CN109667605A - A kind of manual imitation is laid with the construction method and laying rack of tunnel double-lining steel mesh - Google Patents

A kind of manual imitation is laid with the construction method and laying rack of tunnel double-lining steel mesh Download PDF

Info

Publication number
CN109667605A
CN109667605A CN201910126914.5A CN201910126914A CN109667605A CN 109667605 A CN109667605 A CN 109667605A CN 201910126914 A CN201910126914 A CN 201910126914A CN 109667605 A CN109667605 A CN 109667605A
Authority
CN
China
Prior art keywords
door frame
tunnel
rotation
curved support
reinforcement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910126914.5A
Other languages
Chinese (zh)
Inventor
蒋忠全
郑之凯
段平安
王申宇
李学刚
代竟
乔磊
彭勇辉
韩明
刘坤
赵睿
刘年
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Tunnel Group Co Ltd CRTG
Sanchu Co Ltd of China Railway Tunnel Group Co Ltd
Original Assignee
China Railway Tunnel Group Co Ltd CRTG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Tunnel Group Co Ltd CRTG filed Critical China Railway Tunnel Group Co Ltd CRTG
Priority to CN201910126914.5A priority Critical patent/CN109667605A/en
Publication of CN109667605A publication Critical patent/CN109667605A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/107Reinforcing elements therefor; Holders for the reinforcing elements
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/15Plate linings; Laggings, i.e. linings designed for holding back formation material or for transmitting the load to main supporting members
    • E21D11/152Laggings made of grids or nettings
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/40Devices or apparatus specially adapted for handling or placing units of linings or supporting units for tunnels or galleries

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The laying method of tunnel double-lining steel mesh is laid with the embodiment of the invention discloses a kind of manual imitation and is laid with rack, the laying rack includes liftable door frame and the liftable curved support frame at the top of the door frame, the curved support top of the trellis is connected with curved support plate, is provided with several longitudinal grooves with carrying longitudinal reinforcement on the curved support plate along the longitudinal direction;The door frame rear and front end is respectively provided with rotation, the telescopic mechanical arm for being laid with circumferential reinforcement and longitudinal reinforcement;The door frame, which is equipped with, provides the rotation motor of power for the rotation, telescopic mechanical arm;Both ends are respectively provided with the horizontal extension arm for completing the transformation of circumferential reinforcement arc at the top of the door frame;The toggle arm that circumferential reinforcement begins, end ground is set right is respectively provided in the middle part of the door frame both ends.

Description

A kind of manual imitation is laid with the construction method and laying rack of tunnel double-lining steel mesh
Technical field
The present embodiments relate to technical field of tunnel construction, and in particular to a kind of manual imitation laying tunnel double-lining steel mesh Construction method and be laid with rack.
Background technique
Well known, steel mesh laying is a heavy artificial work in tunnel double-lining concrete construction at present, danger Dangerous height.
Tunnel double-lining steel mesh is laid at present: reinforcing bar is all by the way that after upper stage, manpower pushing tow is carried out to tunnel rock face It is tied up.
Longitudinal reinforcement method divides step to stand on rack using hoist engine or operator, by the way of relay, Longitudinal reinforcement is placed on rack.After circumferential reinforcement is laid in place, longitudinal tie up with circumferential direction connects into steel mesh.
Circumferential reinforcement laying is to be divided to two classes: a kind of tunnel double-lining circumferential reinforcement, since reinforcing bar is too long, beyond tunnel cross-section Vertically, horizontal length can not vertically and horizontally lifted and put, have to first along tunnel, longitudinal direction is placed on ground. In conventional construction, operator divides on step standing rack the side by the way of each single artificial relay and transmitted Formula, reinforcing bar be along it is longitudinal with it is vertical it is vertical between certain angle oblique cutting enter, reinforcing bar forward along tunnel contour camber line helix The approximately the same plane for finally progressivelying reach designated position forms circumferential reinforcement.Direction, angle are carried out to reinforcing bar during transmitting The correction of degree, radian.The resistance that operator needs to overcome reinforcing bar downward, longitudinal direction move horizontally resistance and brake forming band The resistance come when single steel bar connects into single ring with inverted arch embedded bar, and is connect not yet with other single steel bar rings Networking, easily along tunnel, longitudinal direction collapses, and generates security risk.
Another kind of use other modes lift after prescinding circumferential reinforcement, are connected in tunnel close to scar position It connects, tie point is more, and cost is higher, and uncontrollable factor is more, and the risk of high altitude operation is bigger, and effect is lower.Reinforcing bar simultaneously Spacing can not manually be precisely controlled.
Summary of the invention
For this purpose, the embodiment of the present invention provides the construction method and laying platform of a kind of manual imitation laying tunnel double-lining steel mesh Frame, to solve in the prior art due to being that working efficiency is low caused by manual operation entirely, the big problem of risk.
To achieve the goals above, the embodiment of the present invention provides the following technical solutions:
A kind of manual imitation is laid with the construction method of tunnel double-lining steel mesh, the described method comprises the following steps:
S1, laying rack is opened to the position for needing to install tunnel reinforced mesh;
S2, so that Hanging Basket is reached ground rotation, telescopic mechanical arm decline, laying longitudinal reinforcement needed for tunnel top is placed It on Hanging Basket, is transported on upper arcuate support frame, and longitudinally by reinforcing bar low water in arc groove plate;
S3, drive rotation, telescopic mechanical arm that lock claw axis is down to the ground of tunnel side by rotation motor, by single or One group of circumferential reinforcement of person is fixed on lock claw axis, and locking is fixed;
S4, curved support frame oil cylinder is risen, drives curved support frame to rise to suitable position, facilitates operator in arc The operation of support frame lower part guarantees operating personnel's safety;
S5, it drives rotation, telescopic mechanical arm to rotate by rotation motor, circumferential reinforcement is driven to pass through arc frame top to tunnel Road other side ground;By controlling left and right two groups of horizontal extensions arm oil cylinder, make the telescopic arm on circumferential reinforcement and horizontal extension frame Drive shaft keeps the process for being in close contact and completing the transformation of circumferential reinforcement arc;And the curved support frame on curved support frame drives Moving axis, the whole story end drive shaft in the drive cylinder of whole story end and artificial setting right on the ground of circumferential reinforcement end, make circumferential direction Reinforcing bar enters from oblique cutting, spiral is run to the circumferential proper alignment process of deployment of same section;
S6, the circumferential reinforcement splice reserved with the inverted arch construction of tunnel side is attached;
S7, hoisting frame jacking cylinder make circumferential reinforcement, top longitudinal reinforcement reach designed elevation position;
S8, it carries out the longitudinal reinforcement on circumferential reinforcement and arc jacking frame to be bundled into mesh sheet;
S9, lock claw axis reduced as far as possible by rotation, telescopic mechanical arm make other end circumferential reinforcement cross lock claw axis with The splice that the inverted arch construction of the tunnel other side is reserved is attached;
S10, Hanging Basket is suspended on lock claw axis;
S11, tunnel longitudinal reinforcement, installation personnel are placed on Hanging Basket;
S12, driving rotation, telescopic mechanical arm, send longitudinal reinforcement to the designated position of tunnel side, pass through pecten spacing Control is by two grommets of concrete to the stable state for being bundled into reinforced mesh with longitudinal reinforcement;
S13, curved support oil cylinder is declined, separates curved support frame with reinforced mesh;
S14, driving rotation, telescopic mechanical arm, the operator hung in basket and longitudinal reinforcement are sent to the tunnel other side and encircleed Wall designated position is tied up with circumferential reinforcement, is finally completed all reinforced mesh and is tied up;
S15, such as tunnel concrete two are lined with multi-story steel mesh, repeat above procedure.
The embodiment of the present invention is further characterized in that, when driving rotation, telescopic mechanical arm oil cylinder, guarantees reinforcing bar in rotary course Do not interfere with tunnel scar.
A kind of manual imitation is laid with the laying rack of tunnel double-lining steel mesh, the layings rack include liftable door frame with Liftable curved support frame at the top of the door frame, the curved support top of the trellis are connected with curved support plate, Several longitudinal grooves with carrying longitudinal reinforcement are provided on the curved support plate along the longitudinal direction;
The door frame rear and front end is respectively provided with rotation, the telescopic mechanical arm for being laid with circumferential reinforcement and longitudinal reinforcement; The door frame, which is equipped with, provides the rotation motor of power for the rotation, telescopic mechanical arm;
Both ends are respectively provided with the horizontal extension arm for completing the transformation of circumferential reinforcement arc at the top of the door frame;The door frame The toggle arm that circumferential reinforcement begins, end ground is set right is respectively provided in the middle part of both ends.
The embodiment of the present invention is further characterized in that, between the spacing between two adjacent longitudinal grooves and longitudinal reinforcement laying Away from identical.
The embodiment of the present invention is further characterized in that it is vertical that door frame front and rear sides bottom is connected with two steel pipes vertically respectively Column, two steel pipe posts are respectively on front side of door frame and the position at rear side both ends;It is perpendicular inside the every steel pipe post Directly it is equipped with door frame elevating ram;Elevating ram cylinder body one end is fixedly connected on the door frame bottom, and the elevating ram is defeated Outlet is connected with running gear.
The embodiment of the present invention is further characterized in that the top of the door frame rear and front end passes through the curved support being equipped with vertically Frame oil cylinder connects curved support frame;Described curved support frame cylinder block one end is fixedly connected at the top of the door frame, output end It is fixedly connected on curved support frame bottom;Top rack is equipped at the top of the door frame, the top rack is in two branch Between support.
The embodiment of the present invention is further characterized in that rear and front end is correspondingly provided with pedestal at the top of the door frame;Both ends pedestal it Between be rotatably connected to shaft;The both ends of the shaft, which is respectively perpendicular, is connected with rotation, telescopic mechanical arm, and two rotations are stretched Lock claw axis is fixedly connected between mechanical arm, the lock claw axis is equipped with several first annular grooves;The lock claw axis is in institute State the one end of rotation, telescopic mechanical arm far from the shaft;The rotation motor is connect by transmission mechanism with the shaft;
The rotation, telescopic mechanical arm cylinder body end horizontal connection have telescopic oil cylinder, and the telescopic oil cylinder output end is fixed to be connected It is connected to the rotation, telescopic mechanical arm telescopic end.
The embodiment of the present invention is further characterized in that the shaft is in circumferential reinforcement center.
The embodiment of the present invention is further characterized in that the rack front-rear position is respectively provided with two contrary water of output end Flat telescopic oil cylinder;The horizontal telescoping oil cylinder cylinder body end is fixedly connected on door frame middle top position, the horizontal telescoping oil cylinder Output end is located at door frame end position;Respectively along front and back between two horizontal telescoping oil cylinders at left and right sides of the door frame To being connected with horizontal extension arm drive shaft;Several second circumferential grooves are provided in the horizontal extension arm drive shaft.
The embodiment of the present invention is further characterized in that the toggle arm includes four be separately positioned in the middle part of four steel pipe posts A beginning, end drive shaft oil cylinder;The beginning, end drive shaft oil cylinder body end are fixedly connected on the steel pipe post;It is described Beginning, end drive shaft are connected with backward along front respectively between two beginnings, end drive shaft oil cylinder at left and right sides of door frame; It is described to begin, be provided with several third circumferential grooves in the drive shaft of end.
The embodiment of the present invention, which has the advantages that, is laid with applying for tunnel double-lining steel mesh the object of the present invention is to provide a kind of Circumferential reinforcement is imitated artificial arm band by the principle of 3 points in the same plane decision camber lines by work method, the laying rack Dynamic reinforcing bar does circumferential rotary motion, passes through curved support frame drive shaft, horizontal extension frame drive shaft, the multistage of whole story end drive shaft The centering function of rotation driving and drive shaft upper groove, so that circumferential reinforcement finally enters in same section drive shaft upper groove, Circumferential reinforcement is completed to enter to be fed to the circumferential process of deployment for giving directions same section from longitudinal oblique cutting with vertical certain angle.It solves The mechanization of the circumferential reinforcement of overlength, intermediate connectionless o'clock sharp root reinforcing bar is laid with, and passes through the positioning support function of curved support frame Can, the security risk of collapsing when single circumferential reinforcement unbundling connection networking is prevented, while solving bar spacing accurate positioning The problem of.Labor intensity greatly reduces, improves effect, reduces construction risk.
Detailed description of the invention
It, below will be to embodiment party in order to illustrate more clearly of embodiments of the present invention or technical solution in the prior art Formula or attached drawing needed to be used in the description of the prior art are briefly described.It should be evident that the accompanying drawings in the following description is only It is merely exemplary, it for those of ordinary skill in the art, without creative efforts, can also basis The attached drawing of offer, which is extended, obtains other implementation attached drawings.
Structure depicted in this specification, ratio, size etc., only to cooperate the revealed content of specification, for Those skilled in the art understands and reads, and is not intended to limit the invention enforceable qualifications, therefore does not have technical Essential meaning, the modification of any structure, the change of proportionate relationship or the adjustment of size are not influencing the function of the invention that can be generated Under effect and the purpose that can reach, should all still it fall in the range of disclosed technology contents obtain and can cover.
Fig. 1 is that the structure for the laying rack that a kind of manual imitation provided in an embodiment of the present invention is laid with tunnel double-lining steel mesh is shown Intention and tunnel longitudinal reinforcement restocking operation schematic diagram;
Fig. 2 is the tunnel ring for the laying rack that a kind of manual imitation provided in an embodiment of the present invention is laid with tunnel double-lining steel mesh To reinforcing bar restocking side view work structure diagram;
Fig. 3 is the tunnel ring for the laying rack that a kind of manual imitation provided in an embodiment of the present invention is laid with tunnel double-lining steel mesh To arrangement of bar tiling working state schematic representation;
Fig. 4 is the tunnel ring for the laying rack that a kind of manual imitation provided in an embodiment of the present invention is laid with tunnel double-lining steel mesh Mesh sheet working state schematic representation is bundled into, longitudinal reinforcement.
In figure: 1, Hanging Basket, 2, rotation, telescopic mechanical arm, 3, door frame, 4, horizontal extension arm drive shaft, 5, horizontal extension arm, 6, top rack, 7, rotation, arm telescopic mechanical arm oil cylinder, 8, curved support plate, 9, curved support frame, 10, rotation motor, 11, Curved support frame oil cylinder, 12, door frame elevating ram, 13, beginning, end drive shaft oil cylinder, 14, running gear, 15, beginning, end drive Moving axis.
Specific embodiment
Embodiments of the present invention are illustrated by particular specific embodiment below, those skilled in the art can be by this explanation Content disclosed by book is understood other advantages and efficacy of the present invention easily, it is clear that described embodiment is the present invention one Section Example, instead of all the embodiments.Based on the embodiments of the present invention, those of ordinary skill in the art are not doing Every other embodiment obtained under the premise of creative work out, shall fall within the protection scope of the present invention;Institute in this specification Such as "upper" of reference, "lower", "left", "right", " centre " term, be merely convenient to the clear of narration, rather than to limit The enforceable range of the present invention, relativeness are altered or modified, under the content of no substantial changes in technology, when being also considered as this hair Bright enforceable scope.
It should be noted that along tunnel direction be it is longitudinal, front and back is to being also longitudinal direction.
A kind of manual imitation provided in an embodiment of the present invention is laid with the construction method of tunnel double-lining steel mesh, please refers to Fig. 1, figure 2, shown in Fig. 3 and Fig. 4, method the following steps are included:
S1, laying rack is opened to the position for needing to install tunnel reinforced mesh;
S2, so that Hanging Basket 1 is reached ground rotation, telescopic mechanical arm decline, laying longitudinal reinforcement needed for tunnel top is put It sets on Hanging Basket, is transported on upper arcuate support frame, and longitudinally by reinforcing bar low water in arc groove plate;
S3, drive rotation, telescopic mechanical arm that lock claw axis is down to the ground of tunnel side by rotation motor, by single or One group of circumferential reinforcement of person is fixed on lock claw axis, and locking is fixed;
S4, curved support frame oil cylinder is risen, drives curved support frame to rise to suitable position, facilitates operator in arc The operation of support frame lower part guarantees operating personnel's safety;
S5, it drives rotation, telescopic mechanical arm to rotate by rotation motor, circumferential reinforcement is driven to pass through arc frame top to tunnel Road other side ground;By controlling left and right two groups of horizontal extensions arm oil cylinder, make the telescopic arm on circumferential reinforcement and horizontal extension frame Drive shaft keeps the process for being in close contact and completing the transformation of circumferential reinforcement arc;And the curved support frame on curved support frame drives Moving axis, the whole story end drive shaft in the drive cylinder of whole story end and artificial setting right on the ground of circumferential reinforcement end, make circumferential direction Reinforcing bar enters from oblique cutting, spiral is run to the circumferential proper alignment process of deployment of same section;
S6, the circumferential reinforcement splice reserved with the inverted arch construction of tunnel side is attached;
S7, hoisting frame jacking cylinder make circumferential reinforcement, top longitudinal reinforcement reach designed elevation position;
S8, it carries out the longitudinal reinforcement on circumferential reinforcement and arc jacking frame to be bundled into mesh sheet;
S9, lock claw axis reduced as far as possible by rotation, telescopic mechanical arm make other end circumferential reinforcement cross lock claw axis with The splice that the inverted arch construction of the tunnel other side is reserved is attached;
S10, Hanging Basket is suspended on lock claw axis;
S11, tunnel longitudinal reinforcement, installation personnel are placed on Hanging Basket;
S12, driving rotation, telescopic mechanical arm, send longitudinal reinforcement to the designated position of tunnel side, pass through pecten spacing Control is by two grommets of concrete to the stable state for being bundled into reinforced mesh with longitudinal reinforcement;
S13, curved support oil cylinder is declined, separates curved support frame with reinforced mesh;
S14, driving rotation, telescopic mechanical arm, the operator hung in basket and longitudinal reinforcement are sent to the tunnel other side and encircleed Wall designated position is tied up with circumferential reinforcement, is finally completed all reinforced mesh and is tied up;
S15, such as tunnel concrete two are lined with multi-story steel mesh, repeat above procedure.
It should be noted that when driving rotation, telescopic mechanical arm oil cylinder, guarantee reinforcing bar rotary course and tunnel scar not Interference.
Specifically, a kind of manual imitation described above is laid with the laying rack of tunnel double-lining steel mesh, Fig. 1 institute is please referred to Show, being laid with rack includes liftable door frame 3 and the liftable curved support frame 9 set on 3 top of door frame, curved support frame 9 Top is connected with curved support plate 8, is provided with several longitudinal directions with carrying longitudinal reinforcement on curved support plate 8 along the longitudinal direction Groove 81;
3 rear and front end of door frame is respectively provided with rotation, the telescopic mechanical arm 2 for being laid with circumferential reinforcement and longitudinal reinforcement;Door Frame 3, which is equipped with, provides the rotation motor 10 of power for rotation, telescopic mechanical arm 2;
3 top both ends of door frame are respectively provided with the horizontal extension arm for completing the transformation of circumferential reinforcement arc;In 3 both ends of door frame Portion is respectively provided with the toggle arm that circumferential reinforcement begins, end ground is set right.
It should be noted that in use, a electrical part is electrically connected with extraneous PLC controller, two adjacent longitudinal directions are recessed Spacing between slot 81 is identical as longitudinal reinforcement laying spacing.
Preferably, 3 front and rear sides bottom of door frame is connected with two steel pipe posts 31 vertically respectively, and two steel pipe posts 31 divide Other places are in the position of 3 front side and rear side both ends of door frame;Door frame elevating ram 12 is equipped with inside every steel pipe post 31 vertically;It lifts 12 cylinder body one end of oil-lifting jar is fixedly connected on 3 bottom of door frame, and 12 output end of elevating ram is connected with running gear 14.
In use, the height of the extension and contraction control door frame by control door frame elevating ram 12, uses the operation of different height Operation.
Preferably, the top of 3 rear and front end of door frame passes through the connection curved support of curved support frame oil cylinder 11 being equipped with vertically Frame 9;11 cylinder body one end of curved support frame oil cylinder is fixedly connected on 3 top of door frame, and output end is fixedly connected on 9 bottom of curved support frame Portion;Top rack 6 is equipped at the top of door frame 3, top rack 6 is between two support frames 9.
In use, the height of the extension and contraction control support plate of control curved support frame oil cylinder, it is solid to carry out top for longitudinal reinforcement It is fixed, convenient for tying up.
Preferably, 3 top rear and front end of door frame is correspondingly provided with pedestal;Shaft is rotatably connected between the pedestal of both ends;Shaft Both ends, which are respectively perpendicular, is connected with rotation, telescopic mechanical arm 2, is fixedly connected with lock claw axis between two rotations, telescopic mechanical arm 2 17, lock claw axis 17 is equipped with several first annular grooves;Lock claw axis 17 is in rotation, the one end of telescopic mechanical arm 2 far from shaft; Rotation motor 10 is connect by transmission mechanism with shaft;Transmission mechanism includes the fixed first gear being set in shaft, rotation Fixing sleeve is equipped with the second gear engaged with the first gear on motor output end;Rotation, 2 cylinder body end of telescopic mechanical arm are horizontal It is connected with telescopic oil cylinder 7,7 output end of telescopic oil cylinder is fixedly connected on rotation, 2 telescopic end of telescopic mechanical arm.
In use, shaft rotation is driven by control rotation motor control, to drive the rotation of both ends of the shaft, telescopic machine The rotation of tool arm.
Preferably, shaft is in circumferential reinforcement center.Achieve the purpose that uniformly to be laid with.
Preferably, 3 front-rear position of rack is respectively provided with two contrary horizontal telescoping oil cylinders of output end 5;Horizontal extension 5 cylinder body end of oil cylinder is fixedly connected on 3 middle top position of door frame, and 5 output end of horizontal telescoping oil cylinder is located at 3 end position of door frame; Horizontal extension arm drive shaft 4 is connected with along the longitudinal direction respectively between two horizontal telescoping oil cylinders 5 of 3 left and right sides of door frame;Water Several second circumferential grooves are provided in flat telescopic arm drive shaft 4.
In use, being water by the flexible movement to drive horizontal extension arm drive shaft of controlled level telescopic oil cylinder Second annular groove in flat telescopic arm drive shaft blocks corresponding circumferential reinforcement, by controlling left and right two groups of horizontal extensions Arm oil cylinder makes the telescopic arm drive shaft on circumferential reinforcement and horizontal extension frame keep being in close contact and completing circumferential reinforcement arc turn The process of change.
Preferably, toggle arm includes four beginnings, end drive shaft oil cylinders for being separately positioned on four steel pipe posts, 31 middle part 13;Begin, drive shaft oil cylinder 13 cylinder body end in end is fixedly connected on steel pipe post 31;Two beginnings, ends of 3 left and right sides of door frame It is connected with beginning, end drive shaft 15 between drive shaft oil cylinder 13 backward along front respectively;It is provided on beginning, end drive shaft 15 several Third circumferential groove.
In use, beginning by control, the telescopic moving beginning of end drive shaft oil cylinder, end drive shaft, make beginning, end driving Third circumferential groove on axis blocks circumferential reinforcement, reaches beginning, the whole story end drive shaft in the drive cylinder of end and manually exists Setting right on the ground of circumferential reinforcement end enters circumferential reinforcement from oblique cutting, spiral is run to the circumferential proper alignment of same section Process of deployment.
Although above having used general explanation and specific embodiment, the present invention is described in detail, at this On the basis of invention, it can be made some modifications or improvements, this will be apparent to those skilled in the art.Therefore, These modifications or improvements without departing from theon the basis of the spirit of the present invention are fallen within the scope of the claimed invention.

Claims (10)

1. the construction method that a kind of manual imitation is laid with tunnel double-lining steel mesh, which is characterized in that the described method comprises the following steps:
S1, laying rack is opened to the position for needing to install tunnel reinforced mesh;
S2, so that Hanging Basket is reached ground rotation, telescopic mechanical arm decline, laying longitudinal reinforcement needed for tunnel top is placed on extension It on basket, is transported on upper arcuate support frame, and longitudinally by reinforcing bar low water in arc groove plate;
S3, drive rotation, telescopic mechanical arm that lock claw axis is down to the ground of tunnel side by rotation motor, it will be single or one Group circumferential reinforcement is fixed on lock claw axis, and locking is fixed;
S4, curved support frame oil cylinder is risen, drives curved support frame to rise to suitable position, facilitates operator in curved support The operation of frame lower part guarantees operating personnel's safety;
S5, it drives rotation, telescopic mechanical arm to rotate by rotation motor, drives circumferential reinforcement to pass through another to tunnel at the top of arc frame Side ground;By controlling left and right two groups of horizontal extensions arm oil cylinder, drive the telescopic arm on circumferential reinforcement and horizontal extension frame Axis keeps the process for being in close contact and completing the transformation of circumferential reinforcement arc;And the curved support frame driving on curved support frame Axis, the whole story end drive shaft in the drive cylinder of whole story end and artificial setting right on the ground of circumferential reinforcement end, make circumferential steel Muscle enters from oblique cutting, spiral is run to the circumferential proper alignment process of deployment of same section;
S6, the circumferential reinforcement splice reserved with the inverted arch construction of tunnel side is attached;
S7, hoisting frame jacking cylinder make circumferential reinforcement, top longitudinal reinforcement reach designed elevation position;
S8, it carries out the longitudinal reinforcement on circumferential reinforcement and arc jacking frame to be bundled into mesh sheet;
S9, by rotation, telescopic mechanical arm reduces as far as possible lock claw axis that other end circumferential reinforcement is made to cross lock claw axis and tunnel The splice that the inverted arch construction of the other side is reserved is attached;
S10, Hanging Basket is suspended on lock claw axis;
S11, tunnel longitudinal reinforcement, installation personnel are placed on Hanging Basket;
S12, driving rotation, telescopic mechanical arm, send longitudinal reinforcement to the designated position of tunnel side, are controlled by pecten spacing By two grommets of concrete to the stable state for being bundled into reinforced mesh with longitudinal reinforcement;
S13, curved support oil cylinder is declined, separates curved support frame with reinforced mesh;
S14, driving rotation, telescopic mechanical arm, the operator hung in basket and longitudinal reinforcement are sent to tunnel other side arch wall and are referred to Positioning is set is tied up with circumferential reinforcement, is finally completed all reinforced mesh and is tied up;
S15, such as tunnel concrete two are lined with multi-story steel mesh, repeat above procedure.
2. the construction method that a kind of manual imitation according to claim 1 is laid with tunnel double-lining steel mesh, which is characterized in that drive When dynamic rotation, telescopic mechanical arm oil cylinder, guarantee that reinforcing bar is not interfered in rotary course and tunnel scar.
3. the laying rack that a kind of manual imitation is laid with tunnel double-lining steel mesh, which is characterized in that the laying rack includes that can rise The door frame (3) of drop and the liftable curved support frame (9) being set at the top of the door frame (3), curved support frame (9) top It is connected with curved support plate (8), is provided with along the longitudinal direction on the curved support plate (8) several and carrying longitudinal reinforcement Longitudinal groove (81);
Door frame (3) rear and front end is respectively provided with rotation, the telescopic mechanical arm for being laid with circumferential reinforcement and longitudinal reinforcement (2);The door frame (3), which is equipped with, provides the rotation motor (10) of power for the rotation, telescopic mechanical arm (2);
Both ends are respectively provided with the horizontal extension arm for completing the transformation of circumferential reinforcement arc at the top of the door frame (3);The door frame (3) toggle arm that circumferential reinforcement begins, end ground is set right is respectively provided in the middle part of both ends.
4. the laying rack that a kind of manual imitation according to claim 3 is laid with tunnel double-lining steel mesh, which is characterized in that phase Spacing between two adjacent longitudinal grooves (81) is identical as longitudinal reinforcement laying spacing.
5. the laying rack that a kind of manual imitation according to claim 3 is laid with tunnel double-lining steel mesh, which is characterized in that institute It states door frame (3) front and rear sides bottom and is connected with two steel pipe posts (31) vertically respectively, two steel pipe posts (31) are respectively Position in door frame (3) front side and rear side both ends;The every steel pipe post (31) is internal to be equipped with door frame lifting oil vertically Cylinder (12);Described elevating ram (12) cylinder body one end is fixedly connected on the door frame (3) bottom, elevating ram (12) output End is connected with running gear (14).
6. the laying rack that a kind of manual imitation according to claim 3 is laid with tunnel double-lining steel mesh, which is characterized in that institute The top for stating door frame (3) rear and front end passes through curved support frame oil cylinder (11) connection curved support frame (9) being equipped with vertically;It is described Curved support frame oil cylinder (11) cylinder body one end is fixedly connected at the top of the door frame (3), and output end is fixedly connected on curved support Frame (9) bottom;Top rack (6) are equipped at the top of the door frame (3), the top rack (6) is in two support frames as described above (9) Between.
7. the laying rack that a kind of manual imitation according to claim 3 is laid with tunnel double-lining steel mesh, which is characterized in that institute It states rear and front end at the top of door frame (3) and is correspondingly provided with pedestal;Shaft is rotatably connected between the pedestal of both ends;The both ends of the shaft difference It is vertically connected with rotation, telescopic mechanical arm (2), two rotations, telescopic mechanical arms are fixedly connected with lock claw axis between (2) (17), the lock claw axis (17) is equipped with several first annular grooves;The lock claw axis (17) is in the rotation, flexible machinery The one end of arm (2) far from the shaft;The rotation motor (10) is connect by transmission mechanism with the shaft;
The rotation, telescopic mechanical arm (2) cylinder body end horizontal connection have telescopic oil cylinder (7), and telescopic oil cylinder (7) output end is solid Surely the rotation, telescopic mechanical arm (2) telescopic end are connected to.
8. the laying rack that a kind of manual imitation according to claim 7 is laid with tunnel double-lining steel mesh, which is characterized in that institute It states shaft and is in circumferential reinforcement center.
9. the laying rack that a kind of manual imitation according to claim 3 is laid with tunnel double-lining steel mesh, which is characterized in that institute It states rack (3) front-rear position and is respectively provided with two contrary horizontal telescoping oil cylinders of output end (5);The horizontal telescoping oil cylinder (5) cylinder body end is fixedly connected on door frame (3) middle top position, and horizontal telescoping oil cylinder (5) output end is located at door frame (3) end Portion position;Water is connected with along the longitudinal direction respectively between two horizontal telescoping oil cylinders (5) at left and right sides of the door frame (3) Flat telescopic arm drive shaft (4);Several second circumferential grooves are provided on the horizontal extension arm drive shaft (4).
10. the laying rack that a kind of manual imitation according to claim 5 is laid with tunnel double-lining steel mesh, which is characterized in that The toggle arm includes four beginnings, end drive shaft oil cylinders (13) being separately positioned in the middle part of four steel pipe posts (31);It is described Begin, end drive shaft oil cylinder (13) cylinder body end is fixedly connected on the steel pipe post (31);At left and right sides of the door frame (3) Beginning, end drive shaft (15) are connected with backward along front respectively between two beginnings, end drive shaft oil cylinder (13);It is described Begin, be provided with several third circumferential grooves in end drive shaft (15).
CN201910126914.5A 2019-02-20 2019-02-20 A kind of manual imitation is laid with the construction method and laying rack of tunnel double-lining steel mesh Pending CN109667605A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910126914.5A CN109667605A (en) 2019-02-20 2019-02-20 A kind of manual imitation is laid with the construction method and laying rack of tunnel double-lining steel mesh

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910126914.5A CN109667605A (en) 2019-02-20 2019-02-20 A kind of manual imitation is laid with the construction method and laying rack of tunnel double-lining steel mesh

Publications (1)

Publication Number Publication Date
CN109667605A true CN109667605A (en) 2019-04-23

Family

ID=66152049

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910126914.5A Pending CN109667605A (en) 2019-02-20 2019-02-20 A kind of manual imitation is laid with the construction method and laying rack of tunnel double-lining steel mesh

Country Status (1)

Country Link
CN (1) CN109667605A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111271094A (en) * 2020-03-03 2020-06-12 中铁工程服务有限公司 Mountain tunnel secondary lining reinforcing bar mechanized operation complete sets
CN111894640A (en) * 2020-08-07 2020-11-06 中电建路桥集团有限公司 Intelligent waterproof board operation platform truck
CN113339021A (en) * 2021-05-31 2021-09-03 中铁工程服务有限公司 Complete equipment for accurately assembling secondary lining steel bars in mountain tunnel
CN113503174A (en) * 2021-05-31 2021-10-15 中铁工程服务有限公司 Precise assembling equipment and construction method for secondary lining steel bars of mountain tunnel
CN114060057A (en) * 2021-11-15 2022-02-18 中铁长安重工有限公司 Tunnel steel bar installation construction method
CN116220731A (en) * 2023-03-14 2023-06-06 广东威恒输变电工程有限公司 Method for installing tunnel pipe joint arc-shaped support

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111271094A (en) * 2020-03-03 2020-06-12 中铁工程服务有限公司 Mountain tunnel secondary lining reinforcing bar mechanized operation complete sets
CN111894640A (en) * 2020-08-07 2020-11-06 中电建路桥集团有限公司 Intelligent waterproof board operation platform truck
CN111894640B (en) * 2020-08-07 2022-03-22 中电建路桥集团有限公司 Intelligent waterproof board operation platform truck
CN113339021A (en) * 2021-05-31 2021-09-03 中铁工程服务有限公司 Complete equipment for accurately assembling secondary lining steel bars in mountain tunnel
CN113503174A (en) * 2021-05-31 2021-10-15 中铁工程服务有限公司 Precise assembling equipment and construction method for secondary lining steel bars of mountain tunnel
CN113339021B (en) * 2021-05-31 2022-11-04 中铁工程服务有限公司 Complete equipment for accurately assembling secondary lining steel bars in mountain tunnel
CN113503174B (en) * 2021-05-31 2023-11-10 中铁工程服务有限公司 Mountain tunnel two-lining steel bar accurate assembly equipment and construction method
CN114060057A (en) * 2021-11-15 2022-02-18 中铁长安重工有限公司 Tunnel steel bar installation construction method
CN114060057B (en) * 2021-11-15 2024-05-28 中铁长安重工有限公司 Tunnel reinforcing steel bar installation construction method
CN116220731A (en) * 2023-03-14 2023-06-06 广东威恒输变电工程有限公司 Method for installing tunnel pipe joint arc-shaped support
CN116220731B (en) * 2023-03-14 2023-11-10 广东威恒输变电工程有限公司 Method for installing tunnel pipe joint arc-shaped support

Similar Documents

Publication Publication Date Title
CN109667605A (en) A kind of manual imitation is laid with the construction method and laying rack of tunnel double-lining steel mesh
CN209704593U (en) A kind of manual imitation is laid with the laying rack of tunnel double-lining steel mesh
CN102913259B (en) Steel arch assembling machine of tunnel vault for repairing damages of existing railway tunnel
CN107988861B (en) Subway work complete set of equipments and method of laying a railway track
CN205153562U (en) Automatic wallboard mounting vehicle
CN110370469B (en) Intelligent concrete cutting trolley
CN107514264A (en) A kind of new Multifunctional performing machine for constructing tunnel
CN206255777U (en) Self-propelled multipurpose is adjustable double lifting point truss straddle truck
CN110685433A (en) Chimney construction device and construction method applying hydraulic lifting and rollover technology
CN111910658B (en) Slope operation platform
CN107829370B (en) High pier is from climbing liquid press to turn over molds construction technology
CN202926344U (en) Tunnel vault steel arch frame mounting machine for existing railway tunnel disease repairing
CN108002244A (en) Lift-on/Lift-off System and its method for high pier stud steel bar template
CN105484168A (en) Rotary hoisting equipment for stiffening beam of suspension bridge and erecting method of stiffening beam
CN107815971B (en) High pier is from climbing liquid press to turn over molds system
CN210103322U (en) Self-driven urban underground prefabricated comprehensive pipe gallery laying and hoisting machine
CN111877728A (en) Lifting type movable operation platform for steel structure overhanging construction
CN218145304U (en) Adjustable lifting appliance
CN113585860B (en) Method for assembling and disassembling double-arm holding pole
CN108625885A (en) A kind of semi-automatic duct piece assembling machine and its assembling method
CN210685565U (en) Chimney is reformed transform and is used inner tube hoist device
CN113955636A (en) Hoisting equipment for assembly type building construction
CN218596064U (en) A pipeline hoisting device for high altitude installation
CN217054601U (en) A auxiliary device for chimney reinforced concrete construction
CN210288079U (en) Trestle bridge template dragging device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination