CN108640409A - A kind of combined biological shore protection and its construction method - Google Patents

A kind of combined biological shore protection and its construction method Download PDF

Info

Publication number
CN108640409A
CN108640409A CN201810336825.9A CN201810336825A CN108640409A CN 108640409 A CN108640409 A CN 108640409A CN 201810336825 A CN201810336825 A CN 201810336825A CN 108640409 A CN108640409 A CN 108640409A
Authority
CN
China
Prior art keywords
layer
slope
filter layer
adsorption filter
gabion
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810336825.9A
Other languages
Chinese (zh)
Other versions
CN108640409B (en
Inventor
唐轶繁
王启湘
王哲
许四法
翁凯文
魏伟伟
陆科颖
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang University of Technology ZJUT
Original Assignee
Zhejiang University of Technology ZJUT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang University of Technology ZJUT filed Critical Zhejiang University of Technology ZJUT
Priority to CN201810336825.9A priority Critical patent/CN108640409B/en
Publication of CN108640409A publication Critical patent/CN108640409A/en
Application granted granted Critical
Publication of CN108640409B publication Critical patent/CN108640409B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • CCHEMISTRY; METALLURGY
    • C02TREATMENT OF WATER, WASTE WATER, SEWAGE, OR SLUDGE
    • C02FTREATMENT OF WATER, WASTE WATER, SEWAGE, OR SLUDGE
    • C02F9/00Multistage treatment of water, waste water or sewage
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/12Revetment of banks, dams, watercourses, or the like, e.g. the sea-floor
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/12Revetment of banks, dams, watercourses, or the like, e.g. the sea-floor
    • E02B3/128Coherent linings made on the spot, e.g. cast in situ, extruded on the spot
    • CCHEMISTRY; METALLURGY
    • C02TREATMENT OF WATER, WASTE WATER, SEWAGE, OR SLUDGE
    • C02FTREATMENT OF WATER, WASTE WATER, SEWAGE, OR SLUDGE
    • C02F1/00Treatment of water, waste water, or sewage
    • C02F1/001Processes for the treatment of water whereby the filtration technique is of importance
    • CCHEMISTRY; METALLURGY
    • C02TREATMENT OF WATER, WASTE WATER, SEWAGE, OR SLUDGE
    • C02FTREATMENT OF WATER, WASTE WATER, SEWAGE, OR SLUDGE
    • C02F1/00Treatment of water, waste water, or sewage
    • C02F1/28Treatment of water, waste water, or sewage by sorption
    • C02F1/281Treatment of water, waste water, or sewage by sorption using inorganic sorbents
    • CCHEMISTRY; METALLURGY
    • C02TREATMENT OF WATER, WASTE WATER, SEWAGE, OR SLUDGE
    • C02FTREATMENT OF WATER, WASTE WATER, SEWAGE, OR SLUDGE
    • C02F3/00Biological treatment of water, waste water, or sewage
    • C02F3/32Biological treatment of water, waste water, or sewage characterised by the animals or plants used, e.g. algae
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/30Flood prevention; Flood or storm water management, e.g. using flood barriers

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Water Supply & Treatment (AREA)
  • Chemical & Material Sciences (AREA)
  • Organic Chemistry (AREA)
  • Hydrology & Water Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Revetment (AREA)

Abstract

A kind of combined biological shore protection and its construction method, including infiltration adsorption filter layer, timber spats, gabion baffling, bed mud ecology bag layer and vegetable layer, infiltration adsorption filter layer is arranged in the joining place in river bank slope and riverbed, and infiltration adsorption filter layer includes two layers of pervious concrete layer and adsorption filter layer;Sheet pile spats bottom end is embedded in close in the riverbed at infiltration adsorption filter layer bottom step outer;Gabion baffling includes objective case net cage and supporter;If bed mud ecology bag layer is made of dry course ecology bag;Vegetable layer is made of soil horizon and vegetation net;The construction method includes the following steps:On riverbank, the step slope surface of slope surface is laid with infiltration adsorption filter layer, gabion baffling and vegetable layer successively, and timber spats is embedded at slope foot.The beneficial effects of the invention are as follows:Ensure that water body fully exchanges, the pollutants such as N, P, heavy metal in effective adsorbed water body, while ensuring itself stronger erosion resistibility, there is good durability and applicability.

