CN109469051A - The construction of manual-excavation cast-in-place pile technique in weak-weathered rock or middle weathering formation area - Google Patents

The construction of manual-excavation cast-in-place pile technique in weak-weathered rock or middle weathering formation area Download PDF

Info

Publication number
CN109469051A
CN109469051A CN201811250599.9A CN201811250599A CN109469051A CN 109469051 A CN109469051 A CN 109469051A CN 201811250599 A CN201811250599 A CN 201811250599A CN 109469051 A CN109469051 A CN 109469051A
Authority
CN
China
Prior art keywords
rock stratum
segment
rock
section
retaining wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811250599.9A
Other languages
Chinese (zh)
Inventor
黄建逵
陆曹平
孟俭杰
杨超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Nantong Three Construction Group Ltd By Share Ltd
Original Assignee
Jiangsu Nantong Three Construction Group Ltd By Share Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Nantong Three Construction Group Ltd By Share Ltd filed Critical Jiangsu Nantong Three Construction Group Ltd By Share Ltd
Priority to CN201811250599.9A priority Critical patent/CN109469051A/en
Publication of CN109469051A publication Critical patent/CN109469051A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/36Concrete or concrete-like piles cast in position ; Apparatus for making same making without use of mouldpipes or other moulds
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • E02D15/04Placing concrete in mould-pipes, pile tubes, bore-holes or narrow shafts

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

Construction of manual-excavation cast-in-place pile technique that the invention discloses one kind in weak-weathered rock or middle weathering formation area, the present invention is in weak-weathered rock or middle weathered rock formation, using the method for water mill drilling cutting rock stratum, successfully solve the problem that surrounding enviroment and job scheduling are restricted, both the driving needs of artificial digging pile had been met, the shock wave effect for eliminate or reducing shot rock generation, also improves the driving speed of artificial digging pile, saves the consumption of labour.

Description

The construction of manual-excavation cast-in-place pile technique in weak-weathered rock or middle weathering formation area
Technical field
The present invention relates to a kind of in weak-weathered rock or middle weathering formation area using drilling cutting rock stratum excavation operation Construction of manual-excavation cast-in-place pile technique, it is specifically a kind of in weak-weathered rock or middle weathered rock formation, it is bored with water mill along manually digging hole Stake carries out the construction of manual-excavation cast-in-place pile technique that circular drilling ring cutting from beginning to end cuts shock wave conduction.
Background technique
Under the big situation for the energy-saving and emission-reduction that the whole world is initiated, construction field has started the revolution of green building, its main feature is that Four sections (it is energy saving, water-saving, section material, save land) one environmental protection.Numerous builders in construction plan, pay attention to intensive land use, sufficiently benefit Building site etc. is discarded with being transformed, therefore, in process of construction, it is necessary to show important to the protection In-particular of existing building.
When carrying out headwork in weak-weathered rock or middle weathering formation area, conventional tunneling construction method is to utilize hand It holds formula pneumatic pick and carries out drillhole blasting driving.Method operating procedure is mature, detonation velocity is fast, work efficiency is high for this, but the impact that explosion generates Wave influences whether the safety of Adjacent Buildings, or even will cause neighbourhood and claim damages dispute etc..In order to efficiently against Blasting shock wave Influence to neighboring buildings;Therefore, it is suitable for carrying out manually in weak-weathered rock or middle weathering formation area there is an urgent need to one kind The construction method of caisson driving solves the above problems.
Summary of the invention
The purpose of the present invention is to provide one kind in weak-weathered rock or middle weathering formation area, and manually digging hole filling pile is applied Work technique.
The technical solution adopted by the present invention is that:
The construction of manual-excavation cast-in-place pile technique in weak-weathered rock or middle weathering formation area, it is characterised in that: including following step It is rapid:
S1: GPS total station, GPC total station measuring staff composition measuring apparatus system are utilized, artificial digging pile center line is made;
S2: in the position of artificial digging pile well head, the steel bar end of binding walling crib framework of steel reinforcement and reserved man-made digging pile mould-pipe, Install walling crib template;
S3: after removing cast-in-place concrete walling crib template, complete armored concrete walling crib is formed;Hoisting frame, peace are installed at walling crib Dress air blower installs air hose and is connected to artificial digging pile shoveling or rock drilling working face;Walling crib and excavated by manual work are manually dug out by several times The earthwork in the stake of hole, and it is stacked at well head mound nearby;It is to be achieved it is a certain amount of after, transported outward with automobile;First segment artificial digging pile After the completion of earth excavation, artificial digging pile inner wall and bottom hole are cleared up immediately, binds first segment retaining wall reinforcing bar, and it is reserved to reserve second segment Retaining wall reinforcing bar installs first segment dado template, pours first segment breast wall concrete, removes first segment dado template, forms first Section reinforced concrete core-tube;After the completion of second segment artificial digging pile earth excavation, artificial digging pile inner wall and bottom hole are cleared up immediately, Second segment retaining wall reinforcing bar is bound, third section is reserved and reserves retaining wall reinforcing bar, install second segment dado template, it is mixed to pour second segment retaining wall Solidifying soil, removes second segment dado template, forms the second segment reinforced concrete core-tube of completion;The third section artificial digging pile earthwork is opened After the completion of digging, artificial digging pile inner wall and bottom hole are cleared up immediately, binds third section retaining wall reinforcing bar, reserve the 4th section of reserved retaining wall steel Muscle installs third section dado template, pours third section breast wall concrete;
S4: circulation construction successively carries out next section of shoveling, binding retaining wall reinforcing bar, installs dado template, pours retaining wall coagulation Soil;
S5: removing dado template, form complete reinforced concrete core-tube, encounter weak-weathered rock or middle weathered rock formation, first presses people The control line of work caisson periphery marks the production line of the drilling cutting rock stratum of water mill brill;
S6: the production line along the drilling cutting rock stratum for marking water mill brill, drilling depth is 600 ㎜, and is connected to form between drilling complete Cutting rock stratum ring;After cutting rock stratum ring is formed, internal rock stratum is then divided into several fritters using electric hand drill, is arranged with well head Internal rock stratum is hoisted to well head, and stacks and form rock slag by elevator, it is to be achieved it is a certain amount of after, transported outward with automobile;Rock stratum After the completion of one section of artificial digging pile rock slag is cleared, rock stratum section accesses air hose for the first time, binds rock stratum first segment retaining wall reinforcing bar, in advance Rock stratum second segment retaining wall reinforcing bar is stayed, rock stratum first segment dado template is installed, pours rock stratum first segment breast wall concrete, removes rock stratum First segment dado template forms reinforced concrete core-tube;Second of access of rock stratum section is along the drilling cutting rock stratum for marking water mill brill Production line, drilling depth is 600 ㎜, and complete cutting rock stratum ring is connected to form between drilling, using electric hand drill by internal rock stratum It is divided into several fritters, internal rock stratum is hoisted to well head, and stacks and form rock slag by the elevator being arranged with well head, wait reach It to after a certain amount of, is transported outward with automobile, after the completion of rock stratum second segment artificial digging pile rock slag is cleared, binds rock stratum second segment retaining wall Reinforcing bar reserves rock stratum third section retaining wall reinforcing bar, installs rock stratum second segment dado template, pour rock stratum second segment breast wall concrete; Rock stratum second segment dado template is removed, second segment reinforced concrete core-tube is formed;Rock stratum section third time access ventilation, water is marked on edge The production line of the drilling cutting rock stratum of abrasive drilling, drilling depth is 600 ㎜, and complete cutting rock stratum ring is connected to form between drilling, and is cut After cutting rock stratum formation ring, internal rock stratum is divided into several fritters using electric hand drill by internal rock stratum;The elevator being arranged with well head, Internal rock stratum is hoisted to well head, and stacks and forms rock slag, it is to be achieved it is a certain amount of after, transported outward with automobile, rock stratum third section people After the completion of work caisson rock slag is cleared, rock stratum third section retaining wall reinforcing bar is bound, the 4th section of rock stratum retaining wall reinforcing bar is reserved, installs rock Layer third section dado template, pours rock stratum third section breast wall concrete, removes rock stratum third section dado template, forms third Duan Gang Reinforced concrete retaining wall;
S7: circulation construction successively carries out the shoveling of lower section of rock stratum, binding retaining wall reinforcing bar, installs dado template, it is mixed to pour retaining wall Solidifying soil, until artificial digging pile bottom reaches designed elevation.
S8: removing rock stratum final stage dado template, form the reinforced concrete core-tube of completion, after being checked and accepted by management, Decentralization is poured by framework of steel reinforcement, the steel reinforcement cage suspension hook, the exhaust manifolds being attached on skeleton of the artificial digging pile checked and accepted, installation The conduit of concrete works pours the concrete of artificial digging pile, until manually digging hole stake top reaches designed elevation.
Advantages of the present invention: in weak-weathered rock or middle weathered rock formation, the method that rock stratum is cut using water mill drilling, at It solves the problems, such as to function that surrounding enviroment and job scheduling are restricted, has both met the driving needs of artificial digging pile, eliminate Or reduce the shock wave effect of shot rock generation, the driving speed of artificial digging pile is also improved, saves labour's Consumption.
Detailed description of the invention
The present invention is described in further detail with reference to the accompanying drawings and detailed description.
Fig. 1 is that figure is completed in artificial digging pile of the present invention positioning;
Fig. 2 is artificial digging pile walling crib reinforcing bar of the present invention, template construction completion figure;
Fig. 2-1 is the top view of Fig. 2;
Fig. 3 is artificial digging pile soil layer section retaining wall reinforcing bar of the present invention, template, concrete construction completion figure;
Fig. 3-1 is the top view of Fig. 3;
Fig. 4 is that figure is completed in artificial digging pile rock stratum section of the present invention punching construction;
Fig. 4-1 is the top view of Fig. 4;
Fig. 5 is manually digging hole rock stratum section retaining wall reinforcing bar of the present invention, template construction completion figure;
Fig. 5-1 is the top view of Fig. 5;
Fig. 6 is that artificial digging pile steel reinforcement cage of the present invention is installed figure;
Fig. 6-1 is the top view of Fig. 6;
Fig. 7 is artificial digging pile concrete construction figure of the present invention;
Fig. 7-1 is the top view of Fig. 7;.
Wherein: 1, GPS total station;2, GPC total station measuring staff;3, artificial digging pile center line;4, well head;5, walling crib reinforcing bar Skeleton;6, steel bar end;7, walling crib template;8, walling crib;9, hoisting frame;10, air blower;11, air hose;12, control line;13, native Heap;14, retaining wall reinforcing bar;15, retaining wall reinforcing bar is reserved;16, dado template;17, retaining wall;18, production line;19, rock stratum ring;20, interior Portion rock stratum;21, rock slag;22, first segment retaining wall reinforcing bar;23, second segment retaining wall reinforcing bar;24, third section dado template;25, steel Reinforced concrete retaining wall;26, framework of steel reinforcement;27, steel reinforcement cage suspension hook;28, exhaust manifolds;29, conduit;30, concrete.
Specific embodiment
As shown in figs. 1-7, the construction of manual-excavation cast-in-place pile technique in weak-weathered rock or middle weathering formation area, including with Lower step:
S1: GPS total station 1,2 composition measuring apparatus system of GPC total station measuring staff are utilized, artificial digging pile center line 3 is made;
S2: in the position of artificial digging pile well head 4, the reinforcing bar of walling crib framework of steel reinforcement 5 and reserved man-made digging pile mould-pipe is bound First 6, walling crib template 7 is installed;
S3: after removing cast-in-place concrete walling crib template 7, forming complete armored concrete walling crib 8, installed at walling crib hoisting frame 9, Installation air blower 10, installation air hose 11 are simultaneously connected to artificial digging pile shoveling or rock drilling working face;By several times manually dig out walling crib and The earthwork in artificial digging pile, and it is stacked at well head mound 13 nearby;It is to be achieved it is a certain amount of after, transported outward with automobile;First segment people After the completion of work caisson earth excavation, artificial digging pile inner wall and bottom hole are cleared up immediately, binds first segment retaining wall reinforcing bar 14, are reserved Second segment reserves retaining wall reinforcing bar 15, installs first segment dado template 16, pours first segment breast wall concrete, removes first segment retaining wall Template 16 forms first segment reinforced concrete core-tube 17;After the completion of second segment artificial digging pile earth excavation, cleaning is artificial immediately Caisson inner wall and bottom hole bind second segment retaining wall reinforcing bar 14, reserve third section and reserve retaining wall reinforcing bar 15, install second segment retaining wall Template 16 pours second segment breast wall concrete, removes second segment dado template 16, forms the second segment armored concrete shield of completion Wall 17;After the completion of third section artificial digging pile earth excavation, artificial digging pile inner wall and bottom hole, binding third section shield are cleared up immediately Wall reinforcing bar 14 reserves the 4th section of reserved retaining wall reinforcing bar 15, installs third section dado template 16, pour third section breast wall concrete;
S4: circulation construction successively carries out next section of shoveling, binding retaining wall reinforcing bar, installs dado template, pours retaining wall coagulation Soil;
S5: removing dado template, form complete reinforced concrete core-tube, encounter weak-weathered rock or middle weathered rock formation, first presses people The control line 12 of work caisson periphery marks the production line 18 of the drilling cutting rock stratum of water mill brill;
S6: the production line 18 along the drilling cutting rock stratum for marking water mill brill, drilling depth are 600 ㎜, and have been connected to form between drilling Whole cutting rock stratum ring 19;After cutting the formation of rock stratum ring 19, internal rock stratum 20 is then divided into several fritters using electric hand drill, uses well The elevator 9 of mouthful setting, is hoisted to well head for internal rock stratum, and stack and form rock slag 21, it is to be achieved it is a certain amount of after, use automobile Outward transport;After the completion of rock stratum first segment artificial digging pile rock slag is cleared, rock stratum section accesses air hose 11 for the first time, binds rock stratum first Section retaining wall reinforcing bar 22, reserves rock stratum second segment retaining wall reinforcing bar 23, installs rock stratum first segment dado template, pours rock stratum first segment shield Wall concrete removes rock stratum first segment dado template, forms reinforced concrete core-tube 25;Mark water in second of access edge of rock stratum section The production line 18 of the drilling cutting rock stratum of abrasive drilling, drilling depth is 600 ㎜, and complete cutting rock stratum ring is connected to form between drilling 19, internal rock stratum 20 is divided into several fritters using electric hand drill, the elevator 9 being arranged with well head, by internal 20 handling of rock stratum To well head, and stack and form rock slag 21, it is to be achieved it is a certain amount of after, transported outward with automobile, rock stratum second segment artificial digging pile rock After the completion of slag is cleared, rock stratum second segment retaining wall reinforcing bar 23 is bound, reserves rock stratum third section retaining wall reinforcing bar, installs rock stratum second segment shield Wall form pours rock stratum second segment breast wall concrete, removes rock stratum second segment dado template, forms second segment armored concrete shield Wall 25;Rock stratum section third time access ventilation, the production line 18 along the drilling cutting rock stratum for marking water mill brill, drilling depth is 600 ㎜, And completely cutting rock stratum ring 19 is connected to form between drilling, after cutting rock stratum forms ring, internal rock stratum 20 will be interior using electric hand drill Portion rock stratum is divided into several fritters;Internal rock stratum is hoisted to well head, and stacks and form rock by the elevator 9 being arranged with well head Slag 21, it is to be achieved it is a certain amount of after, transported outward with automobile, after the completion of rock stratum third section artificial digging pile rock slag is cleared, bind rock stratum Third section retaining wall reinforcing bar reserves the 4th section of rock stratum retaining wall reinforcing bar, installs rock stratum third section dado template 24, pour rock stratum third section Breast wall concrete removes rock stratum third section dado template, forms third section reinforced concrete core-tube 25;
S7: circulation construction successively carries out the shoveling of lower section of rock stratum, binding retaining wall reinforcing bar, installs dado template, it is mixed to pour retaining wall Solidifying soil, until artificial digging pile bottom reaches designed elevation.
S8: removing rock stratum final stage dado template, form the reinforced concrete core-tube of completion, after being checked and accepted by management, Decentralization is by framework of steel reinforcement 26, the steel reinforcement cage suspension hook 27, the exhaust manifolds 28 being attached on skeleton of the artificial digging pile checked and accepted, peace The conduit 29 for filling casting concrete engineering, pours the concrete 30 of artificial digging pile, until manually digging hole stake top reaches design mark It is high.
The present invention, using the method for water mill drilling cutting rock stratum, successfully solves in weak-weathered rock or middle weathered rock formation The problem that surrounding enviroment of having determined and job scheduling are restricted both had met the driving needs of artificial digging pile, eliminates or reduces The shock wave effect that shot rock generates, also improves the driving speed of artificial digging pile, saves the consumption of labour.

Claims (1)

1. the construction of manual-excavation cast-in-place pile technique in weak-weathered rock or middle weathering formation area, it is characterised in that: including following Step:
S1: GPS total station, GPC total station measuring staff composition measuring apparatus system are utilized, artificial digging pile center line is made;
S2: in the position of artificial digging pile well head, the steel bar end of binding walling crib framework of steel reinforcement and reserved man-made digging pile mould-pipe, Install walling crib template;
S3: after removing cast-in-place concrete walling crib template, complete armored concrete walling crib is formed;Hoisting frame, peace are installed at walling crib Dress air blower installs air hose and is connected to artificial digging pile shoveling or rock drilling working face;Walling crib and excavated by manual work are manually dug out by several times The earthwork in the stake of hole, and it is stacked at well head mound nearby;It is to be achieved it is a certain amount of after, transported outward with automobile;First segment artificial digging pile After the completion of earth excavation, artificial digging pile inner wall and bottom hole are cleared up immediately, binds first segment retaining wall reinforcing bar, and it is reserved to reserve second segment Retaining wall reinforcing bar installs first segment dado template, pours first segment breast wall concrete, removes first segment dado template, forms first Section reinforced concrete core-tube;After the completion of second segment artificial digging pile earth excavation, artificial digging pile inner wall and bottom hole are cleared up immediately, Second segment retaining wall reinforcing bar is bound, third section is reserved and reserves retaining wall reinforcing bar, install second segment dado template, it is mixed to pour second segment retaining wall Solidifying soil, removes second segment dado template, forms the second segment reinforced concrete core-tube of completion;The third section artificial digging pile earthwork is opened After the completion of digging, artificial digging pile inner wall and bottom hole are cleared up immediately, binds third section retaining wall reinforcing bar, reserve the 4th section of reserved retaining wall steel Muscle installs third section dado template, pours third section breast wall concrete;
S4: circulation construction successively carries out next section of shoveling, binding retaining wall reinforcing bar, installs dado template, pours retaining wall coagulation Soil;
S5: removing dado template, form complete reinforced concrete core-tube, encounter weak-weathered rock or middle weathered rock formation, first presses people The control line of work caisson periphery marks the production line of the drilling cutting rock stratum of water mill brill;
S6: the production line along the drilling cutting rock stratum for marking water mill brill, drilling depth is 600 ㎜, and is connected to form between drilling complete Cutting rock stratum ring;After cutting rock stratum ring is formed, internal rock stratum is then divided into several fritters using electric hand drill, is arranged with well head Internal rock stratum is hoisted to well head, and stacks and form rock slag by elevator, it is to be achieved it is a certain amount of after, transported outward with automobile;Rock stratum After the completion of one section of artificial digging pile rock slag is cleared, rock stratum section accesses air hose for the first time, binds rock stratum first segment retaining wall reinforcing bar, in advance Rock stratum second segment retaining wall reinforcing bar is stayed, rock stratum first segment dado template is installed, pours rock stratum first segment breast wall concrete, removes rock stratum First segment dado template forms reinforced concrete core-tube;Second of access of rock stratum section is along the drilling cutting rock stratum for marking water mill brill Production line, drilling depth is 600 ㎜, and complete cutting rock stratum ring is connected to form between drilling, using electric hand drill by internal rock stratum It is divided into several fritters, internal rock stratum is hoisted to well head, and stacks and form rock slag by the elevator being arranged with well head, wait reach It to after a certain amount of, is transported outward with automobile, after the completion of rock stratum second segment artificial digging pile rock slag is cleared, binds rock stratum second segment retaining wall Reinforcing bar reserves rock stratum third section retaining wall reinforcing bar, installs rock stratum second segment dado template, pour rock stratum second segment breast wall concrete; Rock stratum second segment dado template is removed, second segment reinforced concrete core-tube is formed;Rock stratum section third time access ventilation, water is marked on edge The production line of the drilling cutting rock stratum of abrasive drilling, drilling depth is 600 ㎜, and complete cutting rock stratum ring is connected to form between drilling, and is cut After cutting rock stratum formation ring, internal rock stratum is divided into several fritters using electric hand drill by internal rock stratum;The elevator being arranged with well head, Internal rock stratum is hoisted to well head, and stacks and forms rock slag, it is to be achieved it is a certain amount of after, transported outward with automobile, rock stratum third section people After the completion of work caisson rock slag is cleared, rock stratum third section retaining wall reinforcing bar is bound, the 4th section of rock stratum retaining wall reinforcing bar is reserved, installs rock Layer third section dado template, pours rock stratum third section breast wall concrete, removes rock stratum third section dado template, forms third Duan Gang Reinforced concrete retaining wall;
S7: circulation construction successively carries out the shoveling of lower section of rock stratum, binding retaining wall reinforcing bar, installs dado template, it is mixed to pour retaining wall Solidifying soil, until artificial digging pile bottom reaches designed elevation;
S8: removing rock stratum final stage dado template, form the reinforced concrete core-tube of completion, after being checked and accepted by management, decentralization The framework of steel reinforcement of artificial digging pile by examination, steel reinforcement cage suspension hook, the exhaust manifolds being attached on skeleton, installation pour coagulation The conduit of geotechnological journey pours the concrete of artificial digging pile, until manually digging hole stake top reaches designed elevation.
CN201811250599.9A 2018-10-25 2018-10-25 The construction of manual-excavation cast-in-place pile technique in weak-weathered rock or middle weathering formation area Pending CN109469051A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811250599.9A CN109469051A (en) 2018-10-25 2018-10-25 The construction of manual-excavation cast-in-place pile technique in weak-weathered rock or middle weathering formation area

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811250599.9A CN109469051A (en) 2018-10-25 2018-10-25 The construction of manual-excavation cast-in-place pile technique in weak-weathered rock or middle weathering formation area

Publications (1)

Publication Number Publication Date
CN109469051A true CN109469051A (en) 2019-03-15

Family

ID=65666187

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811250599.9A Pending CN109469051A (en) 2018-10-25 2018-10-25 The construction of manual-excavation cast-in-place pile technique in weak-weathered rock or middle weathering formation area

Country Status (1)

Country Link
CN (1) CN109469051A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112112170A (en) * 2020-09-18 2020-12-22 中铁济南工程建设监理有限公司 Construction process for manually digging hole and pouring pile in weakly weathered rock or moderately weathered rock stratum area
CN113482013A (en) * 2021-07-12 2021-10-08 中国水电建设集团十五工程局有限公司 Manual hole digging construction method for cast-in-place pile

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106381868A (en) * 2016-09-06 2017-02-08 中交第航务工程局有限公司 Water abrasive drilling construction method for manual hole digging pile

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106381868A (en) * 2016-09-06 2017-02-08 中交第航务工程局有限公司 Water abrasive drilling construction method for manual hole digging pile

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112112170A (en) * 2020-09-18 2020-12-22 中铁济南工程建设监理有限公司 Construction process for manually digging hole and pouring pile in weakly weathered rock or moderately weathered rock stratum area
CN112112170B (en) * 2020-09-18 2021-09-07 中铁济南工程建设监理有限公司 Construction process for manually digging hole and pouring pile in weakly weathered rock or moderately weathered rock stratum area
CN113482013A (en) * 2021-07-12 2021-10-08 中国水电建设集团十五工程局有限公司 Manual hole digging construction method for cast-in-place pile

Similar Documents

Publication Publication Date Title
CN104074199B (en) Underwater bearing platform construction method
CN104806251B (en) Subsidiary inverted excavation construction method for urban subway station under complex environment
CN108867814A (en) It is newly-built to cut dirty branch pipe and existing sewage network is plugged into engineering method
CN106978807A (en) Existing bridge pile pulling device and construction method are passed through by a kind of weak soil shield driving area
CN110344400A (en) The hard rock pore-forming construction technology of churning driven opportunity
CN106988302A (en) A kind of high inclination-angle competent bed rotary digging pile driving construction engineering method
CN113832958B (en) Anti-slide pile construction method with mechanical cooperation with manual excavation
CN110144899B (en) Deformation control structure for foundation pit of soft soil stratum underground parking lot near shallow foundation building and construction method
CN104831733A (en) Arch bridge abutment tunnel type large-angle inclined pile construction method
CN108166771A (en) Steel reinforced concrete pool structural reform makes construction method
CN109469051A (en) The construction of manual-excavation cast-in-place pile technique in weak-weathered rock or middle weathering formation area
CN105862897B (en) Sandy Silt ground shallow foundation original groove pouring construction engineering method
CN108005088A (en) A kind of cross-section foundation pit supporting construction and its construction method
CN110080779A (en) Tunnel tunnel bottom karst cave treatment construction method
CN114232628A (en) Cutting hoop for integrally breaking pile head of cast-in-situ bored pile and construction method
CN112554176B (en) Full-casing twisted pipe follow-up rotary drilling pore-forming construction method
CN101994314A (en) Longhole rectangular terraced antiskid pile jump-preventing excavating construction
CN109024572A (en) A kind of rotary digging pile construction method
CN108222012A (en) A kind of foundation pit anchor cable excision and the construction method that supporting pile is carried out using anchor cable excision system
CN110529120B (en) Construction method for removing invasion limiting structure by chiseling VI-level surrounding rock shallow-buried underground excavation loess tunnel
CN111561262A (en) Hole forming method of rotary drilling rig for large-size pile hole in karst area
CN108374674A (en) Six pilot tunnels, 12 step Underground Space Excavation method for protecting support
CN110130321A (en) The processing method of rock in a kind of manual digging pile construction
CN104988981B (en) A kind of well construction method of riding on present situation operation shield method drainage pipeline
CN205618170U (en) Protective structure of no template punishment rock mass cavity in tunnel engineering

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190315