CN109680703A - Soft Soil Layer open caisson construction method - Google Patents

Soft Soil Layer open caisson construction method Download PDF

Info

Publication number
CN109680703A
CN109680703A CN201811597631.0A CN201811597631A CN109680703A CN 109680703 A CN109680703 A CN 109680703A CN 201811597631 A CN201811597631 A CN 201811597631A CN 109680703 A CN109680703 A CN 109680703A
Authority
CN
China
Prior art keywords
open caisson
sinking
caisson
soil layer
mixing pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811597631.0A
Other languages
Chinese (zh)
Inventor
何亮
张文浩
何德华
邱永钦
陈建宁
董志杰
林涛
杨添
王少萍
招日兴
欧文熹
沈伟滨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Municipal Engineering Group Co Ltd
Guangzhou Municipal Engineering Testing Co
Original Assignee
Guangzhou Municipal Engineering Group Co Ltd
Guangzhou Municipal Engineering Testing Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Municipal Engineering Group Co Ltd, Guangzhou Municipal Engineering Testing Co filed Critical Guangzhou Municipal Engineering Group Co Ltd
Priority to CN201811597631.0A priority Critical patent/CN109680703A/en
Publication of CN109680703A publication Critical patent/CN109680703A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/20Caisson foundations combined with pile foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D23/00Caissons; Construction or placing of caissons
    • E02D23/08Lowering or sinking caissons

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses a kind of Soft Soil Layer open caisson construction methods, by cement mixing pile being arranged and before well sinking in open caisson periphery bored grouting in caisson cutting edge bottom in advance, ensure open caisson during being sunk using drainage open caisson with the earthwork dug transport after can uniform, controllable drown oneself, to avoid open caisson that super heavy and heavy problem of dashing forward occurs in sinking watching, when well sinking to cement mixing stake top, mixing pile is successively abolished by uniform intervals, and it synchronizes and is uniformly arranged big sand pocket, off-load is carried out using the sand pocket i.e. sandbox effect for filling sand to drown oneself, realize open caisson safety, uniform controlled sinking, prevent open caisson from substantially sinking and tilting.The Soft Soil Layer open caisson construction method, construction technology is convenient and reliable, materials are convenient, work progress is safe and reliable, it targetedly solves because in Soft Soil Layer construction open caisson bring safe mass risk problem, ensure the construction quality and safety of open caisson, and construction cost is significantly reduced, meet national energy-saving environmental requirement.

Description

Soft Soil Layer open caisson construction method
Technical field
The present invention relates to a kind of Soft Soil Layer open caisson construction methods.
Background technique
Caisson structure object is on the ground and melt pit for building open caisson, and first production opening armored concrete pit shaft, accomplishes complete High or Partial Height (when merogenesis), after reaching some strength, manually or machinery is constantly layered shoveling, muck haulage in pit shaft, with In well native face gradually decrease, open caisson stack shell borrows its self weight (or under imposed load effect) to overcome frictional force and sword between soil wall The resistance of underfooting soil, constantly cuts native sinking.When merogenesis being taken to make, then during well-sinking or in each stage of sinking, Increase pit shaft section by section, continue to cut the earth, loop back and forth like this, after pit shaft blade foot reaches designed elevation, carries out substrate shaping, Casting concrete bed course and reinforced concrete floor back cover.
If carrying out major diameter open caisson construction in soft soil layer, because the Soft Soil Layer on open caisson periphery has natural moisture content height, hole Gap than big, bad hydraulic permeability, compressibility is high, intensity is low the features such as, open caisson open caisson bottom foundation bearing capacity during sinking construction Be not enough to carry the self weight of top open caisson and cause open caisson super heavy and inclination etc. safe masses problem.
Summary of the invention
The quality problems that major diameter open caisson construction is likely to occur are carried out in Soft Soil Layer, the invention proposes a kind of weak soils Layer open caisson construction method, it is therefore an objective to major diameter open caisson be made to avoid that inclination of open caisson and the super quality such as heavy occur when soft soil layer sinks Problem makes open caisson smoothly be sink to designed elevation position.Specifically adopt the following technical scheme that
Soft Soil Layer open caisson construction method provided by the invention is by being arranged cement mixing pile simultaneously in caisson cutting edge bottom in advance In open caisson periphery bored grouting before well sinking, it is ensured that open caisson using drainage sink during open caisson with the earthwork After being transported by digging can uniform, controllable drown oneself, to avoid open caisson that the super heavy and prominent problem sunk occurs in sinking watching, when When well sinking to cement mixing pile (real stake part) stake top, mixing pile is successively abolished by uniform intervals, and synchronize and uniformly set Big sand pocket is set, off-load is carried out using the sand pocket i.e. sandbox effect for filling sand and drowns oneself, realize open caisson safety, uniformly controlled sinking, prevent Only open caisson substantially sinks and tilts.It is utilized, is finally efficiently solved big by the above-mentioned combination to three key measures Diameter open caisson is in highly difficult technical problems such as prominent heavy, the super heavy and open caisson deflections of soft soil layer.
Advantage: the Soft Soil Layer open caisson construction method, construction technology is convenient and reliable, materials are convenient, work progress is safe and reliable, It targetedly solves because in Soft Soil Layer construction open caisson bring safe mass risk problem, it is ensured that the construction quality of open caisson And safety, and construction cost is significantly reduced, meet national energy-saving environmental requirement.
Detailed description of the invention
The drawings described herein are used to provide a further understanding of the present invention, constitutes part of this application, not Inappropriate limitation of the present invention is constituted, in the accompanying drawings:
Fig. 1 is that plan view is arranged in mixing pile of the embodiment of the present invention;
Fig. 2 is that elevation is arranged in mixing pile of the embodiment of the present invention;
Fig. 3 is mixing pile of embodiment of the present invention supporting caisson schematic diagram;
Fig. 4 is the borehole wall of embodiment of the present invention inlet well plan view;
Fig. 5 is bored grouting of embodiment of the present invention elevation;
Fig. 6 is that plan view is arranged in sand pocket of the embodiment of the present invention;
Fig. 7 is that sand pocket of the embodiment of the present invention abolishes schematic diagram;
Fig. 8 is construction process of embodiment of the present invention schematic diagram.
Specific embodiment
Below in conjunction with attached drawing and specific embodiment, the present invention will be described in detail, herein illustrative examples of the invention And explanation is used to explain the present invention, but not as a limitation of the invention.
The technology contents, which are mainly included in, makes and controls the technical measures that major diameter open caisson smoothly sinks in soft soil layer. The technology is mainly passed through preset in advance cement mixing pile and in the slip casting of borehole wall periphery and by being acted on using the sandbox of sand pocket, is changed Into the process in soft soil layer major diameter open caisson construction, construction process are as follows: preparation of construction → setting mixing pile → excavation of foundation pit → The outer bored grouting of merogenesis production open caisson → borehole wall → draining shoveling sinks down into stirring stake top → abolishes part mixing pile → blade foot Sand pocket → abolishing all mixing piles → is symmetrically filled between mixing pile abolishes the stable sinking of sand pocket → open caisson and back cover simultaneously.
The technology mainly combines the purpose for realizing invention by following three key measures:
One, by being equably arranged a certain number of cement mixing piles (see Fig. 1/2/3) in caisson cutting edge bottom in advance, increase Big caisson cutting edge end Bearing Capacity of Composite Foundation, prevents open caisson super heavy in open caisson.The empty stake of cement mixing pile point and real stake two parts It is empty stake from 2m above absolute altitude from ground to Sinking Well Design bottom, the following are real stakes for remaining.
Two, before well sinking, around open caisson outer wall bored grouting improvement well Zhou Tuti mechanical property (see Fig. 4/ 5), increase external wall friction power, prevent from significantly sinking with bottom mixing pile collective effect, reduce the cost.
Three, when well sinking to stirring stake top, mixing pile is successively abolished by uniform intervals, and synchronize and be uniformly arranged sand Bag carries out off-load using the sandbox effect of sand pocket and drowns oneself, realizes open caisson safety, uniformly controlled sinking, avoid because having abolished stirring Occur hanging between stake region and open caisson bottom and open caisson is caused substantially to sink and tilt (see Fig. 6/7).
Specifically, as shown in figure 8, Soft Soil Layer open caisson construction method detailed step of the present invention is as follows:
One, construction procedure
1, preparation of construction
(1) it constructs early period, it is necessary in conjunction with unit, designing institute and local related geology hydrological data is reconnoitred, determine construction ground Point hydrogeologic condition.
(2) according to " open caisson and Pneumatic Caisson Construction specification " GBT 51130-2016, to open caisson collateral resistance, subsidence factor and High stability is connect to be checked.Determine that parameter, mixing pile specification, material and setting length is arranged in blade foot by checking.
2, mixing pile is set
(1) line setting work need to be strictly carried out when mixing pile is arranged, and carry out apparent mark in the anchor point determined Note.
(2) mixing pile the quantity of the cement injected need to carry out monitoring, when pile level difference is excessive, must abolish before open caisson pours Part stirring pile head, reduces mixing pile elevation difference.When ensuring well sinking to mixing pile position, by the open caisson of mixing pile support Blade foot bottom surface can be in same level.
(3) mixing pile after pile need to mark on the ground, can be used as reference point when open caisson pours.
(4) economical to save, part sky stake, the construction method of lower part reality stake, mixing pile can be used in mixing pile construction Real stake top absolute altitude should be higher than that the above 2m of caisson cutting edge floor design absolute altitude.
3, excavation of foundation pit
(1) unwrapping wire on the spot surveying setting-out: is carried out according to drawing and surface traverse using theodolite, level.
(2) foundation pit height about 1m-2m, according to the appropriate slope of live site condition.Bottom of foundation ditch sideline is from open caisson outer wall 2m Left and right.
(3) bottom of foundation ditch surrounding is arranged the gutter of 30cm × 30cm dimensions above and accesses to sump in foundation pit, Well depth of catchmenting should be than draining ditch depth 50cm.Sump internal water accumulation will be detached by water pump in time.
(4) usage mining machine carries out excavation of foundation pit according to unwrapping wire range, and the earthwork outer in time should be transported to specified place.
4, open caisson is made
(1) according to live site condition, determine that merogenesis pours the number of open caisson in advance.Determine the setting of plain concrete cushion layer Parameter.
(2) unwrapping wire on the spot surveying setting-out: is carried out according to drawing and surface traverse using theodolite, level.
(3) blade foot plain concrete cushion layer pours: carrying out plain concrete cushion layer formwork in boundary of works area, pours.It needs stringent Bed course flatness is controlled, plain concrete cushion layer height and width difference control are within ± 10cm, it is ensured that open caisson can be located after pouring On maintenance level face.After bed course pours, unwrapping wire is carried out in mat surface and carries out blade foot position mark, improves blade foot Construction accuracy.
(4) blade foot is arranged: according to drawing or checking determining blade foot setting type, is carried out according to drawing and mat surface label The binding of blade foot reinforcing bar, formwork and concreting.Pay special attention to reinforce frequency of vibrating when blade foot bottom pours, blade foot pours Before, filled and process plate can be shifted to an earlier date in the position of reserved bottom plate, blade foot removes cystosepiment after the completion of pouring.
(5) scaffold building: double ground steel pipe scaffold is arranged in open caisson periphery, needs to carry out full hall foot hand on the inside of open caisson Frame is set up.Scaffold can just be set up after must being checked according to relevant regulations specification.
(6) template is installed: before the installation of open caisson template, it is necessary to be checked according to relevant regulations specification, bearing height is greater than It need to be expounded through peer review when 8m.
(7) borehole wall pours: borehole wall placement layer by layer is carried out after template is checked and accepted, every layer pours 30-50cm, can adopt simultaneously It is poured, and is vibrated with 1-3 platform pump truck.
(8) steel plate for sealing water: borehole wall section and section between according to specification be arranged steel plate for sealing water, the steel plate for sealing water lap of splice >= 20cm, interior outside are both needed to be fully welded.
5, it cuts the earth and sinks down into stirring stake top absolute altitude
(1) it abolishes bed course: using manually blade foot two sides of the bottom plain concrete cushion layer is abolished using pneumatic pick, being controlled when abolishing broken Except dynamics, damage caisson cutting edge is avoided.
(2) construction equipment: visual soil layer situation selects the crawler-mounted excavator of different tonnages.
(3) it cuts the earth: first digging 1m or so bowl-shape soil layer among open caisson, then uniformly take soil around from centre.When taking Slow down when soil is close to mixing pile and take native speed, open caisson and surrounding soil layer are monitored, open caisson local buckling and deviation are avoided.
6, the outer bored grouting of the borehole wall
(1) line setting: according to soil layer geology and the local hydrology, setting is greater than the boring point of 15 points, hole outside the borehole wall Diameter is greater than 500mm.Unwrapping wire is carried out outside the borehole wall, orients the position of mixing pile under boring point and blade foot.Drilled edge point needs to paste Nearly mixing pile stake side.
(2) bored grouting: being drilled in anchor point using drilling machine, and drilling is under blade foot at the absolute altitude of mixing pile stake bottom. The drilling of all drilled hole point carries out slip casting after finishing, when slip casting selects watertight cement, controls cement mixed weight.
7, mixing pile is abolished
(1) exposure mixing pile: the ring-shaped groove of width a 1m-2m wide, 1m high are excavated in open caisson inner peripheral, makes to stir Stake is exposed in the visual field.
(2) mixing pile construction equipment: is abolished using hand fit's pneumatic pick.
(3) abolish selection: view open caisson specification, 6-8 point of uniform design will abolish mixing pile in point range as abolishing a little Abolish by several times.Each point range is abolished to take in 3 mixing piles.
(4) abolish a mixing pile to abolish: every mixing pile single abolishes height in 30-50cm.Same batch abolishes stirring Stake height must be consistent and measures and adjust after abolishing.
8, sand pocket is set between caisson cutting edge and mixing pile.
(1) after abolishing 6 mixing piles, sand pocket is filled between blade foot and mixing pile.When filling sand pocket and blade foot and Mixing pile fits closely.
(2) sand pocket compactedness: sand body compactedness is 90% or so in single sand pocket.
(3) material selects: common sand pocket, sand in sand body selection can be selected.
9, remaining mixing pile is abolished
(1) after sand pocket is filled, continue to abolish remaining mixing pile.
(2) abolish absolute altitude: abolish absolute altitude with abolish in a little that abolish absolute altitude consistent.So mixing pile absolute altitude is consistent after abolishing.
(3) rear stake face is abolished so mixing pile highness change is within 5cm.
10, sand pocket is abolished
(1) sand pocket is abolished a little: sand pocket, which is abolished, to be a little selected in the middle part of sand pocket.
(2) it abolishes time unification: a little one staff of each arrangement is being abolished when sand pocket is abolished, by special messenger when sand pocket is abolished Commander, command signal are synchronized after assigning and are abolished.
10, open caisson stablizes the simultaneously back cover that sinks
(1) by open caisson self weight and sand body mobility, after sand body flows out sand pocket, open caisson can natural stability sinking.
(2) this engineering method 5.2.7 to 5.2.9 is repeated, up to well sinking to designed elevation.Design is sunk down into open caisson stabilization Bottom sealing is carried out after absolute altitude.
It is provided for the embodiments of the invention technical solution above to be described in detail, specific case used herein The principle and embodiment of the embodiment of the present invention are expounded, the explanation of above embodiments is only applicable to help to understand this The principle of inventive embodiments;At the same time, for those skilled in the art, according to an embodiment of the present invention, in specific embodiment party There will be changes in formula and application range, in conclusion the contents of this specification are not to be construed as limiting the invention.

Claims (2)

1. a kind of Soft Soil Layer open caisson construction method, it is characterised in that:
By the way that a certain number of cement mixing piles are equably arranged in caisson cutting edge bottom in advance, it is compound to increase caisson cutting edge end Foundation bearing capacity prevents open caisson super heavy in open caisson;
Before well sinking, bored grouting improves well Zhou Tuti mechanical property around open caisson outer wall, increases external wall friction power, It prevents from significantly sinking with bottom mixing pile collective effect;
When well sinking to stirring stake top, mixing pile is successively abolished by uniform intervals, and synchronize and be uniformly arranged sand pocket, utilized The sandbox effect of sand pocket carries out off-load and drowns oneself, and realizes open caisson safety, uniformly controlled sinking.
2. a kind of Soft Soil Layer open caisson construction method as described in claim 1, it is characterised in that:
The empty stake of the cement mixing pile point and real stake two parts, from ground to Sinking Well Design bottom above absolute altitude at a certain distance from be empty Stake, the following are real stakes for empty stake.
CN201811597631.0A 2018-12-26 2018-12-26 Soft Soil Layer open caisson construction method Pending CN109680703A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811597631.0A CN109680703A (en) 2018-12-26 2018-12-26 Soft Soil Layer open caisson construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811597631.0A CN109680703A (en) 2018-12-26 2018-12-26 Soft Soil Layer open caisson construction method

Publications (1)

Publication Number Publication Date
CN109680703A true CN109680703A (en) 2019-04-26

Family

ID=66188408

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811597631.0A Pending CN109680703A (en) 2018-12-26 2018-12-26 Soft Soil Layer open caisson construction method

Country Status (1)

Country Link
CN (1) CN109680703A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111042171A (en) * 2019-12-26 2020-04-21 天津市赛英工程技术咨询有限公司 Open caisson construction method suitable for silt soft soil foundation and high underground water level
CN114319406A (en) * 2021-12-07 2022-04-12 上海市基础工程集团有限公司 Sinking stopping method for open caisson in weak stratum
CN115354681A (en) * 2022-09-19 2022-11-18 中建三局绿色产业投资有限公司 Open caisson construction method suitable for house dense area along river basin

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101781896A (en) * 2010-03-20 2010-07-21 浙江裕众建设集团有限公司 Construction method for manufacturing open caisson on concrete cushion
CN102995649A (en) * 2012-12-04 2013-03-27 中国一冶集团有限公司 Method for levelling inclination of open caisson in grading and layer-by-layer manner
KR20140058951A (en) * 2012-11-07 2014-05-15 (주) 선암기술연구소 Caisson tube water-tight structure and under water structure construction method for soft ground
CN105256819A (en) * 2015-09-29 2016-01-20 中国一冶集团有限公司 Improving method for open caisson sinking construction in geology of sludge layer
CN106759426A (en) * 2016-12-30 2017-05-31 中交第二航务工程局有限公司 Soft layer well sinking control method and device

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101781896A (en) * 2010-03-20 2010-07-21 浙江裕众建设集团有限公司 Construction method for manufacturing open caisson on concrete cushion
KR20140058951A (en) * 2012-11-07 2014-05-15 (주) 선암기술연구소 Caisson tube water-tight structure and under water structure construction method for soft ground
CN102995649A (en) * 2012-12-04 2013-03-27 中国一冶集团有限公司 Method for levelling inclination of open caisson in grading and layer-by-layer manner
CN105256819A (en) * 2015-09-29 2016-01-20 中国一冶集团有限公司 Improving method for open caisson sinking construction in geology of sludge layer
CN106759426A (en) * 2016-12-30 2017-05-31 中交第二航务工程局有限公司 Soft layer well sinking control method and device

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111042171A (en) * 2019-12-26 2020-04-21 天津市赛英工程技术咨询有限公司 Open caisson construction method suitable for silt soft soil foundation and high underground water level
CN114319406A (en) * 2021-12-07 2022-04-12 上海市基础工程集团有限公司 Sinking stopping method for open caisson in weak stratum
CN115354681A (en) * 2022-09-19 2022-11-18 中建三局绿色产业投资有限公司 Open caisson construction method suitable for house dense area along river basin

Similar Documents

Publication Publication Date Title
CN106958256B (en) A kind of placement layer by layer, the open caisson construction technique repeatedly sunk
CN104264688B (en) Manually digging hole non-uniform pile support construction process
CN107503257B (en) One kind being close to mountain high-filled subgrade stabilization and Deformation control structure and construction method
US8898996B2 (en) Method for forming a retaining wall, and corresponding retaining wall
CN108035335A (en) A kind of construction freezing method well shaft type underground parking garage method
CN108797598A (en) The construction technology of pre-loaded support struts in a kind of deep basal pit
CN111236957B (en) Mechanical pipe jacking construction process
CN105951711A (en) Enclosing construction method of underground continuous wall of seashore power station
CN207109475U (en) It is close to mountain high-filled subgrade stabilization and Deformation control structure
CN108824445A (en) A kind of foundation pit construction engineering method with enclosure-type mud equilibrium function building enclosure
CN106088127A (en) Open caisson construction method
CN104988948B (en) A kind of construction method of fin-plate type retaining wall
CN102430277B (en) Coarse grid sunk well for physically processing waste water and construction method thereof
CN109680703A (en) Soft Soil Layer open caisson construction method
CN109630127A (en) A kind of construction method of rich water soft stratum ultra-deep shield vertical shaft
CN108457282A (en) Deep water hard rock is without back cover steel sheet pile cofferdam construction method
CN109577365A (en) A kind of pile formula drainage anchor rod barrier wall structure and its construction method
CN107503754A (en) A kind of construction method of VI grade of country rock rich water Shallow tunnel with large cross-section
CN109778869A (en) Foundation ditch construction method
CN110159294A (en) A kind of high steep landform tunnel immediately adjacent to bridge section spreading open cut tunnel construction method
CN208088288U (en) The big areas grain size shiver stone Gao Tian pile foundation fast pore-creating structure
CN108316289A (en) Big grain size shiver stone Gao Tian area's pile foundation fast pore-creating structures and its construction technology
CN108571000A (en) The construction method of underground water cutting when wearing existing railway under a kind of road of location along the river
CN110397050A (en) A kind of light-duty draining barricade of novel beam anchor formula and its construction method
CN104963348B (en) A kind of soft clay area tower crane construction supporting structure and its construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190426

RJ01 Rejection of invention patent application after publication