Description

A kind of combined biological shore protection and its construction method
Technical field
The present invention relates to a kind of combined biological shore protection and its construction methods.
Background technology
Ecological revetment refers to the structure combined with earth working material using plant or plant, one protected river slope surface Kind slope protection form, is a kind of artificial shore protection with nature riverbank property, other than preventing riverbank from caving in, also there is flood detention to mend The functions such as withered, adjusting water level, purification river, the River Landscape that phase is coordinated is formed with ambient enviroment.Synthesis apparently, protect by the ecotype Bank is the improvement of traditional revetment, is product of the river engineering discipline development to opposite advanced stage, is modern's craving and oneself The needs so got along amiably and peacefully, it is the inevitable outcome of bank-protection works technology development and progress.
On the other hand, the mud that river bed is largely deposited seriously affects the Regulation Function of flood control, shipping and water body.Furthermore greatly The pollutant of amount is enriched in bed-silt, if mud is disturbed, some of the contaminants may among deposit returns to river water, Lasting influence is caused to waters.Meanwhile containing the substances such as N, P element needed for a large amount of plant growths, profit in bed-silt again Use mud that there is higher economy and feasibility as the raw material for cultivating plant growth.
The patent of Publication No. 103061310B is a kind of novel ecological habitat shore protection, is built by laying bricks or stones by block stone layer layer and forms life State inhabites area, the access way using the inside and outside water service pipe of connection as aquatic animal, but the shore protection is still largely mixed using reinforcing bar The original natural ecosystems in river are had certain destruction by the earth working materials such as solidifying soil, building block.
The patent of Publication No. 203890955U is that a kind of ecological revetment plants raw structure, using alloy-steel wire cage body in river The joining place in bank slope and riverbed, which is successively piled up, to be formed step-like, plant pad is placed inside alloy steel cage body, plant pad includes base Matter and different types of plant roots and stems or seedling, but the structure is big by water hammering effects, soil body matrix and plant inside cage body Seedling is easily destroyed by water impact, and soil particle can be lost in flow, and water body purification is less efficient.
Invention content
In order to solve the problems, such as that traditional shore protection technology and current part ecological revetment technology erosion resistibility are weaker Or cleaning water it is not high the problems such as, it can be water that the present invention, which proposes a kind of combined biological shore protection and its construction method, the structure, Biology provides the space inhabited with breeding, can ensure that riverbank is exchanged with the sufficient water body in river, being capable of effective adsorbed water body The pollutants such as middle N, P, heavy metal, while the flexible structural system of the shore protection ensures itself stronger erosion resistibility, has Good durability and applicability.
A kind of combined biological shore protection of the present invention, it is characterised in that:Including infiltration adsorption filter layer, sheet pile shield Foot, gabion baffling, bed mud ecology bag layer and vegetable layer, the infiltration adsorption filter layer are arranged in the rank in river bank slope and riverbed Place is met, infiltration adsorption filter layer forms the first staged that can be bonded with the step surface of river bank slope along shore protection slope surface from bottom to top Embankment slope, the infiltration adsorption filter layer include inside and outside two layers of pervious concrete layer and are clipped between two pervious concrete layers Adsorption filter layer, adsorption filter layer be filled between two layers of pervious concrete layer there are gap in;Sheet pile spats bottom end In the embedded riverbed close at infiltration adsorption filter layer bottom step outer, the two is affixed each other by latching;The gabion gear Wall includes the branch for stacking connected objective case net cage from bottom to top along the first staged embankment slope and being filled in objective case net cage Object is supportted, wherein gabion baffling one side is matched with the first staged embankment slope, and another side is formed for stacking bed mud ecology Second staged embankment slope of bag;If the bed mud ecology bag layer is made of dry course ecology bag, bottom ecology bag is stacked on On the step surface on the second staged embankment slope;The vegetable layer is made of soil horizon and vegetation net, and the soil horizon is covered in Gap and its surface layer between gabion baffling top layer, bed mud ecology bag, side of the soil horizon towards riverbed are the slope for water blocking, And the soil horizon of bottom bed mud ecology bag layer covering is less than the peak of sheet pile spats, the soil horizon surface grafting vegetation shape At vegetation net, the vegetation net is divided into water plant, ground cover plant and shrub from bottom to top..
The pervious concrete layer includes being interrupted coarse aggregate, Portland cement and the water of grade, 20~30mm of thickness, Two layers totally, inner clip filter layer, tightly formed with riverside slope face paste on one side it is ladder-like, another side along gabion baffling inner boundary be laid with, Infiltration lane is provided for water body inside and outside shore protection, and soil and filter layer play stable curing in opposite bank, prevent particle with dampening Stream is lost in.
The adsorption filter layer is layed between two layers of pervious concrete layer, 50~60mm of thickness, is granule, zeolite, broken Layer structure made of lime stone and flyash are laid with, granule in the adsorption filter layer, zeolite, rubble lime stone and flyash Volume ratio is 4:2:2:2.The granule grain size is 2~4cm, and the sized zeolite particles are 0.5~1cm, the broken limestone particle size For 0.5~1cm, the flyash grain size is 0.5~300 μm, it is ensured that the elements such as N, P in effective adsorbed water body.
The sheet pile spats is interconnected together using the compound sheet pile intrenched stream beds of FRP and by fore shaft, and sheet pile section has Imitate breadth 600mm, effective height 180mm, thickness 13.4mm.
The gabion baffling is in rectangular parallelepiped structure, is stacked step by step along slope surface by the cuboid gabion filled with supporter It is formed by connecting;The gabion is made of the mesh sheet of the multiple twin shape, hexagon mesh that weave, upper layer net cage one third width It is stacked on lower layer's net cage, stacks step by step, stepped is connected by steel wire lashing between adjacent net cage;Above support For large-sized block of stone, the mixture of rubble, gravel and soil.
The bed mud ecology bag layer piled up by the ecology bag of the organic fertilizer needed for internal filling bed mud and plant growth and It is to obtain after dredging and bed-silt soil after harmless treatment at, the bed mud.
The water plant includes thaliadeabata, raupo and/or mullet grass, and the ground cover plant includes Canna generalis, institute It includes forsythia viridissima Lindl, photinia glabra and/or water cape jasmine to state shrub, and vegetation type is abundant, and shading item is provided for waters and surrounding enviroment Part provides abundant habitat and food source for animals and plants, and the development of root system of plant plays what reinforcement consolidated to shore protection system again Effect.
A kind of construction method of combined type shore protection containing ecological habitat of the present invention, includes the following steps:
1) step arrangement is made in riverbed and riverbank slope surface intersection bank slope, forms it into step slope surface;
2) it is laid with first layer pervious concrete layer in the step slope surface of riverbank slope surface, plays leveling;
3) on the basis of first layer pervious concrete, it is laid with one layer of adsorption filter layer, for adsorbing in disengaging water body N, P or heavy metal element, wherein adsorption filter layer are made of granule, zeolite, rubble lime stone and flyash;
4) second layer pervious concrete layer is re-layed on the basis of adsorption filter layer, plays leveling, and only allow water The infiltration of body, prevents in bank that small size particle is lost in flow in soil body particle and filter layer;
5) after the completion of setting cushion, it will be filled with the cuboid gabion net of large-sized block of stone, rubble and gravel and soil Case lifting is lifted to bed course one by one, and gabion is stacked along slope surface step by step, ultimately forms gabion baffling, is weakened water impact and is made With and slow down flow rate of water flow, wherein the gabion is made of the mesh sheet of the multiple twin shape, hexagon mesh that weave, upper layer net cage One third width is stacked on lower layer's net cage, is stacked step by step, stepped, is connected by steel wire lashing between adjacent net cage It connects;
6) bed mud ecology bag is stacked on the step surface of gabion baffling, and fills soil toward the big gap between bed mud ecology bag Earth forms soil horizon, and soil horizon slope leveling is acute angle with riverbed plane included angle;
7) soil horizon is laid with vegetation net, and vegetation net is according to water level conditions planting aquatic plants, ground cover plant, shrub;
8) current scour erosion condition is typically more serious at slope foot, and sheet pile spats, sheet pile spats is used to adopt at slope foot It is interconnected together with the compound sheet pile intrenched stream beds of FRP and by fore shaft, soil horizon about 0.2~0.3m is higher by the top of sheet pile, with Flow is reduced to washing away at slope foot and to corrode.
The beneficial effects of the invention are as follows:The silt soil that this shore protection is dredged using river bed as the nutrient of plant growth come Source embodies environmentally protective, ecological circulation theory.Shore protection uses fabricated structure system, is provided for aquatile larger Inhabit with breeding space, and give full play to that ecology bag is deformed and is consumed energy by water impact and gabion baffling structure is steady Fixed characteristic enhances shore protection erosion resistibility, is suitable for the higher river of flow rate of water flow.This combined structure system gap is big, Water penetration is good, ensure that the flowing and exchange of water body inside and outside shore protection.This ecological revetment is dual using vegetation and geotechnological filter layer Filtering, filter effect are better than the ecological revetment of common form.
Description of the drawings
Fig. 1 is that the schematic cross-sectional view of this bank protection structure (represents peak level at A;Ordinary water level is represented at B).
Fig. 2 is the schematic top plan view of this bank protection structure.
Fig. 3 is gabion overall structure diagram.
Specific implementation mode
It further illustrates the present invention below in conjunction with the accompanying drawings
With reference to attached drawing:
A kind of combined type shore protection containing ecological habitat of the present invention of embodiment 1, including infiltration adsorption filter layer 1, Sheet pile spats 2, gabion baffling 3, bed mud ecology bag layer 4 and vegetable layer 5, the infiltration adsorption filter layer 1 are arranged in river bank The joining place on slope 6 and riverbed 7, infiltration adsorption filter layer 1 is formed from bottom to top along shore protection slope surface can be with the step surface of river bank slope First staged embankment slope of fitting, the infiltration adsorption filter layer 1 include inside and outside two layers of pervious concrete layer 11 and are clipped in Adsorption filter layer 12 between two pervious concrete layers, adsorption filter layer 12 be filled between two layers of pervious concrete layer 11 there are Gap in;2 bottom end of sheet pile spats is embedded in close in the riverbed 7 at infiltration adsorption filter layer bottom step outer, the two It is affixed each other by latching;The gabion baffling 3 includes stacking connected objective case from bottom to top along the first staged embankment slope Net cage 31 and the supporter being filled in objective case net cage, wherein 3 one side of gabion baffling and the first staged embankment slope Match, another side forms the second staged embankment slope for stacking bed mud ecology bag;The bed mud ecology bag layer 4 is by several Bottom ecology bag is constituted, and bottom ecology bag is stacked on the step surface on the second staged embankment slope;The vegetable layer 5 is by soil Layer 51 and vegetation net 52 form, and the soil horizon 51 is covered in gap and its surface layer between 3 top layer of gabion baffling, bed mud ecology bag, Side of the soil horizon 51 towards riverbed is the slope for water blocking, and the soil horizon of bottom bed mud ecology bag layer covering is less than The peak of sheet pile spats, 51 surface grafting vegetation of the soil horizon form vegetation net 52, and the vegetation net 52 is according to planting soil The environment of earth layer is divided into water plant 521, ground cover plant 522 and shrub 523 from bottom to top.
The pervious concrete layer 11 includes being interrupted coarse aggregate, Portland cement and the water of grade, and thickness 20~ 30mm, two layers totally, inner clip filter layer tightly forms ladder-like, inner boundary of the another side along gabion baffling with riverside slope face paste on one side It is laid with.
The adsorption filter layer 12 is layed between two layers of pervious concrete layer, 50~60mm of thickness, be granule, zeolite, Layer structure made of rubble lime stone and flyash are laid with, granule, zeolite, rubble lime stone and flyash in the adsorption filter layer Volume ratio be 4:2:2:2.The granule grain size is 2~4cm, and the sized zeolite particles are 0.5~1cm, the broken limestone particle Diameter is 0.5~1cm, and the flyash grain size is 0.5~300 μm.
The sheet pile spats 2 is interconnected together using the compound sheet pile intrenched stream beds of FRP and by fore shaft, and sheet pile section has Imitate breadth 600mm, effective height 180mm, thickness 13.4mm.
The gabion baffling 3 is in rectangular parallelepiped structure, by filled with the rectangular of large-sized block of stone, rubble, gravel and soil Body gabion is formed by connecting along slope surface stacking step by step;The gabion size is 1.2m × 0.5m × 3m and 0.5m × 0.5m Two kinds of × 3m, gabion are made of the mesh sheet of the multiple twin shape, hexagon mesh that weave, and upper layer net cage one third width stacks It on lower layer's net cage, stacks, stepped, is connected by steel wire lashing between adjacent net cage step by step.
The bed mud ecology bag layer 4 piled up by the ecology bag of the organic fertilizer needed for internal filling bed mud and plant growth and It is to obtain after dredging and bed-silt soil after harmless treatment at, the bed mud.
The water plant includes thaliadeabata, raupo and/or mullet grass, and the ground cover plant includes Canna generalis, institute It includes forsythia viridissima Lindl, photinia glabra and/or water cape jasmine to state shrub.
A kind of construction method of combined biological shore protection as described in Example 1 of embodiment 2, includes the following steps:
1) step arrangement is made in riverbed and riverbank slope surface intersection bank slope, forms it into step slope surface, wherein platform Wide 900~the 1300mm of rank, the high 500~600mm of step;
2) first layer 20~30mm thickness pervious concrete layers are laid in the step slope surface of riverbank slope surface, play leveling;
3) on the basis of first layer pervious concrete, it is laid with the adsorption filter layer of one layer of 50~60mm thickness, for adsorbing The N or P element in water body are passed in and out, wherein adsorption filter layer is made of granule, zeolite, rubble lime stone and flyash, in filter layer Granule, zeolite, rubble lime stone and flyash volume ratio be 4:2:2:2;
4) pervious concrete layer of the second layer 20~30mm thickness is re-layed on the basis of adsorption filter layer, is played leveling and is made With and only allowing the infiltration of water body, prevent in bank that small size particle is lost in flow in soil body particle and filter layer;
5) after the completion of setting cushion, it will be filled with the cuboid gabion net of large-sized block of stone, rubble and gravel and soil Case lifting is lifted to bed course one by one, and gabion is stacked along slope surface step by step, ultimately forms gabion baffling, is weakened water impact and is made With and slow down flow rate of water flow, wherein the gabion is made of the mesh sheet of the multiple twin shape, hexagon mesh that weave, upper layer net cage One third width is stacked on lower layer's net cage, is stacked step by step, stepped, is connected by steel wire lashing between adjacent net cage It connects;
6) bed mud ecology bag is stacked on the step surface of cage barricade layer, and fills soil toward the big gap between bed mud ecology bag Earth forms soil horizon, and soil horizon slope leveling is 30 ° of gradients with riverbed plane included angle;
7) soil horizon is laid with vegetation net, and vegetation net is improved according to water level conditions planting aquatic plants, ground cover plant, shrub The ability and photosynthesis oxygen delivery capacity of vegetable layer absorption N, P element and heavy metal contaminants;
8) current scour erosion condition is typically more serious at slope foot, and sheet pile spats, sheet pile spats is used to adopt at slope foot It is interconnected together with the compound sheet pile intrenched stream beds of FRP and by fore shaft, soil horizon about 0.2~0.3m, plate is higher by the top of sheet pile The stake effective breadth 600mm in section, effective height 180mm, thickness 13.4mm, sheet pile is embedded in riverbed 1.8m, to reduce flow to slope Washing away to corroding at foot.
Content described in this specification embodiment is only enumerating to the way of realization of inventive concept, protection of the invention Range is not construed as being only limitted to the concrete form that embodiment is stated, protection scope of the present invention also includes art technology Personnel according to present inventive concept it is conceivable that equivalent technologies mean.

Claims (8)

1. a kind of combined biological shore protection, it is characterised in that:Including infiltration adsorption filter layer, sheet pile spats, gabion baffling, bed mud Ecology bag layer and vegetable layer, the infiltration adsorption filter layer are arranged in the joining place in river bank slope and riverbed, and infiltration was adsorbed Filtering layer forms the first staged embankment slope that can be bonded with the step surface of river bank slope along shore protection slope surface from bottom to top, described to ooze Saturating adsorption filter layer includes inside and outside two layers of pervious concrete layer and the adsorption filter layer that is clipped between two pervious concrete layers, absorption Filter layer be filled between two layers of pervious concrete layer there are gap in;The insertion of sheet pile spats bottom end is adsorbed close to infiltration In riverbed at filter layer bottom step outer, the two is affixed each other by latching;The gabion baffling includes along the first ladder The supporter that formula embankment slope stacks connected objective case net cage and is filled in objective case net cage from bottom to top, wherein gabion baffling One side is matched with the first staged embankment slope, and another side forms the second staged embankment for stacking bed mud ecology bag Slope;If the bed mud ecology bag layer is made of dry course ecology bag, bottom ecology bag is stacked on the second staged embankment slope Step surface on;The vegetable layer is made of soil horizon and vegetation net, and the soil horizon is covered in gabion baffling top layer, bed mud life Gap and its surface layer between state bag, side of the soil horizon towards riverbed are slope for water blocking, and bottom bed mud ecology bag The soil horizon of layer covering is less than the peak of sheet pile spats, and the soil horizon surface grafting vegetation forms vegetation net, the vegetation Net is divided into water plant, ground cover plant and shrub from bottom to top.
2. a kind of combined biological shore protection as described in claim 1, it is characterised in that:The pervious concrete layer includes interruption Coarse aggregate, Portland cement and the water of grade, 20~30mm of thickness, two layers totally, inner clip filter layer, on one side with riverbank slope surface It is adjacent to form ladder-like, inner boundary laying of the another side along gabion baffling.
3. a kind of combined biological shore protection as described in claim 1, it is characterised in that:The adsorption filter layer is layed in two layers Between pervious concrete layer, 50~60mm of thickness is layer structure made of granule, zeolite, rubble lime stone and flyash are laid with, Granule in the adsorption filter layer, zeolite, rubble lime stone and flyash volume ratio be 4:2:2:2.The granule grain size be 2~ 4cm, the sized zeolite particles be 0.5~1cm, the broken limestone particle size be 0.5~1cm, the flyash grain size be 0.5~ 300μm。
4. a kind of combined biological shore protection as described in claim 1, it is characterised in that:The sheet pile spats is compound using FRP Sheet pile is embedded in riverbed and is interconnected together by fore shaft, the effective breadth 600mm in sheet pile section, effective height 180mm, thickness 13.4mm。
5. a kind of combined biological shore protection as described in claim 1, it is characterised in that:The gabion baffling is in cuboid knot Structure, by the cuboid gabion filled with large-sized block of stone, rubble, gravel and soil step by step along slope surface stack connection and At;The gabion is made of the mesh sheet of the multiple twin shape, hexagon mesh that weave, and upper layer net cage one third width is stacked in It on lower layer's net cage, stacks, stepped, is connected by steel wire lashing between adjacent net cage step by step.
6. a kind of combined biological shore protection as described in claim 1, it is characterised in that:The bed mud ecology bag layer is filled out by inside The ecology bag for filling the organic fertilizer needed for bed mud and plant growth is piled up, and the bed mud is to be obtained after dredging and by harmless Change treated bed-silt soil.
7. a kind of combined biological shore protection as described in claim 1, it is characterised in that:The water plant include thaliadeabata, Raupo and/or mullet grass, the ground cover plant includes Canna generalis, and the shrub includes forsythia viridissima Lindl, photinia glabra and/or water Cape jasmine.
8. a kind of construction method of combined biological shore protection as described in claim 1~7 any one claim, including with Lower step:
1) step arrangement is made in riverbed and riverbank slope surface intersection bank slope, forms it into step slope surface;
2) it is laid with first layer pervious concrete layer in the step slope surface of riverbank slope surface, plays leveling;
3) on the basis of first layer pervious concrete, it is laid with one layer of adsorption filter layer, for adsorbing N or P in disengaging water body Element, wherein adsorption filter layer are made of granule, zeolite, rubble lime stone and flyash;
4) second layer pervious concrete layer is re-layed on the basis of adsorption filter layer, plays leveling, and only allow water body Infiltration, prevents in bank that small size particle is lost in flow in soil body particle and filter layer;
5) after the completion of setting cushion, the cuboid gabion that will be filled with large-sized block of stone, rubble and gravel and soil is hung Dress is lifted to bed course one by one, and gabion is stacked along slope surface step by step, ultimately forms gabion baffling, weakens water impact effect simultaneously Slow down flow rate of water flow, wherein the gabion is made of the mesh sheet of the multiple twin shape, hexagon mesh that weave, upper layer net cage three divides One of width be stacked on lower layer's net cage, stack, stepped, connected by steel wire lashing between adjacent net cage step by step;
6) bed mud ecology bag is stacked on the step surface of cage barricade layer, and toward the big gap filling soil shape between bed mud ecology bag It is acute angle with riverbed plane included angle at soil horizon;
7) soil horizon is laid with vegetation net, and vegetation net is according to water level conditions planting aquatic plants, ground cover plant, shrub;
8) current scour erosion condition is typically more serious at slope foot, and sheet pile spats, sheet pile spats is used to use FRP at slope foot Compound sheet pile intrenched stream bed is simultaneously interconnected together by fore shaft, is higher by soil horizon at the top of sheet pile, with reduce flow to slope foot at Wash away to corrode.
CN201810336825.9A 2018-04-16 2018-04-16 Combined ecological bank protection and construction method thereof Active CN108640409B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810336825.9A CN108640409B (en) 2018-04-16 2018-04-16 Combined ecological bank protection and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810336825.9A CN108640409B (en) 2018-04-16 2018-04-16 Combined ecological bank protection and construction method thereof

Publications (2)

Publication Number Publication Date
CN108640409A true CN108640409A (en) 2018-10-12
CN108640409B CN108640409B (en) 2023-12-05

Family

ID=63746452

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810336825.9A Active CN108640409B (en) 2018-04-16 2018-04-16 Combined ecological bank protection and construction method thereof

Country Status (1)

Country Link
CN (1) CN108640409B (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109306676A (en) * 2018-11-13 2019-02-05 四川港航建设工程有限公司 The construction method of bank slump reparation structure
CN109368796A (en) * 2018-10-22 2019-02-22 中建水务环保有限公司 A kind of ecoscape shore protection administered for river water quality
CN110042797A (en) * 2019-03-29 2019-07-23 浙江融信环保科技有限公司 A kind of ecology remodeling method of ramp type hardening bank slope
CN110627447A (en) * 2019-10-22 2019-12-31 深圳市信泰工业自动化设备有限公司 Pervious concrete sewage filtering device and method thereof
CN110984193A (en) * 2019-12-24 2020-04-10 河北水熠木丰工程技术有限责任公司 Severe cold mountain area highway cutting side slope ecological protection system
CN112878339A (en) * 2021-01-11 2021-06-01 湘潭大学 Biological self-repairing gabion unit device for filler, preparation method and slope reinforcement method
CN113186872A (en) * 2021-05-17 2021-07-30 李圣 Anti-seepage and anti-impact flood bank for hydraulic engineering and anti-seepage method thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101509243A (en) * 2009-03-13 2009-08-19 山东大学 Ecological shore protection method for stepwise shore
CN204849680U (en) * 2015-07-21 2015-12-09 沈阳鸿润水利工程有限公司 Novel ecological shore protection system
CN106337394A (en) * 2016-09-22 2017-01-18 水利部中国科学院水工程生态研究所 River bank ecological restoration device and method suitable for mountain river characteristics
CN205954567U (en) * 2016-08-24 2017-02-15 浙江省风景园林设计院有限公司 Landscape zhong he lake revetment structure
CN106522160A (en) * 2016-10-24 2017-03-22 廊坊师范学院 Construction method of revetment type ecological landscape

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101509243A (en) * 2009-03-13 2009-08-19 山东大学 Ecological shore protection method for stepwise shore
CN204849680U (en) * 2015-07-21 2015-12-09 沈阳鸿润水利工程有限公司 Novel ecological shore protection system
CN205954567U (en) * 2016-08-24 2017-02-15 浙江省风景园林设计院有限公司 Landscape zhong he lake revetment structure
CN106337394A (en) * 2016-09-22 2017-01-18 水利部中国科学院水工程生态研究所 River bank ecological restoration device and method suitable for mountain river characteristics
CN106522160A (en) * 2016-10-24 2017-03-22 廊坊师范学院 Construction method of revetment type ecological landscape

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109368796A (en) * 2018-10-22 2019-02-22 中建水务环保有限公司 A kind of ecoscape shore protection administered for river water quality
CN109368796B (en) * 2018-10-22 2024-03-15 中建生态环境集团有限公司 Ecological landscape revetment for river water quality treatment
CN109306676A (en) * 2018-11-13 2019-02-05 四川港航建设工程有限公司 The construction method of bank slump reparation structure
CN109306676B (en) * 2018-11-13 2020-07-14 四川港航建设工程有限公司 Construction method of landslide repairing structure
CN110042797A (en) * 2019-03-29 2019-07-23 浙江融信环保科技有限公司 A kind of ecology remodeling method of ramp type hardening bank slope
CN110627447A (en) * 2019-10-22 2019-12-31 深圳市信泰工业自动化设备有限公司 Pervious concrete sewage filtering device and method thereof
CN110984193A (en) * 2019-12-24 2020-04-10 河北水熠木丰工程技术有限责任公司 Severe cold mountain area highway cutting side slope ecological protection system
CN112878339A (en) * 2021-01-11 2021-06-01 湘潭大学 Biological self-repairing gabion unit device for filler, preparation method and slope reinforcement method
CN112878339B (en) * 2021-01-11 2021-10-29 湘潭大学 Biological self-repairing gabion unit device for filler, preparation method and slope reinforcement method
CN113186872A (en) * 2021-05-17 2021-07-30 李圣 Anti-seepage and anti-impact flood bank for hydraulic engineering and anti-seepage method thereof
CN113186872B (en) * 2021-05-17 2023-05-30 黑龙江省水利水电集团有限公司 Impervious impact-resistant flood control dike for hydraulic engineering and impervious method thereof

Also Published As

Publication number Publication date
CN108640409B (en) 2023-12-05

Similar Documents

Publication Publication Date Title
CN108640409A (en) A kind of combined biological shore protection and its construction method
CN208563250U (en) A kind of river channel ecology shore protection
CN208717855U (en) A kind of combined type shore protection containing ecological habitat
KR100917790B1 (en) Grid type hollow block for ecological restoration of bank and construction method of bank using thereof
CN110366986B (en) Vegetation layer structure for recovering slope vegetation of mine polluted waste rock storage yard and recovery method
CN108442320A (en) A kind of combined type shore protection and its construction method containing ecological habitat
CN108547254A (en) A kind of river channel ecology shore protection and its construction method
WO2020220671A1 (en) Mangrove afforestation method and structure for coastal rocky beach
CN108999174B (en) Ecological restoration system for preventing water and soil loss and construction method
CN106522160A (en) Construction method of revetment type ecological landscape
CN109469001B (en) River channel ecological system reconstruction structure and construction operation method thereof
CN102296567A (en) Soft isolation zone method for slope protection at bank zone and surface source pollution control
CN211972073U (en) Urban ecological river cross section
KR100834083B1 (en) Bio - environment vegetation bag and its manufacturing method
CN207498892U (en) A kind of cavernous body ecological revetment
KR102084488B1 (en) Water-energy reduction type crib in which plant can be planted
KR200240391Y1 (en) Block Type Vegetation Gabion Crib
CN111484278A (en) Ecological concrete, ecological protection slope and construction method of ecological protection slope
CN210288254U (en) River channel ecosystem rebuilds structure
CN208394983U (en) A kind of combined biological shore protection
CN217923356U (en) Gabion revetment structure
KR20200106251A (en) Ecological case with reinforcing plate
CN113529754B (en) Granular-body slope ecological slope protection structure and construction method
CN213867615U (en) Ecological overflow dam
CN207405572U (en) A kind of new water-fast timber revetment structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant