CN109371933A - Underground workshop ventilating system - Google Patents

Underground workshop ventilating system Download PDF

Info

Publication number
CN109371933A
CN109371933A CN201811408359.7A CN201811408359A CN109371933A CN 109371933 A CN109371933 A CN 109371933A CN 201811408359 A CN201811408359 A CN 201811408359A CN 109371933 A CN109371933 A CN 109371933A
Authority
CN
China
Prior art keywords
air
workshop
conditioning facilities
air conditioning
room
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811408359.7A
Other languages
Chinese (zh)
Other versions
CN109371933B (en
Inventor
张顺利
谭可奇
龚少红
林起明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Chengdu Engineering Co Ltd
Original Assignee
PowerChina Chengdu Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Chengdu Engineering Co Ltd filed Critical PowerChina Chengdu Engineering Co Ltd
Priority to CN201811408359.7A priority Critical patent/CN109371933B/en
Publication of CN109371933A publication Critical patent/CN109371933A/en
Application granted granted Critical
Publication of CN109371933B publication Critical patent/CN109371933B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B9/00Water-power plants; Layout, construction or equipment, methods of, or apparatus for, making same
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24FAIR-CONDITIONING; AIR-HUMIDIFICATION; VENTILATION; USE OF AIR CURRENTS FOR SCREENING
    • F24F7/00Ventilation
    • F24F7/04Ventilation with ducting systems, e.g. by double walls; with natural circulation
    • F24F7/06Ventilation with ducting systems, e.g. by double walls; with natural circulation with forced air circulation, e.g. by fan positioning of a ventilator in or against a conduit

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Ventilation (AREA)

Abstract

The invention discloses a kind of underground workshop ventilating systems, belong to hydraulic and hydroelectric engineering field, to solve the technical issues of is: the Air Conditioning Facilities of existing underground workshop need specially to open up transport installation of the communications and transportation hole as air-conditioner set, the operation path that overhauls etc..The present invention passes through setting air conditioner auxiliary power house, corresponding transport hanging object hole is set simultaneously, by transporting hanging object hole, it will be by transporting into factory's access tunnel to installing in the air-conditioner set handling to the Air Conditioning Facilities of top in workshop clipping room, there is no need to additionally open up the communications and transportation channel transported and overhauled dedicated for air-conditioner set again, not only corresponding cavity group arrangement complexity and cost saving can have been reduced, but also has made the construction and installation of air-conditioner set, runtime maintenance and manages concentratedly more convenient.

Description

Underground workshop ventilating system
Technical field
The present invention relates to hydraulic and hydroelectric engineering field more particularly to a kind of underground workshop ventilating systems.
Background technique
In underground workshop ventilating system layout design, not only to meet underground power house open air exhaust requirement, also want Consider in the case where arranging Air Conditioning Facilities, the construction and installation, operation and maintenance for taking into account air-conditioner set in Air Conditioning Facilities facilitate Demand.Main building furred ceiling in underground is disposed with special into air exhaust passage under normal conditions, unobstructed to coordinate the cavern layout and air inlet, Air Conditioning Facilities need to arrange close to crown, therefore its elevation is higher relative to the bottom plate in clipping room.
Since the size of underground power house ventilating system air-conditioner set is larger, construction time transport installation, the maintenance of runtime Maintenance requires special traffic aisle.In the prior art, it is the traffic problems for solving above-mentioned Air Conditioning Facilities, need to closing on Working tunnel or access tunnel of marching into the arena make a call to the through Air Conditioning Facilities in a dedicated logical transport hole, cause cavity group arrangement more complicated and increase Construction investment is added, while being also inconvenient to concentrate operational management.
Summary of the invention
Technical problem solved by the present invention is the Air Conditioning Facilities of existing underground workshop need specially to open up one The operation path that transports installation, maintenance etc. of the communications and transportation hole as air-conditioner set.
The technical solution adopted by the present invention to solve the technical problems is: underground workshop ventilating system, including factory Room clipping room and be connected to workshop clipping room into factory's access tunnel, in workshop clipping room close into factory's access tunnel one end push up Portion is provided with Air Conditioning Facilities, and air conditioner auxiliary power house is provided between workshop clipping room and Air Conditioning Facilities, in air conditioner auxiliary power house It is inside vertically provided with transport hanging object hole, the transport hanging object hole is connected to workshop clipping room bottom and Air Conditioning Facilities respectively;It is transporting Lifting appliance is provided in defeated hanging object hole.
Further, the air conditioner auxiliary power house is disposed with transport hanging object hole, installation chamber region in the width direction And staircase.
Further, the installation chamber region includes Air Conditioning Facilities switchboard room, cable vault and control by bottom to top Cabinet room processed.
Further, being provided with air inlet duct at the top of workshop clipping room, installation room is located in air conditioner auxiliary power house Overlying regions are provided with air inlet pressure buffer room, and the air inlet duct is connected by the air outlet of air inlet pressure buffer room and Air Conditioning Facilities It is logical.
Further, being provided with air inlet hole, the air inlet in the air inlet hole and Air Conditioning Facilities in Air Conditioning Facilities upstream side Connection.
Further, the Air Conditioning Facilities are provided with two layers, air-conditioner set, the sky in two layers are respectively arranged at every layer Adjust unit in parallel.
Further, the other end opposite with Air Conditioning Facilities in workshop clipping room is provided with exhaust system.
The beneficial effects of the present invention are: the present invention is by being arranged air conditioner auxiliary power house, while the corresponding transport hanging object of setting It hole will be by transporting the sky to the air-conditioner set handling in workshop clipping room to top into factory's access tunnel by transporting hanging object hole It adjusts and is installed in computer room, there is no need to additionally open up the communications and transportation channel transported and overhauled dedicated for air-conditioner set again, Not only corresponding cavity group arrangement complexity and cost saving can have been reduced, but also has made the construction and installation of air-conditioner set, runtime maintenance And centralized management is more convenient.It, can be by addition, further by the corresponding installation chamber region of setting and staircase in the present invention Chamber region installation is installed and arrangement is used for corresponding controlling terminal, controller switching equipment and the line arrangement etc. of air-conditioner set, it can be further Space is made full use of, the space requirement to Air Conditioning Facilities is reduced;And by the way that corresponding staircase is arranged, then it can facilitate construction When with maintenance, operating personnel is entered in Air Conditioning Facilities and corresponding floor.
Detailed description of the invention
Fig. 1 is arrangement schematic diagram of the underground workshop ventilating system along workshop longitudinal axis section;
Fig. 2 is A-A cross sectional plan view;
Fig. 3 is B-B cross sectional plan view;
Fig. 4 is C-C cross sectional plan view;
Fig. 5 is D-D cross sectional plan view;
In the figure, it is marked as workshop clipping room 1, into factory's access tunnel 2, Air Conditioning Facilities 3, air conditioner auxiliary power house 4, transport hanging object hole 5, chamber region 6, Air Conditioning Facilities switchboard room 61, cable vault 62, control cabinet room 63, staircase 7, air inlet duct 8, air inlet air pressure are installed Surge chamber 9, air inlet hole 10, air-conditioner set 11.
Specific embodiment
The present invention is further described with reference to the accompanying drawings and detailed description.
As shown in Fig. 1 to Fig. 5, underground workshop ventilating system of the present invention, including workshop clipping room 1 with And be connected to workshop clipping room 1 into factory's access tunnel 2, close into being arranged at the top of one end of factory's access tunnel 2 in workshop clipping room 1 There are Air Conditioning Facilities 3, air conditioner auxiliary power house 4 is provided between workshop clipping room 1 and Air Conditioning Facilities 3, in air conditioner auxiliary power house 4 It is vertically provided with transport hanging object hole 5, the transport hanging object hole 5 is connected to 1 bottom of workshop clipping room and Air Conditioning Facilities 3 respectively;? Transport is provided with lifting appliance in hanging object hole 5.
Wherein, the effect of air conditioner auxiliary power house 4 is by its internal transport hanging object hole 5 for will transport to workshop The equipment such as the air-conditioner set 11 in clipping room 1, which are transported to, carries out installation or the maintenance as air-conditioner set 11 in Air Conditioning Facilities 3 Channel;Then air-conditioner set 11 corresponding in this way can pass through again directly by transporting into factory's access tunnel 2 to workshop clipping room 1 It transports in 5 handling to Air Conditioning Facilities 3 of hanging object hole;There is no need to additionally get through one dedicated for air conditioner in Air Conditioning Facilities 3 The logical transport hole of group 11.Without loss of generality, need to match corresponding lifting appliance during transporting 5 handling of hanging object hole. In addition, should also be as the entrance that setting is connected to transport 5 bottom of hanging object hole in the bottom of air conditioner auxiliary power house 4, workshop is installed Between air-conditioner set 11 in 1 be sent to the bottom in transport hanging object hole 5 and lifted by crane.Without loss of generality, aforementioned present invention is for sky It adjusts the transportational process of unit 11 to be summarized as follows: being hung into the transport in factory's access tunnel 2 → workshop, 1 → air conditioner of clipping room auxiliary power house 4 5 → Air Conditioning Facilities of object hole 3;When needing to overhaul, then reversely the air-conditioner set 11 after disassembly is transported outward.Without loss of generality, The corresponding size in channel of above-mentioned each transport air-conditioner set 11 should transport required size according to air-conditioner set 11 and carry out rationally Setting.
More specifically, referring to shown in attached drawing 2 to attached drawing 4,4 edge of air conditioner auxiliary power house is further set in the present invention Width direction is disposed with transport hanging object hole 5, installation chamber region 6 and staircase 7.In this way, by the way that staircase is further arranged 7, construction worker can be facilitated to pass in and out Air Conditioning Facilities 3 and air conditioner auxiliary power house 4 from workshop clipping room 1 by staircase 7 In each floor.Wherein, installation chamber region 6 is the independent construction area being arranged in air-conditioning auxiliary power house 4.Specifically, this hair It includes Air Conditioning Facilities switchboard room 61,62 and of cable vault that the installation chamber region 6 can further be arranged in bright by bottom to top 63 three-decker of control cabinet room, respectively corresponds shown in attached drawing 2 to attached drawing 4;It in this way can be respectively by Air Conditioning Facilities switchboard room 61, cable vault 62 and control cabinet room 63 are for installing the mating required controlling terminal of air-conditioner set 11, controller switching equipment and route Arrangement etc., can further decrease in this way and above-mentioned corollary equipment is installed to space required in Air Conditioning Facilities 3, and then can reduce sky Adjust the excavation space of computer room 3;Meanwhile it can also conveniently be arrived in above-mentioned each floor by staircase 7 and corresponding corollary equipment is carried out Independent maintenance.
In addition, be provided with air inlet duct 8 at the top of workshop clipping room 1 under normal conditions, by air inlet duct 8 by air-conditioner set 11 treated air deliveries are to each demand position of workshop.When the present invention is provided with air conditioner auxiliary power house 4, further in air-conditioning It is located above installation chamber region 6 in machine auxiliary power house 4 and is provided with air inlet pressure buffer room 9, the air inlet duct 8 is slow by air inlet air pressure Room 9 is rushed to be connected to the air outlet of Air Conditioning Facilities 3;Air inlet air pressure is first drained into from the gas that the air outlet of Air Conditioning Facilities 3 is discharged In surge chamber 9, each required position in workshop is delivered to by air inlet duct 8 again after certain buffering.More specifically, in order to improve To the air cycle efficiency and ventilation effect in entire workshop clipping room 1, in the present invention further in workshop clipping room 1 with The opposite other end of Air Conditioning Facilities 3 is provided with exhaust system, by exhaust system by the gas discharging in workshop clipping room 1, with Improve the drafting efficiency in entire workshop.
It is connected in addition, needing to be provided with air inlet hole 10 in the present invention naturally with Air Conditioning Facilities 3, to be fed to Air Conditioning Facilities 3 Air can specifically be arranged in rational positions such as 3 upstream side of Air Conditioning Facilities, downstream side or tops and enter the wind hole 10, in the present invention It is preferred that the upstream side of Air Conditioning Facilities 3 is arranged in air inlet hole 10, the air inlet hole 10 is connected to the air inlet of Air Conditioning Facilities 3, with logical Air inlet hole 10 is crossed to enter the wind to Air Conditioning Facilities 3.
By above-mentioned each setting, the ventilation process of underground workshop ventilating system of the present invention is summarized as follows: Enter the wind 1 top of air inlet pressure buffer room 9 → workshop clipping room at 10 → Air Conditioning Facilities of hole, 3 → Air Conditioning Facilities auxiliary power house, 4 top Each required position → exhaust system discharge in 8 → workshop of air inlet duct.
More specifically, in order to improve 11 quantity of air-conditioner set that can be installed in Air Conditioning Facilities 3, further will in the present invention The Air Conditioning Facilities 3 are provided with two layers, and air-conditioner set 11 is respectively arranged at every layer, and the air-conditioner set 11 in two layers is in parallel.And And two groups of air-conditioner sets 11 can be also respectively arranged in every layer.

Claims (7)

1. underground workshop ventilating system, what is be connected to including workshop clipping room (1) and with workshop clipping room (1) hands over into factory Logical hole (2) are provided with Air Conditioning Facilities (3), feature close into one end of factory's access tunnel (2) top in workshop clipping room (1) It is: air conditioner auxiliary power house (4) is provided between workshop clipping room (1) and Air Conditioning Facilities (3), in air conditioner auxiliary power house (4) Inside be vertically provided with transport hanging object hole (5), the transport hanging object hole (5) respectively with workshop clipping room (1) bottom and Air Conditioning Facilities (3) it is connected to;Lifting appliance is provided in transport hanging object hole (5).
2. underground workshop ventilating system as described in claim 1, it is characterised in that: the air conditioner auxiliary power house (4) It is disposed with transport hanging object hole (5), installation chamber region (6) and staircase (7) in the width direction.
3. the underground workshop ventilating system as described in right wants 2, it is characterised in that: the installation chamber region (6) is the bottom of by Portion to top includes Air Conditioning Facilities switchboard room (61), cable vault (62) and control cabinet room (63).
4. underground workshop ventilating system as described in claim 1, it is characterised in that: on the top of workshop clipping room (1) Portion is provided with air inlet duct (8), is located above installation chamber region (6) in air conditioner auxiliary power house (4) and is provided with air inlet pressure buffer Room (9), the air inlet duct (8) are connected to by entering the wind pressure buffer room (9) with the air outlet of Air Conditioning Facilities (3).
5. underground workshop ventilating system as described in claim 1, it is characterised in that: in Air Conditioning Facilities (3) upstream side It is provided with air inlet hole (10), air inlet hole (10) is connected to the air inlet of Air Conditioning Facilities (3).
6. underground workshop ventilating system as described in claim 1, it is characterised in that: Air Conditioning Facilities (3) setting Have two layers, be respectively arranged at every layer air-conditioner set (11), the air-conditioner set (11) in two layers is in parallel.
7. the underground workshop ventilating system as described in any one of claim 1 to 6, it is characterised in that: in workshop Air Conditioning Facilities (3) opposite other end is provided with exhaust system in clipping room (1).
CN201811408359.7A 2018-11-23 2018-11-23 Underground powerhouse ventilation system of hydropower station Active CN109371933B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811408359.7A CN109371933B (en) 2018-11-23 2018-11-23 Underground powerhouse ventilation system of hydropower station

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811408359.7A CN109371933B (en) 2018-11-23 2018-11-23 Underground powerhouse ventilation system of hydropower station

Publications (2)

Publication Number Publication Date
CN109371933A true CN109371933A (en) 2019-02-22
CN109371933B CN109371933B (en) 2024-02-27

Family

ID=65383284

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811408359.7A Active CN109371933B (en) 2018-11-23 2018-11-23 Underground powerhouse ventilation system of hydropower station

Country Status (1)

Country Link
CN (1) CN109371933B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110965585A (en) * 2019-12-25 2020-04-07 中铁建设集团市政工程有限公司 Multi-multi-arch rectangular tunnel arch division construction method

Citations (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4279539A (en) * 1979-08-17 1981-07-21 Gutierrez Atencio Francisco J Dam with transformable hydroenergetic arrangement
US4896514A (en) * 1987-10-31 1990-01-30 Kabushiki Kaisha Toshiba Air-conditioning apparatus
JP2000193279A (en) * 1998-12-25 2000-07-14 Toshiba Eng Co Ltd Ventilating method inside nuclear reactor building
CN2586756Y (en) * 2002-11-22 2003-11-19 湖南省交通规划勘察设计院 Factory dam common door machine type roof special for power station
CN2926399Y (en) * 2006-02-24 2007-07-25 贵阳铝镁设计研究院 Cargo suspending-hole structure for small warehouse
JP2009250442A (en) * 2008-04-01 2009-10-29 Toyota Motor Corp Air conditioning equipment for building, and building equipped with the same
CN201762695U (en) * 2010-08-17 2011-03-16 中国水电顾问集团华东勘测设计研究院 Structure applicable to large and medium-sized mechanical device to enter long tunnel for overhaul
CN202063649U (en) * 2011-05-20 2011-12-07 中国葛洲坝集团股份有限公司 Equipment hoisting device for special portion of powerhouse
CN203034429U (en) * 2012-08-01 2013-07-03 卢江江 Semi-buried type hydroelectric power house
EP2730701A2 (en) * 2012-11-08 2014-05-14 Moravsky Vyzkum, s.r.o. Underground pumped storage power station
CN104131714A (en) * 2014-06-30 2014-11-05 中国核电工程有限公司 Method for arranging first span of nuclear power station steam turbine plant
CN203938196U (en) * 2014-06-25 2014-11-12 中国电建集团华东勘测设计研究院有限公司 A kind of device for transporting equipment of semi-underground powerhouse
CN204386218U (en) * 2014-12-25 2015-06-10 中国电建集团贵阳勘测设计研究院有限公司 Structure for effectively utilizing workshop space
CN204753538U (en) * 2015-07-03 2015-11-11 中国电建集团贵阳勘测设计研究院有限公司 Arrangement structure of ecological flow small unit of underground workshop
CN204825820U (en) * 2015-08-05 2015-12-02 中国电建集团贵阳勘测设计研究院有限公司 Pressure regulating well structure using traffic hole as upper chamber
CN105155488A (en) * 2015-07-03 2015-12-16 中国电建集团贵阳勘测设计研究院有限公司 Arrangement mode and structure of small ecological flow unit of underground powerhouse of hydropower station
CN205101265U (en) * 2015-11-17 2016-03-23 中国长江三峡集团公司 Fan system of airing exhaust is led to to underground cavern construction time
CN106013013A (en) * 2016-05-30 2016-10-12 广州市恩莱吉能源科技有限公司 Separation and combination type plant system of through-flow hydropower station
CN108597629A (en) * 2018-03-22 2018-09-28 中国核电工程有限公司 A kind of arrangement of nuclear plant safety workshop
CN209429076U (en) * 2018-11-23 2019-09-24 中国电建集团成都勘测设计研究院有限公司 Underground workshop ventilating system

Patent Citations (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4279539A (en) * 1979-08-17 1981-07-21 Gutierrez Atencio Francisco J Dam with transformable hydroenergetic arrangement
US4896514A (en) * 1987-10-31 1990-01-30 Kabushiki Kaisha Toshiba Air-conditioning apparatus
JP2000193279A (en) * 1998-12-25 2000-07-14 Toshiba Eng Co Ltd Ventilating method inside nuclear reactor building
CN2586756Y (en) * 2002-11-22 2003-11-19 湖南省交通规划勘察设计院 Factory dam common door machine type roof special for power station
CN2926399Y (en) * 2006-02-24 2007-07-25 贵阳铝镁设计研究院 Cargo suspending-hole structure for small warehouse
JP2009250442A (en) * 2008-04-01 2009-10-29 Toyota Motor Corp Air conditioning equipment for building, and building equipped with the same
CN201762695U (en) * 2010-08-17 2011-03-16 中国水电顾问集团华东勘测设计研究院 Structure applicable to large and medium-sized mechanical device to enter long tunnel for overhaul
CN202063649U (en) * 2011-05-20 2011-12-07 中国葛洲坝集团股份有限公司 Equipment hoisting device for special portion of powerhouse
CN203034429U (en) * 2012-08-01 2013-07-03 卢江江 Semi-buried type hydroelectric power house
EP2730701A2 (en) * 2012-11-08 2014-05-14 Moravsky Vyzkum, s.r.o. Underground pumped storage power station
CN203938196U (en) * 2014-06-25 2014-11-12 中国电建集团华东勘测设计研究院有限公司 A kind of device for transporting equipment of semi-underground powerhouse
CN104131714A (en) * 2014-06-30 2014-11-05 中国核电工程有限公司 Method for arranging first span of nuclear power station steam turbine plant
CN204386218U (en) * 2014-12-25 2015-06-10 中国电建集团贵阳勘测设计研究院有限公司 Structure for effectively utilizing workshop space
CN204753538U (en) * 2015-07-03 2015-11-11 中国电建集团贵阳勘测设计研究院有限公司 Arrangement structure of ecological flow small unit of underground workshop
CN105155488A (en) * 2015-07-03 2015-12-16 中国电建集团贵阳勘测设计研究院有限公司 Arrangement mode and structure of small ecological flow unit of underground powerhouse of hydropower station
CN204825820U (en) * 2015-08-05 2015-12-02 中国电建集团贵阳勘测设计研究院有限公司 Pressure regulating well structure using traffic hole as upper chamber
CN205101265U (en) * 2015-11-17 2016-03-23 中国长江三峡集团公司 Fan system of airing exhaust is led to to underground cavern construction time
CN106013013A (en) * 2016-05-30 2016-10-12 广州市恩莱吉能源科技有限公司 Separation and combination type plant system of through-flow hydropower station
CN108597629A (en) * 2018-03-22 2018-09-28 中国核电工程有限公司 A kind of arrangement of nuclear plant safety workshop
CN209429076U (en) * 2018-11-23 2019-09-24 中国电建集团成都勘测设计研究院有限公司 Underground workshop ventilating system

Non-Patent Citations (8)

* Cited by examiner, † Cited by third party
Title
孙伟;魏特;杨晓勇;邢凯;: "水布垭水电站暖通空调***的设计与应用", 水电与新能源, no. 06 *
张捷;董丹丹;: "维捷布斯克水电站厂房布置及结构设计", 科技创新导报, no. 31, 1 November 2017 (2017-11-01) *
彭淑英;: "某抽水蓄能电站通风空调设计", 发电与空调, no. 02 *
***: "十三陵抽水蓄能电站地下厂房通风空调***", 华北电力技术, no. 11, 25 November 1995 (1995-11-25) *
王其利;: "图尔古松水电站厂房设计", 科技创新与应用, no. 18, 21 June 2018 (2018-06-21) *
祝效奇, 黄振兴, 阎爱线: "龙羊峡水电站厂房设计", 水力发电, no. 09 *
赵政: "抽水蓄能电站地下厂房布置的比较设计", 西北水电, pages 91 - 97 *
陈鹏等: "大数据技术在水电站地下厂房通风空调***中的应用研究", 水电与新能源, pages 25 - 28 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110965585A (en) * 2019-12-25 2020-04-07 中铁建设集团市政工程有限公司 Multi-multi-arch rectangular tunnel arch division construction method

Also Published As

Publication number Publication date
CN109371933B (en) 2024-02-27

Similar Documents

Publication Publication Date Title
CN209429076U (en) Underground workshop ventilating system
CN109371933A (en) Underground workshop ventilating system
CN108930288A (en) It is a kind of for be equipped with combustion gas cabin pipe gallery ventilation node
CN110118099B (en) Fire ventilation and smoke exhaust method for subway transfer station platform
CN214373247U (en) Proportional model test device for fire smoke control of narrow and long space of underground plant
CN111878954B (en) Use method of pipe gallery ventilation system of non-gas pipeline cabin
CN210463399U (en) Novel ventilation air-conditioning system for subway public area
CN202991094U (en) Integrated monitoring system of tunnel ventilating device
CN211367609U (en) Blast furnace fan system
CN204853807U (en) House garage system of discharging fume of airing exhaust
CN212253033U (en) Pipe gallery ventilation system of non-gas pipeline cabin
CN213667640U (en) Fireproof smoke-discharging exhaust system for garage
CN205135689U (en) Mine ventilation system
CN212079718U (en) Subway train platform
CN213062396U (en) Underground air duct system for inflatable membrane building
CN107142958B (en) Double shield pattern synthesis piping lane node wells
CN220169601U (en) Air treatment unit for class A closed workshop
CN217206556U (en) Dust device is used in subway construction
CN202141344U (en) Blast system of rotary forced-air cooler
CN217132553U (en) Installation and debugging device for regulating valve driving part
CN218895477U (en) Underground works intelligence ventilation control system
CN219775901U (en) Ventilation and air conditioning device for common pipeline of subway station public area
CN219758694U (en) Comprehensive pipe rack power distribution and control device crossing multiple fireproof partitions
CN212454502U (en) Main pit dust exhaust area and parallelly connected return air overall arrangement structure of district of waiting to ventilate
CN218116550U (en) Modular utility tunnel vent

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant