CN109543233A - 一种基于bim技术的机电管线装配式施工方法 - Google Patents

一种基于bim技术的机电管线装配式施工方法 Download PDF

Info

Publication number
CN109543233A
CN109543233A CN201811254971.3A CN201811254971A CN109543233A CN 109543233 A CN109543233 A CN 109543233A CN 201811254971 A CN201811254971 A CN 201811254971A CN 109543233 A CN109543233 A CN 109543233A
Authority
CN
China
Prior art keywords
model
construction
bim
information
prefabricated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811254971.3A
Other languages
English (en)
Inventor
王玉明
杜新骁
胡艳
谷守奎
程海川
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC First Harbor Engineering Co Ltd
CCCC First Harbor Installation Engineering Co Ltd
Original Assignee
CCCC First Harbor Engineering Co Ltd
CCCC First Harbor Installation Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC First Harbor Engineering Co Ltd, CCCC First Harbor Installation Engineering Co Ltd filed Critical CCCC First Harbor Engineering Co Ltd
Priority to CN201811254971.3A priority Critical patent/CN109543233A/zh
Publication of CN109543233A publication Critical patent/CN109543233A/zh
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G1/00Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F2113/00Details relating to the application field
    • G06F2113/16Cables, cable trees or wire harnesses

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Geometry (AREA)
  • General Physics & Mathematics (AREA)
  • Computer Hardware Design (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Theoretical Computer Science (AREA)
  • Computational Mathematics (AREA)
  • Mathematical Analysis (AREA)
  • Mathematical Optimization (AREA)
  • Pure & Applied Mathematics (AREA)
  • Evolutionary Computation (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

本发明是一种基于BIM技术的机电管线装配式施工方法,包括步骤为S1预制加工模型的划分;S2模型的创建;S3模型的处理;S4出预制加工图和预制加工材料单;S5加工构件;S6装配详图;S74D施工模拟;S8现场装配式安装、验收及试运行;S9竣工BIM模型。本发明能增加BIM虚拟构件的数量、种类和规格,减少预制构件的类型和数量,能实现与预制工厂的协同和对接,能通过可视化的直观表达帮助工人更好地理解设计意图,有助于提高工人生产的准确性和质量效率,提高施工效率,降低成本;实现项目进度、施工方案、质量、安全等方面的数字化、精细化和可视化管理,使项目数据具有可追溯性。

Description

一种基于BIM技术的机电管线装配式施工方法
技术领域
本发明涉及装配式施工技术领域,尤其涉及一种基于BIM技术的机电管线装配式施工方法。
背景技术
BIM技术通过三维模型形式和强大的信息整合能力,实现了复杂项目的管线综合设计、专业间协调和施工的优化,对项目的质量、进度、成本等方面控制起到重要作用,同时促进了业主方、设计方、施工方等各方的工作协同。装配式施工是将项目的部分或全部构件进行预制加工,然后运输至现场进行拼装的施工方法。
机电管线具有***复杂、专业交叉协调难度大、工期短等特点,而且机电管线的设计由于是由不同专业、不同设计院设计,根据CAD二维图建模并整合时,使模型常出现错误、遗漏、碰撞和缺陷,会出现设计变更的问题,从而不利于构件的生产,会造成资源的浪费;而且,没有对现场的工程部位进行扫描,由于施工误差会降低模型的精准度,从而影响施工质量和施工效率。
发明内容
本发明旨在解决现有技术的不足,而提供一种基于BIM技术的机电管线装配式施工方法。
本发明为实现上述目的,采用以下技术方案:一种基于BIM技术的机电管线装配式施工方法,包括如下步骤:
S1:预制加工模型的划分
根据管线***、安装区间位置、施工难易程度、集成度、施工进度计划和工厂的预制加工能力进行按批次划分;
S2:模型的创建
根据不同的CAD施工图分别创建三维模型图,将各个三维模型图整合为BIM模型;
S3:模型的处理
(1)BIM模型深化
根据机电管线***和区间安装位置,将不同专业间的BIM模型进行协同优化;
(2)现场扫描校核
对现场进行扫描,获取全面完整的空间三维信息,记录现场地物形态信息,将扫描信息转化为模型并与上述优化的BIM模型进行精细对比校核,并进行优化;
(3)管线综合优化
利用Navisworks软件进行碰撞检测,优化管线排布,在负责的地方,利用MagiCAD软件的支吊架模块,辅助综合支吊架设计,进行综合管线排布优化;
S4:出预制加工图和预制加工材料单
根据加工区域、空间、专业的管线***将BIM模型进行拆分,得到各个构件模型,将各构件模型出CAD二维的预制加工图,预制加工图包含构件的基本属性、加工工艺、使用特点和特殊要求的预制加工材料单;
S5:加工构件
根据预制加工图、预制加工材料单和施工进度,按批次对构件模型进行加工,得到构件,采用二维码技术记录构件和构件模型的信息;
及时更新加工构件模型和其二维码的信息;
S6:装配详图
根据BIM模型出装配详图,包括位置、连接信息、施工工艺、工序特点、特殊要求的信息,以便施工人员安装;
S7:4D施工模拟
利用BIM技术进行4D施工模拟,包括现场组织、工序和拼装模拟,直观、精确地反映整个机电管线装配式施工过程,提前预知主要施工方的控制方法、施工安排、总体规划、场地布置、工序,并进行及时优化;
S8:现场装配式安装、验收及试运行
4D施工模拟优化后,进行现场装配式安装,过程中利用BIM技术和FRID技术进行安装,并形成记录和质量管理信息,利用移动设备和BIM5D云平台实现信息及时获取和反馈,提升施工效率和安全管理质量;
安装完成后,进行验收和试运行,若验收不合格,找出不合格的位置和原因并进行改正,对不合格处重新进行安装和质量管理监督;
S9:竣工BIM模型
验收合格后,形成完整的BIM竣工模型,包括从设计模型到最终完成交付的所有过程的数据,方便后期运行和维护时使用。
特别的,所述施工方法满足GB/T 51235-2017《建筑信息模型施工应用标准》的要求。
特别的,所述步骤S3中现场扫描校核采用三维激光扫描仪扫描。
特别的,所述步骤S5中所述构件、所述构件模型和所述二维码唯一对应。
特别的,所述步骤S5中的信息包括上游信息、生产信息、属性信息、加工图编码信息、工序工艺信息、成品管理信息。
特别的,所述步骤S7中模拟时,需要对复杂节点进行重点和专项施工模拟,对复杂部位和关键使用节点进行提前预演,对施工安装工人和管理人员进行培训,增加其对施工环境和施工措施的熟悉度,保证安全,提高效率。
本发明的有益效果是:本发明能增加BIM虚拟构件的数量、种类和规格,减少预制构件的类型和数量,能实现与预制工厂的协同和对接,能通过可视化的直观表达帮助工人更好地理解设计意图,有助于提高工人生产的准确性和质量效率,提高施工效率,降低成本;实现项目进度、施工方案、质量和安全方面的数字化、精细化和可视化管理,使项目数据具有可追溯性。
附图说明
图1为本发明的施工流程图;
以下将结合本发明的实施例参照附图进行详细叙述。
具体实施方式
下面结合附图和实施例对本发明作进一步说明:
如图1所示,一种基于BIM技术的机电管线装配式施工方法,包括如下步骤:
S1:预制加工模型的划分
根据管线***、安装区间位置、施工难易程度、集成度、施工进度计划和工厂的预制加工能力进行按批次划分;
S2:模型的创建
根据不同的CAD施工图分别创建三维模型图,将各个三维模型图整合为BIM模型;
S3:模型的处理
(1)BIM模型深化
根据机电管线***和区间安装位置,将不同专业间的BIM模型进行协同优化;
(2)现场扫描校核
对现场进行扫描,获取全面完整的空间三维信息,记录现场地物形态信息,将扫描信息转化为模型并与上述优化的BIM模型进行精细对比校核,并进行优化;
(3)管线综合优化
利用Navisworks软件进行碰撞检测,优化管线排布,在负责的地方,利用MagiCAD软件的支吊架模块,辅助综合支吊架设计,进行综合管线排布优化;
S4:出预制加工图和预制加工材料单
根据加工区域、空间、专业的管线***将BIM模型进行拆分,得到各个构件模型,将各构件模型出CAD二维的预制加工图,预制加工图包含构件的基本属性、加工工艺、使用特点和特殊要求的预制加工材料单;
S5:加工构件
根据预制加工图、预制加工材料单和施工进度,按批次对构件模型进行加工,得到构件,采用二维码技术记录构件和构件模型的信息;
及时更新加工构件模型和其二维码的信息;
S6:装配详图
根据BIM模型出装配详图,包括位置、连接信息、施工工艺、工序特点、特殊要求的信息,以便施工人员安装;
S7:4D施工模拟
利用BIM技术进行4D施工模拟,包括现场组织、工序和拼装模拟,直观、精确地反映整个机电管线装配式施工过程提前预知主要施工方的控制方法、施工安排、总体规划、场地布置、工序,并进行及时优化;
S8:现场装配式安装、验收及试运行
施工方案后,进行现场装配式安装,过程中利用BIM技术和FRID技术进行精准安装,并形成记录和质量管理信息,利用移动设备和BIM5D云平台实现信息及时获取和反馈,提升施工效率和安全管理质量;
安装完成后,进行验收和试运行,若验收不合格,找出不合格的位置和原因并进行改正,对不合格处重新进行安装和质量管理监督;
S9:竣工BIM模型
验收合格后,形成完整的BIM竣工模型,包括从设计模型到最终完成交付的所有过程的数据,方便后期运行和维护时使用。
特别的,所述施工方法满足GB/T 51235-2017《建筑信息模型施工应用标准》的要求。
特别的,所述步骤S3中现场扫描校核采用三维激光扫描仪扫描。
特别的,所述步骤S5中所述构件、所述构件模型和所述二维码唯一对应。
特别的,所述步骤S5中的信息包括上游信息、生产信息、属性信息、加工图编码信息、工序工艺信息、成品管理信息。
特别的,所述步骤S7中模拟时,需要对复杂节点进行重点和专项施工模拟,对复杂部位和关键使用节点进行提前预演,对施工安装工人和管理人员进行培训,增加其对施工环境和施工措施的熟悉度,保证安全,提高效率。
本发明在施工过程时,本发明通过装配式建筑BIM构件库的建立,不断增加BIM虚拟构件的数量、种类和规格,逐步形成标准化预制构件库;
本发明能对单个外墙构件的几何属性经过可视化分析,可以对预制外墙板的类型数量进行优化,减少预制构件的类型和数量;
本发明通过BIM模型对建筑构件的信息化表达,构件加工图在BIM模型上直接完成和生成,不仅能清楚地传达传统图纸的二维关系,而且对于复杂的空间剖面关系也可以清楚表达,同时还能够将离散的二维图纸信息集中到一个模型当中,这样的模型能够更加紧密地实现与预制工厂的协同和对接;
本发明在生产加工过程中,BIM信息化技术能自动生成构件下料单、派工单、模具规格参数的生产表单,并且能通过可视化的直观表达帮助工人更好地理解设计意图,可以形成BIM生产模拟动画、流程图、说明图的辅助培训的材料,有助于提高工人生产的准确性和质量效率;
本发明通过碰撞检测分析,可以对传统二维模式下不易察觉的错误、遗漏、碰撞和缺陷进行收集更正,达到设计效率和设计质量的提升,降低成本;
本发明通过施工模拟对复杂部位和关键施工节点进行提前预演,增加工人对施工环境和施工措施的熟悉度,提高施工效率;
本发明以进度计划为主线,以BIM模型为载体,通过BIM模型出各施工阶段、各分***的装配图,来指导现场机电管线装配式安装,同时实现项目进度、施工方案、质量、安全方面的数字化、精细化和可视化管理,同时可以集成项目全生命周期的数据,使项目各方数据具有可追溯性。
上面结合附图对本发明进行了示例性描述,显然本发明具体实现并不受上述方式的限制,只要采用了本发明的方法构思和技术方案进行的各种改进,或未经改进直接应用于其它场合的,均在本发明的保护范围之内。

Claims (6)

1.一种基于BIM技术的机电管线装配式施工方法,其特征在于,包括如下步骤:
S1:预制加工模型的划分
根据管线***、安装区间位置、施工难易程度、集成度、施工进度计划和工厂的预制加工能力进行按批次划分;
S2:模型的创建
根据不同的CAD施工图分别创建三维模型图,将各个三维模型图整合为BIM模型;
S3:模型的处理
(1)BIM模型深化
根据机电管线***和区间安装位置,将不同专业间的BIM模型进行协同优化;
(2)现场扫描校核
对现场进行扫描,获取全面完整的空间三维信息,记录现场地物形态信息,将扫描信息转化为模型并与上述优化的BIM模型进行精细对比校核,并进行优化;
(3)管线综合优化
利用Navisworks软件进行碰撞检测,优化管线排布,在负责的地方,利用MagiCAD软件的支吊架模块,辅助综合支吊架设计,进行综合管线排布优化;
S4:出预制加工图和预制加工材料单
根据加工区域、空间、专业的管线***将BIM模型进行拆分,得到各个构件模型,将各构件模型出CAD二维的预制加工图,预制加工图包含构件的基本属性、加工工艺、使用特点和特殊要求的预制加工材料单;
S5:加工构件
根据预制加工图、预制加工材料单和施工进度,按批次对构件模型进行加工,得到构件,采用二维码技术记录构件和构件模型的信息;
及时更新加工构件模型和其二维码的信息;
S6:装配详图
根据BIM模型出装配详图,包括位置、连接信息、施工工艺、工序特点、特殊要求的信息,以便施工人员安装;
S7:4D施工模拟
利用BIM技术进行4D施工模拟,包括现场组织、工序和拼装模拟,直观、精确地反映整个机电管线装配式施工过程,提前预知主要施工方的控制方法、施工安排、总体规划、场地布置、工序,并进行及时优化;
S8:现场装配式安装、验收及试运行
4D施工模拟优化后,进行现场装配式安装,过程中利用BIM技术和FRID技术进行安装,并形成记录和质量管理信息,利用移动设备和BIM5D云平台实现信息及时获取和反馈;
安装完成后,进行验收和试运行,若验收不合格,找出不合格的位置和原因并进行改正,对不合格处重新进行安装和质量管理监督;
S9:竣工BIM模型
验收合格后,形成完整的BIM竣工模型,包括从设计模型到最终完成交付的所有过程的数据。
2.根据权利要求1所述的一种基于BIM技术的机电管线装配式施工方法,其特征在于,所述施工方法满足GB/T 51235-2017《建筑信息模型施工应用标准》的要求。
3.根据权利要求1所述的一种基于BIM技术的机电管线装配式施工方法,其特征在于,所述步骤S3中现场扫描采用三维激光扫描仪扫描。
4.根据权利要求1所述的一种基于BIM技术的机电管线装配式施工方法,其特征在于,所述步骤S5中所述构件、所述构件模型和所述二维码唯一对应。
5.根据权利要求4所述的一种基于BIM技术的机电管线装配式施工方法,其特征在于,所述步骤S5中的信息包括上游信息、生产信息、属性信息、加工图编码信息、工序工艺信息、成品管理信息。
6.根据权利要求5所述的一种基于BIM技术的机电管线装配式施工方法,其特征在于,所述步骤S7中模拟时,需要对复杂节点进行重点和专项施工模拟,对复杂部位和关键使用节点进行提前预演,对施工安装工人和管理人员进行培训,增加其对施工环境和施工措施的熟悉度。
CN201811254971.3A 2018-10-26 2018-10-26 一种基于bim技术的机电管线装配式施工方法 Pending CN109543233A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811254971.3A CN109543233A (zh) 2018-10-26 2018-10-26 一种基于bim技术的机电管线装配式施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811254971.3A CN109543233A (zh) 2018-10-26 2018-10-26 一种基于bim技术的机电管线装配式施工方法

Publications (1)

Publication Number Publication Date
CN109543233A true CN109543233A (zh) 2019-03-29

Family

ID=65845571

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811254971.3A Pending CN109543233A (zh) 2018-10-26 2018-10-26 一种基于bim技术的机电管线装配式施工方法

Country Status (1)

Country Link
CN (1) CN109543233A (zh)

Cited By (25)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110069881A (zh) * 2019-04-30 2019-07-30 中国十七冶集团有限公司 一种基于bim技术的雨污水***设计施工一体化方法
CN110375113A (zh) * 2019-07-31 2019-10-25 北京毕亦可机电设计咨询有限公司 基于bim的标准模数化机电管道装配方法
CN110439214A (zh) * 2019-07-17 2019-11-12 中铁十二局集团有限公司 地铁防静电地板下槽道优化安装施工方法
CN110952811A (zh) * 2019-10-24 2020-04-03 中天西北建设投资集团有限公司 一种基于bim的装配式机房深化设计流程及其施工方法
CN110990918A (zh) * 2019-11-22 2020-04-10 上海宝冶集团有限公司 基于bim的山地建筑机电管线施工方法
CN111104709A (zh) * 2019-12-31 2020-05-05 青岛国信海天中心建设有限公司 基于bim的大型制冷机房数字化装配方法及***
CN111119480A (zh) * 2019-12-06 2020-05-08 中国十七冶集团有限公司 一种基于bim+mr技术的装配式建筑全景施工管理方法
CN111424985A (zh) * 2020-04-03 2020-07-17 中国十七冶集团有限公司 一种基于bim技术的混凝土自动喷淋养护优化方法
CN111535482A (zh) * 2020-04-18 2020-08-14 湖南顺天建设集团有限公司 铝模施工混凝土结构与工装及机电预留预埋施工方法
CN111724124A (zh) * 2020-05-27 2020-09-29 上海宝冶集团有限公司 基于bim技术的管线综合建造方法
CN111853347A (zh) * 2020-07-10 2020-10-30 青岛新华友建工集团股份有限公司 一种基于bim的超前定位直埋锚栓预制管线支架施工工艺
CN112131637A (zh) * 2020-09-09 2020-12-25 武汉市汉阳市政建设集团有限公司 一种基于bim技术的变曲率弧形管道预制加工安装方法
CN112417634A (zh) * 2020-12-07 2021-02-26 浙江大东吴集团建设有限公司 一种基于bim技术的地下室管线布置方法
CN112613100A (zh) * 2020-12-18 2021-04-06 中铁十一局集团电务工程有限公司 一种基于bim技术的综合管线整体装配方法
CN112632684A (zh) * 2020-12-31 2021-04-09 南通装配式建筑与智能结构研究院 一种基于bim技术地铁环控机房装配式机电施工方法
CN112884290A (zh) * 2021-01-26 2021-06-01 青岛国信海天中心建设有限公司 一种基于bim的现场施工管理方法
CN112906098A (zh) * 2021-01-15 2021-06-04 珠海***创建筑设计有限公司 一种机动车库排风管自动寻路方法和装置
CN112948913A (zh) * 2021-01-26 2021-06-11 柳州工学院 一种基于bim技术的机电管线装配式施工方法
CN113177623A (zh) * 2021-05-21 2021-07-27 铜陵有色建安钢构有限责任公司 基于二维码和Tekla技术的钢结构模块化安装方法
CN113761642A (zh) * 2021-11-10 2021-12-07 北京建工集团有限责任公司 基于bim模型与图形码的匹配、及其检测方法与***
CN114251514A (zh) * 2020-09-23 2022-03-29 中国核工业二三建设有限公司 一种核电施工中的管道安装方法
CN114577187A (zh) * 2020-11-30 2022-06-03 中国核工业二三建设有限公司 一种结合激光扫描技术的大型结构与设备安装方法
CN115544614A (zh) * 2022-09-21 2022-12-30 广东创宇信息工程有限公司 一种基于bim5d远程监控的布线***施工方法
CN115984521A (zh) * 2023-02-06 2023-04-18 上海富凝建筑设计有限公司 装配式智能建造构件的加工图表达方法及***
CN117494356A (zh) * 2023-10-31 2024-02-02 成都建工第九建筑工程有限公司 一种基于bim技术的装配式施工方法

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103093061A (zh) * 2013-02-07 2013-05-08 中铁二十二局集团电气化工程有限公司 一种地铁机电工程综合管线碰撞优化方法
CN105839589A (zh) * 2016-05-27 2016-08-10 中交第航务工程局有限公司 一种构件装配式滚装码头结构及安装方法
CN205827412U (zh) * 2016-05-31 2016-12-21 中交一航局安装工程有限公司 一种基于bim三维模型的港口设备巡视***
CN107256318A (zh) * 2017-07-18 2017-10-17 中国电建集团河南工程公司 基于bim技术的锅炉小管道施工方法
CN107663947A (zh) * 2017-10-31 2018-02-06 中国冶集团有限公司 基于bim的装配式建筑中蒸压加气混凝土板施工方法
CN107958101A (zh) * 2017-11-07 2018-04-24 山东住工装配建筑有限公司 一种基于bim的装配式建筑信息化管理***及方法
CN107977487A (zh) * 2017-11-07 2018-05-01 山东住工装配建筑有限公司 一种基于bim技术的装配式混凝土建筑设计方法
CN108108510A (zh) * 2017-10-27 2018-06-01 广东星层建筑科技股份有限公司 一种基于bim的装配式建筑设计方法及设备

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103093061A (zh) * 2013-02-07 2013-05-08 中铁二十二局集团电气化工程有限公司 一种地铁机电工程综合管线碰撞优化方法
CN105839589A (zh) * 2016-05-27 2016-08-10 中交第航务工程局有限公司 一种构件装配式滚装码头结构及安装方法
CN205827412U (zh) * 2016-05-31 2016-12-21 中交一航局安装工程有限公司 一种基于bim三维模型的港口设备巡视***
CN107256318A (zh) * 2017-07-18 2017-10-17 中国电建集团河南工程公司 基于bim技术的锅炉小管道施工方法
CN108108510A (zh) * 2017-10-27 2018-06-01 广东星层建筑科技股份有限公司 一种基于bim的装配式建筑设计方法及设备
CN107663947A (zh) * 2017-10-31 2018-02-06 中国冶集团有限公司 基于bim的装配式建筑中蒸压加气混凝土板施工方法
CN107958101A (zh) * 2017-11-07 2018-04-24 山东住工装配建筑有限公司 一种基于bim的装配式建筑信息化管理***及方法
CN107977487A (zh) * 2017-11-07 2018-05-01 山东住工装配建筑有限公司 一种基于bim技术的装配式混凝土建筑设计方法

Non-Patent Citations (8)

* Cited by examiner, † Cited by third party
Title
丁烈云等: "《BIM应用·施工》", 同济大学出版社, pages: 288 *
尹晶: "BIM技术在装饰工程管理中应用研究", 《四川水泥》 *
尹晶: "BIM技术在装饰工程管理中应用研究", 《四川水泥》, 28 February 2018 (2018-02-28), pages 1 *
张永清: "建筑安装领域计算机BIM技术研究", 《中国优秀硕士学位论文全文数据库(电子期刊)工程科技II辑》, no. 1, 15 January 2018 (2018-01-15), pages 038 - 85 *
李飞: "BIM技术在地下综合管廊施工阶段的应用", 《中国优秀硕士学位论文全文数据库(电子期刊)工程科技II辑》 *
李飞: "BIM技术在地下综合管廊施工阶段的应用", 《中国优秀硕士学位论文全文数据库(电子期刊)工程科技II辑》, no. 4, 15 April 2017 (2017-04-15), pages 038 - 140 *
章梦晨: "基于BIM的机电安装工程深化设计应用研究", 《中国优秀硕士学位论文全文数据库(电子期刊)工程科技II辑》 *
章梦晨: "基于BIM的机电安装工程深化设计应用研究", 《中国优秀硕士学位论文全文数据库(电子期刊)工程科技II辑》, no. 3, 15 March 2017 (2017-03-15), pages 038 - 312 *

Cited By (28)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110069881A (zh) * 2019-04-30 2019-07-30 中国十七冶集团有限公司 一种基于bim技术的雨污水***设计施工一体化方法
CN110439214A (zh) * 2019-07-17 2019-11-12 中铁十二局集团有限公司 地铁防静电地板下槽道优化安装施工方法
CN110439214B (zh) * 2019-07-17 2021-03-30 中铁十二局集团有限公司 地铁防静电地板下槽道优化安装施工方法
CN110375113A (zh) * 2019-07-31 2019-10-25 北京毕亦可机电设计咨询有限公司 基于bim的标准模数化机电管道装配方法
CN110952811A (zh) * 2019-10-24 2020-04-03 中天西北建设投资集团有限公司 一种基于bim的装配式机房深化设计流程及其施工方法
CN110990918A (zh) * 2019-11-22 2020-04-10 上海宝冶集团有限公司 基于bim的山地建筑机电管线施工方法
CN111119480A (zh) * 2019-12-06 2020-05-08 中国十七冶集团有限公司 一种基于bim+mr技术的装配式建筑全景施工管理方法
CN111104709A (zh) * 2019-12-31 2020-05-05 青岛国信海天中心建设有限公司 基于bim的大型制冷机房数字化装配方法及***
CN111424985A (zh) * 2020-04-03 2020-07-17 中国十七冶集团有限公司 一种基于bim技术的混凝土自动喷淋养护优化方法
CN111535482A (zh) * 2020-04-18 2020-08-14 湖南顺天建设集团有限公司 铝模施工混凝土结构与工装及机电预留预埋施工方法
CN111724124A (zh) * 2020-05-27 2020-09-29 上海宝冶集团有限公司 基于bim技术的管线综合建造方法
CN111853347A (zh) * 2020-07-10 2020-10-30 青岛新华友建工集团股份有限公司 一种基于bim的超前定位直埋锚栓预制管线支架施工工艺
CN112131637A (zh) * 2020-09-09 2020-12-25 武汉市汉阳市政建设集团有限公司 一种基于bim技术的变曲率弧形管道预制加工安装方法
CN112131637B (zh) * 2020-09-09 2024-04-02 武汉市汉阳市政建设集团有限公司 一种基于bim技术的变曲率弧形管道预制加工安装方法
CN114251514A (zh) * 2020-09-23 2022-03-29 中国核工业二三建设有限公司 一种核电施工中的管道安装方法
CN114577187A (zh) * 2020-11-30 2022-06-03 中国核工业二三建设有限公司 一种结合激光扫描技术的大型结构与设备安装方法
CN112417634A (zh) * 2020-12-07 2021-02-26 浙江大东吴集团建设有限公司 一种基于bim技术的地下室管线布置方法
CN112417634B (zh) * 2020-12-07 2023-10-20 浙江大东吴集团建设有限公司 一种基于bim技术的地下室管线布置方法
CN112613100A (zh) * 2020-12-18 2021-04-06 中铁十一局集团电务工程有限公司 一种基于bim技术的综合管线整体装配方法
CN112632684A (zh) * 2020-12-31 2021-04-09 南通装配式建筑与智能结构研究院 一种基于bim技术地铁环控机房装配式机电施工方法
CN112906098A (zh) * 2021-01-15 2021-06-04 珠海***创建筑设计有限公司 一种机动车库排风管自动寻路方法和装置
CN112948913A (zh) * 2021-01-26 2021-06-11 柳州工学院 一种基于bim技术的机电管线装配式施工方法
CN112884290A (zh) * 2021-01-26 2021-06-01 青岛国信海天中心建设有限公司 一种基于bim的现场施工管理方法
CN113177623A (zh) * 2021-05-21 2021-07-27 铜陵有色建安钢构有限责任公司 基于二维码和Tekla技术的钢结构模块化安装方法
CN113761642A (zh) * 2021-11-10 2021-12-07 北京建工集团有限责任公司 基于bim模型与图形码的匹配、及其检测方法与***
CN115544614A (zh) * 2022-09-21 2022-12-30 广东创宇信息工程有限公司 一种基于bim5d远程监控的布线***施工方法
CN115984521A (zh) * 2023-02-06 2023-04-18 上海富凝建筑设计有限公司 装配式智能建造构件的加工图表达方法及***
CN117494356A (zh) * 2023-10-31 2024-02-02 成都建工第九建筑工程有限公司 一种基于bim技术的装配式施工方法

Similar Documents

Publication Publication Date Title
CN109543233A (zh) 一种基于bim技术的机电管线装配式施工方法
CN110909972B (zh) 一种基于bim的钢结构全寿命周期的管理***及方法
Sacks et al. BIM handbook: A guide to building information modeling for owners, designers, engineers, contractors, and facility managers
Nath et al. Productivity improvement of precast shop drawings generation through BIM-based process re-engineering
CN109800536A (zh) 一种基于Revit与Dynamo参数化隧道模型快速建模方法
Woo et al. Use of as-built building information modeling
CN109785436A (zh) 一种基于bim技术的钢筋信息全生命周期的管理方法
CN112257160B (zh) 一种基于bim的垃圾焚烧发电厂标准化正向设计方法
CN110287513A (zh) 一种基于bim技术的预埋件施工方法
Liao et al. A project management framework for enhanced productivity performance using building information modelling
Park BIM-based parametric design methodology for modernized Korean traditional buildings
CN103336856A (zh) 一种基于可视化模型的钢结构虚拟预拼装方法
KR101227723B1 (ko) 파라메트릭 디자인 프로세스를 이용한 한옥설계 지원 정보시스템 구축방법
CN107992643A (zh) 一种基于三维扫描点云数据及人工智能识别与计算的建筑业构部件生产与安装精度控制工艺
CN112252548A (zh) 一种基于bim的幕墙干挂预制加工方法
CN115600298A (zh) 一种基于revit的BIM建筑正向设计标准化出图方法
CN115168971A (zh) 基于构件参数库的装配式建筑设计与建造一体化协同方法
CN113610388A (zh) 基于bim的预制构件设计质量管理方法、装置及设备
CN114329740A (zh) 基于bim的大跨度上承式梁拱组合刚构桥三维正向设计方法
Voss et al. A BPMN-based process map for the design and construction of façades
CN113204284A (zh) 一种基于bim与mr技术的虚拟施工综合管道安装及验收方法
CN112765711A (zh) 一种绿色建筑模拟计算的bim建模方法
CN105956346A (zh) 一种铝合金模板设计***和方法
CN112487534A (zh) 基于bim技术对建筑物进行净高分析的方法
Murphy et al. Leveraging advanced VDC methods and reality capture to increase the predictability for prefabrication

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190329

RJ01 Rejection of invention patent application after publication