CN109322250A - The fast adjustment method of pre-pressing bracket sedimentation absolute altitude - Google Patents

The fast adjustment method of pre-pressing bracket sedimentation absolute altitude Download PDF

Info

Publication number
CN109322250A
CN109322250A CN201811449928.2A CN201811449928A CN109322250A CN 109322250 A CN109322250 A CN 109322250A CN 201811449928 A CN201811449928 A CN 201811449928A CN 109322250 A CN109322250 A CN 109322250A
Authority
CN
China
Prior art keywords
plummet
reinforcing bar
template
sedimentation
precompressed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811449928.2A
Other languages
Chinese (zh)
Inventor
李佰西
黄骥
王殿涛
廖永祥
郭微微
吴大成
莫贤治
林杰辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Original Assignee
China MCC20 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC20 Group Corp Ltd filed Critical China MCC20 Group Corp Ltd
Priority to CN201811449928.2A priority Critical patent/CN109322250A/en
Publication of CN109322250A publication Critical patent/CN109322250A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The fast adjustment method of specifically a kind of pre-pressing bracket sedimentation absolute altitude of the present invention;It is characterized in that: including each bridge respectively in both ends and intermediate six points of arrangement altogether;A reinforcing bar is smeared down toward fixation, reinforcing bar and ground junction with red paint with throwing into respectively at six points and is marked;Hang a plummet respectively on each gang mould board ends and middle, the support beam at bottom die of box-beam plate and at flange template;Before non-precompressed, the inverted cone bottom surface and reinforcing bar face of plummet maintain an equal level;After precompressed, template sedimentation drives plummet decline, there is height difference H between inverted cone bottom surface and reinforcing bar top surface, after adjustment height is calculated by the preloading amount H of the non-precompressed front template height H1 and template of H and measurement, is adjusted.Bracket needed for this fast adjustment method is set up conveniently, and observation is intuitive, measurement is accurate, is reduced the required time of pre-pressing bracket sedimentation adjustment, is accelerated speed of application, improve work efficiency, reduce construction cost.

Description

The fast adjustment method of pre-pressing bracket sedimentation absolute altitude
Technical field
The present invention relates to field of bridge construction, the fast adjustment method of specifically a kind of pre-pressing bracket sedimentation absolute altitude.
Background technique
Currently, construction site adjusts the step for formwork elevation measuring to designed elevation in construction bridges template, after precompressed In, each bracket will measure calculating adjustment height and then just correspond adjustment, and this method is time-consuming and laborious, significantly Increase the workload and construction cost of construction;And formwork after-poppet is intensive, and measurement sight is usually blocked to more The complexity for increasing workload and measurement, reduces the accuracy of measurement data.
Summary of the invention
It is an object of the invention to overcome drawbacks described above, measurement accuracy can be accelerated and guarantee data accuracy by providing one kind Pre-pressing bracket settle absolute altitude fast adjustment method.
In order to achieve the above object, the present invention is implemented as follows:
A kind of fast adjustment method of pre-pressing bracket sedimentation absolute altitude, including
After step 1, template install, each bridge is respectively in both ends and intermediate six points of arrangement altogether;
Step 2, at six points chosen respectively by a #12 or more than reinforcing bar throw into down toward fixation, exposed parts For 1m, reinforcement location is located at selected plummet hitch point side in order to measurement later, and reinforcing bar and ground junction are with red Paint application label, in order to observe whether reinforcing bar has sedimentation phenomenon, to prevent subsequent calculations from error occur;
Step 3 is divided on each gang mould board ends and middle, the support beam at bottom die of box-beam plate and at flange template Not Xuan Gua a plummet, totally six, hang specifically: plummet is hung on support beam at the edge of a wing, and plummet is outstanding at bottom plate It is hung on and clenches on the nail of support beam;
Before step 4, non-precompressed, the inverted cone bottom surface and reinforcing bar face of plummet maintain an equal level;After precompressed, template sedimentation is driven under plummet Drop, have height difference H between inverted cone bottom surface and reinforcing bar top surface, by H with measure non-precompressed front template height H1 and template it is pre- After adjustment height is calculated in pressure settling amount H, the respective holder of six points is adjusted first, then constitutes every two point Plane, the bracket between totally three planes by between two points draw a tight straight line be adjusted.
Bracket needed for this fast adjustment method is set up conveniently, and observation is intuitive, measurement is accurate, is reduced pre-pressing bracket sedimentation and is adjusted Whole required time, accelerates speed of application, improves work efficiency, reduces construction cost.
Detailed description of the invention
Fig. 1 is the erection schematic diagram of six measurement points in this method of adjustment.
Fig. 2 is measurement process schematic diagram one in this method of adjustment.
Fig. 3 is measurement process schematic diagram two in this method of adjustment.
Specific embodiment
The present invention is further illustrated below by way of specific embodiment.
A kind of fast adjustment method of pre-pressing bracket sedimentation absolute altitude, including
As shown in Figure 1, each bridge is respectively in both ends and intermediate six points of arrangement altogether after step 1, template install;
Step 2, at six points chosen respectively by a #12 or more than reinforcing bar 1 throw into down toward fixation, exposed parts For 1m, 1 position of reinforcing bar is located at selected 2 hitch point side of plummet in order to which measurement later, reinforcing bar 1 and ground junction are used Red paint smears label, in order to observe whether reinforcing bar has sedimentation phenomenon, to prevent subsequent calculations from error occur;
Step 3 is divided on each gang mould board ends and middle, the support beam at bottom die of box-beam plate and at flange template Not Xuan Gua a plummet 2, totally six, hang specifically: at the edge of a wing plummet hang on support beam on, plummet 2 at bottom plate It hangs on and clenches on the nail of support beam;
Before step 4, non-precompressed as shown in Figure 2, the inverted cone bottom surface and 1 face of reinforcing bar of plummet 2 maintain an equal level;After precompressed, template sedimentation Drive plummet 2 decline, have height difference H between inverted cone bottom surface and reinforcing bar top surface, by H and measurement non-precompressed front template height H1 with And after adjustment height is calculated in the preloading amount H of template, as shown in figure 3, the respective holder of six points is adjusted first Good, the plane for then constituting every two point, the bracket between totally three planes by drawing a tight straight line between two points It is adjusted.
Bracket needed for this fast adjustment method is set up conveniently, and observation is intuitive, measurement is accurate, is reduced pre-pressing bracket sedimentation and is adjusted Whole required time, accelerates speed of application, improves work efficiency, reduces construction cost.

Claims (1)

1. a kind of fast adjustment method of pre-pressing bracket sedimentation absolute altitude, it is characterized in that: including
After step 1, template install, each bridge is respectively in both ends and intermediate six points of arrangement altogether;
Step 2, at six points chosen respectively by a #12 or more than reinforcing bar throw into down toward fixation, exposed parts For 1m, reinforcement location is located at selected plummet hitch point side in order to measurement later, and reinforcing bar and ground junction are with red Paint application label, in order to observe whether reinforcing bar has sedimentation phenomenon, to prevent subsequent calculations from error occur;
Step 3 is divided on each gang mould board ends and middle, the support beam at bottom die of box-beam plate and at flange template Not Xuan Gua a plummet, totally six, hang specifically: plummet is hung on support beam at the edge of a wing, and plummet is outstanding at bottom plate It is hung on and clenches on the nail of support beam;
Before step 4, non-precompressed, the inverted cone bottom surface and reinforcing bar face of plummet maintain an equal level;After precompressed, template sedimentation is driven under plummet Drop, have height difference H between inverted cone bottom surface and reinforcing bar top surface, by H with measure non-precompressed front template height H1 and template it is pre- After adjustment height is calculated in pressure settling amount H, the respective holder of six points is adjusted first, then constitutes every two point Plane, the bracket between totally three planes by between two points draw a tight straight line be adjusted.
CN201811449928.2A 2018-11-30 2018-11-30 The fast adjustment method of pre-pressing bracket sedimentation absolute altitude Pending CN109322250A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811449928.2A CN109322250A (en) 2018-11-30 2018-11-30 The fast adjustment method of pre-pressing bracket sedimentation absolute altitude

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811449928.2A CN109322250A (en) 2018-11-30 2018-11-30 The fast adjustment method of pre-pressing bracket sedimentation absolute altitude

Publications (1)

Publication Number Publication Date
CN109322250A true CN109322250A (en) 2019-02-12

Family

ID=65258101

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811449928.2A Pending CN109322250A (en) 2018-11-30 2018-11-30 The fast adjustment method of pre-pressing bracket sedimentation absolute altitude

Country Status (1)

Country Link
CN (1) CN109322250A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110589526A (en) * 2019-08-31 2019-12-20 上海二十冶建设有限公司 Safe unloading method for integral cold box of large air separation device

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100761934B1 (en) * 2007-07-23 2007-09-28 주식회사 동우기술단 Bridge safety examination system
CN201787936U (en) * 2010-08-30 2011-04-06 中国一冶集团有限公司 Device for observing prepressing precipitation of bridge bracket
CN102297680A (en) * 2011-07-21 2011-12-28 中铁十局集团有限公司 Support and template subsidence deformation observation method and support subsidence deformation observation apparatus
CN102489916A (en) * 2011-11-28 2012-06-13 长春轨道客车股份有限公司 Deflection adjusting method for camber beam location of car roof installation and welding clamp
CN204712261U (en) * 2015-06-08 2015-10-21 阳光电源股份有限公司 A kind of prefabricated tubular pile mould and the pile tube adopting this mould to make
KR101691378B1 (en) * 2014-07-23 2017-01-09 홍석희 The hybrid girder structures prestressed by using the external prestressing mechanism, and the construction method by rigid connection
CN206648557U (en) * 2016-12-21 2017-11-17 中铁三局集团有限公司 A kind of device for being used to measure girder construction height
CN207095546U (en) * 2017-08-27 2018-03-13 贵州新联***工程集团有限公司 A kind of bridge pre-pressing bracket observation device

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100761934B1 (en) * 2007-07-23 2007-09-28 주식회사 동우기술단 Bridge safety examination system
CN201787936U (en) * 2010-08-30 2011-04-06 中国一冶集团有限公司 Device for observing prepressing precipitation of bridge bracket
CN102297680A (en) * 2011-07-21 2011-12-28 中铁十局集团有限公司 Support and template subsidence deformation observation method and support subsidence deformation observation apparatus
CN102489916A (en) * 2011-11-28 2012-06-13 长春轨道客车股份有限公司 Deflection adjusting method for camber beam location of car roof installation and welding clamp
KR101691378B1 (en) * 2014-07-23 2017-01-09 홍석희 The hybrid girder structures prestressed by using the external prestressing mechanism, and the construction method by rigid connection
CN204712261U (en) * 2015-06-08 2015-10-21 阳光电源股份有限公司 A kind of prefabricated tubular pile mould and the pile tube adopting this mould to make
CN206648557U (en) * 2016-12-21 2017-11-17 中铁三局集团有限公司 A kind of device for being used to measure girder construction height
CN207095546U (en) * 2017-08-27 2018-03-13 贵州新联***工程集团有限公司 A kind of bridge pre-pressing bracket observation device

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
乔长君: "《水电工入门》", 31 January 2013, 国防工业出版社 *
李光前、刘一: "《高速铁路施工技术与管理论文集》", 31 October 2010, 中国铁道出版社 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110589526A (en) * 2019-08-31 2019-12-20 上海二十冶建设有限公司 Safe unloading method for integral cold box of large air separation device

Similar Documents

Publication Publication Date Title
CN101915558B (en) Geometric linear detection method of bridge member
CN106840014A (en) A kind of method for monitoring face along tunnel axial deformation
CN204788890U (en) Full flow field velocity of flow measuring device of laboratory basin experiment
CN105569097A (en) Test device and method for drawing bucket foundation model at any angles
CN203824548U (en) Bridge structure concrete surface observation area measuring instrument
CN109322250A (en) The fast adjustment method of pre-pressing bracket sedimentation absolute altitude
CN103438872A (en) Indoor and field integrated system based on dam three-dimension forward intersection measurement
CN108088366B (en) Non-contact detection device and method for size and deformation of structural model
CN208206518U (en) A kind of medical Pathologic specimen slicing device
CN106289125B (en) A kind of ship closes up greatly the measurement method of step simulations carrying
CN206113861U (en) Device for measuring normal vector of arbitrary point of free -form surface
CN105522555B (en) A kind of three-dimensional line technique in steel truss member bar group hole
CN104457696B (en) Non-leveling type horizontal measuring method
CN107246995A (en) A kind of multi-functional clamp determined for concrete splitting tensile strength
CN105021094A (en) Small-aspect-ratio missile horizontal measuring method
CN211060834U (en) Template concatenation displacement monitoring devices
CN210513142U (en) Single-person operated pay-off instrument
CN204854715U (en) Ship lift ship reception chamber position survey of fire hole device
CN211590755U (en) Self-absorption fixed type multipoint punching positioning tool for irregular plates
CN104291201B (en) Moving sidewalk running fix device
CN104034578A (en) Rack device for Shore hardness tester
CN102717870B (en) Mounting method of large hatch coaming on floating boat
CN204115719U (en) Tunnel cross-section measurement point laying out apparatus
CN204954673U (en) Positioner of pre -buried probe usefulness in concrete sample
CN202484537U (en) Device for adjusting inclined angle of platform

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190212

RJ01 Rejection of invention patent application after publication