CN108951883A - A kind of nuclear power station high-accuracy built-in fitting installation method - Google Patents

A kind of nuclear power station high-accuracy built-in fitting installation method Download PDF

Info

Publication number
CN108951883A
CN108951883A CN201810394169.8A CN201810394169A CN108951883A CN 108951883 A CN108951883 A CN 108951883A CN 201810394169 A CN201810394169 A CN 201810394169A CN 108951883 A CN108951883 A CN 108951883A
Authority
CN
China
Prior art keywords
band steel
top band
embedded part
installation method
nuclear power
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810394169.8A
Other languages
Chinese (zh)
Other versions
CN108951883B (en
Inventor
贾广德
徐恩清
凌长胜
邱奕
王志勇
张宏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Nuclear Industry Huaxing Construction Co Ltd
Original Assignee
China Nuclear Industry Huaxing Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Nuclear Industry Huaxing Construction Co Ltd filed Critical China Nuclear Industry Huaxing Construction Co Ltd
Priority to CN201810394169.8A priority Critical patent/CN108951883B/en
Publication of CN108951883A publication Critical patent/CN108951883A/en
Application granted granted Critical
Publication of CN108951883B publication Critical patent/CN108951883B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/38Connections for building structures in general
    • E04B1/41Connecting devices specially adapted for embedding in concrete or masonry

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The present invention is a kind of pre-buried installation method of nuclear power station high-precision, which includes the first step, the separate design of high-precision embedded part;Second step, the installation of bottom embedded part;Third step, the positioning of top band steel and the first successive step of absolute altitude;4th step, top band steel prevent deformation from fixing;5th step, top band steel are finally welded and fixed.The disposable installation accuracy of high-accuracy built-in fitting is improved using this kind of installation method, reduction is unsatisfactory for the manpower consumption of secondary polishing caused by requiring because of precision, can utilize part clout, improve construction efficiency, create biggish economic benefit and social benefit.

Description

A kind of nuclear power station high-accuracy built-in fitting installation method
Technical field
The present invention relates to a kind of installation of embedded parts method, especially a kind of high-accuracy built-in fitting installation method belongs to nuclear power It the technical field of construction such as stands.
Background technique
Built-in fitting largely exists in nuclear island factory building as equipment, process pipe and the linkage interface of building structure.It is high-precision The built-in fitting electric panel cabinet basis high generally as susceptibility is spent, requires repeatedly adjustment to mention its installation accuracy in design document Height is finally increased to 1mm/m by initial 4mm/m flatness.In practice of construction, although the installation to high-accuracy built-in fitting is given Great attention is given, after the construction of former construction technology, the absolute altitude and levelness of more high-accuracy built-in fitting are not still able to satisfy Design installation accuracy requirement.
For the disposable installation accuracy for improving high-accuracy built-in fitting, reduces the secondary polishing in scene and consume all kinds of resources, drawn The cost risen improves, form a kind of high-accuracy built-in fitting installation method by field practice, the effective solution above problem.
Summary of the invention
It is an object of the invention to: it is directed to above-mentioned disadvantage of the existing technology, proposes high-accuracy built-in fitting installation method, The disposable installation accuracy of high-accuracy built-in fitting is improved, is reduced because precision is unsatisfactory for manually disappearing for secondary polishing caused by requiring Consumption can utilize the unserviceable clout in part, improve construction efficiency.
A kind of nuclear power station high-accuracy built-in fitting installation method, by high-accuracy built-in fitting be set to building floor layer and It fits up in layer, specifically comprises the following steps:
Step 1: lower part embedded part and top band steel are made according to force request;
Step 2: pouring floor layer and lower part embedded part is set in floor layer;
Step 3: successive step at the beginning of carrying out positioning and absolute altitude to top band steel on the embedded part of lower part;
Step 4: top band steel being prevented on the embedded part of lower part to carry out deformation fixation;
Step 5: top band steel is fixedly welded on the embedded part of lower part;
Step 6: grouting forms finishing layer and top band steel is located in finishing layer, the upper side exposure of top band steel In finishing layer upper side.
A kind of nuclear power station high-accuracy built-in fitting installation method, further design is: lower part embedded part bottom side edge Length direction spacing is welded with several holdfasts.
A kind of nuclear power station high-accuracy built-in fitting installation method, further design is: step 2 is specific as follows: Lower part embedded part is bound in the reinforcing bar of floor layer, fixation is poured simultaneously with floor after accurate positioning, so that the lower part embedded part is placed in In floor layer;The positioning slight change of casting process middle and lower part embedded part, on top band steel installation accuracy without influence.
A kind of nuclear power station high-accuracy built-in fitting installation method, further design is: the step 3 is specific Implementation steps include:
Step 3.1: top band steel is layed in above the embedded part of lower part;
Step 3.2: positioning and absolute altitude initial adjustment are carried out to top band steel.
A kind of nuclear power station high-accuracy built-in fitting installation method, further design is: the step 3.1 includes Following steps: top band steel is aligned laying with lower part embedded part center: respectively in top band steel width direction center and lower part The design centre of embedded part is positioned parallel to long side and makes marks out parallel lines, and when installation both guarantees center line alignment.
A kind of nuclear power station high-accuracy built-in fitting installation method, further design is: the step 3.2 includes Following steps: the datum mark of installation high-accuracy built-in fitting floor needed for being determined using level, by 360 ° of irradiation laser infrared lines Level meter is placed on reference point location;Scale is placed on installed top band steel, laser infrared line water is mapped out on scale The ray that level issues, according to the absolute altitude and levelness of successive step top band steel at the beginning of datum mark.It is pre-buried to one section of high-precision After the completion of part adjustment, next section of high-precision degree type embedded part can be carried out and be laid with.
A kind of nuclear power station high-accuracy built-in fitting installation method, further design is: the step 4 is specific Implementation steps include:
Step 4.1: spacing label is done along its length to top band steel;
Step 4.2: absolute altitude and levelness to top band steel make accurate adjustment;
Step 4.3: top band steel is tentatively fixed on lower part embedded part.
A kind of nuclear power station high-accuracy built-in fitting installation method, further design is: the step 4.2 is specific It is as follows: using the control point real-time segmentation of level and binding marker adjustment top band steel absolute altitude and levelness;Absolute altitude and level Degree adjustment is using wedge-shaped iron and the cooperation adjustment of U-shaped iron;Two or more top band steels being parallel to each other be one group, one group between it is high-precision Embedded part is spent using 1m as in the region of radius, height difference is less than or equal to 1mm.
A kind of nuclear power station high-accuracy built-in fitting installation method, further design is: the step 4.3 is specific It is as follows: the absolute altitude and levelness of top band steel meet the requirements after by support column perpendicular to lower part embedded part spacing place, upper end with Top band steel spot welding connection, lower end is connect with lower part embedded part spot welding.After the completion of one group of high-accuracy built-in fitting is laid in place, to every One group of high-accuracy built-in fitting is accurately adjusted, after a control point meets positioning and absolute altitude requirement, immediately using support cylindricality Support is fixed to the control point in formula, prevents absolute altitude and levelness from changing.
A kind of nuclear power station high-accuracy built-in fitting installation method, further design is: the support column uses The round steel of long 50mm, diameter 8mm.
A kind of nuclear power station high-accuracy built-in fitting installation method, further design is: the step 5 is specific Implementation steps include:
Step 5.1: absolute altitude reinspection being made to top band steel before final fix;
Step 5.2: the top band steel absolute altitude for not meeting required precision to absolute altitude makees secondary adjustment;
Step 5.3: top band steel is finally welded and fixed;
A kind of nuclear power station high-accuracy built-in fitting installation method, further design is: step 5.2 is specific such as Under: it carries out the support column cutting that absolute altitude does not meet required precision position to increase support column again after secondary adjustment and fix.
A kind of nuclear power station high-accuracy built-in fitting installation method, further design is: the step 5.3 is specific It is as follows: there are when the gap 5~20mm between lower part embedded part and top band steel, by L=200mm,Round steel, spacing is horizontal It places and the round steel is made to be close to top band steel and lower part embedded part, be finally fixedly welded so that the round steel is fixedly connected with top band steel In lower part embedded part;Gap between lower part embedded part and top band steel is that 0~5mm directly welds top band steel in lower part embedded part.
A kind of nuclear power station high-accuracy built-in fitting installation method, further design is: the welding manner is Intersect interruption welding manner.
The beneficial effects of the present invention are: 1. improve the disposable installation essence of high-accuracy built-in fitting using this kind of installation method Degree, reduction are unsatisfactory for the manpower consumption of secondary polishing caused by requiring because of precision, can utilize part stub bar of reinforced bar clout, centainly Construction efficiency is improved in degree.2. the new process can be generalized in the high embedded part installation of same type required precision, have good Good social application value.
Detailed description of the invention
The present invention will be further described below with reference to the drawings.
The built-in fitting of the prior art is replaced by high-accuracy built-in fitting used by the present embodiment by Fig. 1.
The positioning of the top Fig. 2 band steel and the first successive step operation principle schematic diagram of absolute altitude.
Longitudinal terminal surface structural schematic diagram when the top Fig. 3 band steel Pass line adjustment and Level-adjusting.
The side structure schematic diagram when top Fig. 4 band steel Pass line adjustment and Level-adjusting.
Fig. 5 is C-C shown in Fig. 4 to schematic diagram.
The top Fig. 6 band steel prevents deformation from fixing.
Fig. 7 is schematic diagram in A-A direction shown in Fig. 6.
The top Fig. 8 band steel is finally welded and fixed
Fig. 9 is B-B direction schematic diagram shown in Fig. 8.
Figure 10 is installed grouting schematic diagram.
Mono- group of high-precision embedded part of Figure 11 is installed figure.
Figure 12 be in Figure 11 D-D to schematic diagram.
Specific embodiment
Below in conjunction with Figure of description and specific preferred example, this patent is further described:
A kind of nuclear power station high-accuracy built-in fitting installation method, by high-accuracy built-in fitting be set to the floor layer 13 of building with And in finishing layer 12, specifically comprise the following steps:
Step 1: as shown in Figure 1, making lower part embedded part 2 and top band steel 1, lower part embedded part bottom side edge according to force request Length direction spacing is welded with several holdfast 2-1;
Step 2: pouring floor layer and lower part embedded part is set in floor layer;
Step 3: successive step at the beginning of carrying out positioning and absolute altitude to top band steel on the embedded part of lower part;
Step 4: top band steel being prevented on the embedded part of lower part to carry out deformation fixation;
Step 5: top band steel is fixedly welded on the embedded part of lower part;
Step 6: grouting forms finishing layer and top band steel is located in finishing layer, the upper side exposure of top band steel In finishing layer upper side.
Step 2 is specific as follows: lower part embedded part 2 is bound in the reinforcing bar of floor layer, is poured simultaneously admittedly after accurate positioning with floor It is fixed, so that the lower part embedded part is placed in floor layer;Due to subsequent also to the absolute altitude of top band steel and the adjustment of levelness Step, the positioning slight change of casting process middle and lower part embedded part, on top band steel installation accuracy without influence.
Step 3 specific implementation step includes:
Step 3.1: top band steel is layed in above the embedded part of lower part;
Step 3.2: positioning and absolute altitude initial adjustment are carried out to top band steel.
Specifically, the step 3.1 includes the following steps: that top band steel is aligned laying with lower part embedded part center: respectively It is positioned parallel to long side in the design centre of top band steel width direction center and lower part embedded part to make marks out parallel lines, peace Guarantee the two center line alignment when dress.
The step 3.2 is included the following steps: as shown in Fig. 2, installing high-accuracy built-in fitting needed for being determined using level 360 ° of irradiation laser infrared line level meters 3 are placed on 4 position of datum mark by the datum mark 4 of floor;On installed top band steel Scale 6 is placed, the ray 5 of laser infrared line level meter sending is mapped out on scale, according at the beginning of datum mark on successive step The absolute altitude and levelness of portion's band steel.After the completion of one section of high-accuracy built-in fitting adjusts, next section of high-precision degree type can be carried out and buried Part is laid with.
Step 4 specific implementation step includes:
Step 4.1: to top band steel, spacing label is done in side along its length on it, forms several equidistant controls Point;
Step 4.2: absolute altitude and levelness to top band steel make accurate adjustment;
Step 4.3: top band steel is tentatively fixed on lower part embedded part.
Specifically, the step 4.2 is specific as follows: as shown in Figure 3-Figure 5, using the control of level and binding marker Point real-time segmentation adjustment top band steel absolute altitude and levelness;Absolute altitude and Level-adjusting are cooperated using wedge-shaped iron 10 and U-shaped iron 11 Adjustment, specifically, two wedge-shaped iron are symmetrical arranged at each control point in lower width direction of top band steel, it is flat on top Other wedge-shaped iron is set between the upper side of steel and U-shaped iron;It can be by upper while to be lifted to the formation of top band steel Wedge-shaped iron at lower two is adjusted the levelness and absolute altitude of band steel;Two or more the top band steels being parallel to each other are one Group, the high-precision embedded part between one group is using 1m as in the region of radius, height difference is less than or equal to 1mm.
The step 4.3 is specific as follows: as Figure 6-Figure 7, after the absolute altitude and levelness of top band steel are met the requirements Support column 7 is placed perpendicular to lower part embedded part spacing, 7 upper end of support column is connect with top band steel spot welding, and support column lower end is under Portion's embedded part spot welding connection.After the completion of one group of high-accuracy built-in fitting is laid in place, each group of high-accuracy built-in fitting is carried out accurate Support is fixed to the control point using support column form immediately after one control point meets positioning and absolute altitude requirement in adjustment, Prevent absolute altitude and levelness from changing.
Wherein, the support column uses the round steel of long 50mm, diameter 8mm.
Step 5 specific implementation step includes:
Step 5.1: absolute altitude reinspection being made to top band steel before final fix;
Step 5.2: the top band steel absolute altitude for not meeting required precision to absolute altitude makees secondary adjustment;
Step 5.3: top band steel is finally welded and fixed;
Wherein, step 5.2 is specific as follows: the support column cutting that absolute altitude does not meet required precision position is carried out secondary adjustment Increase support column again afterwards to fix.
The step 5.3 is specific as follows: in conjunction with shown in Fig. 8-Fig. 9, there are 5~20mm between lower part embedded part and top band steel When gap, by L=200mm,Round steel 9, spacing be horizontally arranged and make the round steel 9 at the same be close to top band steel under Portion's embedded part is finally fixedly welded so that the round steel is fixedly connected with top band steel in lower part embedded part;Lower part embedded part and top band steel it Between gap be 0~5mm directly weld top band steel in lower part embedded part.Wherein, the welding manner is to intersect interruption welding side Formula.
It is finally fixedly welded after the embedded part of lower part in top band steel, carries out the setting of finishing layer;If using at this time pre- Molding finishing layer then as shown in Figure 10 reserves grout gap 16 between preforming finishing layer and high-accuracy built-in fitting, and It is in the milk afterwards to grout gap, so that top band steel is fixed in finishing layer.
Finally after the solidification of finishing layer and hardness reach requirement, as shown in Figure 11-Figure 12, set on high-accuracy built-in fitting Set corresponding precision equipment pedestal 15.

Claims (14)

1. high-accuracy built-in fitting is set to the floor layer and dress of building by a kind of nuclear power station high-accuracy built-in fitting installation method Repair in layer that it is characterized by comprising following steps:
Step 1: lower part embedded part and top band steel are made according to force request;
Step 2: pouring floor layer and lower part embedded part is set in floor layer;
Step 3: successive step at the beginning of carrying out positioning and absolute altitude to top band steel on the embedded part of lower part;
Step 4: top band steel being prevented on the embedded part of lower part to carry out deformation fixation;
Step 5: top band steel is fixedly welded on the embedded part of lower part;
Step 6: grouting forms finishing layer and top band steel is located in finishing layer, and the upper side of top band steel is exposed to dress Repair a layer upper side.
2. a kind of nuclear power station high-accuracy built-in fitting installation method according to claim 1, it is characterised in that: lower part embedded part bottom Lateral edge length direction spacing is welded with several holdfasts.
3. a kind of nuclear power station high-accuracy built-in fitting installation method according to claim 1 or 2, it is characterised in that: step 2 Specific as follows: lower part embedded part is bound in the reinforcing bar of floor layer, fixation is poured simultaneously with floor after accurate positioning, so that the lower part Embedded part is placed in floor layer.
4. a kind of nuclear power station high-accuracy built-in fitting installation method according to claim 1, it is characterised in that: the step 3 specific implementation steps include:
Step 3.1: top band steel is layed in above the embedded part of lower part;
Step 3.2: positioning and absolute altitude initial adjustment are carried out to top band steel.
5. a kind of nuclear power station high-accuracy built-in fitting installation method according to claim 5, it is characterised in that: the step 3.1 include the following steps: that top band steel is aligned laying with lower part embedded part center: respectively in top band steel width direction center And the design centre of lower part embedded part is positioned parallel to long side and makes marks out parallel lines, when installation, both guarantees center line alignment.
6. a kind of nuclear power station high-accuracy built-in fitting installation method according to claim 5, it is characterised in that: the step 3.2 include the following steps: the datum mark of installation high-accuracy built-in fitting floor needed for determining using level, by 360 ° of irradiation laser Infrared ray gradienter is placed on reference point location;Scale is placed on installed top band steel, it is red that laser is mapped out on scale The ray that outside line level meter issues, according to the absolute altitude and levelness of successive step top band steel at the beginning of datum mark.
7. a kind of nuclear power station high-accuracy built-in fitting installation method according to claim 1, it is characterised in that: the step 4 specific implementation steps include:
Step 4.1: spacing label is done along its length to top band steel;
Step 4.2: absolute altitude and levelness to top band steel make accurate adjustment;
Step 4.3: top band steel is tentatively fixed on lower part embedded part.
8. a kind of nuclear power station high-accuracy built-in fitting installation method according to claim 8, it is characterised in that: the step 4.2 is specific as follows: using the control point real-time segmentation of level and binding marker adjustment top band steel absolute altitude and levelness;Absolute altitude And Level-adjusting is using wedge-shaped iron and the cooperation adjustment of U-shaped iron;Between two or more the top band steels being parallel to each other are one group, one group High-precision embedded part using 1m as in the region of radius, height difference is less than or equal to 1mm.
9. a kind of nuclear power station high-accuracy built-in fitting installation method according to claim 8, it is characterised in that: the step 4.3 is specific as follows: the absolute altitude and levelness of top band steel place support column perpendicular to lower part embedded part spacing after meeting the requirements, Upper end is connect with top band steel spot welding, and lower end is connect with lower part embedded part spot welding.
10. a kind of nuclear power station high-accuracy built-in fitting installation method, feature according to claim 8-10 any one exist In: the support column uses the round steel of long 50mm, diameter 8mm.
11. a kind of nuclear power station high-accuracy built-in fitting installation method according to claim 1, it is characterised in that: the step Rapid 5 specific implementation step includes:
Step 5.1: absolute altitude reinspection being made to top band steel before final fix;
Step 5.2: the top band steel absolute altitude for not meeting required precision to absolute altitude makees secondary adjustment;
Step 5.3: top band steel is finally welded and fixed.
12. a kind of nuclear power station high-accuracy built-in fitting installation method according to claim 12, it is characterised in that: step 5.2 It is specific as follows: to carry out the support column cutting that absolute altitude does not meet required precision position to increase support column again after secondary adjustment and consolidate It is fixed.
13. a kind of nuclear power station high-accuracy built-in fitting installation method according to claim 13, it is characterised in that: the step 5.3 is specific as follows: there are when the gap 5~20mm between lower part embedded part and top band steel, by L=200mm,Round steel, it is fixed Away from being horizontally arranged and the round steel being made to be close to top band steel and lower part embedded part, finally it is fixedly welded so that the round steel is fixedly connected Portion's band steel is in lower part embedded part;Top band steel is directly welded for 0~5mm and is buried in lower part in gap between lower part embedded part and top band steel Part.
14. a kind of nuclear power station high-accuracy built-in fitting installation method, feature described in 2-14 any one exist according to claim 1 In: the welding manner is to intersect interruption welding manner.
CN201810394169.8A 2018-04-27 2018-04-27 High-precision embedded part installation method for nuclear power station Active CN108951883B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810394169.8A CN108951883B (en) 2018-04-27 2018-04-27 High-precision embedded part installation method for nuclear power station

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810394169.8A CN108951883B (en) 2018-04-27 2018-04-27 High-precision embedded part installation method for nuclear power station

Publications (2)

Publication Number Publication Date
CN108951883A true CN108951883A (en) 2018-12-07
CN108951883B CN108951883B (en) 2020-05-12

Family

ID=64499534

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810394169.8A Active CN108951883B (en) 2018-04-27 2018-04-27 High-precision embedded part installation method for nuclear power station

Country Status (1)

Country Link
CN (1) CN108951883B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109958195A (en) * 2019-01-18 2019-07-02 中国核工业华兴建设有限公司 A kind of nuclear power station heap container supporting embedded part construction method
CN113338326A (en) * 2021-05-12 2021-09-03 中核工程咨询有限公司 Support device and method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202099878U (en) * 2011-04-29 2012-01-04 铁道第三勘察设计院集团有限公司 Embedded part for evacuation platform of magnetic suspension project
CN204001214U (en) * 2014-08-25 2014-12-10 中国化学工程第六建设有限公司 High accuracy capital embedded board
CN102650135B (en) * 2012-05-18 2014-12-17 中国十七冶集团有限公司 Method for leveling embedded parts at bottom of vertical column in sintered ring cooling machine
CN104631488A (en) * 2015-01-26 2015-05-20 广东省建筑工程集团有限公司 Proton beam accelerator pre-buried base plate high-precision installation technology
CN103485549B (en) * 2013-09-23 2015-09-23 中国五冶集团有限公司 Based on the localization method to large-scale built-in fitting
CN106758562A (en) * 2017-04-08 2017-05-31 中国二十二冶集团有限公司 The installation method that track foundation built-in fitting is integrally fixed with track

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202099878U (en) * 2011-04-29 2012-01-04 铁道第三勘察设计院集团有限公司 Embedded part for evacuation platform of magnetic suspension project
CN102650135B (en) * 2012-05-18 2014-12-17 中国十七冶集团有限公司 Method for leveling embedded parts at bottom of vertical column in sintered ring cooling machine
CN103485549B (en) * 2013-09-23 2015-09-23 中国五冶集团有限公司 Based on the localization method to large-scale built-in fitting
CN204001214U (en) * 2014-08-25 2014-12-10 中国化学工程第六建设有限公司 High accuracy capital embedded board
CN104631488A (en) * 2015-01-26 2015-05-20 广东省建筑工程集团有限公司 Proton beam accelerator pre-buried base plate high-precision installation technology
CN106758562A (en) * 2017-04-08 2017-05-31 中国二十二冶集团有限公司 The installation method that track foundation built-in fitting is integrally fixed with track

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109958195A (en) * 2019-01-18 2019-07-02 中国核工业华兴建设有限公司 A kind of nuclear power station heap container supporting embedded part construction method
CN109958195B (en) * 2019-01-18 2020-11-10 中国核工业华兴建设有限公司 Construction method for reactor vessel supporting embedded part of nuclear power station
CN113338326A (en) * 2021-05-12 2021-09-03 中核工程咨询有限公司 Support device and method

Also Published As

Publication number Publication date
CN108951883B (en) 2020-05-12

Similar Documents

Publication Publication Date Title
CN109614719A (en) A kind of refrigerating plant room assembly construction method based on BIM technology
CN100476142C (en) Construction method for combined V-shape steel pipe concrete pile
CN106120561B (en) A kind of cast-in-situ box girder template construct installation method
CN106284787B (en) Assembled superimposed sheet is installed and localization method
CN108951883A (en) A kind of nuclear power station high-accuracy built-in fitting installation method
CN102733313B (en) Cast-in-place beam combined template system and construction method thereof
CN107336346A (en) A kind of beam making bench
CN105317052A (en) Tower crane foundation bolt fixing method
CN110210166A (en) A kind of prefabricated superimposed sheet method for splitting
CN101907201A (en) Casing positioning construction method by automatic leveling plumb method
CN108978485A (en) A kind of steel construction cable-stayed bridge anchor tie plate field installation process
CN105040992B (en) Reverse inverted-insertion type construction method for structural steel columns
CN110172878B (en) Ground transportation rail installation method
CN103590495B (en) The construction method of indoor GIS universal adjustable flooring basis embedded part
CN112095485A (en) Bridge stay cable anchor cylinder pre-embedded positioning device and using method thereof
CN107881914B (en) Wire-dividing tube type cable saddle back field assembly type positioning device and assembly method
CN101875475B (en) Ring crane corbel for nuclear power station and manufacturing method thereof
CN110374012A (en) A kind of prefabricated engineering method of T beam original position Support Method
CN102839671A (en) Concrete supporting reinforced cage prefabricated assembling technology and construction method
CN211221315U (en) Steel bar positioning tool for concrete pouring
CN210529741U (en) Independent foundation embedded bolt mounting structure
CN110315035B (en) Measuring device for mounting sector section base of slab caster and construction method thereof
CN207392744U (en) Prefabricated concrete structure primary-secondary beam connecting integration support system
CN105421780A (en) Construction method of prefabricated concrete structure
CN109267699B (en) Assembled beam slab and construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant