CN108915694A - It the step tunneling boring unprotect layer tight-face blasting of tunnel lower layer and repairs the roads and protects logical construction method - Google Patents

It the step tunneling boring unprotect layer tight-face blasting of tunnel lower layer and repairs the roads and protects logical construction method Download PDF

Info

Publication number
CN108915694A
CN108915694A CN201810719086.1A CN201810719086A CN108915694A CN 108915694 A CN108915694 A CN 108915694A CN 201810719086 A CN201810719086 A CN 201810719086A CN 108915694 A CN108915694 A CN 108915694A
Authority
CN
China
Prior art keywords
blasting
blast hole
layer
lower layer
main blast
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810719086.1A
Other languages
Chinese (zh)
Other versions
CN108915694B (en
Inventor
杜郧隆
罗福生
张国峰
郝二峰
杜津岩
杨秋贵
杜子纯
丁华丽
胡玲玲
陈国栋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan Water Conservancy No2 Engineering Bureau
Original Assignee
Henan Water Conservancy No2 Engineering Bureau
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan Water Conservancy No2 Engineering Bureau filed Critical Henan Water Conservancy No2 Engineering Bureau
Priority to CN201810719086.1A priority Critical patent/CN108915694B/en
Publication of CN108915694A publication Critical patent/CN108915694A/en
Application granted granted Critical
Publication of CN108915694B publication Critical patent/CN108915694B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/006Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries by making use of blasting methods

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)
  • Drilling And Exploitation, And Mining Machines And Methods (AREA)

Abstract

The present invention relates to engineering explosion technical fields, and in particular to the step tunneling boring unprotect layer tight-face blasting of tunnel lower layer and repairs the roads and protects logical construction method, step 1:Tunnel is divided into upper layer and lower layer, benching tunnelling method excavates, step 2:After the 60~80m of bench excavation of upper layer; this spacing is kept to carry out the unprotect layer tight-face blasting of lower layer's step tunneling boring; complex reflex cumulative is installed additional using main blast hole high bunch continuous method and foundation plane bottom plate and buffers the combined blasting method of the unprotect layer explosion of energy dissipator and the presplit blasting of two sides abutment wall, forms the molding of lower layer's step full face blasting.Step 3:Slope course is built on the quick-fried slag muck of tight-face blasting, and 12 ~ 24m spacing is kept to excavate passage of changing its course forwards with tight-face blasting.This method can carry out drillhole blasting operation simultaneously and logical operation is protected in slope course, realize the upper and lower step of narrow tunnel space while carrying out parallel construction, greatly accelerate construction progress.

Description

It the step tunneling boring unprotect layer tight-face blasting of tunnel lower layer and repairs the roads and protects logical construction Method
Technical field
The present invention relates to constructing tunnel and Technology of Blasting fields, and in particular to tunnel lower layer step tunneling boring unprotect It layer tight-face blasting and repairs the roads and protects logical construction method.
Background technique
The large-sized section tunnel relatively narrow for hole width, existing several construction methods cannot reach to lower layer's step simultaneously Carry out drill-blast tunnelling and as upper layer step traffic aisle two functional areas while operation requirement, will affect tunnel excavation Construction speed.Replacing excavating load using positive step tunneling boring, the work surface of only one each step is carrying out excavation construction, So occupying, period construction time is longer, and production efficiency is lower, influences entire manufacturing schedule.It is alternately opened using lower layer's step half range Digging method, the more difficult half range that formed of lower layer's step excavates the construction that half range stays the current alternately operating in road, since lower layer's step can not Operation while forming two functional areas of Blasting Excavation and traffic aisle, affects construction speed.It is squeezed using lower layer's step quick-fried Channel process in broken drawing, increases flow chart and activity duration, speed of application is slower.
Therefore height is larger, in tunnel of narrower width, under the premise of guaranteeing quality, safety, carries out effective and reasonable Quick bursting excavates, and upper layer, lower layer's step tunneling boring need to be overcome to replace the work surface of only one each step in excavating load Carrying out excavation operation, the slower contradiction of construction speed;Overcome to get out of a predicament or an embarrassing situation and can not carry out half range alternately excavation, influences lower layer's platform The contradiction that rank carries out simultaneously as traffic route and Excavation Blasting;Overcome lower layer's Bench Extruding Blasting to draw bracket groove, need match Close brush side and the peaceful increased flow chart of brill quick-fried operation institute of foundation plane bottom plate and when operation that hand air drill carries out two sides abutment wall Between influence;Overcome the difficulty for being not easy to meet the quick-fried mechanical equipment use of large power drill and construction personnel's operation and construction safety condition difference Topic.
Summary of the invention
The purpose of the present invention is overcome the Blasting Excavation in narrow tunnel positive benching tunnelling method construction to lead to existing construction with road guarantor Deficiency in technology, provides that a kind of security performance is high, easily operated, reliable performance, easy for construction, can effectively guarantee quality The construction method of construction speed is improved, it is logical to guarantee that the effective and reasonable Blasting Excavation of progress and road are protected.It realizes and uses positive benching tunnelling method It excavates, overcomes the adverse effect for full face Blasting Excavation of getting out of a predicament or an embarrassing situation, overcome upper layer and lower layer's step that can only have one layer of step list The influence of one job execution is realized and carries out parallel excavation operation simultaneously with lower layer step using upper layer, accelerates construction progress;Overcome When tunnel narrower width, lower layer's step alternately can not excavate the difficulty current with half range by half range, realize the conduct of lower layer's step It is carried out while traffic route passage and Excavation Blasting, realizes the unimpeded needs for meeting the traffic route of upper layer step, it is real Existing upper layer and lower layer's step carry out Excavation Blasting simultaneously, accelerate construction progress;Overcome hand air drill boring work low efficiency, labor The difficulty that fatigue resistance is big, security risk is big is realized and improves working efficiency, improvement in lower layer's step vertical blasthole of hidden hole drilling wagon drill Worker's labour and safety condition;It realizes main blast hole high bunch continuous method, is not clearing up the quick-fried slag of free face previous ramp road In the case of, the explosion that can make to get out of a predicament or an embarrassing situation persistently is carried forward;The unprotect layer Rapid Excavation explosion for realizing foundation plane bottom plate, in big gun Hole bottom hole installs complex reflex cumulative and buffering energy dissipator additional, energy-gathering jetting device and reflection cumulative cushion when explosive initiation The energy-gathering jetting and reflection energy-gathering jetting that bus generates have dual cumulative action, and it is broken can to increase blasthole floor rocks level Line is split, the ability for enhancing fractured rock solves foundation residual, excavates foundation plane bottom plate blasting in once-through to design altitude;Reflection Cumulative cushion, rigid bed course and buffering energy dissipating bed course form three layers of composite cushion together, have energy dissipating buffer function three times, can To cut down explosion energy, the damage that detonation wave retains foundation plane bottom plate rock is reduced, it is complete to reach protection foundation plane floor rock The effect of whole property guarantees bottom hole rock quality;It realizes the presplit blasting of left and right sides abutment wall, reduces explosion wave to reservation rock The damage of body has the function that protect rock integrality, improves the flatness of rock face;Realize that lower layer's step tunneling boring is once quick-fried It is broken into type, is accelerated construction progress.Realization repairs slope course as upper layer on the quick-fried slag muck of lower layer's step tunneling boring tight-face blasting The traffic route of step, it is ensured that upper layer step has a good transport and communication network;Realize the Blasting Excavation and traffic aisle two that lower layer's step is formed Logical operation is protected in job execution and slope course while functional areas;It realizes the construction of parallel operations simultaneously of the upper and lower step, adds Fast construction speed provides work surface and time for the secondary reinforced concrete lining layer work of subsequent tunnel.
To achieve the above object, the present invention uses following technical scheme:
The present invention provides the step tunneling boring unprotect layer tight-face blasting of tunnel lower layer and repairs the roads and protect logical construction method, including with Lower step:
Step 1:According to tunnel section size, tunnel excavation is designed as top-down positive benching tunnelling method digging mode, according to applying The characteristics of work machinery, personnel and construction method, tunnel is divided into upper layer and lower layer step, upper layer step height first(H1)And lower layer Step height(H2)Than being 1.1~1.2.
Step 2:Upper layer step drill-blast tunnelling carries out in advance, utilizes lower layer's step slagging tap and traffic road as upper layer step Road.Upper layer step is excavated using conventional step full-face blast method, and hand air drill bores lateral aperture.
Step 3:After the 60~80m of bench excavation drilling depth of upper layer, the layer tight-face blasting of tunneling boring unprotect is carried out in lower layer's step, And keeping the follow-up of 60~80m spacing to excavate with upper layer step, lower layer's step is being longitudinally divided into two operating areas, and one is complete disconnected Face unprotect layer tight-face blasting region, the other is the region of the slope road as upper layer traffic route.First in lower layer's step The layer tight-face blasting of tunneling boring unprotect is carried out, then builds slope course on the quick-fried slag muck of tight-face blasting, is mentioned for upper layer step For traffic aisle, it is ensured that upper layer step has a good transport and communication network.The tunneling boring unprotect layer tight-face blasting is:Main blast hole carries out elementary errors and squeezes Explosion is pressed, this method is carried forward lower layer's bench blasting persistently in the case where not clearing up quick-fried slag before the scope of freedom.Foundation plane The blasthole of bottom plate keeps foundation plane bottom plate primary using complex reflex cumulative and buffering energy dissipator progress unprotect layer explosion is installed additional Property Blasting Excavation to foundation plane elevation, the smooth reduction for reaching foundation plane rises and falls poor, damage of the reduction explosion to foundation plane rock, Play the role of protecting rock.Both sides abutment wall carries out presplit blasting along design excavation contour line.Lower layer's step is formed after explosion The full face blasting molding of abutment wall, foundation plane bottom plate, disposably reaches excavation design contour line, improves the smooth of palisades Degree, reduces damage of the main blast hole explosion to palisades.Main blast hole is using millisecond detonating mode between " V " type or row, it is possible to provide two perpendicular To the scope of freedom, increase compensating space in blasting, reduces the impact damage to palisades.
The main blast hole of lower layer's step is drilled using down-the-hole trolley, and pre- ceasma is drilled using simple rack formula hidden hole drilling, and drilling is straight Diameter D2,It is D2=90mm .Hidden hole drilling is along the vertical blasthole of lower layer's step top surface drill down, main blast hole drilling inclination angle thetaIt is main=90 °, presplitting Hole drilling tilts slightly outwards extrapolation, extrapolation inclination angle thetaIn advance=87°。
Region, each 12 m of excavation length or so, after 12m are excavated in lower layer's step tunneling boring unprotect layer tight-face blasting Increase by 1~2 row's reinforced hole, reinforces dose, create new compensating space in blasting.Excavation width is the design wide 9.6m in hole.
Step 4:Slope course, slope course are built on the quick-fried slag muck of lower layer's step tunneling boring unprotect layer tight-face blasting As the explosion of lower layer's step is changed its course passage forwards, the rock ballast of original slope course is dug fortune cleaning, along tunnel excavation side To new slope course is built, makes the spacing for keeping 20m between the slope course top of lower layer's step and tight-face blasting region, close The spacing of reason can provide certain compensating space in blasting for tight-face blasting, be conducive to the progress of tight-face blasting.
Two function operation areas of the layer tight-face blasting operation of tunneling boring unprotect and slope course communications and transportation of lower layer's step Domain.It is constructed and is run simultaneously, realizing lower layer's step both can continue to carry out drillhole blasting excavation or in quick-fried slag muck On repair slope course, it is ensured that the transport routes of upper layer step it is unimpeded, and then realize upper layer step and lower layer's step explosion, It digs the more work surfaces of multiplexings kind such as fortune and carries out parallel operations construction and traffic circulation simultaneously, accelerate construction speed.
Further, the tunneling boring unprotect layer tight-face blasting includes the following steps:
Step 3.1:According to the coefficient of volumetric expansion value for pressing slag before the main blast hole of first row, blasthole density is determined;
Reasonable coefficient of volumetric expansion K value range K=1.2~1.5 of quick-fried slag before main blast hole, the size of main blast hole coefficient of volumetric expansion K is to crowded Pressure explosion plays critically important effect, if K value is less than coefficient of volumetric expansion critical value KLIt, will be because of compensating space in blasting when i.e.≤1.1 It is too small, heel row explosion severe crush is caused, the mass effect of tight-face blasting fractured rock is seriously affected.
Step 3.2:According to the size of toe burden and minimum burden, the position of the main blast hole of first row is determined;
Tunneling boring unprotect floor tight-face blasting is to solve have pressure slag without the vertical scope of freedom before quick-fried area, and compensation space is small and carries out Blasting Excavation mode.
The toe burden of the main blast hole of first row is set as WBottom;Because the scope of freedom before the main blast hole of first row is filled out by quick-fried slag Full, compensating space in blasting is small, and explosive energy consumption is big when tight-face blasting, need to carry out explosive energy compensation, in favor of explosion into Row, therefore the main blast hole of first row is using reduction toe burden WBottomDistance, it is opposite to be equal to the practice for increasing explosive payload, with push from By the quick-fried slag of accumulation in front, a compensation space is formed, with the explosion of sharp heel row.The toe burden W of the main blast hole of first rowBottom's Distance is 0.5 times of scarfing cinder explosion burden W, (learning scarfing cinder explosion burden W=3m by common experience and calculating), first Arrange the toe burden W of main blast holeBottom=0.5W =1.5m。
Step 3.3:Complex reflex cumulative is determined according to main Pop Diameter and buffers the diameter and length of energy dissipator;
Step 3.4:Main blast hole drilling ultra-deep is determined according to the length of complex reflex cumulative and buffering energy dissipator;
Main blast hole drilling ultra-deep LC:Main blast hole drilling should rationally increase the ultra-deep value of main blast hole, and be additionally arranged at the bottom again in main blast hole It closes reflection cumulative and buffering energy dissipator carries out the explosion of unprotect layer, excavate foundation plane bottom plate blasting in once-through to foundation plane height Journey, the smooth reduction fluctuating for reaching foundation plane is poor, advantageously accounts for foundation residual, reduces explosion wave and protects to foundation plane bottom plate The damage for staying rock is played the role of protecting rock.It is determined and is drilled according to the length of complex reflex cumulative and buffering energy dissipator Ultra-deep, drilling ultra-deep are complex reflex cumulative and buffering energy dissipator length(Ld)Allow out break value with protective layer excavation(Permit Perhaps it owes to dig 0cm, allow the 20cm that backbreaks)The sum of.
Step 3.5:According to coefficient of volumetric expansion value, toe burden, determines the pitch-row of main blast hole, array pitch, explosive specific charge value, bores Hole length, length, the explosive payload for blocking section;
Main blast hole array pitch, pitch-row:Because being influenced by scope of freedom explosion slag, explosion space compensation need to be carried out, main blast hole is rationally increased Hole reticular density increases explosive energy compensation, to guarantee blasting quality, reduces the residual hole undesirable root in blasthole bottom, increases foundation plane bottom plate The flatness on chassis.In the case where not clearing up quick-fried slag before free face, the explosion that can make to get out of a predicament or an embarrassing situation persistently is carried forward.(1), Array pitch b=0.7W of the every row of the main blast hole of 2nd~6 row;(2), main blast hole close coefficient M=1.05;(3), main blast hole pitch-row a=Mb; (4), main blast hole to pre- ceasma pitch-row a2=0.7a.(5), main blast hole number of rows Np=6 row(Quick-fried head of district 12m);The main every round of blast hole Number Nk=4 holes/row;
Main blast hole explosive specific charge value:The scope of freedom before the main blast hole of first row is crowded with slags, and the shock wave stress wave that explosion generates arrives It forms transmitted wave after entering slag up to the scope of freedom largely to be absorbed by rock slag, energy loss is very big, to solve to have pressure before quick-fried area Slag, compensating space in blasting is small, and explosive energy, which is worn and torn, consumes big problem, and explosive energy is needed to compensate, rule of thumb need raising 30%~ 40%, select biggish explosive specific charge amount.By scarfing cinder rendrock unit consumption empirical value qqObtain the main blast hole explosive specific charge of tight-face blasting Value.
(1), the main blast hole of the 2nd~6 row increase tight-face blasting explosive specific charge value q2=(1+30%)qq =0.49kg/m3
(2), the 1st row increase tight-face blasting explosive specific charge value q1=1.41q2=0.69 kg/m3
Main blast hole explosive specific charge value q when wherein having a free face scarfing cinder explosionq=0.38kg/m3
Main blast hole drilling depth L=lower layer step height H2+ main blast hole drills ultra-deep LC
Block the length of section;The length of reasonable blocking section not only can guarantee that rock was sufficiently rationally crushed and travel forward, but also energy Guarantee, which does not generate, rushes big gun and slungshot, plays the role of making full use of explosion energy;The length L of main blast hole blocking sectiond1=26 D2
The single hole explosive payload of main blast hole is:
(1), the 1st main blast hole of row single hole explosive payload Q1= q1WBottomaL;
(2), the 2nd~6 main blast hole of row single hole explosive payload Q1= q2a bL。
Determine the pitch-row of pre- ceasma, linear charging density, dip angle of hole, drilling ultra-deep, drillable length, the length for blocking section, Explosive payload;
In order to which the rock quality after guaranteeing the smooth and explosion of pre- broken face is rule of thumb estimated;Presplitting hole drilling pitch-row E=11 D 2
Pre- ceasma uses decoupling charge, has radial clearance between Explosive roll and blasthole, can reduce explosion wave Damage to palisades is played the role of protecting palisades, pre- ceasma Decoupling Coefficient η2=bore diameter(D2)/ powder stick diameter(Φ2).
Presplitting hole drilling ultra-deep value Lc2With main blast hole ultra-deep value LCIt is identical, presplitting hole drill hole depth L2= H2+Lc2, and it is main quick-fried Hole drill hole depth L is identical.
The length L of presplitting hole plug sectiond2=11 D2
To guarantee demolition effect, clamping action is overcome, pre- ceasma reinforces explosive payload and is:(1), pre- ceasma linear charging density qLine =800g/m,(2), biggish bottom hole dose to solve foundation residual, form foundation plane bottom plate Rapid Excavation, 1 meter of pre- ceasma bottom hole Reinforce 3 times of dose, QBottom=3qLine=2.40kg;(3), explosive payload Q in the middle and top part of pre- ceasmaOn=(L2- Ld2-L c2)qLine= 3.76kg (continuous medicine dress).
Step 3.6:The vertical main blast hole in a row of same apertures is drilled in the rock mass of excavation area;Main blast hole should ensure that when drilling The precision of dip angle of hole, aperture aperture position error ± 2cm, bore angle deviation 0.5% avoid shadow due to drilling quality is bad Ring demolition effect.
Step 3.7:Abutment wall presplitting hole drilling:
It should be there are certain outer limb, closer to setting when being conducive to lower layer's step blasthole mouth extrapolation when upper layer step abutment wall excavates Count aperture lines.
Lower layer's step tunneling boring unprotect layer tight-face blasting excavates wheel along design with the right and left abutment wall respectively in excavation Profile carries out presplit blasting, disposably reaches excavation design contour line, improves the flatness of palisades, reduces main blast hole explosion to rock The damage of wall.Presplitting hole drilling vertical inclination angle θ2=90 °, the lateral inclination angle of presplitting hole drilling is gently towards abutment wall outer incline extrapolation, laterally Extrapolation inclination angle thetaIn advance=87 °, abutment wall presplitting hole drilling:Aperture avoids pre- ceasma opening from having and owes to dig now close to Design of Side Wall line As.
Step 3.8:Main blast hole and presplitting hole bottom screed-coat it is levelling:Strict control blasthole Bottom Altitude, prevents from increasing Or ultra-deep value is reduced, foundation plane bottom plate out break is avoided the formation of, blasting quality is influenced.Hole depth first is carried out to blasthole before every separate explosion The inspection of degree simultaneously numbers record, and the blasthole of ultra-deep should backfill the rock powder of drilling or sand and consolidate carry out screed-coat, permits by hole depth Perhaps error ± 2cm progress hole depth is levelling, goes directly to design altitude;Not up to depth blasthole should mend brill again and be drilled into design height Journey.
Step 3.9:The ditch of 2~3m depth is dug on the pressure slag on the vertical scope of freedom before blast charging before the main blast hole of first row Slot, the pressure slag height before reducing the vertical scope of freedom, to improve the quality of tight-face blasting, trench depth is not more than the blocking section of blasthole Length, in favor of explosion and safety.
Step 3.10:Production, assembling complex reflex cumulative and buffering energy dissipator are simultaneously launched into main blast hole, and are made compound Reflection cumulative is sufficiently contacted with main blast hole bottom hole rock face or screed-coat with buffering energy dissipator bottom surface, and inspection record.
Step 3.11:Be filled in each main blast hole complex reflex cumulative and buffering energy dissipator and main blasting charge and The detonating material of same delay time is allowed to same to be detonated using the same main blast hole and blast hole projectile filling and with the time Shi Jinhang tight-face blasting and unprotected bottom plate Excavation blasting.Main blast hole is carried out by the explosive payload and loaded length of explosion design Loaded with the explosive and detonating material of pre- ceasma, explosive uses coiled nitrolite, powder stick diameter should be less than blasthole diameter 1cm with On, to facilitate powder stick to enter blasthole.It is designed by explosion initiation net, detonating material uses plastic detonating tube millisecond extension thunder in hole Pipe;
Step 3.12:Main blast hole and presplitting hole plug are carried out by the length of the blocking section of explosion design;Plugging material drilling Rock powder or half-dried loess, when blocking, should consolidate plugging material.
Step 3.13:Dynamite charge finishes, and is connected to the network by the design of explosion initiation net, is detonated after confirming safety.
The NONEL firing network that initiation net is formed using plastic detonating tube millisecond detonator and primacord, i.e., in each loading The non-electrical millisecond delay cap of correspondent section alias is packed into the main blast hole of explosive;The explosive being packed into each pre- ceasma should be tied up On primacord, it is together to form non-electrical blasting network.Main blast hole is using millisecond detonating mode between " V " type or row.Left and right sides The pre- ceasma of wall detonates simultaneously, and pre- ceasma detonates earlier than main blast hole 50ms.Each other detonator interval delay time between main blast hole row Greater than 50ms, the shot rock that reasonable time interval is conducive to front row, which is sufficiently travelled forward and collided, to be crushed, and is created for heel row Compensation space is conducive to explosion.Using indirect initiation mode, detonator is fried mounted in the cumulative of complex reflex cumulative and buffering energy dissipator At medicine and blasthole bottom, blasthole lower part first detonate and fractured rock and move upwards detonation wave, for the explosion for extending blasthole bottom The gas wedge broken rock action time that high temperature and high pressure gas is formed, be conducive to the progress of lower part shot hole blasting broken rock, while detonation stresses Wave strengthens rock breaking efficiency in bottom hole multiple stacking, improves lower part shot hole blasting quality.
Further, the diameter of the complex reflex cumulative and buffering energy dissipator is the 0.8~0.9 of main Pop Diameter Times, 25~35cm of length of complex reflex cumulative and buffering energy dissipator.
Further, the complex reflex cumulative and buffering energy dissipator include the buffering energy dissipating successively laid from bottom to up Bed course, rigid bed course, reflection cumulative cushion and energy-gathering jetting device;The buffering energy dissipating bed course includes cylindrical steel shell and fills Fill out the low-density buffering energy dissipating core in outer steel shell;Rigid bed course, the rigid bed course are fixedly connected with above buffering energy dissipating bed course For circular slab;It has been bolted reflection cumulative cushion above rigid bed course, has reflected cumulative cushion from top to bottom gradually Expansion is in horn-like structure;The periphery of reflection cumulative cushion is laid with energy-gathering jetting device, and energy-gathering jetting device includes cumulative medicine Type cover, waveform adjuster, flexible linear-shaped charge and flexible linear-shaped charge detonating material;The cumulative cavity liner is thin walled shell, and cumulative cavity liner is in The dumb-bell shape that both ends are thick, middle part is tapered, the top inside cumulative cavity liner are laid with waveform adjuster, the waveform adjustment Device is in the funnel-form that bus is curve and the peripheral surface for being set on reflection cumulative cushion top.When every separate explosion, quick-fried area The complex reflex cumulative of each blasthole is identical as buffering energy dissipator structure size.
Further, the drilling ultra-deep is that complex reflex cumulative and buffering energy dissipator length and protective layer excavation allow The sum of out break value.
Further, each excavation length of main blast hole is 12m, increases by 1~2 row's reinforced hole more than 12m, excavation width is to set It is wide to count hole.
Further, each excavation length of pre- ceasma is that 12m is identical with main blast hole, increases by 2~3 reinforcements more than 12m Hole.
Further, after the progress tunneling boring unprotect layer tight-face blasting of lower layer's step proceeds to 12~24m, in quick-fried slag Traffic route of the slope course as upper layer step is built on heap.
Further, slope course longitudinal direction slope ratio is not more than 1:12, width of roadway is greater than 6m.
Compared with prior art, the beneficial effects of the present invention are:
1, method safety performance height of the invention, easily operated, reliable performance, it is easy for construction, it can effectively guarantee matter of constructing Amount improves construction speed, guarantees to carry out effective and reasonable excavation;Overcome the unfavorable shadow that large-scale tunnel full-face blast is excavated It rings, is excavated using benching tunnelling method, meet the condition of mechanical equipment and construction personnel's operation and construction safety technology;It is opened using benching tunnelling method When digging, overcomes the problems, such as that relatively narrow tunnel upper layer lower layer step there can only be an independent step to carry out excavation construction, realize lower layer's platform Rank and upper layer step carry out construction operation simultaneously, accelerate construction progress;Overcome the more difficult carry out half range of lower layer's step of relatively narrow tunnel It alternately excavates, realizes that the traffic route of lower layer's step is current and two function sections of Blasting Excavation carry out traffic circulation simultaneously and open Operation is dug, the unimpeded operation of the traffic route of upper layer step is met, realizes that upper layer step and lower layer's step carry out excavating simultaneously and applies Work accelerates construction progress.
2, lower layer's step carries out excavation construction using tunneling boring unprotect layer tight-face blasting method, is squeezed using main blast hole elementary errors Explosion and foundation plane bottom plate install the explosion of unprotect layer and the two sides abutment wall of " complex reflex cumulative and buffering energy dissipator " additional The blasting construction method for designing three kinds of blasting method organic assemblings of the presplit blasting that sideline is excavated forms lower layer's step after explosion Abutment wall, foundation plane bottom plate full face blasting molding.
3, lower layer's step bores the vertical blasthole in large aperture using hidden hole drilling, and it is quick-fried to realize that lower layer's step tunneling boring unprotect layer squeezes Broken, disposable large area explosion goes out the whole rocks got out of a predicament or an embarrassing situation, and improves mechanized construction level, subtracts hand air drill and bores lateral aperture Drilling depth is short, and speed is slow, large labor intensity, the drawback more than flow chart.Realize the feelings that not scarfing cinder in front of getting out of a predicament or an embarrassing situation has pressure slag It can continue to be carried forward tight-face blasting construction under condition, improve production efficiency.
4, main blast hole uses tight-face blasting, solves to have before quick-fried area pressure slag without vertical free face, the small problem of compensation space, Using smaller reasonable blasthole hole reticular density, reasonable blasthole ultra-deep, biggish explosive specific charge value, explosive energy compensation is carried out, In the case where not clearing up quick-fried slag before the scope of freedom, it is ensured that the blasting quality explosion that makes to get out of a predicament or an embarrassing situation persistently is carried forward.
5, lower layer's step foundation plane bottom plate uses the Rapid Excavation explosion of unprotect layer, and it is poly- to install complex reflex additional in blasthole bottom hole Can with buffering energy dissipator, the bus of energy-gathering jetting device and reflection cumulative cushion generates when explosive initiation energy-gathering jetting and Reflecting energy-gathering jetting has dual cumulative action, can increase the horizontal break line of blasthole floor rocks, and it is biggish to form bottom hole Square position, the ability for enhancing fractured rock solve foundation residual, excavate foundation plane bottom plate blasting in once-through to design altitude, improve Foundation plane explosion flatness;And reflect the steel that cumulative cushion, rigid bed course and buffering energy dissipating bed course form three-decker together Property and bubble property composite cushion, there is the energy dissipating effect that buffers three times, can effectively cut down explosion energy, reduction blasthole bottom Vertical explosion damage, has the function that protect foundation plane floor rock integrality, guarantees bottom hole rock quality.
6, the presplit blasting for realizing both sides abutment wall is reduced by the method for carrying out radial decoupling charge in pre- ceasma Damage of the explosion wave to palisades;Improve the flatness of palisades.
7, the layer tight-face blasting of lower layer's step tunneling boring unprotect is excavated, and has been well solved lower layer's step and should be bored and pops Dig, guarantee smooth problem as upper layer step traffic route again, realize lower layer's step and meanwhile carry out Blasting Excavation with As the traffic route purpose of upper layer step, realizes and repair slope course on the quick-fried slag muck of lower layer's step as upper layer step Traffic route, it is ensured that upper layer step has a good transport and communication network.Two function operation areas of Blasting Excavation and traffic aisle are formd, they can be with Carry out drillhole blasting operation and slope course simultaneously and protect logical operation, and follow hard on upper layer step excavates forward promote and to being pushed forward Into, and then realize the upper and lower step of narrow tunnel space while carrying out more work surface parallel operations constructions, greatly It accelerates construction progress, provides work surface and time for the secondary reinforced concrete lining layer work of subsequent tunnel.
Detailed description of the invention
Fig. 1 is tunnel lower layer step tunneling boring unprotect layer tight-face blasting of the present invention and repairs the roads and protect the longitudinal direction of logical construction method Diagrammatic cross-section.
Fig. 2 is the main blast hole of embodiment 1 and the plan view of pre- ceasma.
Fig. 3 is the main blast hole of embodiment 1 and the diagrammatic cross-section of pre- ceasma arrangement.
Fig. 4 is the diagrammatic cross-section after the single main blast hole powder charge of embodiment 1.
Fig. 5 is the complex reflex cumulative of embodiment 1 and the schematic perspective view of buffering energy dissipator.
Fig. 6 is the complex reflex cumulative of embodiment 1 and the decomposition diagram of buffering energy dissipator.
Fig. 7 is the quick-fried based on complex reflex cumulative and the flexible linear-shaped charge in the blast working of buffering energy dissipator of embodiment 1 The fried circumferential Explosive impact jet action schematic diagram generated.
Fig. 8 is reflection cumulative buffering in the blast working based on complex reflex cumulative and buffering energy dissipator of embodiment 1 The impact jet flow that bed course generates the reflection cumulative of the main blasting charge explosion wave of blasthole acts on schematic diagram.
Fig. 9 is the quick-fried based on complex reflex cumulative and the flexible linear-shaped charge in the blast working of buffering energy dissipator of embodiment 1 The fried circumferential Explosive impact jet action generated and reflection cumulative cushion, rigidity bed course and buffering energy dissipating bed course are to explosion The vertical buffering energy dissipating of shock wave acts on schematic diagram.
Figure 10 is that the reflection cumulative in the blast working based on complex reflex cumulative and buffering energy dissipator of embodiment 1 is slow Rush bed course to the main blasting charge explosion wave of blasthole reflection cumulative generate impact jet flow act on and reflection cumulative cushion, Steel bed course, buffering energy dissipating bed course act on schematic diagram to the vertical buffering energy dissipating of explosion wave.
Numbering in the drawing is:1 is Wall Rock of Tunnel, and 2 be face, and 3 wait for excavation area for upper layer step, and 4 squeeze for lower layer's step Blasting Excavation area is pressed, 5 be main blast hole, and 6 be the slag of tight-face blasting, and 7 be existing slope road, and 8 be the slope road before changing its course translation, 9 be foundation plane bottom plate, and 10 be tunnel, and 11 be down-the-hole drill, and 12 bore lateral aperture for hand air drill, and 13 be the main blast hole of most heel row, and 14 are Pre- ceasma, 15 be the main blast hole of first row, and 16 be lacing hole, and 17 be the scope of freedom, and 18 is block section, and 19 be main blasting charge, and 20 be multiple Reflection cumulative and buffering energy dissipating bed course device are closed, 21 be outer steel shell, and 22 buffer energy dissipating core for low-density, and 23 be rigid bed course, and 24 are Cumulative cavity liner, 25 be reflection cumulative cushion, and 26 be flexible linear-shaped charge, and 27 be waveform adjuster, and 28 be detonating material, and 29 be biography Quick-fried line, the perforation of 30 primacords, 31 be pin bolt, and 32 be circumferential Explosive impact jet stream, and 33 be main blasting charge explosion wave, 34 It is reflection cumulative for the impact jet flow that reflection cumulative of the reflection cumulative cushion to blasthole main charge explosion wave generates, 35 Cushion acts on the vertical buffering energy dissipating of explosion wave, and 36 make the vertical buffering energy dissipating of explosion wave for rigid bed course With 37 be to buffer energy dissipating bed course to act on the vertical buffering energy dissipating of explosion wave, and 38 energy-gathering jetting devices, 39 be primacord.
Specific embodiment
The following examples are intended to illustrate the invention, but is not used to limit the scope of protection of the present invention.Unless otherwise specified, real Apply the conventional means that technological means used in example is well known to those skilled in the art.
Embodiment 1
It the step tunneling boring unprotect layer tight-face blasting of tunnel lower layer and repairs the roads and protects logical construction method, include the following steps:
Step 1:Using benching tunnelling method digging mode, according to tunnel section size, the wide B=9.6m in hole, high H=12.5m, tunnel excavation It is designed as top-down positive benching tunnelling method to excavate, divides upper layer and lower layer step, the high H of upper layer step tunnel1=6.8mm, lower layer's step Height H2=5.7m.Bore blowing-up method excavation construction is all made of in hole, large-scale mucker tool digging transports slag.
Step 2:The excavation of upper layer step is carried out first.Upper layer step drill-blast tunnelling carries out in advance, is made using lower layer's step For upper layer step slag tap and traffic route.Upper layer step is excavated using conventional step full-face blast method, and hand air drill bores water Flat hole.
Step 3:After the bench excavation drilling depth 60m of upper layer, lower layer's step starts to carry out drillhole blasting excavation operation, and keeps Spacing 60m follow-up is excavated.Lower layer's step is divided into two operating areas, and one is tunneling boring unprotect layer tight-face blasting region, separately One is region as the slope road of upper layer traffic route.It is quick-fried that the extruding of tunneling boring unprotect layer is carried out in lower layer's step first It is broken.Then slope course is built on the quick-fried slag muck of tight-face blasting, provides traffic aisle for upper layer step, it is ensured that upper layer step is handed over It is unobstructed logical.Lower layer's step carries out excavation construction using tunneling boring unprotect layer tight-face blasting method, is squeezed using main blast hole elementary errors quick-fried Broken and foundation plane bottom plate installs complex reflex cumulative and the buffering unprotect layer explosion of energy dissipator 20 and setting for two sides abutment wall additional The blasting construction method for counting three kinds of blasting method organic assemblings of the presplit blasting that sideline is excavated forms lower layer's step after explosion Abutment wall, the molding of foundation plane bottom plate full face blasting.
The vertical main blast hole in a row of same apertures is drilled in the rock mass of excavation area;Main blast hole:Using tight-face blasting, unclear Before the reason scope of freedom in the case where quick-fried slag, it is carried forward lower layer's bench blasting persistently.The bottom of main blast hole is compound using installing additional It reflects cumulative and buffers the unprotect layer drillhole blasting of energy dissipator 20, excavate foundation plane bottom plate blasting in once-through to foundation plane Elevation reaches the smooth of foundation plane, and it is poor that reduction rises and falls, and reduces damage of the explosion to foundation plane rock, plays the work of protection rock With.
Presplit blasting:Both sides abutment wall carries out presplit blasting along design excavation contour line, disposably reaches excavation design profile Line improves the flatness of palisades, reduces damage of the main blast hole explosion to palisades.
Initiation net:Main blast hole uses " V " type detonation mode, it is possible to provide it is empty to increase explosion compensation for two vertical scope of freedoms Between, reduce the impact damage to palisades.
The tunneling boring unprotect layer tight-face blasting of lower layer's step includes the following steps:
Step 3.1:According to the coefficient of volumetric expansion value for pressing slag before the main blast hole of first row, front-seat main blast hole density is determined;
By the on-site test in hole and calculating, practical coefficient of volumetric expansion K is the rock loose volume V after explosion1Before explosion Geological diagnostics volume V2Ratio;K value indicates the size of the practical loosening degree of rock after explosion.Practical coefficient of volumetric expansion K=V1/V2= 1.22, meet the requirement of K value range.
Step 3.2:According to the size of toe burden and minimum burden, the position of the main blast hole of first row is determined;
The main blast hole of first row is using reduction toe burden WBottomDistance, take tight-face blasting toe burden WBottomEqual to scarfing cinder explosion 0.5 times of burden W learns scarfing cinder explosion burden W=3m, tight-face blasting toe burden W by experience and calculatingBottom=0.5W= 1.5m。
Step 3.3:Complex reflex cumulative is determined according to main blast hole bore diameter and buffers the diameter and length of energy dissipator 20;
Main blast hole is drilled using down-the-hole trolley, and pre- ceasma is drilled using simple rack formula hidden hole drilling, bore diameter D 2=90mm.It is latent Hole drill is along the vertical blasthole of lower layer's step top surface drill down, main blast hole drilling inclination angle thetaIt is main=90 °, presplitting hole drilling slightly extrapolation is inclined Angle θIn advance=87°.Select 2# rock powdery emulsion explosive and emulsion.
The diameter of the present embodiment complex reflex cumulative and buffering energy dissipator 20 is 0.9 times of bore diameter, is 8cm.It is multiple It closes reflection cumulative and buffering 20 total length of energy dissipator takes 29cm, is i.e. the reflection rigid bed course 1.5cm+ of cumulative cushion 7.5cm+ is slow Rush energy dissipating bed course 20cm=complex reflex cumulative and buffering energy dissipator length 29cm.
Step 3.4:Drilling ultra-deep is determined according to the length of complex reflex cumulative and buffering energy dissipator 20;Complex reflex is poly- It can be with buffering 20 length L of energy dissipatord=29cm, drilling ultra-deep are complex reflex cumulative and buffering 20 length of energy dissipator (29cm)Allow out break value with protective layer excavation(Allow to owe to dig 0cm, allow the 20cm that backbreaks, takes the depth 10cm that actually backbreaks)It With i.e. drilling ultra-deep 39cm.
Step 3.5:According to coefficient of volumetric expansion value, toe burden, determines the pitch-row of main blast hole, array pitch, explosive specific charge value, bores Hole length, length, the explosive payload for blocking section;
Main blast hole blasthole array pitch, pitch-row:Because being influenced by scope of freedom explosion slag, explosion space compensation need to be carried out, master is rationally increased Blast hole hole reticular density increases explosive energy compensation, to guarantee blasting quality, reduces the residual hole undesirable root in blasthole bottom, increases foundation plane The flatness of backplane chassis.In the case where not clearing up quick-fried slag before free face, the explosion that can make to get out of a predicament or an embarrassing situation persistently is carried forward. (1), the every row of the main blast hole of the 2nd~6 row array pitch b=0.7W=2.1m;(2), main blast hole close coefficient M=1.05;(3), main blast hole Pitch-row a=Mb=2.2m;(4), main blast hole to pre- ceasma pitch-row a2=0.7a=1.54m.(5), main blast hole number of rows Np=6 row(Quick-fried area Long 12m);The main every round number Nk=4 holes/row of blast hole;
Main blast hole explosive specific charge value:The scope of freedom before the main blast hole of first row is crowded with slags, and the shock wave stress wave that explosion generates arrives Transmitted wave is formed after entering slag up to the scope of freedom, most of to be absorbed by rock slag, energy loss is very big, to solve to have pressure before quick-fried area Slag, compensating space in blasting is small, and explosive energy consumes big problem, and explosive energy is needed to compensate, rule of thumb need raising 30%~ 40%, select biggish explosive specific charge amount.By scarfing cinder rendrock unit consumption empirical value qqObtain the main blast hole explosive specific charge of tight-face blasting Value.
(1), the main blast hole of the 2nd~6 row increase tight-face blasting explosive specific charge value q2=(1+30%)qq =0.49kg/m3
(2), the 1st row increase tight-face blasting explosive specific charge value q1=1.41q2=0.69 kg/m3
Main blast hole explosive specific charge value q when wherein having a free face scarfing cinder explosionq=0.38kg/m3
Main blast hole drilling depth L=lower layer step height H2+ main blast hole drills ultra-deep LC=6.09m。
Block the length of section:The length of reasonable blocking section not only can guarantee that rock was sufficiently rationally crushed and travel forward, but also energy Guarantee, which does not generate, rushes big gun and slungshot, plays the role of making full use of explosion energy;The length L of main blast hole blocking sectiond1=26 D2= 2.34m。
The single hole explosive payload of main blast hole is:
(1), the main blast hole of first row single hole explosive payload Q1= q1WBottomThe hole the kg/ of aL=0.69*1.5*2.2*6.09=13.86;
(2), the 2nd ~ 6 main blast hole of row single hole explosive payload Q1= q2The hole the kg/ of a bL=0.49*2.2*2.1*6.09=13.79.
Determine the pitch-row of pre- ceasma, linear charging density, dip angle of hole, drilling ultra-deep, drillable length, the length for blocking section, Explosive payload;
In order to which the rock quality after guaranteeing the smooth and explosion of pre- broken face is rule of thumb estimated;Presplitting hole drilling pitch-row E=11 D 2
Pre- ceasma uses decoupling charge, has radial clearance between Explosive roll and blasthole, can reduce explosion wave Damage to palisades is played the role of protecting palisades, pre- ceasma Decoupling Coefficient η2=bore diameter(D2)/ powder stick diameter(Φ2)= 2.8.Presplitting hole drilling pitch-row E=11 D 2=1m.Powder stick(Using 2 ﹟ rock emulsion explosives)Diameter of phi2=32mm。
Presplitting hole drilling ultra-deep value Lc2With main blast hole ultra-deep value LCIt is identical, presplitting hole drill hole depth L2= H2+Lc2, and it is main quick-fried Hole drill hole depth L is identical, is 6.09m.
The length L of presplitting hole plug sectiond2=11 D2=1m。
For guarantee demolition effect, the pre- ceasma of clamping action is overcome to reinforce explosive payload,(1), pre- ceasma linear charging density qLine= 800g/m,(2), biggish bottom hole dose to solve foundation residual, form foundation plane bottom plate Rapid Excavation, 1 meter of pre- ceasma bottom hole Reinforce 3 times of dose, QBottom=3qLine=2.40kg;(3), explosive payload Q in the middle and top part of pre- ceasmaOn=(L2- Ld2-L c2)qLine= 3.76kg (continuous medicine dress).
Step 3.6:The vertical main blast hole in a row of same apertures is drilled in the rock mass of excavation area;It should ensure that drilling is inclined when drilling The precision at angle, aperture aperture position error ± 2cm, bore angle deviation 0.5% avoid influencing explosion because drilling quality is bad Effect.
Step 3.7:Abutment wall presplitting hole drilling:Aperture avoids blasthole opening from having and owes to dig phenomenon close to Design of Side Wall line.? Upper layer step abutment wall should also design certain outer limb when excavating, closer to design when being conducive to lower layer's step blasthole mouth extrapolation Aperture lines.
Lower layer's step tunneling boring unprotect layer tight-face blasting excavates wheel along design with the right and left abutment wall respectively in excavation Profile carries out presplit blasting, disposably reaches excavation design contour line, improves the flatness of palisades, reduces main blast hole explosion to rock The damage of wall.Presplitting hole drilling vertical inclination angle θ2=90 °, the lateral inclination angle of presplitting hole drilling is gently towards abutment wall outer incline extrapolation, laterally Extrapolation inclination angle thetaIn advance=87 °, abutment wall presplitting hole drilling:Aperture avoids pre- ceasma opening from having and owes to dig now close to Design of Side Wall line As.
Step 3.8:Main blast hole and presplitting hole bottom screed-coat it is levelling:The main blast hole of strict control and presplitting hole bottom are high Journey prevents from increasing or reducing ultra-deep value, avoids the formation of foundation plane bottom plate out break, influence blasting quality.It is first right before every separate explosion The inspection that main blast hole and pre- ceasma carry out hole depth simultaneously numbers record, and the blasthole of ultra-deep should backfill the rock powder of drilling or sand and smash It is real to carry out screed-coat, it is levelling by hole depth allowable error ± 2cm progress hole depth, it goes directly to design altitude;Not up to depth blasthole weight New mend is drilled into design altitude.
Step 3.9:It is deep that 2m~2.3m is dug on the pressure slag on the vertical scope of freedom before blast charging before the main blast hole of first row Groove, groove should be less than the length of the blocking section equal to main blast hole, and the pressure slag height before reducing the vertical scope of freedom is crowded to improve Press the quality of explosion.
Step 3.10:Production, assembling complex reflex cumulative and buffering energy dissipating bed course device 20, are launched into main blast hole It is interior, and contact its bottom surface sufficiently with main blast hole bottom rock face or screed-coat, and inspection record.In the present embodiment, presplitting bottom hole Also complex reflex cumulative and buffering energy dissipator 20 have been launched in portion.
Complex reflex cumulative and buffering energy dissipator 20, including buffering energy dissipating bed course, the rigid pad successively laid from bottom to up Layer 23, reflection cumulative cushion 25 and energy-gathering jetting device 38;The buffering energy dissipating bed course includes cylindrical steel shell 21 and fills Fill out the low-density buffering energy dissipating core 22 in outer steel shell 21;It is fixedly connected with rigid bed course 23 above buffering energy dissipating bed course, it is described Rigid bed course 23 is circular slab;Rigid bed course 23 is connected with reflection cumulative cushion 25, reflection cumulative buffering by pin bolt 31 Bed course 25 is gradually expanded from top to bottom in horn-like structure;The periphery of reflection cumulative cushion 25 is laid with energy-gathering jetting device 38, energy-gathering jetting device 38 include cumulative cavity liner 24 and waveform adjuster 27, the cumulative cavity liner 24 be up and down in Empty thin walled shell, the dumb-bell shape that thick, middle part is tapered in both ends of cumulative cavity liner 24, the top cloth inside cumulative cavity liner 24 Equipped with waveform adjuster 27, the waveform adjuster 27 is in the funnel-form that bus is curve and among it with slow with reflection cumulative Cavity that 25 top of bed course matches, gradually expanding from top to bottom is rushed, waveform adjuster 27 is set on reflection cumulative cushion The peripheral surface on 25 top of layer is laid with 2 primacords perforation 30 in the waveform adjuster 27.The reflection cumulative cushion Flexible linear-shaped charge 26 is filled between layer 25 and energy-gathering jetting device 38, the flexible linear-shaped charge 26 is industrial emulsion explosive, flexible linear-shaped charge It is uniformly distributed in 26 to have detonating material 28,1 cyclic annular primacord that the detonating material 28 includes 2 pieces of millisecond detonators, connect with detonator 39 and primacord 29, the primacord 29 is the plastic detonating tube in millisecond detonator, and one end connects the millisecond thunder of detonating material 28 Pipe, the other end, which are led to outside blasthole, is connected to main blasting circuit.Reflection 25 top of cumulative cushion is provided with wearing for a diameter 5mm Cord hole 16, for wearing tow.When every separate explosion, the complex reflex cumulative and buffering 20 structure ruler of energy dissipator of the quick-fried each blasthole in area It is very little identical.
Step 3.11:The main blasting charge of main blast hole and pre- ceasma is carried out by the explosive payload and loaded length of explosion design and is risen Quick-fried body filling, explosive use coiled nitrolite, and powder stick diameter is less than blasthole diameter 1cm, to facilitate powder stick to enter blasthole.It presses Explosion initiation net designs, and detonating material is using in plastic detonating tube millisecond delay cap insertion explosive in hole.The same main blast hole It is filled with complex reflex cumulative and buffering energy dissipator 20 and main blasting charge and the detonating material of same delay time, inside to utilize The same main blast hole and blast hole projectile filling and with the time detonate, allow to carry out tight-face blasting and unprotected bottom plate simultaneously Excavation blasting.
Step 3.12:Main blast hole and presplitting hole plug are carried out by the length of the blocking section of explosion design;Plugging material bores The rock powder in hole, when blocking, consolidate plugging material.
Step 3.13:Dynamite charge finishes, and is connected to the network by the design of explosion initiation net, is detonated after confirming safety.
The NONEL firing network that initiation net is formed using plastic detonating tube millisecond detonator and primacord, i.e., in each loading The non-electrical millisecond delay cap of correspondent section alias is packed into the main blast hole of explosive;It is packed into and leads in each pre- ceasma for being packed into explosive Quick-fried rope, the non-electrical blasting network being together to form.The pre- ceasma of left and right sides abutment wall detonates simultaneously, and pre- ceasma is earlier than main blast hole 50ms detonation.Main blast hole uses " V " type detonation mode, forms two scope of freedoms newly increased from front-seat and side and is conducive to heel row Explosion.Detonation arranges the beginning successively to heel row and side progress " V " type explosion in the past.Each other detonator interval delay time is big between row In 50ms.
Region, each excavation length 12m are excavated in lower layer's step tunneling boring unprotect layer tight-face blasting.Excavation width is design The wide 9.6m in hole.Each pre- ceasma excavation length is identical as main blast hole, is also 12m.
Step 4:Slope course, lower layer's step are built on the quick-fried slag muck of lower layer's step tunneling boring unprotect layer tight-face blasting Tunneling boring unprotect layer tight-face blasting be persistently carried forward bursting work, keep having at a distance from 60m with upper layer step face. After carrying out tight-face blasting every time, fortune is dug with digging machine in time and removes explosion rock ballast extra at the top of the step of upper layer, it is ensured that the coast is clear.
With the tunneling boring unprotect layer tight-face blasting of lower layer's step be persistently carried forward and slope course should also follow it is quick-fried It is broken to elapse forwards:After the progress tunneling boring unprotect layer tight-face blasting of lower layer's step proceeds to 24m, with digging on quick-fried slag muck Traffic route of the slope course as upper layer step is built in machine maintenance, it is ensured that upper layer step has a good transport and communication network.Slope course longitudinal direction slope ratio is 1:12, width of roadway should be 6m.Between the slope course top and tight-face blasting region of lower layer's step between holding 20m or so Away from.
Two function operation areas of the layer tight-face blasting operation of tunneling boring unprotect and slope course communications and transportation of lower layer's step Domain is constructed and is run simultaneously, realize lower layer's step can continue carry out drillhole blasting excavation can also be on quick-fried slag muck Repair slope road, it is ensured that the transport routes of top bar it is unimpeded, and then realize upper layer step and lower layer's step explosion, dig fortune etc. The more work surfaces of multiplexing kind carry out parallel operations construction and traffic circulation simultaneously, accelerate construction speed, while using tight-face blasting There can be the case where pressure slag drillhole blasting before the vertical scope of freedom, be continued for being carried forward, work continuously, upper layer platform can be closely followed The excavation progress of rank.Since lower layer's step uses the layer tight-face blasting of tunneling boring unprotect, forms the abutment wall of lower layer's step, builds base The molding of face bottom plate full face blasting, several procedures once complete, and lower layer's step uses down-the-hole drill drilling, aperture compared with Greatly, digging machine, dumper is cooperated to slag tap, mechanization degree is high, and side's amount of onepull is larger, and drilling depth is longer, and high production efficiency is applied Work progress is fast, has saved construction production cost and time, it is ensured that integral construction progress, and be the secondary reinforcing bar of subsequent tunnel Concrete lining work provides working space and time.
2 Blasting Example effect of embodiment
Certain water conservancy construction engineering rock blasting is excavated, and is observed after multiple explosion, 1.5~2m of quick-fried heap bump height, quick-fried heap is uniform. Empty slot before first row blasthole to free face is filled up by quick-fried slag to be piled up, without big preshoot phenomenon;Front initial pile slag is without obvious displacement Phenomenon.Last artillery salvo hole, which slightly moves forward, to be turned over.Two sides abutment wall presplit blasting turns over phenomenon without big inside punching.
It excavates clear bottom after multiple explosion to watch, the rarer deficient digging phenomenon of foundation plane bottom plate, it is high that most regions reach design Journey, rare phenomenon of backbreaking.Big blasting crack is substantially not visible at foundation plane bottom plate blasthole to exist.Clearly may be used in two abutment wall presplitting holes See, rock wall surface is more smooth, and Half cast factor is high, reaches 85%, can't see apparent blasting crack and exists.Quick-fried slag occurs without boulder, rock Stone diameter is uniform, is suitble to dig fortune.
Not big slungshot occurs when multiple explosion, and no big concussion of blasting occurs, and vault side in top is checked after explosion The pneumatically placed concrete layer of wall does not find crack, does not occur loosening, chip off-falling phenomenon, the country rock of surrounding also not cracked loosening chip off-falling Phenomenon shows that concussion of blasting retains rock mass to surrounding and do not cause damage and failure.
The positive step tunneling boring of embodiment 3 replaces excavating load tunnel excavation
The hydraulic tunnel of certain new reservoir is as gateway opening type non-pressure tunnel, long 516m, excavated section size high 12.5m, wide 9.6m.Rock is andesitic porphyrite.
Tunnel is divided into upper and lower two layers of step, layering is excavated.The high 6.8m of upper layer step, the high 5.7m of lower layer's step.It adopts Lateral aperture, which is bored, with hand air drill carries out Blasting Excavation.Upper and lower two layers of step tunneling boring replaces excavation construction, and on upper layer, step carries out complete When section drill-blast tunnelling, using lower layer's step as road of slagging tap.Because lower layer's step height is larger, required slope course is longer, For 40~50m, and hand air drill is used to bore lateral aperture, the length of each Blasting Excavation only has 3~4m, and the rock ballast amount of institute's explosion can not Accomplish the slope course of 40~50m long.Furthermore slope course gland is blocked in the scope of freedom in lower layer's step drilling Blasting Excavation area Before, the spatial position of drillhole blasting is occupied, hand air drill can not be carried out by, which causing, bores lateral aperture and bursting work.In this way, working as upper layer Current using lower layer's step as traffic route when step carries out Blasting Excavation and mucks haulage, lower layer's step stops Blasting Excavation.To After the bench excavation to 60~80m of upper layer, upper layer step stops Blasting Excavation, then excavates lower layer's step;Upper layer, lower layer's platform in this way Rank alternate cycles carry out Excavation Blasting.This upper layer, lower layer's step alternately excavate construction method, every time only one The work surface of rank is carrying out excavation construction, so occupying, period construction time is longer, and production efficiency is lower, influences construction speed, And then can not work for the secondary reinforced concrete lining layer of subsequent tunnel and working space and time are provided, affect integral construction into Degree.
4 lower layer's step half range of embodiment replaces excavating load tunnel excavation
The hydraulic tunnel of certain new reservoir is as gateway opening type non-pressure tunnel, long 516m, excavated section size high 12.5m, wide 9.6m.Rock is andesitic porphyrite.
Lower layer's step is divided into the two half range regions in left and right, when left half range carries out drill-blast tunnelling operation, another right half range conduct The traffic route of upper layer step.After left half range Blasting Excavation tunnels 30~50m, that is, transform into as the traffic route of upper layer step, so Blasting Excavation is carried out again after carrying out the dismounting of right half range traffic route again afterwards, and such half range drill-blast tunnelling and another half range stay road current Alternately, that is, it forms half range alternately to excavate, and then forms the parallel construction of upper layer and lower layer step.Lower layer's step uses hand air drill Bore lateral aperture.The half range slope road road surface of lower layer's step is relatively narrow, and ramp longitudinal slope height difference is big(5.7m), the outer Slope of ramp horizontal slope Spend larger, it is larger that slope foot occupies another half range Blasting Excavation area area, influences construction of explosion and slags tap operation, while the slope that height difference is big Road, to the upper layer step of reverse travel muck haulage vehicle security implication it is very big.Under being influenced by these factors so that hole width is relatively narrow The more difficult half range that formed of floor step excavates the construction that half range stays the current alternately operating in road, since lower layer's step can not form explosion Operation while excavation and two functional areas of traffic aisle, can not form the more work surfaces of multiplexing kind of upper layer step Yu lower layer's step Parallel operations construction is carried out simultaneously, there can only be a step to carry out construction operation, occupied period construction time is longer, production effect Rate is lower, influences construction speed, so can not be provided for the secondary reinforced concrete lining layer work of subsequent tunnel working space and Time affects integral construction progress.
Channel process tunnel excavation in the drawing of 5 lower layer's Bench Extruding Blasting of embodiment
The hydraulic tunnel of certain new reservoir is as gateway opening type non-pressure tunnel, long 516m, excavated section size high 12.5m, wide 9.6m.Rock is andesitic porphyrite.
In lower layer's step top surface, the Blasting Excavation area of 5~6m wide is arranged along central axes, bores vertical blasthole with hidden hole drilling, into Row high bunch continuous method draws bracket groove, repairs slope road on the explosion rock ballast of bracket groove after explosion, the traffic route as upper layer step. Tight-face blasting technology is used simultaneously, can make hidden hole drilling that bracket groove be drawn to be continued for being carried forward the quick-fried operation of brill.To in lower layer's step Slot, which is slagged tap, to be changed after road digs and transport 40~50m, then carries out the photoface exploision brush side of both sides abutment wall and peaceful with hand air drill brill lateral aperture The quick-fried operation of the brill of foundation plane bottom plate.Channel process can solve the drill-blast tunnelling of lower layer's step and the road of upper layer step in tight-face blasting drawing The current problem in road can form the parallel operations construction of upper layer and lower layer step.
Draw bracket groove using hidden hole drilling, bore quick-fried operation and rock ballast clear it is more troublesome, because of the bracket groove narrower width drawn, only There is the width of 6 ~ 7m, hidden hole drilling operation is more difficult, and especially it is highly difficult to clear rock ballast for digging machine, since digging machine volume is larger, holds very much Easily encounter the palisades of middle trough rim, digging machine can not turn round entrucking in bracket groove, the length that can only be skimmed, and skim inside-out also compared with Long, mechanical work efficiency is very low, time-consuming,
Lateral aperture need be also bored after drawing bracket groove with hand air drill and carry out the brush side of two sides abutment wall and the quick-fried work of brill that foundation plane bottom plate is peaceful Industry, but the brush side of abutment wall is limited by hand air drill and the peaceful each excavation length of foundation plane bottom plate only has 3 ~ 5m, and abutment wall Brush side also needs to set up every time, dismantle that scaffold is time-consuming, and each cycle period is longer, need when each foundation plane bottom plate is peaceful The rock ballast that manually clear up bottom, can just measure unwrapping wire, then drillhole blasting, and these increased more flow charts And the activity duration, operating expenses is increased, and speed of application is slower.
The embodiment of the above is only used to explain the present invention, the scope of the present invention is not limited, for this technology It, certainly can be according to technology contents disclosed in this specification, by way of replacing or changing for the technical staff in field Other embodiments are made easily, therefore all changes and improvements etc. done in the principle of the present invention and process conditions, it should all wrap It includes in scope of the present invention patent.

Claims (10)

1. the step tunneling boring unprotect layer tight-face blasting of tunnel lower layer and repairing the roads and protecting logical construction method, which is characterized in that including Following steps:
Step 1:Using positive benching tunnelling method digging mode, tunnel is divided into upper layer and lower layer step, upper layer step height and lower layer's step Height is than being 1.1~1.2:1;
Step 2:Upper layer step is excavated using step full-face blast method;
Step 3:After the 60~80m of bench excavation drilling depth of upper layer, the layer tight-face blasting of tunneling boring unprotect is carried out in lower layer's step, and protect The follow-up of 60~80m spacing is held to excavate;The tunneling boring unprotect layer tight-face blasting is:Main blast hole carries out high bunch continuous method, builds The blasthole of basal plane bottom plate is using installation complex reflex cumulative and buffering energy dissipator(20)Carry out the explosion of unprotect layer, both sides abutment wall Presplit blasting is carried out along design excavation contour line;
Step 4:Build slope course on the quick-fried slag muck of lower layer's step tunneling boring unprotect layer tight-face blasting, slope course with The explosion of lower layer's step is changed its course passage forwards, makes to keep 12 between the slope course top of lower layer's step and tight-face blasting region The spacing of~24m.
2. the method according to claim 1, wherein the tunneling boring unprotect layer tight-face blasting includes following step Suddenly:
Step 3.1:According to the coefficient of volumetric expansion value for pressing slag before the main blast hole of first row, main blast hole density is determined;
Step 3.2:According to the size of toe burden and minimum burden, the position of the main blast hole of first row is determined;
Step 3.3:Complex reflex cumulative and buffering energy dissipator are determined according to main Pop Diameter(20)Diameter and length;
Step 3.4:According to complex reflex cumulative and buffering energy dissipator(20)Length determine main blast hole drilling ultra-deep;
Step 3.5:According to coefficient of volumetric expansion value, toe burden, determines the pitch-row of main blast hole, array pitch, explosive specific charge value, drills deeply The length and explosive payload of degree, blocking section;
Step 3.6:The vertical main blast hole in a row of same apertures is drilled in the rock mass of excavation area;
Step 3.7:Abutment wall presplitting hole drilling, for pre- ceasma to abutment wall outer incline extrapolation, extrapolation inclination angle is 87 °;
Step 3.8:Carry out the levelling of main blast hole and presplitting hole bottom screed-coat;
Step 3.9:The groove for pressing digging 2~3m depth on slag on the vertical scope of freedom, trench depth are little before the main blast hole of first row In the length of the blocking section of main blast hole;
Step 3.10:Production, assembling complex reflex cumulative and buffering energy dissipator(20)And it launches into main blast hole;
Step 3.11:Complex reflex cumulative and buffering energy dissipator are filled in each main blast hole(20), main blasting charge and The detonating material of same delay time is allowed to same to be detonated using the same main blast hole and blast hole projectile filling and with the time Shi Jinhang tight-face blasting and unprotected bottom plate Excavation blasting;Main blast hole is carried out by the explosive payload and loaded length of explosion design It is loaded with the explosive and detonating material of pre- ceasma;It is designed by explosion initiation net, detonating material uses plastic detonating tube millisecond extension thunder Pipe;
Step 3.12:Main blast hole and presplitting hole plug are carried out by the length of the blocking section of explosion design;
Step 3.13:It is connected to the network by the design of explosion initiation net, is detonated after confirming safety.
3. according to the method described in claim 2, it is characterized in that, the complex reflex cumulative and buffering energy dissipator(20)'s Diameter is 0.8~0.9 times of main Pop Diameter, complex reflex cumulative and buffering energy dissipator(20)Length be 25~35cm.
4. according to the method described in claim 2, it is characterized in that, the complex reflex cumulative and buffering energy dissipator(20)Packet Include buffering energy dissipating bed course, the rigid bed course successively laid from bottom to up(23), reflection cumulative cushion(25)With energy-gathering jetting device (38);Complex reflex cumulative and buffering energy dissipator when every separate explosion, in the quick-fried each main blast hole in area(20)Structure size is identical.
5. according to the method described in claim 2, it is characterized in that, the drilling ultra-deep is complex reflex cumulative and buffering energy dissipating Device(20)Length and protective layer excavation allow the sum of out break value.
6. the method according to claim 1, wherein main blast hole is using millisecond detonating mode between " V " type or row.
7. increasing by 1 more than 12m the method according to claim 1, wherein each excavation length of main blast hole is 12m ~2 row's reinforced holes, excavation width are that design hole is wide.
8. increasing by 2 more than 12m the method according to claim 1, wherein each excavation length of pre- ceasma is 12m ~3 reinforced holes.
9. the method according to claim 1, wherein when lower layer's step carries out the layer tight-face blasting of tunneling boring unprotect After proceeding to 12~24m, traffic route of the slope course as upper layer step is built on quick-fried slag muck.
10. according to the method described in claim 9, it is characterized in that, slope course longitudinal direction slope ratio is not more than 1:12, slope course Width of roadway is greater than 6m.
CN201810719086.1A 2018-07-03 2018-07-03 Construction method for tunnel lower-layer step full-section protective-layer-free extrusion blasting and road repairing and access protection Active CN108915694B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810719086.1A CN108915694B (en) 2018-07-03 2018-07-03 Construction method for tunnel lower-layer step full-section protective-layer-free extrusion blasting and road repairing and access protection

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810719086.1A CN108915694B (en) 2018-07-03 2018-07-03 Construction method for tunnel lower-layer step full-section protective-layer-free extrusion blasting and road repairing and access protection

Publications (2)

Publication Number Publication Date
CN108915694A true CN108915694A (en) 2018-11-30
CN108915694B CN108915694B (en) 2020-03-31

Family

ID=64423609

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810719086.1A Active CN108915694B (en) 2018-07-03 2018-07-03 Construction method for tunnel lower-layer step full-section protective-layer-free extrusion blasting and road repairing and access protection

Country Status (1)

Country Link
CN (1) CN108915694B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110307761A (en) * 2019-06-25 2019-10-08 中国水利水电第四工程局有限公司 One kind being used for the one-time formed method of diversion tunnel middle layer full face tunneling
CN112539064A (en) * 2020-11-30 2021-03-23 青岛理工大学 Blasting vibration reduction construction method for close tunnel with composite pilot tunnel and preset composite vibration isolation layer
CN113803075A (en) * 2021-09-15 2021-12-17 中国铁建大桥工程局集团有限公司 Efficient and environment-friendly tunnel excavation construction method
CN114705092A (en) * 2022-03-09 2022-07-05 车兆学 Method for uniformly positioning and continuously distributing ground coordinates for strip mine bench blasting drilling

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20110041868A (en) * 2009-10-16 2011-04-22 (주)한국투아치 Variable and reinforced type double bore tunnels and method for constructing the same
CN103968721A (en) * 2014-05-26 2014-08-06 武汉大学 Hole bottom energy gathering and dissipating device suitable for inclined blast hole and capable of improving blasting excavation flatness of foundation surface
CN106091848A (en) * 2016-06-22 2016-11-09 四川路桥华东建设有限责任公司 A kind of realize overlength, high inclination-angle tunnel anchorage tops bar the method for explosion
CN107687799A (en) * 2017-10-19 2018-02-13 武汉大学 A kind of device for reducing methods of blasting toes in open
CN108050902A (en) * 2018-01-12 2018-05-18 中铁上海工程局集团有限公司 A kind of tunnel blasting excavation method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20110041868A (en) * 2009-10-16 2011-04-22 (주)한국투아치 Variable and reinforced type double bore tunnels and method for constructing the same
CN103968721A (en) * 2014-05-26 2014-08-06 武汉大学 Hole bottom energy gathering and dissipating device suitable for inclined blast hole and capable of improving blasting excavation flatness of foundation surface
CN106091848A (en) * 2016-06-22 2016-11-09 四川路桥华东建设有限责任公司 A kind of realize overlength, high inclination-angle tunnel anchorage tops bar the method for explosion
CN107687799A (en) * 2017-10-19 2018-02-13 武汉大学 A kind of device for reducing methods of blasting toes in open
CN108050902A (en) * 2018-01-12 2018-05-18 中铁上海工程局集团有限公司 A kind of tunnel blasting excavation method

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
康迎宾 等: "挤压***拉中槽在前坪水库中的应用", 《河南水利与南水北调》 *
罗福生 等: "《中国水利报:河南前坪工程"三洞"完工零事故》", 29 June 2018 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110307761A (en) * 2019-06-25 2019-10-08 中国水利水电第四工程局有限公司 One kind being used for the one-time formed method of diversion tunnel middle layer full face tunneling
CN112539064A (en) * 2020-11-30 2021-03-23 青岛理工大学 Blasting vibration reduction construction method for close tunnel with composite pilot tunnel and preset composite vibration isolation layer
CN112539064B (en) * 2020-11-30 2022-02-11 青岛理工大学 Blasting vibration reduction construction method for close tunnel with composite pilot tunnel and preset composite vibration isolation layer
CN113803075A (en) * 2021-09-15 2021-12-17 中国铁建大桥工程局集团有限公司 Efficient and environment-friendly tunnel excavation construction method
CN113803075B (en) * 2021-09-15 2024-05-31 中国铁建大桥工程局集团有限公司 Efficient and environment-friendly tunnel excavation construction method
CN114705092A (en) * 2022-03-09 2022-07-05 车兆学 Method for uniformly positioning and continuously distributing ground coordinates for strip mine bench blasting drilling

Also Published As

Publication number Publication date
CN108915694B (en) 2020-03-31

Similar Documents

Publication Publication Date Title
CN108661643B (en) It a kind of coal working face end adopts return channel and cuts top release shield lane method
CN105333778B (en) Medium-deep hole large-section composite cut blasting structure and method
CN108915694A (en) It the step tunneling boring unprotect layer tight-face blasting of tunnel lower layer and repairs the roads and protects logical construction method
CN109339797B (en) Extremely-small-clear-distance tunnel exit shock absorption construction method
CN104596375A (en) Fully mechanized excavation construction method for rock roadway
CN113154974B (en) Tunnel roof pressing smooth blasting method
CN110118084B (en) Ultra-deep shaft construction method
CN108132006A (en) Anti-clogging quick well formation undercut blast hole arrangement and its blasting method
CN103983147A (en) Permafrost region road tunnel peripheral hole blasting construction method
CN108798672B (en) A kind of mining methods for the area's ore high-efficiency mining that collapses greatly
CN108645300A (en) Complex reflex cumulative and buffering energy dissipator and the blasting construction method based on the device
CN109668487A (en) Micro-vibration rock and soil blasting controls construction method
CN111411962A (en) Coal mine rock burst treatment method
CN107328327A (en) The soft or hard blast hole loading structure and its method for being mingled with beded rock mass Long-hole Bench Blasting
CN105466290A (en) Cutting excavation blasting method
CN111023930B (en) Tunnel step excavation method
CN104457466A (en) Explosion method of open-cut tunnel segment
CN116658178B (en) Ultra-small clear distance tunnel subsection differential blasting vibration reduction and isolation construction method
CN110230959B (en) Rock cutting slope controlled blasting method
CN108917503A (en) The horizontal presplit blasting method of deep hole applied to power station rock excavation
CN209263807U (en) Micro-vibration rock and soil blasting structure
CN108132004A (en) Armored concrete water-retaining cofferdam blasting demolishing method
CN111457804A (en) Method for blasting IV-grade massive crushed rock with disordered development and wide fracture surface
CN112964143B (en) Three-time blasting method for hollow hole straight-hole cut
CN109900175B (en) Low-damage blasting method for underground mine roadway tunneling

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant