CN108590716A - A kind of tunnel crosses rich water tomography tree root type and dredges water blockoff integral construction method - Google Patents

A kind of tunnel crosses rich water tomography tree root type and dredges water blockoff integral construction method Download PDF

Info

Publication number
CN108590716A
CN108590716A CN201810348236.2A CN201810348236A CN108590716A CN 108590716 A CN108590716 A CN 108590716A CN 201810348236 A CN201810348236 A CN 201810348236A CN 108590716 A CN108590716 A CN 108590716A
Authority
CN
China
Prior art keywords
tree root
root type
main borehole
tunnel
tomography
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810348236.2A
Other languages
Chinese (zh)
Inventor
孟庆彬
韩立军
刘晓帅
张明伟
田茂霖
陶祥令
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China University of Mining and Technology CUMT
Original Assignee
China University of Mining and Technology CUMT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China University of Mining and Technology CUMT filed Critical China University of Mining and Technology CUMT
Priority to CN201810348236.2A priority Critical patent/CN108590716A/en
Publication of CN108590716A publication Critical patent/CN108590716A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/001Improving soil or rock, e.g. by freezing; Injections
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Structural Engineering (AREA)
  • Soil Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

Rich water tomography tree root type, which is crossed, the invention discloses a kind of tunnel dredges water blockoff integral construction method, by setting position construction main borehole first on the excavation contour line in tunnel, then by design and construction tree root type branch hole in main borehole, ensure that the borehole bottom location of main borehole and tree root type branch hole is fallen in tomography;In the hydrophobic construction stage, using main borehole and tree root type branch hole in communication as weep hole;In the mortar depositing construction stage, using main borehole and tree root type branch hole in communication as injected hole.The present invention has the advantages that a multi-purpose simple and feasible, economic and practical, hole, combining the two ways of dredging and plugging, safe and efficient, quick pass through rich water tomography for tunnel, tunnel etc. are safe and efficient and provides a kind of new method.

Description

A kind of tunnel crosses rich water tomography tree root type and dredges water blockoff integral construction method
Technical field
The present invention relates to a kind of tunnels to cross the thin water blockoff integral construction method of rich water tomography tree root type, is suitable for coal mine, iron The underground engineerings such as mine, nonferrous metal mine, tunnel, subway are a kind of safe and efficient construction methods for passing through rich water tomography.
Background technology
China is the resources big countries such as coal, iron ore in the world, as china natural resources exploit expanding rapidly and opening for scale Adopt the increase of depth, the hydraulic pressure that when exploitation is born is increasing, and it is in increase tendency, China's mine to cause down-hole water inrush accident Well is to be endangered one of the countries with the most serious ... by floods in the world.Fault and broken zone is common in underworkings digging process Unfavorable geologic body, fault belt be as a low-intensity, that yielding, water penetration is big, water-resistance is poor and water content is big is soft Weak band exists;Since rich water tomography is aqueous abundant, the underground water in tomography upper lower burrs water-bearing layer can be collected, come with abundant supply Source can cause tunnel that the disasters such as gushing water or prominent mud, Qing Zheying occurs if not taking specially treated technical measures in roadway excavation Mine normal production is rung, economic loss is caused;Severe one causes mine partially or fully to be flooded, and extends the mine construction duration or is forced to close Mine, or even cause great personnel casualty accidents and huge economic loss.Currently, floods, which have become, influences mine safety life One of significant problem of production, water damage preventing and controlling have become each mining area and ensure the great research topic that safety in production must face One of.
By long-term mine water management research and field practice, mine is mainly using hydrophobic and grouting for water blocking (at present Face pre-pouring grout, pre grouting from the working face, tunnel front pre-grouting) etc. two major classes water control technique, successfully solve a large amount of technology Problem is made that major contribution for containment mine water disaster accident.But China part ore district hydrogeologic is with engineering Matter condition is extremely complex (water content is big, water recharging is more, hydraulic pressure is high, fault tectonic development), occur mine water disaster accident because Element is also sufficiently complex, some hydrophobic measures and grouting process etc. are more single or with strong points and poor for applicability at present, in reality It has some limitations during engineering use, causes mine effect of harnessing the river undesirable;On the other hand, using grouting for water blocking When need a large amount of drilling of constructing, it is stifled to ensure to be formed after slip casting but due to the complexity at water source and variability in rich water tomography Water curtain generally requires a large amount of drilling of constructing, and this adds increased quantities and project cost;Also, by existing construction technology water The construction quality of flat influence, drilling cannot ensure that (degree of skewness is excessive in the construction process for some drillings, it is caused to fall completely The outside of tomography is without entering the precalculated position in tomography;Some drilling deviation distances are excessive and formed after causing slip casting Grouting for water blocking fixing collar it is non-intersecting, with the presence of grouting for water blocking blank loophole area, the slip casting for being unfavorable for underground water blocks and filling Reinforce), cause grouting for water blocking effect poor.Therefore, there is an urgent need for an a kind of simple and feasible, economic and practical, holes of research and development to be mostly used, dredges bridging It closes, safe and efficient mine is harnessed the river new process.
Invention content
Goal of the invention:In order to overcome the deficiencies in the prior art, a kind of tunnel of present invention offer to cross rich water tomography tree Root type dredges water blockoff integral construction method, is constructed by the way of multi-purpose, combining the two ways of dredging and plugging using a hole, be it is a kind of it is simple and feasible, Economic and practical, safe and efficient new method of harnessing the river.
Technical solution:To achieve the above object, the technical solution adopted by the present invention is:
A kind of tunnel crosses rich water tomography tree root type and dredges water blockoff integral construction method, first on the excavation contour line in tunnel By setting position construction main borehole, then ensure main borehole and tree root by design and construction tree root type branch hole in main borehole The borehole bottom location of type branch hole is fallen in tomography;In the hydrophobic construction stage, by main borehole and tree root type branch in communication Drilling is used as weep hole;In the mortar depositing construction stage, using main borehole and tree root type branch hole in communication as injected hole.
Preferably, after the completion of main borehole is constructed, in main borehole interior installing hole mouth steel pipe, mounting hole steel pipe can play guarantor The effect protected main borehole, prevent main borehole from caving in, while ensureing the smooth construction of tree root type branch hole.
Preferably, in the hydrophobic construction stage, it is connected to aperture steel pipe and drain pipe using ring flange, while in the steel pipe of aperture Permeable plug is installed;Underground water flows into hydrophobic tube side-by-side by tree root type branch hole and main borehole and goes out, and permeable plug is hydrophobic to flowing into The underground water of pipe is filtered, and prevents hydrophobic blockage.
Preferably, in the mortar depositing construction stage, it is connected to aperture steel pipe and high-pressure slip-casting hose using controllable type slurry casting machine, simultaneously Non-return valve is installed in high-pressure slip-casting hose;The slurries that high-pressure injection pump pumps out inject main borehole and tree by high-pressure slip-casting hose Root type branch hole;Slurries adverse current is prevented by non-return valve, slurries is avoided to waste;The stream of slurries is controlled by controllable type slurry casting machine Amount ensures that slurries are surely measured by main borehole and is evenly injected into tree root type branch hole so that slurries are in main borehole and tree root The grouting for water blocking curtain formed in type branch hole can hand over circle, achieve the purpose that quick water blockoff and country rock carrying.
Preferably, by slip casting recorder record grouting parameter, grouting parameter include slurries pump out pressure, slurries stream Amount and slip casting time, slip casting recorder can reflect the dynamic change of the mobility status and grouting parameter of slurries in real time, be convenient for and When adjustment grouting parameter to ensure slip casting effect.
Specifically, rich water tomography tree root type is crossed in the tunnel dredges water blockoff integral construction method, include the following steps:
Step 1:Orientation geological drilling rig is placed in tunnel, drilling rod is mounted on orientation geological drilling rig, orientation is started Geological drilling rig drives drilling rod high speed rotation, by setting position construction main borehole on the excavation contour line in tunnel;Wait for that main borehole is applied After the completion of work, in main borehole interior installing hole mouth steel pipe;By design and construction tree root type branch hole in main borehole, ensure main borehole It is fallen in tomography with the borehole bottom location of tree root type branch hole;
Step 2:Permeable plug is installed in the steel pipe of aperture, aperture steel pipe and drain pipe are connected to using ring flange, by hydrophobic The underground water for entering tree root type branch hole and main borehole is discharged in the gutter of roadway floor by pipe;Permeable plug can be effectively prevent The granule mediums such as rubble, sand, mud in tomography are flowed into drain pipe, avoid hydrophobic blockage so that underground water can In time, smooth, be efficiently flowed into drain pipe, while can also reduce or the pressure of removal underground water (hydrophobic pressure release), profit In follow-up slip casting;
Step 3:After the completion of the hydrophobic construction stage, the connection of ring flange and aperture steel pipe is released, while being taken out permeable Plug;It is connected to aperture steel pipe and high-pressure slip-casting hose using controllable type slurry casting machine, while non-return valve being installed in high-pressure slip-casting hose; The slurries that high-pressure injection pump pumps out quickly are sufficiently injected main borehole and tree root type branch hole by high-pressure slip-casting hose, by inverse Only valve prevents slurries adverse current, and the flow of slurries is controlled by controllable type slurry casting machine, ensures slurries in main borehole and tree root type branch It is spread in tree root shape space in drilling, forms grouting for water blocking curtain and carrying reinforcing body, both can avoid slurries in main borehole and tree Diffusion is uneven and be formed by the non-intersecting problem of grouting for water blocking fixing collar after leading to slip casting in root type branch hole, and can prevent Lead to water blockoff failure of the slurries in main borehole and tree root type branch hole caused by insufficient infusion because grouting pressure is too small.
Preferably, mortar depositing construction stage, injection slurries are cement class or polyurethane sludge injection material.
Advantageous effect:Tunnel provided by the invention crosses rich water tomography tree root type and dredges water blockoff integral construction method, is suitable for The underground engineerings such as coal mine, iron ore, nonferrous metal mine, tunnel, subway are a kind of safe and efficient construction parties for passing through rich water tomography Method, this method is simple and feasible, economic and practical, a hole is multi-purpose, combining the two ways of dredging and plugging, safe and efficient, is that tunnel, tunnel etc. are safe and efficient fast Speed passes through rich water tomography and provides a kind of new method.
Description of the drawings
Fig. 1 is the position view of main borehole and tree root type branch hole;
Fig. 2 is the construction schematic diagram of main borehole and tree root type branch hole;
Fig. 3 is the construction schematic diagram in hydrophobic stage;
Fig. 4 is the construction schematic diagram in slip casting stage;
Including:The tunnels 1-, 2- excavation contour lines, 3- orient geological drilling rig, 4- drilling rods, 5- main boreholes, 6- tree root types branch Drilling, the apertures 7- steel pipe, the permeable plugs of 8-, 9- ring flanges, 10- drain pipes, 11- fixing card cables, the gutters 12-, 13- controllable types note Starch device, 14- non-return valves, 15- high-pressure injection pumps, 16- slip casting recorders, 17- high-pressure slip-casting hoses, 18- tomographies.
Specific implementation mode
The present invention is further described below in conjunction with the accompanying drawings.
A kind of tunnel crosses rich water tomography tree root type and dredges water blockoff integral construction method, includes the following steps:
Step 1:Orientation geological drilling rig 3 is placed in tunnel 1, drilling rod 4 is mounted on orientation geological drilling rig 3, is started It orients geological drilling rig 3 and drives 4 high speed rotation of drilling rod, it is (straight by setting position construction main borehole 5 on the excavation contour line 2 in tunnel 1 Diameter is 120~150mm or so);After the completion of waiting for that main borehole 5 is constructed, in 5 interior installing hole mouth steel pipe 7 of main borehole;In main borehole 5 By design and construction tree root type branch hole 6, (a diameter of 60~80mm or so is divided into 6~10, symmetrical in tree root shape, edge It is in spatial spread fault trend), ensure that the borehole bottom location of main borehole 5 and tree root type branch hole 6 is fallen in tomography 18;Construction Main borehole 5 after the completion and 6 position of tree root type branch hole are as shown in Figure 1, work progress is as shown in Figure 2;
Step 2:As shown in figure 3, in the hydrophobic stage, in aperture, the permeable plug 8 of installation in steel pipe 7, is connected to using ring flange 9 The underground water for entering tree root type branch hole 6 and main borehole 5 is discharged to lane by aperture steel pipe 7 and drain pipe 10 by drain pipe 10 In the gutter 12 of 1 bottom plate of road;The granule mediums such as rubble, sand, the mud that permeable plug 8 can be effectively prevent in tomography 18 are flowed into In drain pipe 10, drain pipe 10 is avoided to block so that underground water smooth can be efficiently flowed into drain pipe 10, while also can Enough reductions or the hydrophobic pressure release of pressure of removal underground water, are conducive to follow-up slip casting;
Step 3:After the completion of the hydrophobic construction stage, the connection of ring flange 9 and aperture steel pipe 7 is released, while being taken out permeable Plug 8;As shown in figure 4, in the slip casting stage, it is connected to aperture steel pipe 7 and high-pressure slip-casting hose 17 using controllable type slurry casting machine 13, simultaneously Non-return valve 14 is installed in high-pressure slip-casting hose 17;The cement class or polyurethane sludge injection material that high-pressure injection pump 15 pumps out pass through High-pressure slip-casting hose 17 is quickly sufficiently injected main borehole 5 and tree root type branch hole 6, and slurries adverse current is prevented by non-return valve 14, The flow of slurries is controlled by controllable type slurry casting machine 13, ensures that slurries are in tree root shape in main borehole 5 and tree root type branch hole 6 Space is spread, and grouting for water blocking curtain and carrying reinforcing body are formed, and both can avoid slurries in main borehole 5 and tree root type branch hole 6 Interior diffusion is uneven and is formed by the non-intersecting problem of grouting for water blocking fixing collar after leading to slip casting, and can prevent because of grouting pressure mistake It is small and cause slurries in main borehole 5 and tree root type branch hole 6 caused by insufficient infusion water blockoff failure;Slip casting process In, grouting parameter is recorded by slip casting recorder 16, grouting parameter includes slurries when pumping out pressure, the flow of slurries and slip casting Between, the dynamic change of the mobility status and grouting parameter of slurries is monitored in real time, convenient for adjustment grouting parameter in time and ensures slip casting Effect.
In hydrophobic pressure release and during mortar depositing construction, the drilling (main borehole and tree root type branch hole) used of when slip casting with Drilling used is same drilling when hydrophobic, has achieved the purpose that a hole is mostly used (recycling) and avoids repeating pore-creating, then Reduce drilling hole amount and saves project cost;The hydrophobic pressure release in tunnel is realized simultaneously and the combination of grouting for water blocking (is dredged Bridging is closed), it forms tunnel and dredges stifled integrated synthesis and harness the river technology, improve mine and harness the river effect.
The above is only a preferred embodiment of the present invention, it should be pointed out that:For the ordinary skill people of the art For member, various improvements and modifications may be made without departing from the principle of the present invention, these improvements and modifications are also answered It is considered as protection scope of the present invention.

Claims (7)

1. a kind of tunnel crosses rich water tomography tree root type and dredges water blockoff integral construction method, it is characterised in that:First in tunnel (1) By setting position construction main borehole (5) on excavation contour line (2), then by design and construction tree root type branch in main borehole (5) It drills (6), ensures that the borehole bottom location of main borehole (5) and tree root type branch hole (6) is fallen in tomography (18);In hydrophobic construction rank Section regard main borehole (5) and tree root type branch hole (6) in communication as weep hole;In the mortar depositing construction stage, by main borehole (5) and tree root type branch hole (6) in communication is used as injected hole.
2. tunnel according to claim 1 crosses rich water tomography tree root type and dredges water blockoff integral construction method, it is characterised in that: After the completion of main borehole (5) construct, in main borehole (5) interior installing hole mouth steel pipe (7).
3. tunnel according to claim 2 crosses rich water tomography tree root type and dredges water blockoff integral construction method, it is characterised in that: In the hydrophobic construction stage, using ring flange (9) connection aperture steel pipe (7) and drain pipe (10), while the peace in aperture steel pipe (7) Fill permeable plug (8).
4. tunnel according to claim 2 crosses rich water tomography tree root type and dredges water blockoff integral construction method, it is characterised in that: In the mortar depositing construction stage, using controllable type slurry casting machine (13) connection aperture steel pipe (7) and high-pressure slip-casting hose (17), while in height Installation non-return valve (14) in pressure grouting hose (17);The slurries that high-pressure injection pump (15) pumps out are noted by high-pressure slip-casting hose (17) Enter main borehole (5) and tree root type branch hole (6), slurries adverse current is prevented by non-return valve (14), passes through controllable type slurry casting machine (13) flow of slurries is controlled.
5. tunnel according to claim 4 crosses rich water tomography tree root type and dredges water blockoff integral construction method, it is characterised in that: Grouting parameter is recorded by slip casting recorder (16), grouting parameter includes slurries when pumping out pressure, the flow of slurries and slip casting Between.
6. tunnel according to claim 1 crosses rich water tomography tree root type and dredges water blockoff integral construction method, it is characterised in that: Include the following steps:
Step 1:Orientation geological drilling rig (3) is placed in tunnel (1), drilling rod (4) is mounted on orientation geological drilling rig (3), Start orientation geological drilling rig (3) and drive drilling rod (4) high speed rotation, is applied by setting position on the excavation contour line (2) of tunnel (1) Work main borehole (5);After the completion of waiting for main borehole (5) construction, in main borehole (5) interior installing hole mouth steel pipe (7);In main borehole (5) By design and construction tree root type branch hole (6), ensure that the borehole bottom location of main borehole (5) and tree root type branch hole (6) is fallen disconnected In layer (18);
Step 2:In aperture, the permeable plug (8) of installation in steel pipe (7), uses ring flange (9) connection aperture steel pipe (7) and drain pipe (10), the underground water for entering tree root type branch hole (6) and main borehole (5) is discharged to by tunnel (1) bottom plate by drain pipe (10) Gutter (12) in;
Step 3:After the completion of the hydrophobic construction stage, the connection of ring flange (9) and aperture steel pipe (7) is released, while being taken out permeable It fills in (8);It is connected to aperture steel pipe (7) and high-pressure slip-casting hose (17) using controllable type slurry casting machine (13), while soft in high-pressure slip-casting Manage installation non-return valve (14) in (17);The slurries that high-pressure injection pump (15) pumps out inject main borehole by high-pressure slip-casting hose (17) (5) and tree root type branch hole (6) slurries adverse current, is prevented by non-return valve (14), passes through controllable type slurry casting machine (13) control slurry The flow of liquid ensures that slurries are spread in main borehole (5) and tree root type branch hole (6) in tree root shape space, it is stifled to form slip casting Water curtain and carrying reinforcing body.
7. tunnel according to claim 1 crosses rich water tomography tree root type and dredges water blockoff integral construction method, it is characterised in that: Mortar depositing construction stage, injection slurries are cement class or polyurethane sludge injection material.
CN201810348236.2A 2018-04-18 2018-04-18 A kind of tunnel crosses rich water tomography tree root type and dredges water blockoff integral construction method Pending CN108590716A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810348236.2A CN108590716A (en) 2018-04-18 2018-04-18 A kind of tunnel crosses rich water tomography tree root type and dredges water blockoff integral construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810348236.2A CN108590716A (en) 2018-04-18 2018-04-18 A kind of tunnel crosses rich water tomography tree root type and dredges water blockoff integral construction method

Publications (1)

Publication Number Publication Date
CN108590716A true CN108590716A (en) 2018-09-28

Family

ID=63613473

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810348236.2A Pending CN108590716A (en) 2018-04-18 2018-04-18 A kind of tunnel crosses rich water tomography tree root type and dredges water blockoff integral construction method

Country Status (1)

Country Link
CN (1) CN108590716A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110273708A (en) * 2019-07-01 2019-09-24 长沙矿山研究院有限责任公司 A kind of hydrophobic method of roadway support structural body control
CN110486049A (en) * 2019-08-29 2019-11-22 龙口矿业集团有限公司 A kind of rich water sandstone tunnel passing fault crushed zone comprehensive processing method
CN113153309A (en) * 2021-03-09 2021-07-23 中铁工程装备集团有限公司 Tunnel construction method
CN117780354A (en) * 2024-02-28 2024-03-29 安徽建筑大学 Method for reinforcing bottom of shaft of coal mine vertical shaft to be built by thick loose layer thin bedrock by sparse-filling

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102031950A (en) * 2010-12-06 2011-04-27 煤炭科学研究总院西安研究院 Hole-forming process method for comb gas extraction borehole in coal seam roof
CN102518464A (en) * 2011-12-09 2012-06-27 中国神华能源股份有限公司 Method for extracting gas at corner on recovery working face in coal mine
CN102587959A (en) * 2012-03-13 2012-07-18 华晋煤层气综合利用有限责任公司 Method for draining coal seam gas
CN102926770A (en) * 2012-11-08 2013-02-13 中国神华能源股份有限公司 Underground draining and grouting process in thin bedrock and thick loose sand layer rich water areas
CN103410564A (en) * 2013-08-29 2013-11-27 中南大学 Tunnel water gushing treatment structure and construction method thereof
CN104234738A (en) * 2014-07-21 2014-12-24 河南理工大学 Low-permeability coal bed multi-branch directional drilling seam cutting anti-reflection method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102031950A (en) * 2010-12-06 2011-04-27 煤炭科学研究总院西安研究院 Hole-forming process method for comb gas extraction borehole in coal seam roof
CN102518464A (en) * 2011-12-09 2012-06-27 中国神华能源股份有限公司 Method for extracting gas at corner on recovery working face in coal mine
CN102587959A (en) * 2012-03-13 2012-07-18 华晋煤层气综合利用有限责任公司 Method for draining coal seam gas
CN102926770A (en) * 2012-11-08 2013-02-13 中国神华能源股份有限公司 Underground draining and grouting process in thin bedrock and thick loose sand layer rich water areas
CN103410564A (en) * 2013-08-29 2013-11-27 中南大学 Tunnel water gushing treatment structure and construction method thereof
CN104234738A (en) * 2014-07-21 2014-12-24 河南理工大学 Low-permeability coal bed multi-branch directional drilling seam cutting anti-reflection method

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110273708A (en) * 2019-07-01 2019-09-24 长沙矿山研究院有限责任公司 A kind of hydrophobic method of roadway support structural body control
CN110486049A (en) * 2019-08-29 2019-11-22 龙口矿业集团有限公司 A kind of rich water sandstone tunnel passing fault crushed zone comprehensive processing method
CN113153309A (en) * 2021-03-09 2021-07-23 中铁工程装备集团有限公司 Tunnel construction method
CN113153309B (en) * 2021-03-09 2022-03-15 中铁工程装备集团有限公司 Tunnel construction method
CN117780354A (en) * 2024-02-28 2024-03-29 安徽建筑大学 Method for reinforcing bottom of shaft of coal mine vertical shaft to be built by thick loose layer thin bedrock by sparse-filling
CN117780354B (en) * 2024-02-28 2024-05-14 安徽建筑大学 Method for reinforcing bottom of shaft of coal mine vertical shaft to be built by thick loose layer thin bedrock by sparse-filling

Similar Documents

Publication Publication Date Title
CN107288657B (en) The weak cementing rock mass seepage failure area slip casting integrated control method of top of underground
CN103603689B (en) Curtain grouting construction method for treating mined-out areas
CN108590716A (en) A kind of tunnel crosses rich water tomography tree root type and dredges water blockoff integral construction method
CN103334770B (en) One is grown up reverse-slope tunnel ultra high water pressure rich water zone of fracture construction method
CN104747075B (en) Anti-collapsing drilling method for grout spraying of soft coal seam
CN106014201B (en) A kind of outer release hole safe construction technique of tunnel grouting curtain
CN112746849B (en) Shaft water-carrying digging and building method
CN108590706A (en) One kind being used for speciality single-track railway tunnel drifter with booms Construction Techniques of Grouting in Heavy Curtain
CN105909265B (en) Pass through the anti-protuberance retrusive deep hole grouting system and method for existing shield tunnel
CN109519150A (en) One kind being directed to the biggish plugging dewatering well device and method of water yield
CN104389634B (en) A kind of mine vertical shaft sieve well shaft wall structure and controlled trapping method thereof
CN105274994B (en) Anti-suck sludge proof grouting process and grouting device in deep saturated sand
CN207761705U (en) Gas drainage system based on roof horizontal drilling
CN101251020A (en) Subsection hole-drilling repeatedly slip-casting method
CN113217043A (en) Efficient and rapid plugging method and construction method for water source with water inrush fault water guide zone
CN110821498B (en) Safe and rapid water plugging and reinforcing method in strong water-rich soft surrounding rock of operation tunnel
CN205591201U (en) Water treatment system is gushed to interior refuse dump
CN104929565A (en) Double-layered grouting guide pipe
CN208502786U (en) Multilevel hierarchy suspension device for rich water sandy gravel stratum tunnel
CN110685292A (en) Foundation pit drainage system and construction method thereof
CN111441775B (en) Rapid grouting arching reinforcement method before excavation of tunnel in stratum with poor groutability and difficult self-stabilization
CN213116341U (en) Underground pressurized grouting water plugging soft and hard aggregate intermittent controllable filling device
CN104929564A (en) High-pressure water hole grouting and feeding device
CN205475198U (en) Karst area solution cavity coats soil layer slip casting reinforcing apparatus
CN114991774A (en) Ground subsection descending type grouting method for crushed andesite basalt stratum

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180928

RJ01 Rejection of invention patent application after publication