CN109137990A - A kind of prefabricated cushion cap of land delay-pour joint sectional type and its production and installation method - Google Patents

A kind of prefabricated cushion cap of land delay-pour joint sectional type and its production and installation method Download PDF

Info

Publication number
CN109137990A
CN109137990A CN201810789841.3A CN201810789841A CN109137990A CN 109137990 A CN109137990 A CN 109137990A CN 201810789841 A CN201810789841 A CN 201810789841A CN 109137990 A CN109137990 A CN 109137990A
Authority
CN
China
Prior art keywords
cushion cap
piecemeal
pile foundation
reinforcing bar
preformed hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810789841.3A
Other languages
Chinese (zh)
Inventor
张金树
史红军
鲁朝光
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Guangzhou Engineering Group Co Ltd CRECGZ
Original Assignee
China Railway Guangzhou Engineering Group Co Ltd CRECGZ
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Guangzhou Engineering Group Co Ltd CRECGZ filed Critical China Railway Guangzhou Engineering Group Co Ltd CRECGZ
Priority to CN201810789841.3A priority Critical patent/CN109137990A/en
Publication of CN109137990A publication Critical patent/CN109137990A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/12Manhole shafts; Other inspection or access chambers; Accessories therefor
    • E02D29/14Covers for manholes or the like; Frames for covers
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B23/00Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
    • B28B23/0025Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects with installation or service material, e.g. tubes for electricity or water
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B23/00Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
    • B28B23/02Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B7/00Moulds; Cores; Mandrels
    • B28B7/0002Auxiliary parts or elements of the mould
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B7/00Moulds; Cores; Mandrels
    • B28B7/16Moulds for making shaped articles with cavities or holes open to the surface, e.g. with blind holes
    • B28B7/18Moulds for making shaped articles with cavities or holes open to the surface, e.g. with blind holes the holes passing completely through the article

Landscapes

  • Engineering & Computer Science (AREA)
  • Manufacturing & Machinery (AREA)
  • Chemical & Material Sciences (AREA)
  • Ceramic Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses a kind of land prefabricated cushion caps of delay-pour joint sectional type, including the first cushion cap piecemeal and the second cushion cap piecemeal, first cushion cap piecemeal and the second cushion cap piecemeal are equipped with several pile foundation preformed holes, pile foundation preformed hole reinforcing bar cage is equipped with around pile foundation preformed hole, it is additionally provided with several pile foundation connection reinforcing bars, further include link block, several grout sleeves are equipped in link block, the both ends of each grout sleeve are connected with the first connection reinforcing bar and the second connection reinforcing bar.This land prefabricated cushion cap of delay-pour joint sectional type, pass through the first connection reinforcing bar of grout sleeve connection and the second connection reinforcing bar, it connects the first cushion cap piecemeal and the second cushion cap piecemeal to form prefabricated cushion cap entirety by link block, stable structure is reliable, first cushion cap piecemeal and second cushion cap piecemeal Prefabrication in factory, accelerate the progress of bridge construction, prefabricated cushion cap is divided into the first cushion cap piecemeal and the second cushion cap piecemeal, guarantee the construction safety of transport and lifting, the invention is used for land cushion cap technical field.

Description

A kind of prefabricated cushion cap of land delay-pour joint sectional type and its production and installation method
Technical field
The present invention relates to land cushion cap technical field, more particularly to a kind of prefabricated cushion cap of land delay-pour joint sectional type and It is produced and installation method.
Background technique
Traditional land cushion cap uses cast in situs Construction Mode, i.e. excavation pit → arrangement pile crown reinforcing bar → construction cushion coat → binding cushion cap reinforcing bar → vertical reinforcing template → pours cushion cap concrete → maintenance → demoulding.Bearing platform construction under cast-in-place mode exists Following technical disadvantages: (1) construction quality of concrete is more difficult to control, is easy to appear and runs the common quality defects such as mould, spillage, leakage, applies Work speed is slow, influences bridge superstructure construction speed;(2) waste of raw materials such as cement, steel, rubble are serious, water, electricity, gas Usage amount is big, and bracket, template, fastener etc. are easily lost, and maintenance status is difficult to ensure;(3) construction personnel needed is more, labour Intensity is larger, and construction environment is big by natural environment influence, and under sleet, high temperature, cold snap, bearing platform construction is impacted, worker Work situation is poor;(4) surrounding enviroment are easily caused noise pollution by a large amount of concrete cast-in-situ construction, generate a large amount of building Construction rubbish.
Summary of the invention
The purpose of the present invention is to provide a kind of prefabricated cushion cap of land delay-pour joint sectional type and its production and installation method, Raw material and manual labor are saved, is accelerated construction progress.
The technical solution used in the present invention is:
A kind of land prefabricated cushion cap of delay-pour joint sectional type, including the first cushion cap piecemeal and the second cushion cap piecemeal, first holds Platform piecemeal and the second cushion cap piecemeal are equipped with several pile foundation preformed holes, are equipped with pile foundation preformed hole reinforcing bar around pile foundation preformed hole Cage passes through pile foundation preformed hole inner wall and is equipped with several pile foundations connection reinforcing bar, further includes the first cushion cap piecemeal of connection and the second cushion cap point The link block of block, link block is interior to be equipped with several grout sleeves, and one end of each grout sleeve is connected with the first cushion cap piecemeal of insertion First connection reinforcing bar and the other end are connected with the second connection reinforcing bar of the second cushion cap piecemeal of insertion.
A kind of production of the land prefabricated cushion cap of delay-pour joint sectional type and installation method, comprise the following production steps that
A, processing and fabricating the first cushion cap piecemeal and the bed die of the second cushion cap piecemeal, 4 side forms, several columnar stakes respectively Several side openings are opened up on side form on the inside of base preformed hole template, the first cushion cap piecemeal and the second cushion cap piecemeal, pile foundation reserves casement Several through-holes are opened up on the wall surface of plate;And the cushion cap steel reinforcement cage of the first cushion cap piecemeal and the second cushion cap piecemeal, pile foundation are assembled respectively Preformed hole reinforcing bar cage;
B, the bed die of the first cushion cap piecemeal and the second cushion cap piecemeal is fixed in installation, and cushion cap steel reinforcement cage, pile foundation preformed hole are mended In on corresponding bed die, pile foundation preformed hole template is installed on pile foundation preformed hole for strong steel reinforcement cage, side form, pile foundation preformed hole formwork hoisting In reinforcing bar cage;
C, several first connection reinforcing bars of each side opening installation on the side form on the inside of the first cushion cap piecemeal;It is held across second Several second connection reinforcing bars of each side opening installation on side form on the inside of platform piecemeal;
D, the through-hole in pile foundation preformed hole template is horizontally inserted into pile foundation connection reinforcing bar, and pile foundation connection reinforcing bar one end is protruded into In cushion cap steel reinforcement cage, the other end is stayed in pile foundation preformed hole template;
E, casting concrete conserves concrete after the completion of pouring, and removes side form and pile foundation preformed hole template;
Further include following installation steps:
F, excavation of foundation pit and the base processing of installed position are carried out;
G, the first cushion cap piecemeal of lifting makes in pile foundation insertion pile foundation preformed hole in installation site, wears on the first connection reinforcing bar Enter grout sleeve, then lift the second cushion cap piecemeal to make pile foundation be inserted into pile foundation preformed hole in installation site, grout sleeve is slided to the Grouting material is injected from the injected hole of every grout sleeve in the center of one connection reinforcing bar and the second connection reinforcing bar;
H, link block side form is installed, and casting concrete, the first cushion cap piecemeal and the second cushion cap piecemeal are connected to be formed it is pre- Cushion cap processed is whole;
I, stirrup is bound from bottom to top in pile foundation preformed hole, casting concrete is to prefabricated cushion cap top surface, in prefabricated cushion cap Top is installed by pier stud;
Production stage and installation steps can carry out simultaneously.
It is further used as the improvement of technical solution of the present invention, in step f, to the first cushion cap piecemeal and the second cushion cap piecemeal Installation site is cleared up, and one layer of rubble is laid in fitting limit and is tamped, and weak part, fills out compacting using changing in ground Method reinforcement pours one layer of blinding concrete within 20cm on the outside of fitting limit, and with plate vibrator vibration tamp, protects The flatness for demonstrate,proving bed course basis is not more than 2mm.
It is further used as the improvement of technical solution of the present invention, in step f, after the completion of excavation of foundation pit and base processing, and label The center and pile foundation center of the installation site of first cushion cap piecemeal and the second cushion cap piecemeal out, and draw the first cushion cap piecemeal and Four side sidelines of two cushion cap piecemeal installation sites and the round edge line of pile foundation.
It is further used as the improvement of technical solution of the present invention, to the first cushion cap piecemeal and the second cushion cap piecemeal in step g Lifting uses gantry crane, installs two walking tracks in installation site two sides, two dragons are installed between two walking tracks Gantry crane machine, two gantry cranes pass through what is drawn above track handling the first cushion cap piecemeal or the second cushion cap piecemeal to pile foundation Four sides sideline and pile foundation round edge line adjust the position of the first cushion cap piecemeal or the second cushion cap piecemeal, decentralization to and ground distance 10cm, pause decentralization, checks the deviation situation on the first cushion cap piecemeal or four side of the second cushion cap piecemeal and the four edges line drawn, really Recognize errorless rear decentralization.
It is further used as the improvement of technical solution of the present invention, and the installation of pier stud uses Precast Pier Columns mode in step i, The vertical pier stud for connecting with Precast Pier Columns is installed in pile foundation preformed hole and connects reinforcing bar, then casting concrete, then is pacified Fill Precast Pier Columns.
It is further used as the improvement of technical solution of the present invention, and the installation of pier stud uses cast-in-place pier stud mode in step i, Foot stall steel muscle cage and Pier Formwork are assembled above prefabricated cushion cap, then pour coagulation from bottom to top from the bottom of pile foundation preformed hole At the top of soil to Pier Formwork.
It is further used as the improvement of technical solution of the present invention, in step a, selects prefabricated place, pre-fabricated factory is built, to pre- Place processed integrally carries out positioning division, determines template processing assembling station, reinforcing bar assembling station, Prefabrication station, maintenance storage Deposit station.
It is further used as the improvement of technical solution of the present invention, and pile foundation preformed hole template includes several templates mutually spliced point Block, in step a, through-hole is opened in the stitching portion of each template piecemeal.
It is further used as the improvement of technical solution of the present invention, pile foundation preformed hole reinforcing bar cage and pile foundation preformed hole template it Between cushion block is installed.
Beneficial effects of the present invention: this land prefabricated cushion cap of delay-pour joint sectional type is connected by grout sleeve connection first Reinforcing bar and the second connection reinforcing bar are connect, connecting the first cushion cap piecemeal and the second cushion cap piecemeal by link block, to form prefabricated cushion cap whole Body, stable structure is reliable, the first cushion cap piecemeal and second cushion cap piecemeal Prefabrication in factory, thus by traditional bearing platform construction Most of work be transferred to factory's completion, improve the pouring construction quality of concrete, save raw material and hand labor Power, and the progress of bridge construction is accelerated, prefabricated cushion cap is divided into the first cushion cap piecemeal and the second cushion cap piecemeal, is conducive to reduce Transport and hoisting process in weight and size, guarantee transport and lifting go on smoothly and construction safety.
Detailed description of the invention
The present invention will be further explained below with reference to the attached drawings:
Fig. 1 is the overall structure diagram of the prefabricated cushion cap of the embodiment of the present invention;
Fig. 2 is the top view of the prefabricated cushion cap of the embodiment of the present invention;
Fig. 3 is the side view of the prefabricated cushion cap of the embodiment of the present invention;
Fig. 4 is the structural schematic diagram of the first cushion cap piecemeal of the embodiment of the present invention;
Fig. 5 is the production procedure block diagram of the first cushion cap piecemeal of the embodiment of the present invention and the second cushion cap piecemeal;
Fig. 6 is the installation procedure block diagram of the first cushion cap piecemeal of the embodiment of the present invention and the second cushion cap piecemeal;
Fig. 7 is the lifting schematic diagram of the first cushion cap piecemeal of the embodiment of the present invention and the second cushion cap piecemeal;
Fig. 8 is the lifting schematic diagram of the first cushion cap piecemeal of the embodiment of the present invention and the second cushion cap piecemeal;
Fig. 9 is the structural schematic diagram of grout sleeve of the embodiment of the present invention;
Figure 10 is the planar structure schematic diagram of grout sleeve of the embodiment of the present invention;
Figure 11 is the top view of pile foundation of embodiment of the present invention preformed hole reinforcing bar cage and pile foundation preformed hole template;
Figure 12 is the structural schematic diagram of pile foundation preformed hole template of the embodiment of the present invention;
Figure 13 is the expanded view of pile foundation preformed hole template of the embodiment of the present invention.
Specific embodiment
Referring to Fig.1~Figure 13, the present invention are a kind of land prefabricated cushion cap of delay-pour joint sectional type, including the first cushion cap piecemeal 11 and the second cushion cap piecemeal 12, the first cushion cap piecemeal 11 and the second cushion cap piecemeal 12 be equipped with several pile foundation preformed holes 2, surround stake Base preformed hole 2 is equipped with pile foundation preformed hole reinforcing bar cage 5, passes through 2 inner wall of pile foundation preformed hole and is equipped with several pile foundations connection reinforcing bar 3, Further include the link block 9 for connecting the first cushion cap piecemeal 11 and the second cushion cap piecemeal 12, is equipped with several grout sleeves in link block 9 91, one end of each grout sleeve 91 is connected with the first connection reinforcing bar 111 and the other end connection of the first cushion cap piecemeal 11 of insertion There is the second connection reinforcing bar 121 of the second cushion cap piecemeal 12 of insertion.
This land prefabricated cushion cap of delay-pour joint sectional type, first prefabricated first cushion cap piecemeal 11 and the second cushion cap piecemeal respectively 12, then lifting the first cushion cap piecemeal 11 and the second cushion cap piecemeal 12 is installed on it in pile foundation 8, is connected by grout sleeve 91 First connection reinforcing bar 111 and the second connection reinforcing bar 121, then pour link block 9 and make the first cushion cap piecemeal 11 and the second cushion cap piecemeal It is whole that 12 connections form prefabricated cushion cap 1.
First cushion cap piecemeal 11 and the second Prefabrication in factory of cushion cap piecemeal 12, thus by the big of traditional bearing platform construction Part work has been transferred to factory's completion, improves the pouring construction quality of concrete, saves raw material and manual labor, and Accelerate the progress of bridge construction.Prefabricated cushion cap 1 is divided into the first cushion cap piecemeal 11 and the second cushion cap piecemeal 12, is conducive to reduce Transport and hoisting process in weight and size, guarantee transport and lifting go on smoothly and construction safety.It is reserved by pile foundation Hole 2, pile foundation preformed hole reinforcing bar cage 5 and pile foundation connection reinforcing bar 3 realize effective connection of prefabricated cushion cap 1 and pile foundation 8, guarantee pre- The installation of cushion cap 1 processed is fixed reliable.
A kind of production of the land prefabricated cushion cap of delay-pour joint sectional type and installation method, comprise the following production steps that
A1, the prefabricated place of selection, build pre-fabricated factory, integrally carry out positioning division to prefabricated place, determine that template is processed Station, reinforcing bar assembling station, Prefabrication station, maintenance storage station are assembled, sub-station produces prefabricated first cushion cap piecemeal 11 With the second cushion cap piecemeal 12, be conducive to the orderly progress and the guarantee quality of production of production.
A2, it is processed on assembling station in template and processes template, respectively the first cushion cap of processing and fabricating piecemeal 11 and the second cushion cap The bed die of piecemeal 12,4 side forms, several columnar pile foundation preformed hole templates 4, the first cushion cap piecemeal 11 and the second cushion cap piecemeal Several side openings are opened up on the side form of 12 insides, open up several through-holes on the wall surface of pile foundation preformed hole template 4;Station is assembled in reinforcing bar Upper banding steel cage assembles the cushion cap steel reinforcement cage of the first cushion cap piecemeal 11 and the second cushion cap piecemeal 12 respectively, pile foundation preformed hole is mended Strong steel reinforcement cage 5.
B, the bed die of the first cushion cap piecemeal 11 and the second cushion cap piecemeal 12 is mounted on Prefabrication station, will be held Platform steel reinforcement cage, pile foundation preformed hole reinforcing bar cage 5, side form, pile foundation preformed hole template 4 are lifted on corresponding bed die, and pile foundation is pre- Template of boxing out 4 is installed in pile foundation preformed hole reinforcing bar cage 5, as shown in figure 11.
C, several first connection reinforcing bars 111 of each side opening installation on the side form of 11 inside of the first cushion cap piecemeal;It passes through Several second connection reinforcing bars 121 of each side opening installation on the side form of second cushion cap piecemeal, 12 inside.
D, the through-hole in pile foundation preformed hole template 4 is horizontally inserted into pile foundation connection reinforcing bar 3, and pile foundation connects 3 one end of reinforcing bar It protrudes into cushion cap steel reinforcement cage, the other end stays in pile foundation preformed hole template 4.Pile foundation preformed hole reinforcing bar cage 5 is connected with pile foundation Reinforcing bar 3 ensure that being reliably connected for subsequent first cushion cap piecemeal 11 and the second cushion cap piecemeal 12 and pile foundation 8, to guarantee to top The secure support of pier stud.
E, concreting in lifts wants symmetrical casting concrete on 4 periphery of pile foundation preformed hole template, prevents pile foundation preformed hole Sidesway occurs for template 4, and the first cushion cap piecemeal 11 and the second cushion cap piecemeal 12, flat-pushing first cushion cap piecemeal are obtained after the completion of pouring 11 and second cushion cap piecemeal 12 to maintenance store station, concrete is conserved, after conserve 12 hours under room temperature, dismounting side form With pile foundation preformed hole template 4, various defects are repaired, continue maintenance to 85% or more intensity.After removing pile foundation preformed hole template 4, The pile foundation preformed hole 2 connecting with pile foundation 8 is formed at pile foundation preformed hole template 4.
The above are the Prefabrication step of the first cushion cap piecemeal 11 and the second cushion cap piecemeal 12, the first cushion cap piecemeals 11 and Transport is installed to building site after the completion of the production of two cushion cap piecemeals 12, further includes installation steps.First cushion cap piecemeal 11 is being installed While with the second cushion cap piecemeal 12, production, i.e. the first cushion cap piecemeal 11 and the second cushion cap point can proceed in pre-fabricated factory The production of block 12 and installation steps can carry out simultaneously, greatly speed up construction speed.Installation steps are as follows:
F1, the excavation of foundation pit for carrying out installed position and base processing, to the first cushion cap piecemeal 11 and the second cushion cap piecemeal 12 installation site is cleared up, and one layer of rubble is laid in fitting limit and is tamped, and weak part, fills out rammer using changing in ground Real method reinforcement pours one layer of blinding concrete within 20cm on the outside of fitting limit, and with plate vibrator vibro-rammer It is real, guarantee that the flatness on bed course basis is not more than 2mm.
F2, mark the first cushion cap piecemeal 11 and the second cushion cap piecemeal 12 installation site 8 center of center and pile foundation, and Draw four side sidelines of 12 installation site of the first cushion cap piecemeal 11 and the second cushion cap piecemeal and the round edge line of pile foundation 8.
G1, the first cushion cap piecemeal 11 and the second cushion cap piecemeal 12 are lifted, according to the first cushion cap piecemeal 11 and second The dimension and weight of cushion cap piecemeal 12 is cooperated using single machine large-tonnage truck crane or crawler crane or two-shipper truck crane or crawler crane, If place is more smooth, using wire center as axis, held first using the scheme that gantry crane 72 lifts along line direction Platform piecemeal 11 and 12 installation site two sides of the second cushion cap piecemeal are laid with the two walking tracks 71 in left and right, two walking tracks 71 it Between install two gantry cranes 72, as shown in Figure 7.
G2, the first cushion cap piecemeal 11 of lifting are inserted into pile foundation 8 in pile foundation preformed hole 2 in installation site, concrete operations are as follows: two A gantry crane 72 wirerope or hanging belt the same by four root long degree, material, catch on 11 4 jiaos of the first cushion cap piecemeal Pre-buried gib headed bolt hangs nail, along walking 71 the first cushion cap of handling piecemeal 11 of track to 8 top of pile foundation, slowly transfers, during which not The position all around of the first cushion cap piecemeal 11 of disconnected adjustment corresponds pile foundation preformed hole 2 and the pile crown of pile foundation 8, and pile foundation 8 is inserted Enter in pile foundation preformed hole 2.The position of the first cushion cap piecemeal 11, decentralization are adjusted by the four side sidelines drawn and 8 round edge line of pile foundation When cushion cap is to ground distance 10cm, the deviation on 11 4 side of the first cushion cap piecemeal and the four edges line drawn is checked in pause decentralization Situation confirms errorless rear decentralization, if error is larger, can lift by crane the first cushion cap piecemeal 11 again, transfers installation after adjusting again.
G3, grout sleeve 91 is penetrated on the first connection reinforcing bar 111 of the first cushion cap piecemeal 11.
G4, the second cushion cap piecemeal 12 of lifting make pile foundation 8 be inserted into pile foundation preformed hole 2, the second cushion cap piecemeal 12 in installation site Lifting operation it is identical with the first cushion cap piecemeal 11, the first cushion cap piecemeal 11 and the second cushion cap piecemeal 12 is opposite installs.
G5, the center that grout sleeve 91 is slided to the first connection reinforcing bar 111 and the second connection reinforcing bar 121, are in the milk from every The injected hole 911 of sleeve 91 injects grouting material, until closing injected hole 911 and plasma discharge after uniform grouting material is discharged in plasma discharge hole 912 Hole 912.
H, after grouting material set strength reaches design requirement intensity, link block side form is installed, then casting concrete shape At link block 9, the first cushion cap piecemeal 11 is connected by link block 9 and the second cushion cap piecemeal 12 forms prefabricated cushion cap 1 integrally, first Connection reinforcing bar 111, second connect reinforcing bar 121 and grout sleeve 91 ensure that the first cushion cap piecemeal 11 and the second cushion cap piecemeal 12 with The bonding strength of link block 9.Prefabricated cushion cap 1 is divided into the first cushion cap piecemeal 11 and the second cushion cap piecemeal 12, is conducive to reduce fortune Weight and size in defeated and hoisting process, guarantee transport and lifting go on smoothly and construction safety.Link block 9 pours completion Afterwards, layering the first cushion cap piecemeal 11 of symmetrical backfill and 12 periphery foundation pit of the second cushion cap piecemeal, and successively tamp.
The above are the liftings of the first cushion cap piecemeal 11 and the second cushion cap piecemeal 12, need to be in pile foundation preformed hole 2 after the completion of lifting Interior casting concrete is to be connected and fixed prefabricated cushion cap 1 and pile foundation 8, when the pier stud for installing prefabricated 1 top of cushion cap is applied using different When work method, the casting method of 2 inner concrete of pile foundation preformed hole is different, following steps:
When the installation of i1, pier stud use Precast Pier Columns mode, installed in pile foundation preformed hole 2 it is vertical for it is pre- The pier stud of pier stud connection processed connects reinforcing bar, binds stirrup from bottom to top to prefabricated 1 top surface of cushion cap, installs fixed pier stud and connect reinforcing bar Locator, then concreting in lifts to prefabricated 1 top surface of cushion cap, then install Precast Pier Columns.
When the installation of i2, pier stud use cast-in-place pier stud mode, i.e. cast in situs pier stud, on 2 periphery of pile foundation preformed hole, 3cm thickness Pier Formwork mounting seat is laid with high grade mortar levelling, it is ensured that horizontal, high grade mortar inner edge must not invade pier stud Inside template, in order to avoid cause pier stud necking down.On prefabricated cushion cap 1, steel pipe support is erected, binds pier stud steel reinforcement cage, it is pre- in pile foundation It boxes out the stirrup of from coil to coil installation from bottom to top in 2, then merogenesis lifts Pier Formwork.Finally since 2 bottom of pile foundation preformed hole, from On down, the casting concrete by the way of tumbling barrel placement layer by layer, until at the top of Pier Formwork.Prefabricated cushion cap 1 and pier stud coagulation At native label variation, i.e., the interface of prefabricated cushion cap 1 and pier stud can be after the concrete initial set in pile foundation preformed hole 2, then pours Pier stud concrete.After the completion of pouring after curing concrete to job specfication proof strength, Pier Formwork is removed, next peace is arrived in circulation Fill station.The construction technology poured together with pier stud using pile foundation preformed hole 2 guarantees the company of pile foundation 8, prefabricated cushion cap 1 and pier stud It connects reliably, to guarantee integrally-built stability and the secure support to bridge.
As a preferred embodiment of the present invention, as shown in Figure 12 and Figure 13, pile foundation preformed hole template 4 includes several mutual The template piecemeal 41 of splicing, in step a2, through-hole is opened in the stitching portion of each template piecemeal 41, uses spiral shell between each template piecemeal 41 It tethers and connects.Pile foundation preformed hole template 4 uses block design, so that installation and removal are more convenient.
As a preferred embodiment of the present invention, pacify between pile foundation preformed hole reinforcing bar cage 5 and pile foundation preformed hole template 4 Equipped with cushion block 6, to protect pile foundation preformed hole reinforcing bar cage 5.
As a preferred embodiment of the present invention, the aperture of pile foundation preformed hole template 4 is slightly larger than the diameter of pile foundation 8, pile foundation The quantity of preformed hole template 4 and pile foundation 8 is 4.Pile foundation preformed hole reinforcing bar cage 5 adds the sample of stirrup using lengthways main steel bar Formula, the big 2-3cm of 8 radius of radius ratio pile foundation.
Have the advantage that (1) first by 11 He of the first cushion cap piecemeal using this land prefabricated cushion cap of delay-pour joint sectional type Second cushion cap piecemeal 12 is pre-formed, then handling is installed in place, and most of work of traditional bearing platform construction is transferred in factory It completes, accelerates bridge lower part engineering construction progress, realize industrialized production and installation;(2) prefabricated cushion cap 1 is divided into first to hold Platform piecemeal 11 and the second cushion cap piecemeal 12 guarantee that construction is reliable and safety, solve large-scale, the prefabricated cushion cap 1 of ultra-large type lifting, Transport, installation problem, have reached factory, scene is taken into account, and reduce the load carrying behaviour requirement to lifting, transporting equipment;(3) it reduces The construction qualities common faults such as race mould, spillage under the cast-in-place mode of reinforced concrete pile cap tradition, improve reinforced concrete pile cap Construction quality;(4) engineering generally saves the construction materials such as cement, reinforcing bar, rubble, saves water, electricity, gas resource, mentions The utilization rate of the various circulation materials such as high trestle, template, fastener, reduces project inputs and cost;(5) artificial make is reduced Dosage reduces labor intensity of workers, a part of site operation personnel is switched to millworker, fundamentally ensure the body of worker And physical and mental health, improve the construction operation environment of worker;(6) noise effect in construction is reduced and reduced, is reduced The generation of construction rubbish.
Certainly, the invention is not limited to above embodiment, and those skilled in the art are without prejudice to originally Equivalent modifications or replacement can be also made under the premise of spirit, these equivalent variation or replacement are all contained in the application right It is required that in limited range.

Claims (10)

1. a kind of land prefabricated cushion cap of delay-pour joint sectional type, it is characterised in that: held including the first cushion cap piecemeal (11) and second Platform piecemeal (12), the first cushion cap piecemeal (11) and the second cushion cap piecemeal (12) are equipped with several pile foundation preformed holes (2), surround The pile foundation preformed hole (2) is equipped with pile foundation preformed hole reinforcing bar cage (5), passes through the pile foundation preformed hole (2) if inner wall is equipped with Dry pile foundation connection reinforcing bar (3), further includes the link block for connecting the first cushion cap piecemeal (11) and the second cushion cap piecemeal (12) (9), several grout sleeves (91) are equipped in the link block (9), one end of each grout sleeve (91) is connected with insertion institute The first connection reinforcing bar (111) and the other end for stating the first cushion cap piecemeal (11) are connected with insertion the second cushion cap piecemeal (12) Second connection reinforcing bar (121).
2. production and the installation method of a kind of land prefabricated cushion cap of delay-pour joint sectional type, which is characterized in that including following production Step:
A, bed die, 4 side forms, several cylindrical shapes of difference the first cushion cap of processing and fabricating piecemeal (11) and the second cushion cap piecemeal (12) Pile foundation preformed hole template (4), the first cushion cap piecemeal (11) and the second cushion cap piecemeal (12) if on the inside of side form on open up dry side Hole opens up several through-holes on the wall surface of pile foundation preformed hole template (4);And the first cushion cap piecemeal (11) and the second cushion cap are assembled respectively Cushion cap steel reinforcement cage, the pile foundation preformed hole reinforcing bar cage (5) of piecemeal (12);
B, the bed die of the first cushion cap piecemeal (11) and the second cushion cap piecemeal (12) is fixed in installation, and cushion cap steel reinforcement cage, pile foundation are reserved Hole reinforcing bar cage (5), side form, pile foundation preformed hole template (4) are lifted on corresponding bed die, pile foundation preformed hole template (4) peace Loaded in pile foundation preformed hole reinforcing bar cage (5);
C, several first connections reinforcing bar (111) of each side opening installation on the side form on the inside of the first cushion cap piecemeal (11) are passed through;It passes through Several second connections reinforcing bar (121) of each side opening installation on side form on the inside of second cushion cap piecemeal (12);
D, it passes through the through-hole in pile foundation preformed hole template (4) and is horizontally inserted into pile foundation connection reinforcing bar (3), pile foundation connects reinforcing bar (3) one End is protruded into cushion cap steel reinforcement cage, and the other end stays in pile foundation preformed hole template (4);
E, casting concrete conserves concrete after the completion of pouring, and removes side form and pile foundation preformed hole template (4);
Further include following installation steps:
F, excavation of foundation pit and the base processing of installed position are carried out;
G, the first cushion cap piecemeal (11) of lifting makes in pile foundation (8) insertion pile foundation preformed hole (2) in installation site, connects steel first Grout sleeve (91) are penetrated on muscle (111), then lift the second cushion cap piecemeal (12) to keep pile foundation (8) insertion pile foundation pre- in installation site It boxes out (2), grout sleeve (91) is slided to the center of the first connection reinforcing bar (111) and the second connection reinforcing bar (121), is filled from every The injected hole (911) for starching sleeve (91) injects grouting material;
H, link block side form, and casting concrete are installed, the first cushion cap piecemeal (11) and the second cushion cap piecemeal (12) are connected into shape It is whole at prefabricated cushion cap (1);
I, stirrup is bound from bottom to top in pile foundation preformed hole (2), casting concrete is held to prefabricated cushion cap (1) top surface prefabricated Pier stud is installed above platform (1);
The production stage and installation steps can carry out simultaneously.
3. the production of the land prefabricated cushion cap of delay-pour joint sectional type according to claim 2 and installation method, feature exist In: in the step f, the installation site of the first cushion cap piecemeal (11) and the second cushion cap piecemeal (12) is cleared up, is being installed It is laid with one layer of rubble in range simultaneously to tamp, weak part in ground, using changing the method reinforcement for filling out compacting, on the outside of fitting limit Within 20cm, one layer of blinding concrete is poured, and with plate vibrator vibration tamp, guarantee that the flatness on bed course basis is not more than 2mm。
4. the production of the land prefabricated cushion cap of delay-pour joint sectional type according to claim 2 and installation method, feature exist In: in the step f, after the completion of excavation of foundation pit and base processing, mark the first cushion cap piecemeal (11) and the second cushion cap piecemeal (12) center of installation site and pile foundation (8) center, and draw the first cushion cap piecemeal (11) and the second cushion cap piecemeal (12) peace Four side sidelines of holding position and the round edge line of pile foundation (8).
5. the production of the land prefabricated cushion cap of delay-pour joint sectional type according to claim 4 and installation method, feature exist In: gantry crane (72) are used to the lifting of the first cushion cap piecemeal (11) and the second cushion cap piecemeal (12) in the step g, are being pacified Two walking tracks (71) are installed in holding position two sides, two gantry cranes (72) of installation between two walking tracks (71), and two A gantry crane (72) passes through above track handling the first cushion cap piecemeal (11) or the second cushion cap piecemeal (12) to pile foundation (8) The four side sidelines drawn and pile foundation (8) round edge line adjust the position of the first cushion cap piecemeal (11) or the second cushion cap piecemeal (12), under Put to ground distance 10cm, pause decentralization checks the first cushion cap piecemeal (11) or (12) four side of the second cushion cap piecemeal and draws Four edges line deviation situation, confirm it is errorless after decentralization.
6. the production of the land prefabricated cushion cap of delay-pour joint sectional type according to claim 2 and installation method, feature exist In: the installation of pier stud uses Precast Pier Columns mode in the step i, and installation is vertical in pile foundation preformed hole (2) is used for The pier stud connecting with Precast Pier Columns connects reinforcing bar, then casting concrete, then installs Precast Pier Columns.
7. the production of the land prefabricated cushion cap of delay-pour joint sectional type according to claim 2 and installation method, feature exist In: the installation of pier stud uses cast-in-place pier stud mode in the step i, and foot stall steel muscle cage is assembled above prefabricated cushion cap (1) And Pier Formwork, then at the top of the bottom of pile foundation preformed hole (2) from bottom to top casting concrete to Pier Formwork.
8. the production of the land prefabricated cushion cap of delay-pour joint sectional type according to claim 2 and installation method, feature exist In: in the step a, prefabricated place is selected, pre-fabricated factory is built, positioning division is integrally carried out to prefabricated place, determines template Processing assembling station, reinforcing bar assembling station, Prefabrication station, maintenance storage station.
9. the production of the land prefabricated cushion cap of delay-pour joint sectional type according to claim 2 and installation method, feature exist It include several template piecemeals (41) mutually spliced in: the pile foundation preformed hole template (4), in the step a, through-hole is opened in The stitching portion of each template piecemeal (41).
10. the production of the land prefabricated cushion cap of delay-pour joint sectional type according to claim 2 and installation method, feature exist In: it is equipped between pile foundation preformed hole reinforcing bar cage (5) and pile foundation preformed hole template (4) cushion block (6).
CN201810789841.3A 2018-07-18 2018-07-18 A kind of prefabricated cushion cap of land delay-pour joint sectional type and its production and installation method Pending CN109137990A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810789841.3A CN109137990A (en) 2018-07-18 2018-07-18 A kind of prefabricated cushion cap of land delay-pour joint sectional type and its production and installation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810789841.3A CN109137990A (en) 2018-07-18 2018-07-18 A kind of prefabricated cushion cap of land delay-pour joint sectional type and its production and installation method

Publications (1)

Publication Number Publication Date
CN109137990A true CN109137990A (en) 2019-01-04

Family

ID=64801043

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810789841.3A Pending CN109137990A (en) 2018-07-18 2018-07-18 A kind of prefabricated cushion cap of land delay-pour joint sectional type and its production and installation method

Country Status (1)

Country Link
CN (1) CN109137990A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110202690A (en) * 2019-07-22 2019-09-06 浙江省交通规划设计研究院有限公司 A kind of prefabricated cushion cap construction of two columned pier and its construction method
CN111002462A (en) * 2019-07-19 2020-04-14 中国二十冶集团有限公司 Processing method of reinforcing through-length steel bar at bottom of prefabricated overlapped wallboard
CN111851564A (en) * 2020-06-29 2020-10-30 中国国家铁路集团有限公司 Spliced bearing platform plate structure connected with pile foundation and construction method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101476326A (en) * 2009-01-23 2009-07-08 广州市市政集团有限公司 Bearing platform prefabrication and construction method
CN201981547U (en) * 2011-02-09 2011-09-21 中交第四航务工程勘探设计院有限公司 Above-water bearing platform structure combined precasting installation with cast-in-place
CN204456162U (en) * 2015-02-12 2015-07-08 江苏建院营造有限公司 A kind of pulling-resistant type prefabricated tubular pile be connected with cushion cap
CN105970987A (en) * 2016-06-22 2016-09-28 山东明达建筑科技有限公司 Assembled construction prefabricated foundation
CN206987200U (en) * 2016-12-28 2018-02-09 中冶建筑研究总院有限公司 A kind of short grout sleeve of bar connecting
CN207017294U (en) * 2017-08-04 2018-02-16 上海宝冶集团有限公司 Equipment anchor bolt buries the construction tool of reserving hole
CN207240442U (en) * 2017-08-11 2018-04-17 湖南中铁五新钢模有限责任公司 Grout sleeve positioning mold is used in a kind of prefabricated components main reinforcement connection

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101476326A (en) * 2009-01-23 2009-07-08 广州市市政集团有限公司 Bearing platform prefabrication and construction method
CN201981547U (en) * 2011-02-09 2011-09-21 中交第四航务工程勘探设计院有限公司 Above-water bearing platform structure combined precasting installation with cast-in-place
CN204456162U (en) * 2015-02-12 2015-07-08 江苏建院营造有限公司 A kind of pulling-resistant type prefabricated tubular pile be connected with cushion cap
CN105970987A (en) * 2016-06-22 2016-09-28 山东明达建筑科技有限公司 Assembled construction prefabricated foundation
CN206987200U (en) * 2016-12-28 2018-02-09 中冶建筑研究总院有限公司 A kind of short grout sleeve of bar connecting
CN207017294U (en) * 2017-08-04 2018-02-16 上海宝冶集团有限公司 Equipment anchor bolt buries the construction tool of reserving hole
CN207240442U (en) * 2017-08-11 2018-04-17 湖南中铁五新钢模有限责任公司 Grout sleeve positioning mold is used in a kind of prefabricated components main reinforcement connection

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
中南建筑设计院股份有限公司: "《建筑工程设计文件编制深度规定》", 31 May 2017, 中国建材工业出版社 *
欧震修: "《建筑工程施工监理手册(第二版)》", 31 May 2001, 中国建筑工业出版社 *
罗建华等: "《桥梁施工技术》", 31 August 2009, 西南交通大学出版社 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111002462A (en) * 2019-07-19 2020-04-14 中国二十冶集团有限公司 Processing method of reinforcing through-length steel bar at bottom of prefabricated overlapped wallboard
CN110202690A (en) * 2019-07-22 2019-09-06 浙江省交通规划设计研究院有限公司 A kind of prefabricated cushion cap construction of two columned pier and its construction method
CN111851564A (en) * 2020-06-29 2020-10-30 中国国家铁路集团有限公司 Spliced bearing platform plate structure connected with pile foundation and construction method

Similar Documents

Publication Publication Date Title
CN106120568B (en) The construction method of cross a river Main Bridge bridge pier secondary locking temporary consolidation structure
CN111119059B (en) Ultrahigh composite support system for high-pier cast-in-place box girder and construction method
CN107419802A (en) A kind of Precast Concrete Frame and construction method
CN111535197B (en) Pier column construction method
CN109137990A (en) A kind of prefabricated cushion cap of land delay-pour joint sectional type and its production and installation method
CN107338801B (en) Prestressing force assembled Complex retaining wall structure and construction method
CN109972519B (en) Construction method of prefabricated hollow pier installation structure
CN110219667B (en) Tunnel inverted arch and inverted arch filling layer substituted steel-concrete combined structure and construction process
CN208072415U (en) Deep foundation pit reinforced concrete support part changes structure
CN109083184A (en) A kind of prefabricated cushion cap of land sectional type and its production and installation method
CN207277541U (en) Prefabricated component and cast-in-place column assembled integral concrete frame structure
CN106958259B (en) A kind of concrete towers column foundation and its construction method
CN207047881U (en) The prefabricated cushion cap of core is filled with joint bar
CN103628883A (en) Non-bracket overlong steel bar binding mobile molding method of deep-narrow vertical shaft
CN114575589A (en) Construction method for lifting template of electric hoist of steel reinforced concrete structural column
CN108978699A (en) Land integral prefabricated bearing platform and production and installation method thereof
CN108951683A (en) A kind of prefabricated cushion cap of land superposed type and its production and installation method
CN116677061A (en) Municipal rainwater and sewage inspection well integrated prefabricated installation device and construction method thereof
CN112575771B (en) Environment-friendly construction method for vertical support system of reverse-acting underground engineering steel concrete with piles and columns
CN108457191A (en) Large span T-steel structure beam sections for joining island bridge install closure method
CN211074115U (en) Prefabricated cushion cap structure of double-column type mound
CN210256628U (en) Self-adaptive outer mold system for prefabricating concrete
CN208267093U (en) A kind of Precast Concrete Frame
CN114718112B (en) Pit formwork construction method in straight wall pit
CN115059041B (en) Self-lifting assembled form for lock head empty box structure concrete

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190104