CN109636312A - Land control engineering online monitoring and management system - Google Patents
Land control engineering online monitoring and management system Download PDFInfo
- Publication number
- CN109636312A CN109636312A CN201811360996.1A CN201811360996A CN109636312A CN 109636312 A CN109636312 A CN 109636312A CN 201811360996 A CN201811360996 A CN 201811360996A CN 109636312 A CN109636312 A CN 109636312A
- Authority
- CN
- China
- Prior art keywords
- subsystem
- project
- land control
- monitoring
- management
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000012544 monitoring process Methods 0.000 title claims abstract description 64
- 238000007726 management method Methods 0.000 claims abstract description 80
- 238000012552 review Methods 0.000 claims abstract description 11
- 238000013461 design Methods 0.000 claims abstract description 10
- 238000013439 planning Methods 0.000 claims abstract description 7
- 238000007689 inspection Methods 0.000 claims abstract description 6
- 230000008520 organization Effects 0.000 claims abstract description 6
- 239000000463 material Substances 0.000 claims abstract description 4
- 238000000034 method Methods 0.000 claims description 12
- 230000008569 process Effects 0.000 claims description 9
- 238000011156 evaluation Methods 0.000 claims description 8
- 238000004891 communication Methods 0.000 claims description 6
- 230000007246 mechanism Effects 0.000 claims description 6
- 238000005259 measurement Methods 0.000 claims description 4
- 230000001360 synchronised effect Effects 0.000 claims description 3
- 238000010276 construction Methods 0.000 description 14
- 230000008859 change Effects 0.000 description 5
- 239000002689 soil Substances 0.000 description 3
- 238000013210 evaluation model Methods 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 239000000178 monomer Substances 0.000 description 2
- 241001269238 Data Species 0.000 description 1
- 230000004075 alteration Effects 0.000 description 1
- 238000012550 audit Methods 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000005540 biological transmission Effects 0.000 description 1
- 230000015572 biosynthetic process Effects 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000005611 electricity Effects 0.000 description 1
- 230000003760 hair shine Effects 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 230000006855 networking Effects 0.000 description 1
- 238000012545 processing Methods 0.000 description 1
- 238000009418 renovation Methods 0.000 description 1
- 238000005070 sampling Methods 0.000 description 1
- 238000007619 statistical method Methods 0.000 description 1
- 238000012795 verification Methods 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
- G06Q10/103—Workflow collaboration or project management
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/10—Services
- G06Q50/26—Government or public services
Landscapes
- Business, Economics & Management (AREA)
- Engineering & Computer Science (AREA)
- Strategic Management (AREA)
- Human Resources & Organizations (AREA)
- Tourism & Hospitality (AREA)
- Economics (AREA)
- Theoretical Computer Science (AREA)
- Entrepreneurship & Innovation (AREA)
- Marketing (AREA)
- General Physics & Mathematics (AREA)
- General Business, Economics & Management (AREA)
- Physics & Mathematics (AREA)
- Educational Administration (AREA)
- Primary Health Care (AREA)
- Development Economics (AREA)
- General Health & Medical Sciences (AREA)
- Data Mining & Analysis (AREA)
- Health & Medical Sciences (AREA)
- Operations Research (AREA)
- Quality & Reliability (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention discloses land control engineering online monitoring and management systems, comprising: project management subsystem, making a report on and managing for land control project information data;Management subsystem is verified, the information for the acquisition of synchronizing moving end is to Platform Server;Project is mobile to examine subsystem, carries out examination examination & approval to the project material declared for authorities;Subsystem is made an on-the-spot survey by designing unit, for land control planning design of item unit inspection of the scene of a crime information make a report on and scene photograph collect;Subsystem is made a report in log, for generating the log inserted with current geographic position and being sent to Platform Server;Monitoring and warning subsystem, for monitoring land control project implementation progress;Subsystem is made an on-the-spot survey by management organization, for positioning and showing the project information of corresponding land control project, and input reconnaissance trip data;Engineering checks management subsystem, for filling in engineering review result.It significantly improves the transmitting of project data information, feedback efficiency, is conducive to project dynamic monitoring and supervision.
Description
Technical field
The present invention relates to land control engineering regulation technique fields, and in particular to a kind of land control engineering online monitoring and management system
System.
Background technique
Land control engineering has the characteristics that the implementation cycle is long, management node is more, it is more to be related to object, formation data is more, when
Preceding land control project management lacks effective tool, it is difficult to which land control is comprehensively and effectively supervised in realization.Due to conventional tube
Reason theory and means fall behind, and weaken profession and check on function, inevitably occur failing such as builder, management person existing to project as required
Carry out the work, builder's diary, supervision diary make a report on not in time, it is lack of standardization etc..Traditional land control project Supervision Measures are difficult to
The target of " wisdom territory " construction is adapted to, therefore there is an urgent need to seek a kind of new land control project supervision method, realizes soil
The dynamic monitoring of ground renovation full-service, overall process promotes land control supervision level and working efficiency.
Summary of the invention
In view of the deficiencies in the prior art, the purpose of the present invention is to provide a kind of land control engineering online monitoring and managements
System is quickly transmitted between construction, supervision each side convenient for information and data, and supervising in overall process comprehensively for land control, it is more effective to provide
Tool.
To achieve the above objectives, the technical solution adopted by the present invention is that: land control engineering online monitoring and management system, packet
It includes:
Project management subsystem, for putting on record for land control project information data;
Management subsystem is verified, log, photographic intelligence to Platform Server for the acquisition of synchronizing moving end;
Backstage operation management subsystem, for configuring permission to user account and responding the account application and cancellation of user;
Project is mobile to examine subsystem, for authorities personnel to the project material declared in project management subsystem into
Row examines examination & approval, examines that approval results are synchronized to Platform Server;
Subsystem is made an on-the-spot survey by designing unit, for land control planning design of item unit inspection of the scene of a crime information make a report on and it is existing
Field collection of photos;
Builder's diary makes a report on subsystem, for generating the builder's diary inserted with current geographic position and being sent to platform clothes
Business device;
Supervision diary makes a report on subsystem, generates the supervision diary inserted with current geographic position and is sent to platform service
Device;
Monitoring and warning subsystem, for monitoring land control project implementation progress;
Subsystem is made an on-the-spot survey by management organization, for according to current location judge user locating for land control project, and show
The project information of corresponding land control project;It is also used to input reconnaissance trip data;
Engineering checks management subsystem, for filling in engineering review result and generating the scene photograph identified with geographical location
Information is simultaneously sent to Platform Server.
Further, land control engineering online monitoring and management system further include: arable land monitoring and evaluation subsystem, it is cultivated for receiving
Geological measuring grade monitors the location data of field operation sampled point, and summarizes arable land sample detecting data.
Further, land control engineering online monitoring and management system further include: a dsp subsystem, on the electronic map
Inquire the spatial data of land control project and display.
Further, land control engineering online monitoring and management system further include: intermediary's management subsystem, for inquiring soil
Ground regulation working mechanism and personal information and intermediary's examination examination rule.
Further, the builder's diary makes a report on subsystem and supervision diary is made a report on subsystem and is also used on the electronic map
History log label is generated, the history log label is for showing history log after user clicks the label.
Further, the engineering review management subsystem marks on the electronic map has checked Project Areas and associating on-the-spot
Check information.
Further, the monitoring and warning subsystem carries out short message warning to project process, fund and attendance.
Further, land control engineering online monitoring and management system further includes mobile monitoring terminal, the mobile monitoring terminal
Include:
Microprocessor passes through wireless network signal transceiver module and Platform Server communication connection;
Face recognition module is identified for human face image information;
Positioning device position simultaneously record position data to the site of selection;
Input unit, for inputting text or voice messaging;
Filming apparatus, for acquiring project scene photograph.
Further, the Platform Server is stored with platform database, and the platform database includes:
Service database, builder's diary, supervision diary and site operation photo including user information and field data acquisition
Information;
Spatial database, including land control project spatial dimension, present status of land utilization, satellite remote-sensing image, soil are whole
Control the spatial data of planning.
Further, a dsp subsystem calls the Map Services data of ArcGIS Server publication and for electricity
The inquiry of sub- map, area measure, distance measurements are calculated and map overlay is shown.
Compared with prior art, the beneficial effects of the present invention are:
Whenever and wherever possible convenient for spatial datas such as land control project spatial dimension, projects library, present status of land utilization
It has access to, by numerical map instead of traditional paper map, improves the convenient degree and working efficiency that field operation is made an on-the-spot survey;It can be right
Whether five high-ranking official such as builder, management person reaches project scene as required and carries out remote supervisory, and project associated mechanisms has been supervised to blame
Appoint and implements;It is made a report on for engineering construction, the log of supervisor and the review of inspector engineering is provided convenience, be administrative staff day
Normal inspection on the spot, real example retain management, mobile examination etc. and provide support, and it is lack of standardization, easy to be lost to improve traditionally on paper log
Defect;Improve the audit examination & approval efficiency of land control project;Builder's diary, the prison uploaded by personnel such as construction, management
The information such as log, site operation photo are managed, convenient for the remote supervisory to land control project site operation situation.
Detailed description of the invention
Fig. 1 is the composed structure schematic diagram of land control engineering online monitoring and management system in the embodiment of the present invention.
Fig. 2 is mobile monitoring terminal data communications schematic illustration in the embodiment of the present invention.
In figure: 1, project management subsystem;2, management subsystem is verified;3, intermediary's management subsystem;4, a figure
Subsystem;5, backstage operation management subsystem;6, project is mobile examines subsystem;7, subsystem is made an on-the-spot survey by designing unit;8, it constructs
Subsystem is made a report in log;9, supervision diary makes a report on subsystem;10, monitoring and warning subsystem;11, subsystem is made an on-the-spot survey by management organization;
12, engineering checks management subsystem;13, arable land monitoring and evaluation subsystem.
Specific embodiment
Invention is further described in detail with reference to the accompanying drawings and embodiments.
Shown in Figure 1, the embodiment of the present invention provides land control engineering online monitoring and management system comprising:
Project management subsystem 1 is checked for putting on record for land control project information data for administrative responsibile institution, is wrapped
Include approve and initiate a project, planning and designing, capital budgeting and assign, implements prepare, implement monitoring, design alteration (in advance change, daily change
With final change), the project implementations link information such as the project acceptance inspection (contract section checks and accepts, final acceptance of construction and check and accept rectification) makes a report on;
Management subsystem 2 is verified, pipe is verified in log, photographic intelligence to Platform Server for the acquisition of synchronizing moving end
The data that reason subsystem 2 is made a report on by all kinds of personnel in synchronizing moving end, to personnel, condition of going on duty carries out long-range monitoring on the spot;
Backstage operation management subsystem 5, for configuring permission to user account and responding the account application and cancellation of user,
And the maintenance of system;
Project is mobile to examine subsystem 6, for authorities personnel to the project material declared in project management subsystem 1
Examination examination & approval are carried out, examine that approval results are synchronized to Platform Server;Project is mobile simultaneously examines that subsystem 6 is adjusted according to request
It takes and examines examination & approval data, facilitate administrative examination and approval personnel to check backlog essential information and attachment data, and then in movement
The examination & approval of backlog are completed on terminal device, approval results are passed back in real time, and project is mobile to examine subsystem 6;
Subsystem 7 is made an on-the-spot survey by designing unit, for land control planning design of item unit inspection of the scene of a crime information make a report on and
Scene photograph is collected, and the information that designer makes an on-the-spot survey the upload collection in worksite of subsystem 7 by designing unit facilitates to Platform Server
Subsequent design work is transferred;
Builder's diary makes a report on subsystem 8, for generating the builder's diary inserted with current geographic position and being sent to platform
Server;Builder makes a report on subsystem 8 by builder's diary and makes a report on engineering site condition of construction and upload construction photographic intelligence,
Can auxiliary construction person easily work out construction monthly magazine;
Supervision diary makes a report on subsystem 9, generates the supervision diary inserted with current geographic position and is sent to platform service
Device;Management person makes a report on subsystem 9 by supervision diary and makes a report on supervision diary and upload scene photograph information, can assist management person
Easily work out management monthly magazine;
Monitoring and warning subsystem 10, for monitoring land control project implementation progress;Monitoring and warning subsystem 10 and platform
Server communication realizes the number of entry, construction scale, investment rule by reading the project information being stored on Platform Server
The information subregions such as mould, newly-increased farmland quantity, progress of implementation, fund appropriation progress, year-by-year, classifying type statistical analysis, and
It is shown in the form of chart etc. is intuitionistic and concise, it is convenient to consult project implementation situation whenever and wherever possible, and according to builder's diary, management
Situation is made a report in log, realizes the analysis to builder, management person's monthly arrival project scene number of days, auxiliary agency mechanism examines
Core examination, and then supervise working mechanism duty fulfillment;
Subsystem 11 is made an on-the-spot survey by management organization, for according to current location judge user locating for land control project, and show
Show the approving and initiate a project, design of corresponding land control project, construction information;It is also used to input reconnaissance trip data;Approve and initiate a project,
Design, change and acceptance phase field operation are made an on-the-spot survey or daily when patrolling on the spot, by mobile terminal GPS positioning to being presently in position
Set, the information of the single engineering in current location checked by queried for items engineering data base, and make a report on reconnaissance trip situation, suggest and
The information such as floor photo, to complete reconnaissance trip verification table;
Engineering checks management subsystem 12, shines for filling in engineering review result and generating the scene identified with geographical location
Piece information is simultaneously sent to Platform Server;The inspector that engineering checks unit logs in engineering by mobile terminal and checks management subsystem
After 12, by GPS positioning to Project Areas, point to be checked is selected, is checked wait check a design information for monomer engineering, and according to reality
Ground samples situation, compares the design value and practical review value of engineering, and takes pictures, and the engineering for filling in, uploading monomer engineering is multiple
Nuclear information table.
In above scheme, land control engineering online monitoring and management system further include: arable land monitoring and evaluation subsystem 13, for connecing
The location data for receiving farmland quality grade monitoring field operation sampled point is conducive to subsequent to arable land development monitoring, arable land monitoring and evaluation
After system 13 summarizes arable land sampling monitoring data, then corresponding evaluation model is selected to comment farmland quality by expert
Valence, evaluation result are transmitted to Platform Server through arable land monitoring and evaluation subsystem 13.
Further, land control engineering online monitoring and management system further include: a dsp subsystem 4, in electronic map
The upper spatial data for inquiring land control project and display.Land use data, engineering library data, satellite remote-sensing image number
According to and planning class data etc. data exported in a manner of electronic map after the parsing of GIS information system, carry out amount of area convenient for user
It calculates, distance measurements are calculated, map overlay is shown, site interrogation etc..
Further, land control engineering online monitoring and management system further include: intermediary's management subsystem 3, for inquiring
Land control working mechanism and personal information and intermediary's examination examination rule.Intermediary's management subsystem 3 is provided with warp
Cross land control management unit and the intermediary's performance appraisal, land control project Evaluation of Financial Expenditure Achievement index body of examination & approval
System and evaluation model, based on putting information bank, construction Supervision log library etc. on record by project, by land control project, personnel, fund
Data are dynamically associated and are analyzed, and auxiliary authorities realize the intelligence to land control project management unit and intermediary
Change performance appraisal.
Further, builder's diary makes a report on subsystem 8 and supervision diary makes a report on subsystem 9 and is also used to give birth on the electronic map
It is marked at history log, history log label is for showing history log after user clicks label.
Further, engineering review management subsystem 12 marks that have checked Project Areas and associating on-the-spot multiple on the electronic map
Nuclear information.
Explanation is needed further exist for, subsystem 11 is made an on-the-spot survey by management organization, builder's diary makes a report on subsystem 8, supervision diary
Make a report on subsystem 9, subsystem 7 is made an on-the-spot survey by designing unit, engineering review management subsystem 12 user object be respectively management unit,
Unit in charge of construction, supervisor, designing unit, engineering check unit.
Further, monitoring and warning subsystem 10 carries out short message prompt to project process, fund and attendance, plays and mentions
Wake up supervision role, project process, fund and attendance situation are counted, and it is not up to standard to progress, fund appropriation is too late
When, personnel's fulfilling progress short message warning supervisor not in place.
Further, land control engineering online monitoring and management system further includes mobile monitoring terminal, and mobile monitoring terminal includes:
Microprocessor, by wireless network signal transceiver module and Platform Server communication connection, valiant dragon processing is can be selected in microprocessor
Device, Lian Fake processor etc.;Face recognition module when filling in log for login system, carries out recognition of face, prevents day
The phenomenon that will is write, so that personnel's fulfilling is supervised, the human face image information input microprocessor of acquisition, then integrated by APP
Conventional images identification module carries out image comparison to identify face information;Positioning device is positioned and is remembered to the site of selection
Position data is recorded, Platform Server storage is finally transmitted to;Input unit, for inputting text or voice messaging, entry item
Information;Filming apparatus, for acquiring project scene photograph.
In aforementioned mobile monitoring terminal, input unit is one of keyboard, touch control input module or voice input module
Or it is several, it is selected according to different input demand scenes.Wireless network signal transceiver module is WiFi module, 4G/5G is wireless
One or more of communication module can be selected according to project scene is practical.The project information and project scene filled in are adopted
The photo of collection is transmitted to Platform Server through wireless network signal transceiver module and saves.
Platform Server is stored with platform database, and platform database includes: service database, including user information and
Builder's diary, supervision diary and the site operation photographic intelligence of field data acquisition;Spatial database, including land control project space
The spatial data that range, present status of land utilization, satellite remote-sensing image, land control are planned.
Further, a dsp subsystem 4 calls the Map Services data of ArcGIS Server publication and for electronically
The inquiry of figure, area measure, distance measurements are calculated and map overlay is shown.
Mobile monitoring terminal by wireless network obtains data from Platform Server and uploads collection in worksite data to flat
Platform server, land control engineering online monitoring and management system, which sorts data into, is stored in Platform Server and construction platform database.
The present invention is conducive to data and timely updates and feed back, the overview of project whole process, dynamic monitoring and examination & approval, supervision, realizes project scene
Information supervises in overall process comprehensively for land control to the quick transmission of each side and provides more effective tool, realizes land control business pipe
Generalization, project application networking, management standardization, approval process, supervision intelligence are managed, land control section is further promoted
Huas, fining and wisdom management level.
The present invention is not limited to the above-described embodiments, for those skilled in the art, is not departing from
Under the premise of the principle of the invention, several improvements and modifications can also be made, these improvements and modifications are also considered as protection of the invention
Within the scope of.The content being not described in detail in this specification belongs to the prior art well known to professional and technical personnel in the field.
Claims (10)
1. land control engineering online monitoring and management system, characterized in that it comprises:
Project management subsystem, for putting on record for land control project information data;
Management subsystem is verified, log, photographic intelligence to Platform Server for the acquisition of synchronizing moving end;
Backstage operation management subsystem, for configuring permission to user account and responding the account application and cancellation of user;
Project is mobile to examine subsystem, examines for authorities personnel the project material declared in project management subsystem
Examination & approval are looked into, examine that approval results are synchronized to Platform Server;
Subsystem is made an on-the-spot survey by designing unit, for land control planning design of item unit inspection of the scene of a crime information make a report on and scene shine
Piece is collected;
Builder's diary makes a report on subsystem, for generating the builder's diary inserted with current geographic position and being sent to platform service
Device;
Supervision diary makes a report on subsystem, for generating the supervision diary inserted with current geographic position and being sent to platform service
Device;
Monitoring and warning subsystem, for monitoring land control project implementation progress;
Subsystem is made an on-the-spot survey by management organization, for according to current location judge user locating for land control project, and show corresponding
The project information of land control project;It is also used to input reconnaissance trip data;
Engineering checks management subsystem, for filling in engineering review result and generating the scene photograph information identified with geographical location
And it is sent to Platform Server.
2. land control engineering online monitoring and management system as described in claim 1, which is characterized in that further include:
Arable land monitoring and evaluation subsystem for receiving the location data of farmland quality grade monitoring field operation sampled point, and summarizes cultivated
Ground sample detecting data.
3. land control engineering online monitoring and management system as described in claim 1, which is characterized in that further include:
One dsp subsystem, for inquiring spatial data and the display of land control project on the electronic map.
4. land control engineering online monitoring and management system as described in claim 1, which is characterized in that further include:
Intermediary's management subsystem, for inquiring land control working mechanism and personal information and intermediary's examination examination rule
Then.
5. land control engineering online monitoring and management system as described in claim 1, which is characterized in that the builder's diary makes a report on son
System and supervision diary make a report on subsystem and are also used to generate history log label on the electronic map, and the history log label is used
In showing history log after user clicks the label.
6. land control engineering online monitoring and management system as described in claim 1, which is characterized in that engineering review management
System marks on the electronic map has checked Project Areas and associating on-the-spot review information.
7. land control engineering online monitoring and management system as described in claim 1, which is characterized in that the monitoring and warning subsystem
Short message warning is carried out to project process, fund and attendance.
8. land control engineering online monitoring and management system as described in claim 1, which is characterized in that further include mobile monitoring end
End, the mobile monitoring terminal include:
Microprocessor passes through wireless network signal transceiver module and Platform Server communication connection;
Face recognition module is identified for human face image information;
Positioning device position simultaneously record position data to the site of selection;
Input unit, for inputting text or voice messaging;
Filming apparatus, for acquiring project scene photograph.
9. land control engineering online monitoring and management system as described in claim 1, which is characterized in that the Platform Server storage
There is platform database, the platform database includes:
Service database, builder's diary, supervision diary and site operation photographic intelligence including user information and field data acquisition;
Spatial database, including land control project spatial dimension, present status of land utilization, satellite remote-sensing image, land control rule
The spatial data drawn.
10. land control engineering online monitoring and management system as claimed in claim 3, which is characterized in that a dsp subsystem
Call the Map Services data of ArcGISServer publication and the inquiry for electronic map, area measure, distance measurements calculation
It is shown with map overlay.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811360996.1A CN109636312A (en) | 2018-11-15 | 2018-11-15 | Land control engineering online monitoring and management system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811360996.1A CN109636312A (en) | 2018-11-15 | 2018-11-15 | Land control engineering online monitoring and management system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109636312A true CN109636312A (en) | 2019-04-16 |
Family
ID=66068137
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811360996.1A Pending CN109636312A (en) | 2018-11-15 | 2018-11-15 | Land control engineering online monitoring and management system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109636312A (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110730431A (en) * | 2019-10-10 | 2020-01-24 | 中国地铁工程咨询有限责任公司 | Route display system and method based on mobile terminal map |
CN112183916A (en) * | 2019-07-09 | 2021-01-05 | 浙江时空智子大数据有限公司 | Land reserve life cycle management system |
CN113011783A (en) * | 2021-04-19 | 2021-06-22 | 浙江博润空间科技有限公司 | Land reclamation supervision platform and supervision method |
CN116384946A (en) * | 2023-05-31 | 2023-07-04 | 中交第四航务工程勘察设计院有限公司 | Method and system for project field management based on mobile terminal program |
CN116681313A (en) * | 2023-08-02 | 2023-09-01 | 菏泽市国土综合整治服务中心 | Land comprehensive renovation project supervision system |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104616433A (en) * | 2015-02-04 | 2015-05-13 | 清华大学 | Real-time monitoring and early warning system for foundation pit engineering |
CN105160708A (en) * | 2015-08-26 | 2015-12-16 | 中国电建集团北京勘测设计研究院有限公司 | Information system for integration of indoor work and field work in engineering geology |
CN106326448A (en) * | 2016-08-26 | 2017-01-11 | 广州市城市规划勘测设计研究院 | GIS (geographic information system) information collecting method and system |
CN106447182A (en) * | 2016-09-20 | 2017-02-22 | 华仙军 | Survey and design system generating chart uploading information automatically |
CN106779417A (en) * | 2016-12-20 | 2017-05-31 | 黄河勘测规划设计有限公司 | The collection of engineering investigation information digitalization, management and integrated application method |
CN106855994A (en) * | 2015-12-09 | 2017-06-16 | 星际空间(天津)科技发展有限公司 | A kind of mobile law enforcement management system based on land resources supervision |
CN108228775A (en) * | 2017-12-28 | 2018-06-29 | 陈菡 | Land and resources datas management system based on cloud platform |
CN108491545A (en) * | 2018-04-04 | 2018-09-04 | 重庆高南房地产信息服务有限责任公司 | A kind of Land and resources datas movement supervisory systems |
CN108681816A (en) * | 2018-05-17 | 2018-10-19 | 山东省土地调查规划院 | A kind of Land Comprehensive supervisory systems and method |
-
2018
- 2018-11-15 CN CN201811360996.1A patent/CN109636312A/en active Pending
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104616433A (en) * | 2015-02-04 | 2015-05-13 | 清华大学 | Real-time monitoring and early warning system for foundation pit engineering |
CN105160708A (en) * | 2015-08-26 | 2015-12-16 | 中国电建集团北京勘测设计研究院有限公司 | Information system for integration of indoor work and field work in engineering geology |
CN106855994A (en) * | 2015-12-09 | 2017-06-16 | 星际空间(天津)科技发展有限公司 | A kind of mobile law enforcement management system based on land resources supervision |
CN106326448A (en) * | 2016-08-26 | 2017-01-11 | 广州市城市规划勘测设计研究院 | GIS (geographic information system) information collecting method and system |
CN106447182A (en) * | 2016-09-20 | 2017-02-22 | 华仙军 | Survey and design system generating chart uploading information automatically |
CN106779417A (en) * | 2016-12-20 | 2017-05-31 | 黄河勘测规划设计有限公司 | The collection of engineering investigation information digitalization, management and integrated application method |
CN108228775A (en) * | 2017-12-28 | 2018-06-29 | 陈菡 | Land and resources datas management system based on cloud platform |
CN108491545A (en) * | 2018-04-04 | 2018-09-04 | 重庆高南房地产信息服务有限责任公司 | A kind of Land and resources datas movement supervisory systems |
CN108681816A (en) * | 2018-05-17 | 2018-10-19 | 山东省土地调查规划院 | A kind of Land Comprehensive supervisory systems and method |
Non-Patent Citations (2)
Title |
---|
李宗华 等: "武汉市土地整治管理信息平台建设与应用", 《地理空间信息》 * |
陈熙: "土地整治重大工程项目建设监测管理***的设计与实现", 《科技创新与应用》 * |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112183916A (en) * | 2019-07-09 | 2021-01-05 | 浙江时空智子大数据有限公司 | Land reserve life cycle management system |
CN112183916B (en) * | 2019-07-09 | 2023-10-31 | 浙江时空智子大数据有限公司 | Land reserve life cycle management system |
CN110730431A (en) * | 2019-10-10 | 2020-01-24 | 中国地铁工程咨询有限责任公司 | Route display system and method based on mobile terminal map |
CN110730431B (en) * | 2019-10-10 | 2023-04-07 | 中国地铁工程咨询有限责任公司 | Route display system and method based on mobile terminal map |
CN113011783A (en) * | 2021-04-19 | 2021-06-22 | 浙江博润空间科技有限公司 | Land reclamation supervision platform and supervision method |
CN116384946A (en) * | 2023-05-31 | 2023-07-04 | 中交第四航务工程勘察设计院有限公司 | Method and system for project field management based on mobile terminal program |
CN116681313A (en) * | 2023-08-02 | 2023-09-01 | 菏泽市国土综合整治服务中心 | Land comprehensive renovation project supervision system |
CN116681313B (en) * | 2023-08-02 | 2023-10-10 | 菏泽市国土综合整治服务中心 | Land comprehensive renovation project supervision system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109636312A (en) | Land control engineering online monitoring and management system | |
CN110852601B (en) | Big data application method and system for environmental monitoring law enforcement decision | |
CN114841625B (en) | National forest resource continuous checking cloud platform and sample plot monitoring method | |
CN105118005B (en) | Communities ' Integrated management system | |
CN103927860A (en) | GPS (Global Position System)-positioned meter reading smart handheld machine and meter reading system | |
CN109767374A (en) | A kind of house collection platform | |
KR102538887B1 (en) | Forest Carbon Credit Trading System Based on Forest Management Automation System | |
CN106462875A (en) | Air quality metrology system | |
CN112050092A (en) | Water supply pipe network leakage information management system, building method and application | |
CN109784840A (en) | A kind of construction survey automatic data collection processing method being associated with engineering structure task | |
Walter et al. | Measuring the wisdom of the crowd: How many is enough? | |
CN114511432A (en) | Digital country management service system based on block chain | |
CN117669943A (en) | Intelligent engineering construction project construction progress monitoring method and system based on BIM | |
CN103973902A (en) | Quantizing device and monitoring system and method for business quality of user perception | |
CN117272362A (en) | Block chain-based carbon emission perfect management method and system | |
CN115507828A (en) | Territorial surveying and mapping method and system based on remote sensing image | |
CN115271514A (en) | Communication enterprise monitoring method and device, electronic equipment and storage medium | |
CN109325711A (en) | Urban track traffic civil engineering structure Defect inspection management system and its workflow | |
CN115934693A (en) | Dynamic calculation method for regional real population | |
CN109544112A (en) | Resettlement implementation & management system | |
CN111091455B (en) | Integrated tax source management system for house, land and tax collection | |
CN112150326A (en) | Enterprise intellectual property cloud office digital management system | |
Liu | Urban groundwater quality monitoring and state-owned assets management optimization based on spatial information processing | |
CN113807797A (en) | Underground engineering construction management and monitoring system integrated with BIM and intelligent algorithm | |
CN109493441A (en) | A kind of method and system for realizing comprehensive improvement patrol based on two dimensional code |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190416 |