CN109681083A - A kind of installation method of aluminum window - Google Patents

A kind of installation method of aluminum window Download PDF

Info

Publication number
CN109681083A
CN109681083A CN201910087472.8A CN201910087472A CN109681083A CN 109681083 A CN109681083 A CN 109681083A CN 201910087472 A CN201910087472 A CN 201910087472A CN 109681083 A CN109681083 A CN 109681083A
Authority
CN
China
Prior art keywords
window
frame body
upper frame
installation
slot
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910087472.8A
Other languages
Chinese (zh)
Other versions
CN109681083B (en
Inventor
赵维和
王磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin Wuqing Construction Engineering Group Co.,Ltd.
Original Assignee
Wuqing District Tianjin Construction Engineering Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuqing District Tianjin Construction Engineering Corp filed Critical Wuqing District Tianjin Construction Engineering Corp
Priority to CN201910087472.8A priority Critical patent/CN109681083B/en
Publication of CN109681083A publication Critical patent/CN109681083A/en
Application granted granted Critical
Publication of CN109681083B publication Critical patent/CN109681083B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E06DOORS, WINDOWS, SHUTTERS, OR ROLLER BLINDS IN GENERAL; LADDERS
    • E06BFIXED OR MOVABLE CLOSURES FOR OPENINGS IN BUILDINGS, VEHICLES, FENCES OR LIKE ENCLOSURES IN GENERAL, e.g. DOORS, WINDOWS, BLINDS, GATES
    • E06B1/00Border constructions of openings in walls, floors, or ceilings; Frames to be rigidly mounted in such openings
    • E06B1/56Fastening frames to the border of openings or to similar contiguous frames
    • E06B1/60Fastening frames to the border of openings or to similar contiguous frames by mechanical means, e.g. anchoring means
    • EFIXED CONSTRUCTIONS
    • E06DOORS, WINDOWS, SHUTTERS, OR ROLLER BLINDS IN GENERAL; LADDERS
    • E06BFIXED OR MOVABLE CLOSURES FOR OPENINGS IN BUILDINGS, VEHICLES, FENCES OR LIKE ENCLOSURES IN GENERAL, e.g. DOORS, WINDOWS, BLINDS, GATES
    • E06B1/00Border constructions of openings in walls, floors, or ceilings; Frames to be rigidly mounted in such openings
    • E06B1/56Fastening frames to the border of openings or to similar contiguous frames
    • E06B1/58Fastening frames to the border of openings or to similar contiguous frames by filling up the joints, e.g. by cementing
    • EFIXED CONSTRUCTIONS
    • E06DOORS, WINDOWS, SHUTTERS, OR ROLLER BLINDS IN GENERAL; LADDERS
    • E06BFIXED OR MOVABLE CLOSURES FOR OPENINGS IN BUILDINGS, VEHICLES, FENCES OR LIKE ENCLOSURES IN GENERAL, e.g. DOORS, WINDOWS, BLINDS, GATES
    • E06B7/00Special arrangements or measures in connection with doors or windows
    • E06B7/28Other arrangements on doors or windows, e.g. door-plates, windows adapted to carry plants, hooks for window cleaners
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G13/00Installations of lightning conductors; Fastening thereof to supporting structure

Landscapes

  • Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Door And Window Frames Mounted To Openings (AREA)

Abstract

The present invention relates to a kind of installation methods of aluminum window, belong to the technical field of building doors and windows installing engineering, its key points of the technical solution are that a kind of installation method of aluminum window, comprising the following steps: S1, snap the line look for rule;S2, the installation site for determining wall thickness direction;S3, window frame is fixedly installed in window;In step s 2, a horizontal location block downwards is bonded in the corresponding position on the top of window, one vertically oriented piece is respectively bonded in the two sides of window, window frame includes upper frame body and lower frame body, the top of upper frame body offers vertically oriented slot, the two sides of upper frame body offer horizontal location slot, it will be in the vertically oriented piece of vertically oriented slot of insertion when installation, horizontal location block is inserted into horizontal location slot, and it stamps bolt and to form fixation between upper frame body and window, after lower frame body is aligned with upper frame body again, the bottom of lower frame body and two sides are bolted with window, achieve the effect that improve window frame installation accuracy.

Description

A kind of installation method of aluminum window
Technical field
The present invention relates to the technical field of building doors and windows installing engineering more particularly to a kind of installation methods of aluminum window.
Background technique
Aluminum window refers to a kind of window for using aluminum alloy building section production frame, fanning member structure, mainly by aluminum window The composition such as frame, fan, glass, Hardware fitting and sealing material.
The existing common mounting means of aluminum window is substantially are as follows: S1, civil construction are in wall etc. reserved opening;S2, Before the plastering wet construction of hole and wall, window frame is installed by bolt and wall connecting;S3, between window frame and wall Gap filling polyurethane foams.
But window frame is generally similar with reserved hole size, therefore the resistance being subject to when window frame is filled in hole compared with Greatly, operator sometimes even needs to pound window frame in hole using hammer, but so the installation of window frame can deposit In the not high problem of installation accuracy.
Summary of the invention
The purpose of the present invention is to provide a kind of aluminum window installation methods for improving window frame installation accuracy.
Technical purpose of the invention has the technical scheme that
A kind of aluminum window installation method, comprising the following steps:
S1, snap the line look for rule: finding out window sideline top, will be drawn under window sideline with big line pendant, and cross at window Label picks chisel processing to mouth side not straight individually;
S2, the installation site for determining wall thickness direction: according to exterior wall drawing and the width of windowsill, determine aluminum window in wall thickness The installation site in direction, and snap the line positions;
S3, window frame is fixedly installed in window;
S4, the gap filling polyurethane foams between window frame and wall;
In step s 2, after the installation site for determining wall thickness direction, one is bonded in the corresponding position on the top of window and is erected Straight horizontal location block directed downwardly is respectively bonded one vertically oriented piece, vertically oriented piece in the two sides of window and horizontal location block exists In same plane, window frame includes upper frame body and lower frame body, and the top of upper frame body offers compatible vertical with vertically oriented piece Locating slot, the two sides of upper frame body offer horizontal location slot compatible with horizontal location block, and when installation inserts vertically oriented piece Enter in vertically oriented slot, horizontal location block is inserted into horizontal location slot, and stamp bolt and make shape between upper frame body and window At fixation, the bottom of upper frame body offers card slot, and card slot opens up direction through upper frame body, the slot bottom centre bit of card slot along window The place of setting offers vertical binding groove, and the top of lower frame body is fixedly installed fixture block compatible with card slot, the top bullet of fixture block Property be connected with fastening column compatible with binding groove, after upper frame body is installed, push lower frame body make fixture block insertion card slot in, The compression of column hand is fastened until fastening column is inserted into binding groove, then the bottom of lower frame body and two sides and window are connected by bolt It connects.
Through the above technical solutions, window frame is divided into upper frame body and lower frame body two parts, when installation, first consolidates upper frame body It is scheduled on window, and reaches window frame using the cooperation of vertically oriented piece and vertically oriented slot, horizontal location block and horizontal location slot Locating effect, then again by lower frame body along window sliding to locating piece insertion locating slot in, when slide into fastening column alignment When in binding groove, fastening column be can be inserted to which upper frame body and lower frame body to be fixed in binding groove, will be whole compared to directly A window frame is fixed in window, is divided into two parts and is installed so that the resistance that is subject to during installation of window frame is smaller, for the peace of window frame It is also smaller to fill precision influence, after upper frame body and lower frame body alignment, then forms fixation with bolt and wall respectively, window frame can be made Distribution of force it is uniform, overall offset will not occur after long-term use for window frame, to further improve the use of window frame Service life.
The present invention is further arranged to: the two sides of the upper frame body and lower frame body are fixedly connected with multiple fixation spring tabs, Threaded hole is offered on fixation spring tab, in step s3, is fixedly connected with fixation spring tab with the side wall of window using expansion bolt, And downward close to the fixation spring tab inclination of outdoor side.
Through the above technical solutions, squeezing into expansion bolt after upper frame body is positioned and making shape between upper frame body and wall At fixation, equally, lower frame body and metope form fixation also by expansion bolt, and the fixation spring tab close to outdoor side tilts court Under, therefore when rainwater protrudes into the gap between window frame and wall, rainwater can slide along fixation spring tab directed downwardly is tilted, without It can be entered the room along fixation spring tab, improve rainproof effect.
The present invention is further arranged to: before carrying out step S3, to upper frame body and lower frame body towards window inner wall Side carries out preservative treatment.
