CN109083154A - A kind of ultra-deep super thick enters rock basement diaphragm wall multiple-grooved section connector processing constructing structure - Google Patents

A kind of ultra-deep super thick enters rock basement diaphragm wall multiple-grooved section connector processing constructing structure Download PDF

Info

Publication number
CN109083154A
CN109083154A CN201810960240.4A CN201810960240A CN109083154A CN 109083154 A CN109083154 A CN 109083154A CN 201810960240 A CN201810960240 A CN 201810960240A CN 109083154 A CN109083154 A CN 109083154A
Authority
CN
China
Prior art keywords
ultra
connector
diaphragm wall
super thick
enters rock
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810960240.4A
Other languages
Chinese (zh)
Inventor
张文
张明
梁森
陈锐
卢杨益
王志宏
钟棋栊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Fourth Bureau First Construction Engineering Co Ltd
Original Assignee
China Construction Fourth Bureau First Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Fourth Bureau First Construction Engineering Co Ltd filed Critical China Construction Fourth Bureau First Construction Engineering Co Ltd
Priority to CN201810960240.4A priority Critical patent/CN109083154A/en
Publication of CN109083154A publication Critical patent/CN109083154A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/18Bulkheads or similar walls made solely of concrete in situ
    • E02D5/187Bulkheads or similar walls made solely of concrete in situ the bulkheads or walls being made continuously, e.g. excavating and constructing bulkheads or walls in the same process, without joints

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

The present invention provides a kind of ultra-deep super thick and enters rock basement diaphragm wall multiple-grooved section connector processing method, this method first opens diaphram wall and puts 1m outside slot, link slot pilot hole, in the case where guaranteeing verticality tolerance amount and I-steel outer side wing edge size, churning driven cleaning slot section joint bleeding cement and solidification sandbag are maximally utilized, the workload of subsequent slotter is reduced.To solve the problems, such as the problems of above-mentioned prior art.Belong to building foundation pit supporting technical field.

Description

A kind of ultra-deep super thick enters rock basement diaphragm wall multiple-grooved section connector processing constructing structure
Technical field
The present invention relates to a kind of ultra-deep super thick to enter rock diaphram wall multiple-grooved section connector processing method, belongs to building foundation pit branch Protect technical field.
Background technique
With the development in pluralism of building structure, diaphram wall is increasingly used in pattern foundation pit supporting structure.Traditionally Lower continuous wall groove segment connector processing method is usually to put 600mm outside pilot hole, pours and is finished at jump bit to slot section inner concrete Manage slot section joint sandbag and bleeding cement.This engineering is due to neighbouring subway, steel reinforcement cage bulky dimensions, and long 63.52m is wide The features such as 6.00m, thick 1.38m, forbids in subway protection area using the jump bit that noise is big, efficiency is slow.Jump bit is by connector Place's sandbag and bleeding cement are disposed, and the woven bag clast of sandbag can not also be removed in the slot section of joint, the milling of adjacent slot section Woven bag clast can make slotter plugging when slot.This engineering diaphram wall east, west, the wide 1500mm of north side wall, pilot hole are put outside The construction thinking of 600mm seriously affects slot section connector processing construction function without sufficiently coordinating slotter and churning driven working time Effect.The construction of conventional process connector did not had the comparative simulation carried out before and after technological improvement using BIM three-dimensional Actual Simulation technology also.
Summary of the invention
It is an object of the invention to: a kind of ultra-deep super thick is provided and enters rock basement diaphragm wall multiple-grooved section connector processing method, To solve the problems, such as the problems of above-mentioned prior art.
To solve the above problems, such a ultra-deep super thick of proposed adoption enters rock basement diaphragm wall multiple-grooved section connector processing side Method, this method first open diaphram wall and put 1m outside slot, link slot pilot hole, are guaranteeing outside verticality tolerance amount and I-steel In the case where side wing edge size, churning driven cleaning slot section joint bleeding cement and solidification sandbag are maximally utilized, is reduced subsequent The workload of slotter.
When uncontrollable factor occurs in slot section joint buried concrete, using I-steel, triple high-pressure rotary jet grouting piles and rear note The common sealing of slurry technology, ensure that the impermeability at underground continuous wall connector;
After first slotted line, the casting concrete initial set of link slot section, connector case is pulled out, is connect using the churning driven cleaning with brush wall device Head provides precondition for closed slots section reinforcing bar cage hoisting.
Before underground continuous wall connector processing, underground continuous wall connector is handled first with BIM three-dimensional Actual Simulation technology It improves front and back way to be simulated, the operability of churning driven processing connector after ex ante analysis improves, and to jump bit before improving Churning driven facture carries out simulation comparison after facture and improvement, carries out special discussion for the problem of simulation process exposure, really Protect largest optimization technical solution, science, Accuracy and high efficiency in guarantee this technology practical operation.
Compared with prior art, the present invention utmostly uses churning driven construction operation, reduces the processing of slotter connector Construction operation degree, working efficiency significantly improve, and have saved construction cost;Slot section joint buried concrete inevitably occurs Uncontrollable factor ensure that underground continuous wall connector using I-steel, triple high-pressure rotary jet grouting piles and the common sealing of Post Grouting Technique The impermeability at place and the integral rigidity of diaphram wall;Because of the angle 90o that churning driven can not reach the I-steel edge of a wing and web is formed Connector is cleared up using the churning driven with brush wall device in position, thoroughly removes joint solidification sandbag and bleeding cement, while being closure Slot section reinforcing bar cage hoisting provides precondition;Ex ante analysis improve after churning driven processing connector operability, and to improvement before Churning driven facture carries out simulation comparison after jump bit facture and improvement, begs for for the problem progress special project of simulation process exposure By, it is ensured that largest optimization the technical program, guarantee science in this technology practical operation, Accuracy and high efficiency;This method It covers and is put into grouting behind shaft or drift lining waterproof construction overall process outside pilot hole early period, sundry item implementation can be extended to.
Specific embodiment
To make the object, technical solutions and advantages of the present invention clearer, the present invention will be made below further detailed Explanation.
Embodiment:
The present embodiment provides a kind of ultra-deep super thick to enter rock basement diaphragm wall multiple-grooved section connector processing method, with permanent big center projects For, this technology puts 1000mm outside slot, link slot pilot hole by considering construction of diaphragm wall early period comprehensively, to first opening, can be most Bigization reduces subsequent slotter treatment trough section connector work using churning driven cleaning slot section joint solidification sandbag and bleeding cement Amount, improves work efficiency;Inevitably there is uncontrollable factor in slot section joint buried concrete, using I-steel, triple high pressures Rotary churning pile and the common sealing of Post Grouting Technique, ensure that the impermeability at underground continuous wall connector;First slotted line, link slot section are poured After building concrete initial set, connector case is pulled out, connector is cleared up using the churning driven with brush wall device, is mentioned for closed slots section reinforcing bar cage hoisting For precondition.
The project is had the following characteristics that after being handled using the above method
1) diaphram wall processing connector uses Spiral digging machine and slotter coordinating operation.Since this project diaphram wall width is 1500mm, steel reinforcement cage clear span 1380mm, pilot hole put 1000mm outside, and the churning driven that diameter is 800mm can be selected to carry out joint Reason utmostly uses churning driven construction operation, reduces slotter connector processing construction operation degree, and working efficiency is able to greatly Width is promoted, and has saved construction cost.
2) most as deep as 64m, inevitably there is uncontrollable factor, adopts this project diaphram wall in slot section joint buried concrete With I-steel, triple high-pressure rotary jet grouting piles and the common sealing of Post Grouting Technique, ensure that impermeability at underground continuous wall connector and The integral rigidity of diaphram wall.
3) after first slotted line, the casting concrete initial set of link slot section, connector case is pulled out.Because churning driven can not reach I-steel Connector is cleared up using the churning driven with brush wall device in the angular position 90o that the edge of a wing and web are formed, and thoroughly removes joint solidification sandbag And bleeding cement, while precondition is provided for closed slots section reinforcing bar cage hoisting.
4) before underground continuous wall connector processing, first with BIM three-dimensional Actual Simulation technology to underground continuous wall connector processing Improvement before and after way simulated, ex ante analysis improve after churning driven processing connector operability, and to improve before impact Churning driven facture carries out simulation comparison after hammer facture and improvement, carries out special discussion for the problem of simulation process exposure, Ensure largest optimization the technical program, science, Accuracy and high efficiency in guarantee this technology practical operation.
5) this method is covered is put into grouting behind shaft or drift lining waterproof construction overall process outside pilot hole early period, can extend to sundry item Implement.
The above embodiments are only used to illustrate and not limit the technical solutions of the present invention, although referring to above-described embodiment to this hair It is bright to be described in detail, it will be apparent to an ordinarily skilled person in the art that: still the present invention can be modified or be waited With replacement, without departing from the spirit or scope of the invention, or any substitutions, should all cover in power of the invention In sharp claimed range.

Claims (4)

1. a kind of ultra-deep super thick enters rock basement diaphragm wall multiple-grooved section connector processing method, it is characterised in that: this method is to underground Diaphragm wall first opens and puts 1m outside slot, link slot pilot hole, in the feelings for guaranteeing verticality tolerance amount and I-steel outer side wing edge size Under condition, churning driven cleaning slot section joint bleeding cement and solidification sandbag are maximally utilized.
2. a kind of ultra-deep super thick enters rock basement diaphragm wall multiple-grooved section connector processing method, feature according to claim 1 It is: when uncontrollable factor occurs in slot section joint buried concrete, using I-steel, triple high-pressure rotary jet grouting piles and grouting behind shaft or drift lining skill The common sealing of art.
3. a kind of ultra-deep super thick enters rock basement diaphragm wall multiple-grooved section connector processing method, feature according to claim 1 It is: after first slotted line, the casting concrete initial set of link slot section, pulls out connector case, connect using the churning driven cleaning with brush wall device Head.
4. a kind of ultra-deep super thick enters rock basement diaphragm wall multiple-grooved section connector processing method, feature according to claim 1 It is: before underground continuous wall connector processing, underground continuous wall connector is handled first with BIM three-dimensional Actual Simulation technology improvement Front and back way is simulated, the operability of churning driven processing connector after ex ante analysis improves, and to jump bit processing before improving Churning driven facture carries out simulation comparison after method and improvement, carries out special discussion for the problem of simulation process exposure, it is ensured that most Big optimisation technique scheme.
CN201810960240.4A 2018-08-22 2018-08-22 A kind of ultra-deep super thick enters rock basement diaphragm wall multiple-grooved section connector processing constructing structure Pending CN109083154A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810960240.4A CN109083154A (en) 2018-08-22 2018-08-22 A kind of ultra-deep super thick enters rock basement diaphragm wall multiple-grooved section connector processing constructing structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810960240.4A CN109083154A (en) 2018-08-22 2018-08-22 A kind of ultra-deep super thick enters rock basement diaphragm wall multiple-grooved section connector processing constructing structure

Publications (1)

Publication Number Publication Date
CN109083154A true CN109083154A (en) 2018-12-25

Family

ID=64794230

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810960240.4A Pending CN109083154A (en) 2018-08-22 2018-08-22 A kind of ultra-deep super thick enters rock basement diaphragm wall multiple-grooved section connector processing constructing structure

Country Status (1)

Country Link
CN (1) CN109083154A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115094915A (en) * 2022-05-25 2022-09-23 浙江土工岩土科技有限公司 Grooving construction method for slightly weathered volcanic geological underground continuous wall

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101177724B1 (en) * 2012-02-21 2012-08-28 주식회사 대창중기계 Rock socket-soil. cement. wall method

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101177724B1 (en) * 2012-02-21 2012-08-28 주식회사 대창중기계 Rock socket-soil. cement. wall method

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
丛蔼森等: "《深基坑防渗体的设计施工与应用》", 31 March 2012, 知识产权出版社 *
宗春华: "坚硬岩层内地下连续墙成槽工艺的比选", 《建筑施工》 *
陈松等: "超深基坑地下连续墙作为主体结构的设计方法研究", 《建筑结构》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115094915A (en) * 2022-05-25 2022-09-23 浙江土工岩土科技有限公司 Grooving construction method for slightly weathered volcanic geological underground continuous wall

Similar Documents

Publication Publication Date Title
CN108194102B (en) The dismounting of limit section and safe stress check calculation construction method are invaded in Tunnel deformation
CN205422813U (en) Detachable filling and retaining wall
CN106522989B (en) The method of ventilating shaft structure and shield driving parallel construction
CN102061923B (en) Tunnel construction method capable of protecting existing building
CN104631475A (en) Safe and fast construction method of down-traversing river shallow depth bored tunnel
CN108442943A (en) A kind of branch-cut bridge section tunnel and Double side heading method construction method
CN106812540B (en) Shield initial plain wall sealing water-stopping reinforcing structure and construction process
CN106321107A (en) Method for controlling overcut tunnel construction of rock cantilever heading machine
CN111287759B (en) Shallow-buried close-connection underground excavation tunnel construction method
CN110700841B (en) Double-side-wall guide pit type excavation method for tunnel excavation
CN209604016U (en) Shallow embedding layer of sand tunnel shielding portal end soil body ruggedized construction
CN102400694A (en) Reinforcement method for combined part of shield tunnel and mining-method tunnel
CN107724351A (en) A kind of diversion tunnel vertical cyclindrical shape stopper structure pattern and method
CN107575237A (en) A kind of subsurface excavation method is combined the construction method of construction subway station with shield method
CN109083154A (en) A kind of ultra-deep super thick enters rock basement diaphragm wall multiple-grooved section connector processing constructing structure
CN110055973A (en) Construction space foundation pit enclosure structure and water-stopping method under by high metal bridge in limited time
CN212250042U (en) Subway station end reinforcing structure for water-rich sand layer shield construction
CN108374674A (en) Six pilot tunnels, 12 step Underground Space Excavation method for protecting support
CN208830321U (en) A kind of support pile and the two-in-one constructing device of water-stop curtain
CN108755660A (en) One kind entering 30 meters of construction method of underground continuous wall of rock close to subway
CN109469051A (en) The construction of manual-excavation cast-in-place pile technique in weak-weathered rock or middle weathering formation area
CN209687506U (en) Wear river shallow buried covered excavation electric power tunnel constructing structure
CN109681213B (en) Construction method for accelerating urban underground road by adding vertical shaft turning positive hole at inclined shaft end
CN111075453A (en) Excavation method for reducing tunnel deformation and mud inrush and water inrush
CN110107313A (en) It is a kind of with existing line altogether to Urban Underground Passage construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20181225