质包含:各岩层i的弹性模量Ei、厚度hi和容重γi
优选地,在所述的步骤(S2)中,所述计算采用的公式为:
优选地,在所述的步骤(S1)中,所述矸石充填条带为倾斜长壁矸石充填条带,其采用综合机械化矸石充填方法进行充填。
优选地,所述矸石充填条带和垮落顶板条带的宽度均与所述采煤工作面向前推进的距离相等。
优选地,所述采煤工作面向前推进的距离为40m。
本发明的采煤填充控制地表沉降的方法,解决了现有矸石充填用量大成本高的问题,具有以下优点:
(1)本发明的方法对采空区后方进行了局部的矸石充填,采用矸石充填条带与垮落顶板条带间隔设置,局部矸石条带充填的范围比采空区全矸石充填缩短了一半,减少了矸石用量的同时也降低了成本,并提高了采煤工作面的推进速度,提升了采煤效率;
(2)本发明的方法采用高水充填,需要在矸石条带形成后进行,工序上与采煤及矸石充填不发生冲突,可并行进行,其充填范围为各关键层下方的离层空间,关键层及其下部的岩层恰好形成了高水充填所需要的模板体系,避免了构筑专门的模板体系,不仅减少了填充工序,而且还降低了高水充填的成本,可大量使用;
(3)本发明的方法采用矸石条带结合高水充填,实现了优势互补,又克服了各自的缺陷,形成了以矸石条带作为支撑主体,高水充填离层空间为辅的充填体系,可以较好地实现控制地表沉陷的目的。
附图说明
图1为本发明的倾斜长壁矸石条带与高水充填的纵剖面示意图。
图2为本发明的倾斜长壁矸石条带与高水充填的平面示意图。
图3为本发明的矿井岩层中关键层的计算示意图。
具体实施方式
以下结合附图和实施例对本发明的技术方案做进一步的说明。
一种采煤填充控制地表沉降的方法,该方法包含:
(S1)如图1所示,为本发明的倾斜长壁矸石条带与高水充填的纵剖面示意图,如图2所示,为本发明的倾斜长壁矸石条带与高水充填的平面示意图,煤层1的侧面作为采煤工作面9,在该采煤工作面9上设置有:充填支架10,在采煤时,采煤工作面9每向前推进一距离,沿推进方向构筑矸石充填条带8,并通过垮落法形成垮落顶板条带7,且矸石充填条带8与垮落顶板条带7间隔设置;
(S2)如图3所示,为本发明的矿井岩层中关键层的计算示意图,根据矿井岩层的物理力学性质,计算各岩层2的荷载(qi)1,i=1……n,若岩层i+1的荷载qi1小于其下层岩层i的荷载(qi-1)1,则岩层i+1作为关键层3,找出所有的关键层3;
(S3)在垮落时,在垮落顶板条带7上方的各关键层3和其下层岩层2之间形成离层空间6;
(S4)在离层空间6上的关键层3钻孔形成注浆通道5,离层空间6与注浆通道5相通,高水材料通过该注浆通道5从下层至上层依次填充入离层空间6内,形成高水充填体,实现矸石充填条带与高水充填体的联合支撑体系,以支撑岩层2及表土层4。
在步骤(S2)中,物理力学性质包含:各岩层i的弹性模量Ei、厚度hi和容重γi
在步骤(S2)中,计算采用的公式为:
在步骤(S1)中,矸石充填条带8为倾斜长壁矸石充填条带,其采用综合机械化矸石充填方法进行充填。
矸石充填条带8和垮落顶板条带7的宽度均与采煤工作面9向前推进的距离相等。
采煤工作面(9)向前推进的距离为40m。采煤工作面9每次向前推进的距离越大,则采煤效率越高,但是控制地表沉降的效果则越差;反之则控制地表沉降的效果越好,采煤效率越低。保持矸石充填条带8和垮落顶板条带7的宽度均与采煤工作面9向前推进的距离相等,以保证地表不会沉降。
实施例1
一种采煤填充控制地表沉降的方法,如图1和图2所示,前方煤层1后即为综合机械化矸石充填采煤工作面9,采煤工作面9布置有充填液压支架10,矸石充填条带8间隔布置,间隔距离为40m,矸石充填条带8之间采用垮落法管理顶板,其垮落后形成垮落顶板条带7。
综合机械化矸石充填的采煤工作面9每往前推进40m进行充填作业,构筑沿推进方向宽度为40m的矸石充填条带8,矸石充填条带8与垮落顶板条带7间隔布置,垮落顶板条带7的宽度也为40m。
如图3所示,按公式计算岩层荷载,其中,Ei、hi和γi分别为各岩层i的弹性模量、厚度及容重;依公式从岩层1逐层往上计算,当出现时(qi+1)1<(qi)1,即上一层的荷载小于下层的荷载,则第i+1层岩层即为关键层3,一直往上计算到表土层4下部的岩层n,直到找出所有关键层3,各关键层3下即为可能的离层空间6,注浆通道5需要穿透各关键层3,并从底层关键层3开始注入高水材料(高水速凝固材料),直到最上层关键层3。
在垮落顶板条带7上部的各关键层3之下钻有注浆通道5,关键层3下部的离层空间6用高水材料充填,形成高水充填体;形成矸石充填条带8和高水充填体的联合支撑体系以支撑上部岩层2及表土层4。
本发明的方法经过构筑矸石充填条带及进行覆岩离层高水材料注浆充填,形成了矸石条带和高水充填体的支撑体系,矸石充填条带是支撑主体,高水充填体的主要作用是保证各关键层不发生破断,避免了关键层破断波及地表,又对采空区进行的是局部充填,比全部充填减少了一半的充填量,既考虑了采煤效率,又考虑了控制地表沉降的效果,提高了采煤工作面的推进速度,且相应的也提高了经济效益。
综上所述,本发明的采煤填充控制地表沉降的方法通过联合矸石充填和高水材料充填,以控制地表沉降,不仅提高了支撑效果,降低了成本,而且还能实现更大规模的开采填充。
尽管本发明的内容已经通过上述优选实施例作了详细介绍,但应当认识到上述的描述不应被认为是对本发明的限制。在本领域技术人员阅读了上述内容后,对于本发明的多种修改和替代都将是显而易见的。因此,本发明的保护范围应由所附的权利要求来限定。

Claims (6)

1.一种采煤填充控制地表沉降的方法,其特征在于,该方法包含:
(S1)煤层(1)的侧面作为采煤工作面(9),在该采煤工作面(9)上设置有:充填支架(10),在采煤时,所述的采煤工作面(9)每向前推进一距离,沿推进方向构筑矸石充填条带(8),并通过垮落法形成垮落顶板条带(7),且所述的矸石充填条带(8)与所述的垮落顶板条带(7)间隔设置;
(S2)根据矿井岩层的物理力学性质,计算各岩层(2)的荷载(qi)1,i=1……n,若岩层i+1的荷载(qi)1小于其下层岩层i的荷载(qi-1)1,则岩层i+1作为关键层(3),找出所有的关键层(3);
(S3)在垮落时,在所述的垮落顶板条带(7)上方的各关键层(3)和其下层岩层(2)之间形成离层空间(6);
(S4)在所述离层空间(6)上的关键层(3)钻孔形成注浆通道(5),所述的离层空间(6)与注浆通道(5)相通,高水材料通过该注浆通道(5)从下至上依次填充入所述的离层空间(6)内,形成高水充填体,实现充填条带与高水充填体的联合支撑体系,以支撑岩层(2)及表土层(4)。
2.根据权利要求1所述的采煤填充控制地表沉降的方法,其特征在于,在所述的步骤(S2)中,所述的物理力学性质包含:各岩层i的弹性模量Ei、厚度hi和容重γi
3.根据权利要求2所述的采煤填充控制地表沉降的方法,其特征在于,在所述的步骤(S2)中,所述计算采用的公式为:
4.根据权利要求1-3中任意一项所述的采煤填充控制地表沉降的方法,其特征在于,在所述的步骤(S1)中,所述矸石充填条带(8)为倾斜长壁矸石充填条带,其采用综合机械化矸石充填方法进行充填。
5.根据权利要求4所述的采煤填充控制地表沉降的方法,其特征在于,所述矸石充填条带(8)和垮落顶板条带(7)的宽度均与所述采煤工作面(9)向前推进的距离相等。
6.根据权利要求5所述的采煤填充控制地表沉降的方法,其特征在于,所述采煤工作面(9)向前推进的距离为40m。
CN201810947745.7A 2018-08-20 2018-08-20 一种采煤填充控制地表沉降的方法 Pending CN109681206A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810947745.7A CN109681206A (zh) 2018-08-20 2018-08-20 一种采煤填充控制地表沉降的方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810947745.7A CN109681206A (zh) 2018-08-20 2018-08-20 一种采煤填充控制地表沉降的方法

Publications (1)

Publication Number Publication Date
CN109681206A true CN109681206A (zh) 2019-04-26

Family

ID=66185573

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810947745.7A Pending CN109681206A (zh) 2018-08-20 2018-08-20 一种采煤填充控制地表沉降的方法

Country Status (1)

Country Link
CN (1) CN109681206A (zh)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110145363A (zh) * 2019-04-30 2019-08-20 中国矿业大学(北京) 一种实现综采面垮落到充填开采过渡的顶板控制方法
CN110424966A (zh) * 2019-07-25 2019-11-08 中国矿业大学 一种超高水材料充填工作面矸石泵送留巷无煤柱开采方法
CN110552717A (zh) * 2019-05-27 2019-12-10 中铁十八局集团第四工程有限公司 砂卵石地层盾构隧道地表分层差异沉降空间注浆减沉方法
CN110593874A (zh) * 2019-10-09 2019-12-20 中国矿业大学 一种煤矿强弱强全采全充方法
CN110671145A (zh) * 2019-10-24 2020-01-10 中国煤炭地质总局勘查研究总院 一种大采宽厚煤层开采复合注浆方法
CN112049682A (zh) * 2020-10-23 2020-12-08 孙嘉岐 一种采空区煤矸石支护性实体充填方法
CN112360550A (zh) * 2020-10-28 2021-02-12 安徽理工大学 一种沿空留巷中低位顶板离层区煤基固废膏体注充方法
CN115341903A (zh) * 2022-08-19 2022-11-15 中国矿业大学 面向煤炭开采和耕地保护协同发展的地下采煤设计方法
CN117449900A (zh) * 2023-10-12 2024-01-26 北京科技大学 一种控制采场岩层移动及地表沉降的方法

Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3588175A (en) * 1969-04-15 1971-06-28 Atlantic Richfield Co Methods for mining deep thick oil shale deposits
CN103216236A (zh) * 2013-03-13 2013-07-24 中国矿业大学(北京) 一种采场覆岩离层的注浆减沉方法
CN104405437A (zh) * 2014-10-08 2015-03-11 中国矿业大学 一种固体充填与综采混合式工作面开采方法
CN104912590A (zh) * 2015-05-26 2015-09-16 山东科技大学 一种砂岩顶板中厚煤层间隔式充填留巷方法
CN105317459A (zh) * 2015-11-19 2016-02-10 中国矿业大学(北京) 一种用于控制坚硬顶板大面积垮落灾害的分区充填方法
CN105332733A (zh) * 2015-09-25 2016-02-17 山东科技大学 普采工作面采空区泵送胶结材料的条带充填方法
CN105507947A (zh) * 2015-12-07 2016-04-20 平顶山天安煤业股份有限公司 一种网络化矸石充填方法
CN106150545A (zh) * 2016-08-05 2016-11-23 太原理工大学 一种根据顶板垮落特征进行采空区部分充填的方法
CN206174997U (zh) * 2016-10-25 2017-05-17 淮北工业建筑设计院有限责任公司 一种采动覆岩走向分区隔离注浆充填结构
CN106958446A (zh) * 2017-06-01 2017-07-18 湖南科技大学 一种急倾斜煤层开采的岩层移动及地表沉陷的控制方法
CN107916933A (zh) * 2017-11-20 2018-04-17 河南理工大学 一种坚硬顶板煤层采空区空间留设方法
CN107989613A (zh) * 2017-11-14 2018-05-04 太原理工大学 一种覆岩离层分区隔离注浆充填开采煤层全部回采方法
CN108194132A (zh) * 2017-12-27 2018-06-22 山东科技大学 一种墩式连拱式采空区处理方法
CN108204244A (zh) * 2016-12-20 2018-06-26 中国矿业大学(北京) 矸石间隔充填采煤法

Patent Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3588175A (en) * 1969-04-15 1971-06-28 Atlantic Richfield Co Methods for mining deep thick oil shale deposits
CN103216236A (zh) * 2013-03-13 2013-07-24 中国矿业大学(北京) 一种采场覆岩离层的注浆减沉方法
CN104405437A (zh) * 2014-10-08 2015-03-11 中国矿业大学 一种固体充填与综采混合式工作面开采方法
CN104912590A (zh) * 2015-05-26 2015-09-16 山东科技大学 一种砂岩顶板中厚煤层间隔式充填留巷方法
CN105332733A (zh) * 2015-09-25 2016-02-17 山东科技大学 普采工作面采空区泵送胶结材料的条带充填方法
CN105317459A (zh) * 2015-11-19 2016-02-10 中国矿业大学(北京) 一种用于控制坚硬顶板大面积垮落灾害的分区充填方法
CN105507947A (zh) * 2015-12-07 2016-04-20 平顶山天安煤业股份有限公司 一种网络化矸石充填方法
CN106150545A (zh) * 2016-08-05 2016-11-23 太原理工大学 一种根据顶板垮落特征进行采空区部分充填的方法
CN206174997U (zh) * 2016-10-25 2017-05-17 淮北工业建筑设计院有限责任公司 一种采动覆岩走向分区隔离注浆充填结构
CN108204244A (zh) * 2016-12-20 2018-06-26 中国矿业大学(北京) 矸石间隔充填采煤法
CN106958446A (zh) * 2017-06-01 2017-07-18 湖南科技大学 一种急倾斜煤层开采的岩层移动及地表沉陷的控制方法
CN107989613A (zh) * 2017-11-14 2018-05-04 太原理工大学 一种覆岩离层分区隔离注浆充填开采煤层全部回采方法
CN107916933A (zh) * 2017-11-20 2018-04-17 河南理工大学 一种坚硬顶板煤层采空区空间留设方法
CN108194132A (zh) * 2017-12-27 2018-06-22 山东科技大学 一种墩式连拱式采空区处理方法

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
姚琦: "急倾斜煤层综采走向分段充填及其岩层控制研究", 《中国博士论文学位论文全文数据库工程科技I辑》 *
耿献文: "《矿山压力测控技术》", 31 August 2013, 中国矿业大学出版社 *

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110145363A (zh) * 2019-04-30 2019-08-20 中国矿业大学(北京) 一种实现综采面垮落到充填开采过渡的顶板控制方法
CN110145363B (zh) * 2019-04-30 2024-03-29 中国矿业大学(北京) 一种实现综采面垮落到充填开采过渡的顶板控制方法
CN110552717A (zh) * 2019-05-27 2019-12-10 中铁十八局集团第四工程有限公司 砂卵石地层盾构隧道地表分层差异沉降空间注浆减沉方法
CN110424966A (zh) * 2019-07-25 2019-11-08 中国矿业大学 一种超高水材料充填工作面矸石泵送留巷无煤柱开采方法
CN110593874A (zh) * 2019-10-09 2019-12-20 中国矿业大学 一种煤矿强弱强全采全充方法
CN110593874B (zh) * 2019-10-09 2020-12-01 中国矿业大学 一种煤矿强弱强全采全充方法
WO2021068691A1 (zh) * 2019-10-09 2021-04-15 巨峰 一种煤矿强弱强全采全充方法
CN110671145A (zh) * 2019-10-24 2020-01-10 中国煤炭地质总局勘查研究总院 一种大采宽厚煤层开采复合注浆方法
CN112049682A (zh) * 2020-10-23 2020-12-08 孙嘉岐 一种采空区煤矸石支护性实体充填方法
CN112360550A (zh) * 2020-10-28 2021-02-12 安徽理工大学 一种沿空留巷中低位顶板离层区煤基固废膏体注充方法
CN115341903A (zh) * 2022-08-19 2022-11-15 中国矿业大学 面向煤炭开采和耕地保护协同发展的地下采煤设计方法
CN117449900A (zh) * 2023-10-12 2024-01-26 北京科技大学 一种控制采场岩层移动及地表沉降的方法

Similar Documents

Publication Publication Date Title
CN109681206A (zh) 一种采煤填充控制地表沉降的方法
CN106223958B (zh) 倾斜中厚矿体分区凿岩阶段落矿嗣后充填协同采矿法
WO2021068691A1 (zh) 一种煤矿强弱强全采全充方法
CN108661705B (zh) 条采采空区四位一体综合治理施工方法
AU2013358812B2 (en) Solid-filling coal mining method with two pre-excavated tunnels for advancing
AU2020100234A4 (en) Method for water conservation mining by filling flexible strip
Steiner Tunnelling in squeezing rocks: case histories
CN106930763B (zh) 一种充填复采特厚煤层残采区护巷煤柱的方法
CN110242301A (zh) 一种顶板含水层两步骤注浆改性保水采煤方法
CN101864957B (zh) 大量放矿同步充填无顶柱留矿采矿方法
CN103615250B (zh) 分条间柱全空场开采嗣后充填协同采矿法
Han et al. Multiple and long-term disturbance of gob-side entry retaining by grouped roof collapse and an innovative adaptive technology
CN103437769B (zh) 组合再造结构体中深孔落矿协同锚索支护嗣后充填采矿法
CN103016053A (zh) 一种采空区局部充填控制地表沉陷的方法
CN108194132B (zh) 一种墩式连拱式采空区处理方法
CN108518222A (zh) 膏体充填结合顶板预裂复采特厚煤层停采线煤柱的方法
US20180195386A1 (en) Parallel digging, mining and filling operation coal mining method for controlling overlaying strata fracture and surface subsidence
CN110671145A (zh) 一种大采宽厚煤层开采复合注浆方法
CN102230396A (zh) 煤矿采空区随采随充充填方法
CN104500070B (zh) 一种连续采煤机膏体充填开采方法
CN103437768B (zh) 一种不留顶底柱预置空间充填采矿法
CN103742146B (zh) 墩柱式充填法采煤工艺
CN108708723A (zh) 一种煤岩柱交替支撑无煤柱充填开采减沉方法
CN104088662B (zh) 一种固体充填采煤沿空留巷支护墙体的施工方法
CN108087021A (zh) 一种充填采煤回收遗留煤柱并控制隔水关键层稳定的方法

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190426

RJ01 Rejection of invention patent application after publication