Through the above technical solutions, after the side of upper frame body and lower frame body carries out preservative treatment, it can be to avoid rear Joint filling substance is directly contacted with upper frame body and lower frame body when continuous joint filling, so that electrochemistry occur, corrodes aluminum window, therefore big The anti-corrosion ability of upper frame body and lower frame body is improved greatly.It carries out when carrying out preservative treatment by design requirement, is such as wanted without design When asking, can brushing anti-corrosion material, such as Banana Type anticorrosive paint, also Pasting plastic film is protected.
The present invention is further arranged to: before carrying out step S3, first being installed one close to outdoor side in window and is kept away Thunder block, lightning-arrest block are connected with the trigged thunder line for extending downward into ground, fix one close to outdoor side in lower frame body and take shelter from the thunder The lightning-arrest item of block contact.
Through the above technical solutions, installing lightning-arrest block can be improved the lightning protection capability under thunderstorm weather, safety is improved.
The present invention is further arranged to: after step s 3, thermal insulation material is filled in the gap between window frame and wall And sealing material.
Through the above technical solutions, after filling thermal insulation material and sealing material in gap between window frame and wall, Indoor insulating power can be improved.
The present invention is further arranged to: after step s4, being beaten toward gap of the window frame between outdoor side and wall Enter water-proof climate resisting sealant.
Through the above technical solutions, squeezing into water-proof climate resisting sealant toward gap of the window frame between outdoor side and wall Later, the waterproof performance and weatherability that window frame installation place can be improved, avoiding rainwater from protruding into interior leads to Moisture Problem In Buildings, and Improve indoor insulating power.
The present invention is further arranged to: after step s4, being beaten toward gap of the window frame between indoor side and wall Enter silicon cave sealant.
Through the above technical solutions, silicon cave sealant has outstanding weatherability characteristics and the excellent resistance to height of uvioresistant Indoor heat insulating ability can be improved while improving the adhering and sealing between window frame and wall in the performances such as temperature, corrosion resistance Energy and Corrosion Protection.
In conclusion advantageous effects of the invention are as follows:
1, it is obstructed smaller by the way that the upper frame body and lower frame body that can gradually install is arranged so that the installation of window frame is relatively simple, into And improve installation accuracy;
2, make window frame that there is good lightning protection effect by installing lightning-arrest block;
3, by stamping water-proof climate resisting glue and in window frame around indoor side around outdoor side in window frame Silicon cave sealant is stamped, so that also can be improved thermal insulation property while be bonded closer between window frame and wall.
Detailed description of the invention
Fig. 1 is final installation condition schematic diagram of the invention;
Fig. 2 is the status diagram for installing vertically oriented piece He horizontal location block;
Fig. 3 is the structural schematic diagram of upper frame body;
Fig. 4 is the structural schematic diagram that upper frame body is intended to emphasize binding groove;
Fig. 5 is the perspective view of the explosion of lower frame body;
Fig. 6 is the status diagram for installing upper frame body;
Fig. 7 is the status diagram for installing lightning-arrest block.
Appended drawing reference: 1, window frame;11, upper frame body;111, vertically oriented slot;112, horizontal location slot;113, card slot; 1131, binding groove;12, lower frame body;121, fixture block;122, column is fastened;2, horizontal location block;21, vertically oriented piece;3, fixed bullet Piece;4, lightning-arrest block;41, trigged thunder line;42, lightning-arrest item.
Specific embodiment
Below in conjunction with attached drawing, invention is further described in detail.
A kind of installation method of aluminum window, the specific steps are as follows:
S1, snap the line look for rule: finding out window sideline top, will be drawn under window sideline with big line pendant, and cross at window Label picks chisel processing to mouth side not straight individually;After handling window well, so that the installation resistance that window frame 1 is subject to is smaller, to make Obtain installation process ratio smoothly.
S2, the installation site for determining wall thickness direction: according to exterior wall drawing and the width of windowsill, determine that aluminum window exists The installation site in wall thickness direction, and snap the line positions;
S3, window frame 1 is fixedly installed in window;Before installation, as shown in Figure 1, window frame 1 includes mutually matched upper ledge first 12 two parts of body 11 and lower frame body, upper frame body 11 and lower frame body 12 are in U-shape, before installation, to upper frame body 11 and lower frame body 12 carry out preservative treatment towards the side of window inner wall, carry out when carrying out preservative treatment by design requirement, such as without design requirement When, can brushing anti-corrosion material, such as Banana Type anticorrosive paint, also Pasting plastic film is protected.
As shown in Figures 2 and 3, a vertically oriented slot 111 then is opened up on the top of upper frame body 11, is leaned in upper frame body 11 A horizontal location slot 112 is respectively opened up at the position of nearly window two sides, and when horizontal location slot 112 opens up extends upward through upper frame body 11, it is then flexibly positioned, it is adhesively fixed one vertically oriented piece 21 on the top of window, is respectively adhesively fixed one in the two sides of window A horizontal location block 2, and vertically oriented piece 21 is adapted with vertically oriented slot 111, horizontal location block 2 and horizontal location slot 112 are adapted, and then fix multiple fixation spring tabs with bolt respectively close to indoor and close outdoor two sides in upper frame body 11 3, and diagonally downward, then upper frame body 11 is installed along far from indoor direction in the fixation spring tab 3 close to outdoor side, it installs When, close to window inner wall upward sliding upper frame body 11, so that in the vertically oriented piece 21 vertically oriented slot 111 of insertion, horizontal location Block 2 is inserted into horizontal location slot 112, and upper frame body 11 is positioned vertically block 21 and horizontal location block 2 is blocked and positioned, positioning Later, it will be formed and fixed between fixation spring tab 3 and window inner wall using expansion bolt, so far, shape between upper frame body 11 and window At fixation.
Upper ledge is first installed when installing since window frame 1 is divided into 12 two parts of upper frame body 11 and lower frame body with reference to Fig. 6 Body 11 can reduce the installation resistance between window frame 1 and window, improve the convenience of installation, meanwhile, vertically oriented piece 21 and water Flat locating piece 2 can position upper frame body 11, improve the installation accuracy of upper frame body 11.
With reference to Fig. 4 and Fig. 5, after installing upper frame body 11, continue that lower frame body 12 is installed, the bottom of upper frame body 11 offers One vertical card slot 113, and card slot 113 runs through upper frame body 11 towards outdoor direction along indoor, in the slot bottom of card slot 113 A vertical binding groove 1131 upward is offered at heart position, and the top corresponding position of lower frame body 12 is fixedly installed one A fixture block 121 compatible with card slot 113, the top of fixture block 121 is elasticly connected with one can be sliding with 121 opposed vertical of fixture block Dynamic fastening column 122, specific elastic connection way are as follows: open a slot on the top of fixture block 121, be fixedly installed bullet in slot Spring, fastening column 122 are fixedly connected with spring.Therefore when installing lower frame body 12, fixture block 121 is directed at card slot 113, compression fastening column 122, push lower frame body 12 that upper frame body 11 and lower frame body 12 are aligned, when fixture block 121 is fully inserted into card slot 113, fastening Column 122 is also sprung into binding groove 1131, and outside 12 faced chamber of lower frame body and indoor two sides are also fixedly installed multiple fixations Elastic slice 3, likewise, the fixation spring tab 3 towards outdoor side tilts downward, fixation spring tab 3 is abutted with window, i.e. 11 He of upper frame body Lower frame body 12 formed it is relatively fixed, recycle expansion bolt will be fixedly connected between fixation spring tab 3 and window so that upper ledge Body 11, lower frame body 12 and window form stable fixation (with reference to Fig. 1), and the mode of installation can reduce installation resistance by several times, from And improve the smoothness and installation accuracy of installation.
In conjunction with Fig. 7, before lower frame body 12 is installed, first lightning-arrest block 4 is set in window at the position of outdoor side, keeps away There are two the settings of thunder block 4, and two lightning-arrest blocks 4 are fixedly connected with two vertical planes of window respectively, and block 4 of taking shelter from the thunder uses bonding side Formula and window form fixation, and lightning-arrest block 4 is fixedly connected with the trigged thunder line 41 for stretching to ground towards outdoor side, then exist Lightning-arrest item 42 is fixed with bolt in the corresponding position of lower frame body 12, and when installing lower frame body 12, lightning-arrest item 42 is abutted with lightning-arrest block 4. The setting of lightning-arrest block 4 can prevent from being struck by lightning in thunderstorm weather, improve safety.
After installing upper frame body 11 and lower frame body 12, in the gap between window frame 1 and wall fill thermal insulation material with And sealing material, when such as design is not by choke material kind is provided, using mineral wool or glass felt rug layered tamping, to window when filling The gap of the surrounding of frame 1 carries out simultaneously, firmly cannot be excessive when filling, deforms after preventing 1 stress of window frame.
S4, the gap filling polyurethane foams between window frame 1 and wall;Polyurethane foams can by window frame 1 with Gap between window is eliminated, and is improved the mounting stability between insulating power and window frame 1 and window, is then leaned on toward window frame 1 Water-proof climate resisting sealant is squeezed into gap between nearly outdoor side and wall, can be improved the waterproof performance of 1 installation place of window frame with And weatherability, avoiding rainwater from protruding into interior leads to Moisture Problem In Buildings, and improves indoor insulating power;Then close toward window frame 1 Silicon cave sealant is squeezed into gap between indoor side and wall, and silicon cave sealant has outstanding weatherability characteristics and excellent The performances such as uvioresistant high and low temperature resistance and corrosion resistance can be with while improving the adhering and sealing between window frame 1 and wall Improve indoor thermal insulation property and Corrosion Protection.
In conclusion in the present invention, the mounting means of window frame 1 is disposably embedded 1 mounting means of window frame and changed from traditional Become the gradation mounting means of upper frame body 11 and lower frame body 12, so that the frictional resistance that window frame 1 is subject to during installation is reduced, from And make installation process more smooth, and can reduce due to frictional force it is excessive caused by installation accuracy reduce.
This specific embodiment is only explanation of the invention, is not limitation of the present invention, those skilled in the art Member can according to need the modification that not creative contribution is made to the present embodiment after reading this specification, but as long as at this All by the protection of Patent Law in the scope of the claims of invention.

Claims (7)

1. a kind of installation method of aluminum window, comprising the following steps:
S1, snap the line look for rule: finding out window sideline top, will be drawn under window sideline with big line pendant, and cross at window Label picks chisel processing to mouth side not straight individually;
S2, the installation site for determining wall thickness direction: according to exterior wall drawing and the width of windowsill, determine aluminum window in wall thickness The installation site in direction, and snap the line positions;
S3, window frame (1) is fixedly installed in window;
S4, the gap filling polyurethane foams between window frame (1) and wall;
It is characterized by: in step s 2, after the installation site for determining wall thickness direction, in the corresponding position on the top of window The horizontal location block (2) of bonding one downwards, is respectively bonded one vertically oriented piece (21) in the two sides of window, vertically oriented In the same plane, window frame (1) includes upper frame body (11) and lower frame body (12), upper frame body for block (21) and horizontal location block (2) (11) top offer with vertically oriented piece (21) compatible vertically oriented slot (111), the two sides of upper frame body (11) open up There is a compatible horizontal location slot (112) with horizontal location block (2), by vertically oriented piece (21) the vertically oriented slot of insertion when installation (111) in, by horizontal location block (2) insertion horizontal location slot (112), and stamp bolt make upper frame body (11) and window it Between formed and fix, the bottom of upper frame body (11) offers card slot (113), and card slot (113) opens up direction through upper ledge along window Body (11), the slot bottom center position of card slot (113) offer vertical binding groove (1131), and the top of lower frame body (12) is fixed Be provided with card slot (113) compatible fixture block (121), the top of fixture block (121) is elasticly connected with and binding groove (1131) phase The fastening column (122) of adaptation pushes lower frame body (12) that fixture block (121) is made to be inserted into card slot after upper frame body (11) installation (113) in, the compression of fastening column (122) hand is until in fastening column (122) insertion binding groove (1131), then by the bottom of lower frame body (12) Portion and two sides are bolted with window.
2. a kind of installation method of aluminum window according to claim 1, it is characterised in that: the upper frame body (11) and The two sides of lower frame body (12) are fixedly connected with multiple fixation spring tabs (3), and fixation spring tab offers threaded hole on (3), in step S3 In, fixation spring tab (3) is fixedly connected with the side wall of window using expansion bolt, and the fixation spring tab (3) close to outdoor side Inclination is downward.
3. a kind of installation method of aluminum window according to claim 1, it is characterised in that: before carrying out step S3, Preservative treatment is carried out towards the side of window inner wall to upper frame body (11) and lower frame body (12).
4. a kind of installation method of aluminum window according to claim 1, it is characterised in that: before carrying out step S3, One lightning-arrest block (4) first is installed close to outdoor side in window, lightning-arrest block (4) are connected with the trigged thunder line for extending downward into ground (41), the lightning-arrest item (42) contacted with lightning-arrest block (4) is fixed close to outdoor side in lower frame body (12).
5. a kind of installation method of aluminum window according to claim 1, it is characterised in that: after step s 3, toward window Thermal insulation material and sealing material are filled in gap between frame (1) and wall.
6. a kind of installation method of aluminum window according to claim 5, it is characterised in that: after step s4, toward window Water-proof climate resisting sealant is squeezed into gap of the frame (1) between outdoor side and wall.
7. a kind of installation method of aluminum window according to claim 1, it is characterised in that: after step s4, toward window Silicon cave sealant is squeezed into gap of the frame (1) between indoor side and wall.
CN201910087472.8A 2019-01-29 2019-01-29 Installation method of aluminum alloy window Active CN109681083B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910087472.8A CN109681083B (en) 2019-01-29 2019-01-29 Installation method of aluminum alloy window

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910087472.8A CN109681083B (en) 2019-01-29 2019-01-29 Installation method of aluminum alloy window

Publications (2)

Publication Number Publication Date
CN109681083A true CN109681083A (en) 2019-04-26
CN109681083B CN109681083B (en) 2020-09-08

Family

ID=66194238

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910087472.8A Active CN109681083B (en) 2019-01-29 2019-01-29 Installation method of aluminum alloy window

Country Status (1)

Country Link
CN (1) CN109681083B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110173189A (en) * 2019-06-05 2019-08-27 皓耀时代(福建)集团有限公司 A kind of mounting structure and its installation method of house window frame
CN110397372A (en) * 2019-06-22 2019-11-01 东莞市建工集团有限公司 Efficient erection of doors and windows method

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1274794A (en) * 2000-02-28 2000-11-29 林俊桢 Auxiliary frame and its construction process
GB2407827A (en) * 2003-10-29 2005-05-11 Komfort Office Environments Resiliently fitting panel or the like into frame or aperture
KR100617368B1 (en) * 2004-09-18 2006-08-29 주식회사 알루폼스코리아 Structure of fixing of window frame and construction method
CN103967386A (en) * 2014-05-13 2014-08-06 二十二冶集团第一建设有限公司 Anti-leakage joint processing method of first filling gap of outer window of building
CN105275308A (en) * 2015-10-30 2016-01-27 成都标建铝业有限公司 Aluminum window with size being easy to adjust
CN205297159U (en) * 2015-11-24 2016-06-08 天津市海涛门窗有限公司 Novel building window structure
CN107476706A (en) * 2017-09-20 2017-12-15 湖州欧贝得门业有限公司 A kind of double solid wood door frames for opening timber
CN107587815A (en) * 2017-09-20 2018-01-16 湖州欧贝得门业有限公司 A kind of combined type timber
CN208089097U (en) * 2018-03-29 2018-11-13 天津市万尔特钢结构有限公司 A kind of steel construction window that can quickly pre-install

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1274794A (en) * 2000-02-28 2000-11-29 林俊桢 Auxiliary frame and its construction process
GB2407827A (en) * 2003-10-29 2005-05-11 Komfort Office Environments Resiliently fitting panel or the like into frame or aperture
KR100617368B1 (en) * 2004-09-18 2006-08-29 주식회사 알루폼스코리아 Structure of fixing of window frame and construction method
CN103967386A (en) * 2014-05-13 2014-08-06 二十二冶集团第一建设有限公司 Anti-leakage joint processing method of first filling gap of outer window of building
CN105275308A (en) * 2015-10-30 2016-01-27 成都标建铝业有限公司 Aluminum window with size being easy to adjust
CN205297159U (en) * 2015-11-24 2016-06-08 天津市海涛门窗有限公司 Novel building window structure
CN107476706A (en) * 2017-09-20 2017-12-15 湖州欧贝得门业有限公司 A kind of double solid wood door frames for opening timber
CN107587815A (en) * 2017-09-20 2018-01-16 湖州欧贝得门业有限公司 A kind of combined type timber
CN208089097U (en) * 2018-03-29 2018-11-13 天津市万尔特钢结构有限公司 A kind of steel construction window that can quickly pre-install

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110173189A (en) * 2019-06-05 2019-08-27 皓耀时代(福建)集团有限公司 A kind of mounting structure and its installation method of house window frame
CN110397372A (en) * 2019-06-22 2019-11-01 东莞市建工集团有限公司 Efficient erection of doors and windows method

Also Published As

Publication number Publication date
CN109681083B (en) 2020-09-08

Similar Documents

Publication Publication Date Title
CN109681083A (en) A kind of installation method of aluminum window
CN208309858U (en) A kind of insulated fire plate used for building exterior wall
KR102287955B1 (en) Finishing panel for exterior wall and finishing structure for exterior wall using the same
CN110397370A (en) A kind of method of anti-leakage of door & window and wall construction using this method
CN214697464U (en) Existing door and window transformation mounting structure
CN215804046U (en) Novel window frame mounting structure
CN210767952U (en) A outer wall insulation structure for old house transformation
CN210264441U (en) Sealing rubber strip for aluminum alloy door and window
CN108360946B (en) External independent assembly type heat-insulation door and window sleeve
CN203796065U (en) Rainwater-seepage-preventing device for plastic-steel window
CN208310555U (en) A kind of mounting structure of door and window auxiliary frame and door and window outline border
CN209603734U (en) A kind of heat-insulated windowsill of antiseep and the sill structure using the windowsill
CN107687239B (en) Integrated external wall panel mounting structure and construction method
CN108166890B (en) Mounting structure of door and window auxiliary frame and door and window outer frame
TW202033875A (en) Water-repellent window structure
CN216713474U (en) Sleeve pipe mounting structure and box steel construction building
KR102015433B1 (en) Curtain wall
CN111364878A (en) Passive type window externally-hung type door and window pre-installation structure for building and installation method
CN206385983U (en) A kind of window frame and connecting structure of wall
CN100559007C (en) A kind of window water-tight device
CN209384905U (en) A kind of modified housing window bridge cut-off
CN112095930B (en) Roof decoration structure of skylight member and round steel support and construction method
CN216157061U (en) Passive basement
CN219931062U (en) Anti-seepage wallboard for large-area basement construction
CN109594893A (en) A kind of noise control environmental protection and energy saving aluminium alloy window

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address

Address after: Room 302, think tank building, No.1 Quanli Road, Huangzhuang street, Wuqing District, Tianjin

Patentee after: Tianjin Wuqing Construction Engineering Group Co.,Ltd.

Address before: 301700 No.9 East yongyang Road, Yangcun, Wuqing District, Tianjin

Patentee before: TIANJIN CITY WUQING DISTRICT ARCHITECTURAL ENGINEERING GENERATION Co.

CP03 Change of name, title or address