CN108411714A - The high peg board of roadbed and its construction method - Google Patents

The high peg board of roadbed and its construction method Download PDF

Info

Publication number
CN108411714A
CN108411714A CN201810438416.XA CN201810438416A CN108411714A CN 108411714 A CN108411714 A CN 108411714A CN 201810438416 A CN201810438416 A CN 201810438416A CN 108411714 A CN108411714 A CN 108411714A
Authority
CN
China
Prior art keywords
roadbed
loading plate
grouting pipe
subgrade
peg board
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810438416.XA
Other languages
Chinese (zh)
Inventor
张世杰
杜文山
宣立华
崔俊杰
马旭东
饶增
王晶
姚瑞珽
刘仕东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Engineering Consulting Group Co Ltd
Original Assignee
China Railway Engineering Consulting Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Engineering Consulting Group Co Ltd filed Critical China Railway Engineering Consulting Group Co Ltd
Priority to CN201810438416.XA priority Critical patent/CN108411714A/en
Publication of CN108411714A publication Critical patent/CN108411714A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B2/00General structure of permanent way
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B2/00General structure of permanent way
    • E01B2/006Deep foundation of tracks

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Railway Tracks (AREA)

Abstract

The invention discloses a kind of high peg board of roadbed and its construction methods comprising:Loading plate is layed in roadbed;Cast-in-situ bored pile, one end stretch into the loading plate, and the other end stretches into below ground;And several Grouting Pipes, run through the loading plate, slip casting can be implemented with down space to the loading plate by the Grouting Pipe.During operation, when generating phenomena such as part is come to nothing between roadbed filling when the loading plate of the high pile slab structure of roadbed and below, slip casting maintenance is carried out to loading plate underlying space using Grouting Pipe, thus avoids security risk, and it is easy to operate, it can effectively reduce maintenance cost.

Description

The high peg board of roadbed and its construction method
Technical field
The present invention relates to subgrade engineering field more particularly to a kind of high peg boards of roadbed and its construction method.
Background technology
The high peg board of roadbed is a kind of structure type being made of foundation pile, loading plate being arranged inside roadbed, is widely used in In high speed railway construction, application range includes:The uncontrollable deep soft soil high-fill roadbed of settlement after construction, collapsibility are yellow Dirt road base, Karst Subgrade etc..By a plurality of high ferro line construction and the practice test of operation, can be had using the high pile slab structure of roadbed Effect control road bed settlement after construction, but part is banketed compared with elevated formation level using after high pile slab structure, is more than stake because roadbed ontology settles Harden structure settles or roadbed ontology is because local Loess Collapsibility, karst collapse etc. generate excessive sedimentation, causes loading plate and Qi Xialu Phenomenon of coming to nothing is generated between based filler, there are security risks.
Invention content
The present invention be directed to the prior art drawbacks described above, a kind of high peg board of roadbed is provided, have the high peg board of the roadbed and its Construction method is come to nothing during operation when generating part between the loading plate and roadbed filling below of the high pile slab structure of roadbed Phenomena such as when, using Grouting Pipe to loading plate underlying space carry out slip casting maintenance, thus avoid security risk, and operation side Just, maintenance cost can effectively be reduced.
The technical solution adopted by the present invention to solve the technical problems is:
On the one hand, a kind of high peg board of roadbed is provided comprising:Loading plate is layed in roadbed;Cast-in-situ bored pile, One end is stretched into the loading plate, and the other end stretches into below ground;And several Grouting Pipes, run through the loading plate, can lead to It crosses the Grouting Pipe and slip casting is implemented with down space to the loading plate.
Preferably, at least one Grouting Pipe, which is equipped with, is used for block.
Preferably, a diameter of 100mm of the Grouting Pipe.
Preferably, the high peg board of the roadbed further includes:Roadbed and track;The roadbed includes:It sets successively from top to bottom Surface layer of subgrade bed, bottom layer of subgrade and the roadbed ontology set;On the surface layer of subgrade bed, the loading plate is laid with the track laying In the receiving portion of the bottom layer of subgrade, for carrying the surface layer of subgrade bed and track;Described cast-in-situ bored pile one end is stretched into In the loading plate, the other end stretches into below ground after passing through the roadbed ontology.
Preferably, the Grouting Pipe is located at below the surface layer of subgrade bed.
On the other hand, a kind of construction method of the high peg board of above-mentioned roadbed is also provided comprising following steps:
S1, bottom layer of subgrade is filled on roadbed ontology, and the appearance for being laid with the loading plate is reserved in the bottom layer of subgrade Receive portion, and the construction drill bored concrete pile in described accommodation section;
S2, the reinforcing bar binding for carrying out the loading plate, while the pre-buried Grouting Pipe;
S3, block is added at the top of the Grouting Pipe, is fallen into prevent sundries, and casting concrete is to form the carrying Plate;
S4, after concrete reach design strength 70% after carry out loading plate plate top graded broken stone filling technology, described in formation Surface layer of subgrade bed.
Preferably, further include step S5, need to the loading plate underlying space carry out slip casting safeguard when, cut the carrying Graded broken stone above plate opens block and carries out slip casting;And after step S6, slip casting, block is added, use concrete backfill Cut the hole that graded broken stone is formed.
Preferably, in the step S2, after the pre-buried Grouting Pipe, reinforcing bar is welded between adjacent Grouting Pipe.
The advantageous effect of technical solution of the present invention is:
The present invention can be during operation, when generation office between the loading plate and roadbed filling below of the high pile slab structure of roadbed When phenomena such as portion comes to nothing, slip casting maintenance is carried out to loading plate underlying space using Grouting Pipe, thus avoids security risk, and grasp Facilitate, can effectively reduce maintenance cost, improves maintenance effects.
Description of the drawings
Present invention will be further explained below with reference to the attached drawings and examples, in attached drawing:
Fig. 1 is the structural plan figure of the high peg board of roadbed in the embodiment of the present invention one;
Fig. 2 is the structure section figure of the high peg board of roadbed in the embodiment of the present invention one.
Specific implementation mode
In order to make the purpose of the present invention, technical solution and advantage be more clearly understood, below in conjunction with drawings and examples, The present invention will be described in further detail.It should be understood that specific embodiment described herein is only used for explaining this hair It is bright, it is not intended to limit the present invention.
Embodiment one:
As shown in Figs. 1-2, the high peg board of roadbed of the invention includes:Loading plate 3, is layed in roadbed;Cast-in-situ bored pile 1, one end stretches into the loading plate 3, and the other end stretches into below ground;And several Grouting Pipes 4, run through the loading plate 3, slip casting can be implemented with down space to the loading plate 3 by the Grouting Pipe 4;As a result, when subgrade settlement is more than roadbed height stake Harden structure settles or roadbed is because local Loess Collapsibility, karst collapse etc. generate excessive sedimentation, causes that loading plate 3 and Qi Xialu occurs When generating phenomena such as coming to nothing between based filler, slip casting maintenance, behaviour can be implemented with down space to the loading plate 3 by Grouting Pipe 4 Make simply, maintenance effects are good, and need not substantially be changed to structure, and maintenance engineering amount is small, at low cost;
In the present embodiment, the Grouting Pipe 4 is steel Grouting Pipe, a diameter of 100mm, and at least one Grouting Pipe 4 tops are equipped with the block for preventing foreign matter from entering, and to further strengthen the intensity of structure entirety, between adjacent Grouting Pipe 4 It is welded with reinforcing bar;Meanwhile the Grouting Pipe 4 and cast-in-situ bored pile 1 are based on uniform force distribution so that slip casting is easy to control System reduces maintenance cost, and ensures that structure entirety stress and slip casting are uniform.
Further, as shown in Fig. 2, the high peg board of the roadbed further includes:Roadbed and track 6;Specifically, the roadbed Including:Surface layer of subgrade bed 10, bottom layer of subgrade 11 and the roadbed ontology 12 set gradually from top to bottom;The track 6 is no tiny fragments of stone, coal, etc. rail Road, on the surface layer of subgrade bed 10, the loading plate 3 is layed in the receiving portion of the bottom layer of subgrade 11 symmetrical laying, is used for Carry the surface layer of subgrade bed 10 and track 6;1 one end of the cast-in-situ bored pile is stretched into the loading plate 3, and the other end passes through institute Below ground is stretched into after stating roadbed ontology 12;On this basis, the Grouting Pipe 4 is located at 10 lower section of the surface layer of subgrade bed, prevents It, which is protruded, influences driving;Secondly, to enhance buffering effect, bed course 2 is equipped between the loading plate 3 and the bottom layer of subgrade 11.
Embodiment two:
Present embodiments provide a kind of construction method of track described in embodiment two comprising following steps:
S1, bottom layer of subgrade is filled on roadbed ontology, and the appearance for being laid with the loading plate is reserved in the bottom layer of subgrade Receive portion, and the construction drill bored concrete pile in described accommodation section;
S2, the reinforcing bar binding for carrying out the loading plate, while the pre-buried Grouting Pipe, and be welded between adjacent Grouting Pipe Reinforcing bar;
S3, block is added at the top of the Grouting Pipe, is fallen into prevent sundries, and casting concrete is to form the carrying Plate;
S4, after concrete reach design strength 70% after carry out loading plate plate top graded broken stone filling technology, described in formation Surface layer of subgrade bed;
S5, need to the loading plate underlying space carry out slip casting safeguard when, cut the graded broken stone above the loading plate, It opens block and carries out slip casting;
And after step S6, slip casting, block is added, the hole formed with concrete backfill cutting graded broken stone.
In conclusion during railroad embankment, when between the loading plate and roadbed filling below of the high pile slab structure of roadbed When generating phenomena such as part is come to nothing, slip casting maintenance is carried out to loading plate underlying space using Grouting Pipe, thus avoids safety hidden Suffer from, and easy to operate, can effectively reduce maintenance cost, improves maintenance effects.
The foregoing is merely presently preferred embodiments of the present invention, is not intended to limit the invention, it is all the present invention spirit and Within principle, any modification, equivalent replacement, improvement and so on should all be included in the protection scope of the present invention.

Claims (8)

1. a kind of high peg board of roadbed, which is characterized in that including:Loading plate is layed in roadbed;Cast-in-situ bored pile, one end It stretches into the loading plate, the other end stretches into below ground;And several Grouting Pipes, run through the loading plate, institute can be passed through It states Grouting Pipe and slip casting is implemented with down space to the loading plate.
2. the high peg board of roadbed as described in claim 1, which is characterized in that at least one Grouting Pipe is equipped with for covering Cap.
3. the high peg board of roadbed as claimed in claim 2, which is characterized in that a diameter of 100mm of Grouting Pipe.
4. the high peg board of roadbed as described in claim 1, which is characterized in that the high peg board of roadbed further includes:Roadbed and rail Road;
The roadbed includes:Surface layer of subgrade bed, bottom layer of subgrade and the roadbed ontology set gradually from top to bottom;The track laying On the surface layer of subgrade bed, the loading plate is layed in the receiving portion of the bottom layer of subgrade, for carrying the surface layer of subgrade bed And track;Described cast-in-situ bored pile one end is stretched into the loading plate, and the other end stretches into ground after passing through the roadbed ontology Below.
5. the high peg board of roadbed as claimed in claim 4, which is characterized in that the Grouting Pipe is located at below the surface layer of subgrade bed.
6. a kind of construction method of the high peg board of roadbed as described in claim any one of 1-5, which is characterized in that including walking as follows Suddenly:
S1, bottom layer of subgrade is filled on roadbed ontology, and the receiving portion for being laid with the loading plate is reserved in the bottom layer of subgrade, And the construction drill bored concrete pile in described accommodation section;
S2, the reinforcing bar binding for carrying out the loading plate, while the pre-buried Grouting Pipe;
S3, block is added at the top of the Grouting Pipe, is fallen into prevent sundries, and casting concrete is to form the loading plate;
S4, after concrete reach design strength 70% after carry out loading plate plate top graded broken stone filling technology, to form the bedding Surface layer.
7. construction method as claimed in claim 6, which is characterized in that further include step S5, need to be to empty below the loading plate Between carry out slip casting when safeguarding, cut the graded broken stone above the loading plate, open block and carry out slip casting;And step S6, note After slurry, block is added, the hole formed with concrete backfill cutting graded broken stone.
8. construction method as claimed in claim 6, which is characterized in that adjacent after the pre-buried Grouting Pipe in the step S2 Reinforcing bar is welded between Grouting Pipe.
CN201810438416.XA 2018-05-09 2018-05-09 The high peg board of roadbed and its construction method Pending CN108411714A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810438416.XA CN108411714A (en) 2018-05-09 2018-05-09 The high peg board of roadbed and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810438416.XA CN108411714A (en) 2018-05-09 2018-05-09 The high peg board of roadbed and its construction method

Publications (1)

Publication Number Publication Date
CN108411714A true CN108411714A (en) 2018-08-17

Family

ID=63138339

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810438416.XA Pending CN108411714A (en) 2018-05-09 2018-05-09 The high peg board of roadbed and its construction method

Country Status (1)

Country Link
CN (1) CN108411714A (en)

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010229696A (en) * 2009-03-27 2010-10-14 Railway Technical Res Inst Repair method for laborsaving track
JP2012031699A (en) * 2010-08-03 2012-02-16 Kfc Ltd Track support force reinforcement method
CN102926304A (en) * 2012-11-28 2013-02-13 中铁第四勘察设计院集团有限公司 Reinforcement method and reinforcement structure for treating railway soft soil roadbed settlement overweight before operation
CN103276639A (en) * 2013-06-07 2013-09-04 中铁第四勘察设计院集团有限公司 Roadbed structure for deep soft soil region
CN103321118A (en) * 2013-07-09 2013-09-25 中铁第四勘察设计院集团有限公司 Bridge road transition section roadbed structure of deep layer yielding ground regions
CN204000470U (en) * 2014-02-28 2014-12-10 中铁第四勘察设计院集团有限公司 The U-shaped waterproof construction of high stake
CN106049196A (en) * 2016-06-08 2016-10-26 杭州江润科技有限公司 Construction method of ballastless track subgrade with combined flexible piles and pile rafts at same fracture surfaces
CN107938455A (en) * 2017-11-28 2018-04-20 中铁工程设计咨询集团有限公司 The ruggedized construction and reinforcement means of the roadbed ground of Soft Soil Layer folder basaltic layer structure
CN208792056U (en) * 2018-05-09 2019-04-26 中铁工程设计咨询集团有限公司 The high peg board of roadbed

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010229696A (en) * 2009-03-27 2010-10-14 Railway Technical Res Inst Repair method for laborsaving track
JP2012031699A (en) * 2010-08-03 2012-02-16 Kfc Ltd Track support force reinforcement method
CN102926304A (en) * 2012-11-28 2013-02-13 中铁第四勘察设计院集团有限公司 Reinforcement method and reinforcement structure for treating railway soft soil roadbed settlement overweight before operation
CN103276639A (en) * 2013-06-07 2013-09-04 中铁第四勘察设计院集团有限公司 Roadbed structure for deep soft soil region
CN103321118A (en) * 2013-07-09 2013-09-25 中铁第四勘察设计院集团有限公司 Bridge road transition section roadbed structure of deep layer yielding ground regions
CN204000470U (en) * 2014-02-28 2014-12-10 中铁第四勘察设计院集团有限公司 The U-shaped waterproof construction of high stake
CN106049196A (en) * 2016-06-08 2016-10-26 杭州江润科技有限公司 Construction method of ballastless track subgrade with combined flexible piles and pile rafts at same fracture surfaces
CN107938455A (en) * 2017-11-28 2018-04-20 中铁工程设计咨询集团有限公司 The ruggedized construction and reinforcement means of the roadbed ground of Soft Soil Layer folder basaltic layer structure
CN208792056U (en) * 2018-05-09 2019-04-26 中铁工程设计咨询集团有限公司 The high peg board of roadbed

Similar Documents

Publication Publication Date Title
CN204401447U (en) A kind of structure preventing bumping at bridge-head
CN104195911B (en) The one section Widening Embankment structure of suspended wall height barricade embankment near water and construction method
CN106522037A (en) Widening subgrade structure based on existing railway subgrade and construction method of widening subgrade structure
CN103276639B (en) Roadbed structure for deep soft soil region
CN104746501B (en) Treatment method and structure of bridge-head foundation sliding settlement
KR101893408B1 (en) Track bearing pile structure for strengthening end bearing capacity to restrain subsidence of soft soil, and construction method for the same
CN101144256B (en) Slag-free orbit reinforced concrete pile net structure roadbed and construction method thereof
CN203960700U (en) The closed road structure of stake holder U-lag
CN204849508U (en) Roadbed structure of soft soil foundation highway road bridge changeover portion
CN103452130B (en) The deformed bar net board-like barricade of reinforcement earth pillar
CN106087628B (en) Without the cast-in-place baffle plate foam concrete light road bank structure of conical slope and construction method
CN107190602A (en) A kind of river degradation section pile formula foam concrete light road bank structure and construction method
CN207727452U (en) A kind of back filling behind abutment structure sheaf for preventing culvert jump vehicle
CN108166395B (en) A kind of construction method for building beam bridge across Business Line
EP2744942B1 (en) Railway track support system
RU2668529C1 (en) High speed main road
CN204059125U (en) One suspended wall height barricade embankment near water section Widening Embankment structure
CN208792056U (en) The high peg board of roadbed
CN102635104A (en) Wedge-shaped Geocell cement reinforced soil structure for road-bridge connection and construction method thereof
CN102352582A (en) Reinforced soil-cement pile strengthening structure of railway roadbed
CN110792010A (en) Roadbed reinforcing structure for preventing vehicle bump at bridge head and construction method thereof
CN108411714A (en) The high peg board of roadbed and its construction method
CN207552833U (en) A kind of elevated bridge basal perimeter ground road structure
CN104652299B (en) Construction method is shifted out in the whole hole of a kind of existing bridges and culverts of electric railway
CN103790079B (en) A kind of roadbed prestressed reinforcement intensifying method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180817