CN105421780A - Construction method of prefabricated concrete structure - Google Patents

Construction method of prefabricated concrete structure Download PDF

Info

Publication number
CN105421780A
CN105421780A CN201510702353.0A CN201510702353A CN105421780A CN 105421780 A CN105421780 A CN 105421780A CN 201510702353 A CN201510702353 A CN 201510702353A CN 105421780 A CN105421780 A CN 105421780A
Authority
CN
China
Prior art keywords
superposed beam
profiled sheet
concrete structure
construction method
prefabricated concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510702353.0A
Other languages
Chinese (zh)
Other versions
CN105421780B (en
Inventor
董荣贵
吉剑峰
宋银华
杨亦贵
蔡红兵
陈希
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
GUOQIANG CONSTRUCTION GROUP CO Ltd
Original Assignee
GUOQIANG CONSTRUCTION GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GUOQIANG CONSTRUCTION GROUP CO Ltd filed Critical GUOQIANG CONSTRUCTION GROUP CO Ltd
Priority to CN201510702353.0A priority Critical patent/CN105421780B/en
Publication of CN105421780A publication Critical patent/CN105421780A/en
Application granted granted Critical
Publication of CN105421780B publication Critical patent/CN105421780B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/02Conveying or working-up concrete or similar masses able to be heaped or cast
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention provides a construction method of a prefabricated concrete structure, and belongs to the technical field of fixed buildings. The technical problem that an existing construction method of a concrete structure cannot meet the requirements of high efficiency and strength is solved. The construction method of the prefabricated concrete structure comprises the steps that a, a superposed beam and a profiled steel sheet are manufactured; b, the superposed beam is installed; c, the profiled steel sheet is installed; d, steel bar binding is carried out; e, concrete construction is carried out. The construction method has the advantages that the whole strength of the concrete structure obtained after construction is finished is high, the construction time in a construction site can be greatly shortened, and the construction efficiency is improved.

Description

A kind of construction method of prefabricated concrete structure
Technical field
The invention belongs to technical field of fixed buildings, relate to a kind of construction method of prefabricated concrete structure.
Background technology
In modern architecture, cast-in-place integral formula is concrete structure form the earliest, first building of template is carried out before concreting, at laying pipeline and reinforcing bar, carry out concrete building again after completing, this form of construction work also exists long construction period, produce and realize that industrialization, circulation material are many, the high deficiency of construction cost compared with difficult.
Along with the prefabricated concrete structure that the development of building construction technology is arisen at the historic moment, namely crossbeam and floor have all first been prepared in factory, only building of pillar is carried out in building site, by the mode of lifting, crossbeam and floor are lifted on pillar again, although which efficiency is higher, but its globality is more weak, poor seismic behavior, to problems such as lifting requirements are high.
Summary of the invention
The object of the invention is to there are the problems referred to above for existing technology, propose a kind of construction method of prefabricated concrete structure, the technical problem that the present invention solves can improve efficiency of construction when ensureing bulk strength.
Object of the present invention realizes by following technical proposal:
A construction method for prefabricated concrete structure, is characterized in that, comprises the following steps:
A, prepare superposed beam and profiled sheet: to build in advance on mould according to required size in factory and obtain superposed beam, obtain profiled sheet according to required size by Sheet Metal Forming Technology in factory;
B, superposed beam is installed: superposed beam is transported to building site, by crane by superposed beam lifting to cast-in-place post corrects the position of superposed beam after lifting, to be corrected complete after by junction steel plate, the embedded iron parts on cast-in-place post and superposed beam is welded and fixed;
C, installation profiled sheet: profiled sheet is transported to building site, made the slit opening of adjacent profiled sheet align by crane by profiled sheet lifting to adjacent two superposed beams, be connected by adjacent profiled sheet by binding clasp;
D, assembling reinforcement: between superposed beam and on profiled sheet, lay reinforcing bar;
E, concrete construction: cleaning superposed beam and profiled sheet also water and keep moistening, then concreting adopt vibrator vibration compacting, carry out maintenance after having built concrete to concrete.
After having built concrete, profiled sheet and the concrete of building thereon form compoboard; By first by superposed beam and profiled sheet prefabricated inside factory, material cost and cost of labor can be saved, the lower and environmental protection and energy saving of cost; Prefabricated superposed beam and profiled sheet are accurately installed successively, greatly can save the engineering time at building-site, thus improve efficiency of construction; After completing concreting, superposed beam and profiled sheet form monolithic concrete structure, and the concrete structure bulk strength obtained by this construction method is high, industrialization degree is high and overall economic efficiency is remarkable; Self-contained in factory, the superposed beam of therefore building is reliable and stable, thus can ensure the bulk strength after having built.
In the construction method of above-mentioned prefabricated concrete structure, between step a and step b, carry out surveying setting-out, the cement paste on superposed beam and cast-in-place post, the loosening foreign material such as concrete and iron rust are cleaned out; Measure cast-in-place post absolute altitude suitable for reading with level gauge, the carrying out adjustment that adjacent cast-in-place post absolute altitude suitable for reading does not wait is corrected; With total powerstation at cast-in-place post mark center line suitable for reading; Center line is marked by the mode of snap the line at the two ends of superposed beam to be lifted.Above-mentioned operation carries out adequate preparation for installing superposed beam, makes to locate superposed beam efficiently, accurately when installing superposed beam, thus improves efficiency of construction.
In the construction method of above-mentioned prefabricated concrete structure, in step b, when correcting superposed beam position, slightly stirring superposed beam when the site error of superposed beam is less by crowbar and making it to aim at; When the site error of superposed beam is larger, again lifts superposed beam by crane and correct.Effectively superposed beam can be in place by the method, also can avoid damaging superposed beam, ensure the bulk strength of concrete structure.
In the construction method of above-mentioned prefabricated concrete structure, surveying setting-out is carried out between step b and step c, first the cement paste on superposed beam end face, the loosening foreign material such as concrete and iron rust are cleaned out, on superposed beam, marked the position line of profiled sheet lay again by the mode of snap the line, when lifting, profiled sheet is put according to the position line.This operation carries out adequate preparation for installing profiled sheet, makes to locate profiled sheet efficiently, accurately when installing profiled sheet, thus improves efficiency of construction.
In the construction method of above-mentioned prefabricated concrete structure, in step c, the lap length of end on superposed beam of profiled sheet is at least greater than 50mm.Ensure the support strength of profiled sheet, thus ensure the bulk strength of concrete structure.
In the construction method of above-mentioned prefabricated concrete structure, in step c, adopt soft hoist cable or wire rope lifting profiled sheet during lifting, and add rubber in the corner of profiled sheet.This step plays protection profiled sheet, avoids profiled sheet to occur deformation, thus ensures the bulk strength of concrete structure.
In the construction method of above-mentioned prefabricated concrete structure, after completing steps c, adopt the port shutoff that cement paste will be formed between the slit opening of profiled sheet and superposed beam.This step can be avoided occurring spillage when concreting.
In the construction method of above-mentioned prefabricated concrete structure, pipe laying is carried out between step c and steps d, according to design drawing in the precalculated position perforate of profiled sheet and cutting, then at the tapping of profiled sheet and cut place laying wire pipeline or water pipe or air pipeline.Perforate and cutting adopt Plasma cutting machine, avoid damaging profiled sheet overlay coating; Raceway for wiring, water pipe and air pipeline are embedded in profiled sheet, avoid pipeline to expose.
Compared with prior art, it is high that the construction method of this prefabricated concrete structure has the concrete structure bulk strength obtained after having constructed, and greatly can save the engineering time at building-site, improves the advantage of efficiency of construction.
Accompanying drawing explanation
Fig. 1 is the construction sequence flow chart in detailed description of the invention.
Detailed description of the invention
Be below specific embodiments of the invention and by reference to the accompanying drawings, technical scheme of the present invention is further described, but the present invention be not limited to these embodiments.
As shown in Figure 1, the construction method of prefabricated concrete structure comprises the following steps the present embodiment: a, prepare superposed beam and profiled sheet; B, installation superposed beam; C, installation profiled sheet; D, assembling reinforcement and e, concrete construction, specifically:
In step a, to build in advance on mould according to required size in factory and obtain superposed beam, superposed beam is divided into girder and secondary beam.Profiled sheet is obtained according to required size by Sheet Metal Forming Technology in factory.
Before carrying out step b, carry out surveying setting-out, the cement paste on superposed beam and cast-in-place post, the loosening foreign material such as concrete and iron rust are cleaned out; Measure cast-in-place post absolute altitude suitable for reading with level gauge, the carrying out adjustment that adjacent cast-in-place post absolute altitude suitable for reading does not wait is corrected; With total powerstation at cast-in-place post mark center line suitable for reading, perform mark; Center line is marked by the mode of snap the line at the two ends of superposed beam to be lifted.
In step b, superposed beam is transported to building site, by crane by superposed beam lifting to cast-in-place post, first by main cable and girder to cast-in-place post, is more accurately lifted by secondary beam on girder, girder is longitudinally arrange, secondary beam is that horizontal line is arranged; After lifting, the position of superposed beam is corrected, when correcting superposed beam position, slightly stirring superposed beam when the site error of superposed beam is less by crowbar and making it to aim at; When the site error of superposed beam is larger, again lifts superposed beam by crane and correct.To be corrected complete after by junction steel plate, the embedded iron parts on cast-in-place post and superposed beam is welded and fixed.
Surveying setting-out was carried out before carrying out step c, first the cement paste on the end face of superposed beam, the loosening foreign material such as concrete and iron rust are cleaned out, on superposed beam, marked the position line of profiled sheet lay again by the mode of snap the line, when lifting, profiled sheet is put according to the position line.
In step c, profiled sheet is transported to building site, by in profiled sheet lifting to adjacent two superposed beams, the slit opening of adjacent profiled sheet is alignd by crane, soft hoist cable or wire rope lifting profiled sheet is adopted during lifting, and add rubber in the corner of profiled sheet, the lap length of end on superposed beam of profiled sheet is at least greater than 50mm, and as preferably, the lap length of end on superposed beam of profiled sheet can be 55mm, 60mm or 70mm etc.; By binding clasp, adjacent profiled sheet is connected, adopts the port shutoff that cement paste will be formed between the slit opening of profiled sheet and superposed beam simultaneously.
In the laggard row pipe laying of completing steps c, adopt Plasma cutting machine in the precalculated position perforate of profiled sheet and cutting according to design drawing, then at the tapping of profiled sheet and cut place laying wire pipeline or water pipe or air pipeline.
In steps d, between superposed beam and on profiled sheet, lay reinforcing bar; The reinforcing bar laid is divided into two-layer up and down, and lower floor's reinforcing bar is positioned at the groove of profiled sheet, and top reinforcement is positioned at the top of profiled sheet, the even colligation of top reinforcement spacing, and the crotch of top reinforcement vertically stretches in the groove of profiled sheet down.
In step e, cleaning superposed beam and profiled sheet also water and keep moistening, then concreting adopt vibrator vibration compacting, carry out maintenance after having built concrete to concrete.
After having built concrete, profiled sheet and the concrete of building thereon form compoboard; By first by superposed beam and profiled sheet prefabricated inside factory, material cost and cost of labor can be saved, the lower and environmental protection and energy saving of cost; Prefabricated superposed beam and profiled sheet are accurately installed successively, greatly can save the engineering time at building-site, thus improve efficiency of construction; After completing concreting, superposed beam and profiled sheet form monolithic concrete structure, and the concrete structure bulk strength obtained by this construction method is high, industrialization degree is high and overall economic efficiency is remarkable; Self-contained in factory, the superposed beam of therefore building is reliable and stable, thus can ensure the bulk strength after having built.
Specific embodiment described herein is only to the explanation for example of the present invention's spirit.Those skilled in the art can make various amendment or supplement or adopt similar mode to substitute to described specific embodiment, but can't depart from spirit of the present invention or surmount the scope that appended claims defines.

Claims (8)

1. a construction method for prefabricated concrete structure, is characterized in that, comprises the following steps:
A, prepare superposed beam and profiled sheet: to build in advance on mould according to required size in factory and obtain superposed beam, obtain profiled sheet according to required size by Sheet Metal Forming Technology in factory;
B, superposed beam is installed: superposed beam is transported to building site, by crane by superposed beam lifting to cast-in-place post corrects the position of superposed beam after lifting, to be corrected complete after by junction steel plate, the embedded iron parts on cast-in-place post and superposed beam is welded and fixed;
C, installation profiled sheet: profiled sheet is transported to building site, made the slit opening of adjacent profiled sheet align by crane by profiled sheet lifting to adjacent two superposed beams, be connected by adjacent profiled sheet by binding clasp;
D, assembling reinforcement: between superposed beam and on profiled sheet, lay reinforcing bar;
E, concrete construction: cleaning superposed beam and profiled sheet also water and keep moistening, then concreting adopt vibrator vibration compacting, carry out maintenance after having built concrete to concrete.
2. the construction method of prefabricated concrete structure according to claim 1, is characterized in that, carries out surveying setting-out between step a and step b, the cement paste on superposed beam and cast-in-place post, the loosening foreign material such as concrete and iron rust is cleaned out; Measure cast-in-place post absolute altitude suitable for reading with level gauge, the carrying out adjustment that adjacent cast-in-place post absolute altitude suitable for reading does not wait is corrected; With total powerstation at cast-in-place post mark center line suitable for reading; Center line is marked by the mode of snap the line at the two ends of superposed beam to be lifted.
3. the construction method of prefabricated concrete structure according to claim 1 and 2, is characterized in that, in step b, when correcting superposed beam position, slightly stirring superposed beam make it to aim at when the site error of superposed beam is less by crowbar; When the site error of superposed beam is larger, again lifts superposed beam by crane and correct.
4. the construction method of prefabricated concrete structure according to claim 1, it is characterized in that, surveying setting-out is carried out between step b and step c, first the cement paste on superposed beam end face, the loosening foreign material such as concrete and iron rust are cleaned out, on superposed beam, marked the position line of profiled sheet lay again by the mode of snap the line, when lifting, profiled sheet is put according to the position line.
5. the construction method of the prefabricated concrete structure according to claim 1 or 4, is characterized in that, in step c, the lap length of end on superposed beam of profiled sheet is at least greater than 50mm.
6. the construction method of the prefabricated concrete structure according to claim 1 or 4, is characterized in that, in step c, adopts soft hoist cable or wire rope lifting profiled sheet, and add rubber in the corner of profiled sheet during lifting.
7. the construction method of prefabricated concrete structure according to claim 1, is characterized in that, after completing steps c, adopts the port shutoff that cement paste will be formed between the slit opening of profiled sheet and superposed beam.
8. the construction method of prefabricated concrete structure according to claim 1, it is characterized in that, pipe laying is carried out between step c and steps d, according to design drawing in the precalculated position perforate of profiled sheet and cutting, then at the tapping of profiled sheet and cut place laying wire pipeline or water pipe or air pipeline.
CN201510702353.0A 2015-10-26 2015-10-26 A kind of construction method of prefabricated concrete structure Active CN105421780B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510702353.0A CN105421780B (en) 2015-10-26 2015-10-26 A kind of construction method of prefabricated concrete structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510702353.0A CN105421780B (en) 2015-10-26 2015-10-26 A kind of construction method of prefabricated concrete structure

Publications (2)

Publication Number Publication Date
CN105421780A true CN105421780A (en) 2016-03-23
CN105421780B CN105421780B (en) 2018-08-17

Family

ID=55500285

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510702353.0A Active CN105421780B (en) 2015-10-26 2015-10-26 A kind of construction method of prefabricated concrete structure

Country Status (1)

Country Link
CN (1) CN105421780B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106193623A (en) * 2016-07-29 2016-12-07 刘祥锦 A kind of prefabricated concrete structure construction method
TWI687042B (en) * 2019-06-11 2020-03-01 李青枬 Supporting construction method of solar module

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2189625Y (en) * 1993-12-15 1995-02-15 曹凤兰 Preformed frame component of hollow ferro-concrete
CN2390933Y (en) * 1999-06-04 2000-08-09 同济大学 Square steel pipe concrete beam and column jointing gusset
CN1263971A (en) * 2000-02-24 2000-08-23 施民 Technology for building house with centrifugal structural concrete members and frames without brick walls
CN101113604A (en) * 2007-06-22 2008-01-30 东南大学 Full-prefabricated assembled concrete frame construction
KR20120074130A (en) * 2010-12-27 2012-07-05 재단법인 포항산업과학연구원 Compisite column structure for steel and concrete

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2189625Y (en) * 1993-12-15 1995-02-15 曹凤兰 Preformed frame component of hollow ferro-concrete
CN2390933Y (en) * 1999-06-04 2000-08-09 同济大学 Square steel pipe concrete beam and column jointing gusset
CN1263971A (en) * 2000-02-24 2000-08-23 施民 Technology for building house with centrifugal structural concrete members and frames without brick walls
CN101113604A (en) * 2007-06-22 2008-01-30 东南大学 Full-prefabricated assembled concrete frame construction
KR20120074130A (en) * 2010-12-27 2012-07-05 재단법인 포항산업과학연구원 Compisite column structure for steel and concrete

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106193623A (en) * 2016-07-29 2016-12-07 刘祥锦 A kind of prefabricated concrete structure construction method
TWI687042B (en) * 2019-06-11 2020-03-01 李青枬 Supporting construction method of solar module

Also Published As

Publication number Publication date
CN105421780B (en) 2018-08-17

Similar Documents

Publication Publication Date Title
CN204054323U (en) Steel construction assembled beam making bench
CN102134907B (en) Construction method of steel bar truss floor support plate
CN104100092B (en) The track-type facilities of a kind of pitched roof pouring construction and method
CN202559384U (en) Prefabricated assembled pipe-jacking working well
CN204435638U (en) A kind of hollow laminated floor slab
CN202012153U (en) Steel bar positioning fixture
CN105196414A (en) Prefabricated T-beam web plate rebar jig frame and prestressed T-beam construction method
CN105421780A (en) Construction method of prefabricated concrete structure
CN106836600A (en) A kind of reinforcing bar composite floor for power transformation engineering
CN109667376A (en) Novel superposed superstructure and its construction method suitable for steel construction H profile steel beam
CN101949215A (en) Mounting construction method of steel structure support seat
CN207176731U (en) A kind of prefabricated concrete pipe gallery support
CN103132465A (en) Underground box culvert constructing method closely attached to pile foundation bearing platform
CN211472960U (en) Assembled outer wall based on reinforced concrete frame structure
CN209703805U (en) A kind of novel superposed superstructure suitable for steel construction H profile steel beam
CN201972312U (en) Vertical steel bar positioning device in slip-forming construction
CN207177027U (en) One kind is inverted steel bar girder concrete folding plate
CN102839671A (en) Concrete supporting reinforced cage prefabricated assembling technology and construction method
CN103276840B (en) Nuclear power plant composite floor slab module and construction method thereof
CN204955097U (en) Prefabricated T web reinforcing bar bed -jig
CN205712473U (en) A kind of PC beam column node connection device
CN104153467A (en) Device for connecting shear wall and concrete floor in construction structure and arranging method thereof
CN209760295U (en) Pre-buried T type bolt fixed knot of underground pipe gallery electric power support constructs
CN209722908U (en) Steel structure body
CN211646906U (en) Assembly type superposed component node optimization structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant