CN102926304A - Reinforcement method and reinforcement structure for treating railway soft soil roadbed settlement overweight before operation - Google Patents

Reinforcement method and reinforcement structure for treating railway soft soil roadbed settlement overweight before operation Download PDF

Info

Publication number
CN102926304A
CN102926304A CN2012104950381A CN201210495038A CN102926304A CN 102926304 A CN102926304 A CN 102926304A CN 2012104950381 A CN2012104950381 A CN 2012104950381A CN 201210495038 A CN201210495038 A CN 201210495038A CN 102926304 A CN102926304 A CN 102926304A
Authority
CN
China
Prior art keywords
roadbed
settlement
pile cover
pipe
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2012104950381A
Other languages
Chinese (zh)
Other versions
CN102926304B (en
Inventor
周青爽
李小和
赵新益
曾长贤
张守周
姚洪锡
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Siyuan Survey and Design Group Co Ltd
Original Assignee
China Railway Siyuan Survey and Design Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Siyuan Survey and Design Group Co Ltd filed Critical China Railway Siyuan Survey and Design Group Co Ltd
Priority to CN201210495038.1A priority Critical patent/CN102926304B/en
Publication of CN102926304A publication Critical patent/CN102926304A/en
Application granted granted Critical
Publication of CN102926304B publication Critical patent/CN102926304B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Foundations (AREA)

Abstract

The invention discloses a reinforcement method and a reinforcement structure for treating railway soft soil roadbed settlement overweight before operation. The reinforcement structure mainly consists of five parts, namely a main bearing structure system, a reinforced cushion layer structure system, a foundation bed drainage system, a settlement observation system and a reserved grouting system. The technical problems that the existing roadbed is greatly damaged, the construction period is long, the construction property is low, the quality is difficult to control and the problem that the soft soil roadbed settlement overweight is caused in the conventional technical scheme are effectively solved.

Description

Process reinforcement means and ruggedized construction that the front railway soft soil roadbed settlement of operation exceeds standard
Technical field
The present invention relates to the Roadbed Construction Technology field, refer to particularly a kind of reinforcement means and ruggedized construction that the front railway soft soil roadbed settlement of operation exceeds standard of processing.
Technical background
At present, be used for to solve the exceed standard technological means of problem of railway soft soil roadbed settlement before the operation and mainly contain the lateral restraint stake in conjunction with drilled pile technology under long spiral CFG stake (Cement Fly-ash Grave, CFG) technology and the bedding under substrate slurry injection technique, displacement lightweight material technology, the bedding etc.
Existing lateral restraint stake is carried out lateral restraint in conjunction with substrate slurry injection technique need to construct 3~4 row's rotary churning piles or pile tube near the toe of embankment both sides, satisfy the need and adopt at the bottom of the levee foundation static pressure grouting to reinforce drawing the hole near side slope and the toe, have advantages of the resistance to overturning that can improve embankment structure, reduce foundation settlement and destroy little to existing roadbed.But this technical process poor controllability, consolidation effect remain time check, can not thoroughly solve the soft soil roadbed settlement problem that exceeds standard.
Existing displacement lightweight material technology is to replace former roadbed filling by light fillings such as employing air bubble mix light-textured soils behind the excavation section by section roadbed, can alleviate the load of ground, thereby reduce the stability of foundation settlement and raising ground, and quality controllability is high.But it is large that this technology is destroyed existing roadbed, and the roadbed scheme exploitativeness that road bed is provided with the works that cable channel etc. is difficult to remove is poor.
Long spiral CFG stake and drilled pile structure technology need be removed track structure, contact net lines etc. under the bedding, require to be excavated to certain depth under the curb, thoroughly effect a radical cure the solution sedimentation by construction CFG stake or drilled pile in the road bed scope and exceed standard and the subgrade stability problem.This technology is limited to the destruction of existing roadbed, but construction period is longer, and without pioneer road and pumping material at need, exploitativeness is poor at the scene.
At present, not yet find to existing roadbed destroy little, exploitativeness good, quality is easy to control and can be than casual labourer's thorough exceed standard technology of problem of railway soft soil roadbed settlement before the radical cure operation in the phase.
Summary of the invention
Purpose of the present invention is exactly that a kind of reinforcement means and ruggedized construction that the front railway soft soil roadbed settlement of operation exceeds standard of processing will be provided, and the method and structure are little to existing roadbed destruction, exploitativeness good, quality is easy to control and can thoroughly effect a radical cure the technical problem that the front railway soft soil roadbed settlement of operation exceeds standard in the phase than the casual labourer.
For realizing this purpose, designed a kind of processing of the present invention runed the reinforcement means that front railway soft soil roadbed settlement exceeds standard, and it comprises the steps:
Step 1: remove track structure and the contact net lines in the soft soil roadbed zone of railway that needs reinforcement, then excavate roadbed top bedding, form foundation ditch, a plurality of prestressed high-strength concrete piles of vertical insertion roadbed inside are set at foundation ditch;
Step 2: the pre-buried vertical Grouting Pipe that is interconnected successively in described foundation ditch, laterally Grouting Pipe and vertically Grouting Pipe, the foundation ditch of the roadbed pre-buried pile cover in bottom and roadbed body relative displacement monitor and roadbed body settlement monitoring device behind excavation, then lift the good a plurality of pile cover reinforcing cages of in advance colligation to corresponding prestressed high-strength concrete pile, between adjacent pile cover reinforcing cage, connecting reinforcement is installed, perfusion pile cover concrete in the pile cover reinforcing cage, form pile cover reach the intensity of designing requirement until the pile cover concrete after, filling concrete between described adjacent pile cover, described pile cover and roadbed body relative displacement monitor are between pile cover and roadbed;
Step 3: above pile cover, lay composite geo-membrane, above composite geo-membrane, lay medium-sand seam, lay first floor graded broken stone layer at medium-sand seam, laying high-strength geo-grid bed course on first floor graded broken stone layer, lay second layer graded broken stone layer at high-strength geo-grid bed course, roadbed body settlement monitoring device pre-buried in the step 2 runs through pile cover, composite geo-membrane, medium-sand seam, first floor graded broken stone layer, high-strength geo-grid bed course and second layer graded broken stone layer, and insert in the roadbed bottom of described roadbed body settlement monitoring device;
Step 4: the two ends at described foundation ditch arrange the tapping pipe that leads to side slope, and an end of described tapping pipe inserts medium-sand seam, and the other end of tapping pipe leads to side slope, namely form the ruggedized construction of the front railway soft soil roadbed settlement of operation.
The roadbed of described a plurality of prestressed high-strength concrete pile behind excavation is evenly arranged, and laterally the spacing between adjacent prestressed high-strength concrete pile equates, vertically the spacing between adjacent prestressed high-strength concrete pile also equates.
Spacing between described laterally adjacent prestressed high-strength concrete pile is 2 ~ 3m; Spacing between described vertically adjacent prestressed high-strength concrete pile is 2 ~ 3m.
In step 2, roadbed behind excavation is pre-buried pile cover settlement monitoring device also, pile cover is inserted in the bottom of described pile cover settlement monitoring device, and composite geo-membrane, medium-sand seam, first floor graded broken stone layer, high-strength geo-grid bed course and second layer graded broken stone layer are run through in the top of pile cover settlement monitoring device.
In step 1, excavation roadbed 1 ~ 2m to the curb forms foundation ditch, in step 2, at side slope curb position, both sides pre-buried curb settlement monitoring device.
Described pile cover and roadbed body relative displacement monitor comprise single-point sedimentation joint measurement displacement meter, anchor head, flange and the first mounting pipe; In the step 2, pre-buried pile cover and roadbed body relative displacement monitor are front at the foundation ditch bottom of roadbed excavation monitoring device mounting groove, bottom at the monitor mounting groove is laid and tamping bottom land medium coarse sand bed course, the first mounting pipe is set in the monitor mounting groove, single-point sedimentation joint measurement displacement meter is set in the first mounting pipe, insert in the pile cover by anchor head on the top of single-point sedimentation joint measurement displacement meter, the bottom of single-point sedimentation joint measurement displacement meter is provided with flange, medium coarse sand bed course at the bottom of the described flange link slot, Cast-in-situ Piles in Sand-filling in the filling slot between described the first mounting pipe and the monitor mounting groove.
Described roadbed body settlement monitoring device comprises settlement plate base, sedimentation measuring staff, the second mounting pipe and pipe cap, wherein, the top of described the second mounting pipe connects pipe cap, the bottom of the second mounting pipe is arranged on the settlement plate base, in described the second mounting pipe the sedimentation measuring staff is set, the top of described sedimentation measuring staff is stretched out the second mounting pipe and is lower than pipe cap, and the bottom of sedimentation measuring staff connects the settlement plate base, and described settlement plate base is connected with roadbed.
Described curb settlement monitoring device comprises grout injection in screw thread drill rod and the hole, and the place offers vertical channel at curb, and the screw thread drill rod is set in the described vertical channel, between described vertical channel and the screw thread drill rod grout injection is set.
A kind ofly run the ruggedized construction that front railway soft soil roadbed settlement exceeds standard, comprise roadbed, be opened in the foundation ditch at roadbed top, described foundation ditch is provided with a plurality of prestressed high-strength concrete piles of vertical insertion roadbed inside, the top of described each prestressed high-strength concrete pile arranges pile cover, between the described adjacent pile cover connecting reinforcement and concrete are set, composite geo-membrane is laid at the top of described pile cover, above composite geo-membrane, lay medium-sand seam, lay first floor graded broken stone layer on the described medium-sand seam, laying high-strength geo-grid bed course on the described first floor graded broken stone layer is laid second layer graded broken stone layer on the described high-strength geo-grid bed course;
Pile cover and roadbed body relative displacement monitor are set between described pile cover and the roadbed, also be provided with the roadbed body settlement monitoring device that runs through pile cover, composite geo-membrane, medium-sand seam, first floor graded broken stone layer, high-strength geo-grid bed course and second layer graded broken stone layer on the described roadbed, insert in the roadbed bottom of described roadbed body settlement monitoring device.
The vertical Grouting Pipe that setting is interconnected successively in the described foundation ditch, horizontal Grouting Pipe and vertical Grouting Pipe.
The two ends of described foundation ditch arrange the tapping pipe that leads to side slope, and an end of described tapping pipe inserts medium-sand seam, and the other end of tapping pipe leads to side slope.
Described a plurality of prestressed high-strength concrete pile is evenly arranged at roadbed, laterally the spacing between adjacent prestressed high-strength concrete pile equates, vertically the spacing between adjacent prestressed high-strength concrete pile also equates, the spacing between described laterally adjacent prestressed high-strength concrete pile is 2 ~ 3m; Spacing between described vertically adjacent prestressed high-strength concrete pile is 2 ~ 3m.
Curb place, described side slope both sides is provided with curb settlement monitoring device;
Described pile cover and roadbed body relative displacement monitor comprise single-point sedimentation joint measurement displacement meter, anchor head, flange and the first mounting pipe; Offer the monitor mounting groove on the described roadbed, medium coarse sand bed course at the bottom of the bottom laying groove of monitor mounting groove, the first mounting pipe is set in the monitor mounting groove, single-point sedimentation joint measurement displacement meter is set in the first mounting pipe, insert in the pile cover by anchor head on the top of single-point sedimentation joint measurement displacement meter, the bottom of single-point sedimentation joint measurement displacement meter is provided with flange, medium coarse sand bed course at the bottom of the described flange link slot, Cast-in-situ Piles in Sand-filling in the filling slot between described the first mounting pipe and the monitor mounting groove;
Described roadbed body settlement monitoring device comprises settlement plate base, sedimentation measuring staff, the second mounting pipe and pipe cap, wherein, the top of described the second mounting pipe connects pipe cap, the bottom of the second mounting pipe is arranged on the settlement plate base, in described the second mounting pipe the sedimentation measuring staff is set, the top of described sedimentation measuring staff is stretched out the second mounting pipe and is lower than pipe cap, and the bottom of sedimentation measuring staff connects the settlement plate base, and described settlement plate base is connected with roadbed;
Described curb settlement monitoring device comprises grout injection in screw thread drill rod and the hole, and described curb place offers vertical channel, and the screw thread drill rod is set in the described vertical channel, between described vertical channel and the screw thread drill rod grout injection is set.
Beneficial effect of the present invention is:
1, the present invention only need remove track, contact net lines and roadway excavation 1 ~ 2m to the curb, and to the destructiveness less of roadbed, the main structure construction duration is short, and quality is easy to control.
2, reinforced cushion layer structure of the present invention system with train, track and bedding approximately 50% Load Transfer to the main bearing structure system that is formed by prestressed high-strength concrete pile+pile cover, because prestressed high-strength concrete pile stretches into effective bearing stratum, greatly reduced the load that the roadbed body bears, the sedimentation of prestressed high-strength concrete pile element body because efficiency of pile groups satisfies the need can be played effect of contraction again, thereby can fundamentally control soft soil roadbed settlement, guarantee the ride comfort of track and the safe operation of train.
3, the bedding drainage system of setting of the present invention can effectively be got rid of the bedding internal water, prevents Defect of Foundation Bed of Express.
4, reservation filling system of the present invention can select reasonable opportunity that the position of coming to nothing, roadbed body part under the pile cover is carried out after-teeming slurry and processed according to the settlement observation system data, thereby avoid the pile cover stress condition to worsen, guaranteed the globality of roadbed, the new structure pattern that this patent proposes can better be applicable to process before the operation railway soft soil roadbed settlement of the duration anxiety problem that exceeds standard.
On the whole, ruggedized construction of the present invention is by main bearing structure system, reinforced cushion layer structure system, bedding drainage system, settlement observation system and reserve filling system five major parts and form, efficiently solve the prior art scheme to existing roadbed destroy large, long in time limit, exploitativeness is poor, quality is wayward and can't effect a radical cure the problem that soft soil roadbed settlement exceeds standard.
Description of drawings
Fig. 1 is soft soil roadbed settlement punishment new structure schematic cross-sectional view among the present invention;
Fig. 2 is schematic cross-sectional view behind roadway excavation top, the Central Plains of the present invention formation foundation ditch;
Fig. 3 is the structural representation of pile cover and roadbed body relative displacement monitor among the present invention;
Fig. 4 is the structural representation of pile cover settlement monitoring device among the present invention;
Fig. 5 is the structural representation of curb settlement monitoring device among the present invention;
Fig. 6 is the structural representation of roadbed body settlement monitoring device among the present invention;
Among the figure, 1-main bearing structure system, 1.1-prestressed high-strength concrete pile, 1.2-pile cover, 2-reinforced cushion layer structure system, 2.1-high-strength geo-grid bed course, 2.2-first floor graded broken stone layer, 2.3-connecting reinforcement, 2.4-concrete, 2.5-second layer graded broken stone layer, 3-bedding drainage system, 3.1-composite geo-membrane, 3.2-tapping pipe, 3.3-medium-sand seam, 4-settlement observation system, 4.1-pile cover and roadbed body relative displacement monitor, 4.1.1-single-point sedimentation joint measurement displacement meter, 4.1.2-monitor mounting groove, 4.1.3-anchor head, 4.1.4-flange, 4.1.5 the-the first mounting pipe, 4.1.6 Cast-in-situ Piles in Sand-filling in the-groove, 4.1.7-bottom land medium coarse sand bed course, 4.2-pile cover settlement monitoring device, 4.2.1-drill rod, 4.2.2-steel sleeve, 4.2.3-line pipe cap, 4.3-curb settlement monitoring device, 4.3.1-screw thread drill rod, 4.3.2-cement paste, 4.4-roadbed body settlement monitoring device, 4.4.1-settlement plate base, 4.4.2-sedimentation measuring staff, 4.4.3 the-the second mounting pipe, 4.4.4-pipe cap, 5.1-vertical Grouting Pipe, 5.2-horizontal Grouting Pipe, 5.3-vertical Grouting Pipe, 6-road structure, 6.1-roadbed, 6.2-side slope, 6.3-foundation ditch.
The specific embodiment
The present invention is described in further detail below in conjunction with the drawings and specific embodiments:
A kind of processing runed the reinforcement means that front railway soft soil roadbed settlement exceeds standard, and shown in Fig. 1 ~ 6, it comprises the steps:
Step 1: track structure and the contact net lines of removing the soft soil roadbed zone of railway that needs reinforcement, then excavate roadbed 6.1 top beddings, form foundation ditch 6.3, a plurality of prestressed high-strength concrete piles 1.1 of vertical insertion roadbed 6.1 inside are set at foundation ditch 6.3, after prestressed high-strength concrete pile 1.1 constructions are finished, in time adopt the pea gravel concreten filling closely knit between prestressed high-strength concrete pile 1.1 and hole wall;
Step 2: in the foundation ditch 6.3 interior pre-buried vertical Grouting Pipe 5.1 that are interconnected successively, laterally Grouting Pipe 5.2 and vertically Grouting Pipe 5.3, above-mentioned vertical Grouting Pipe 5.1, laterally Grouting Pipe 5.2 and vertically Grouting Pipe 5.3 be used for the position of coming to nothing, roadbed body part under the pile cover is carried out the after-teeming slurry and processed, can avoid the pile cover stress condition to worsen, guarantee the globality of roadbed, the pre-buried pile cover in foundation ditch 6.3 bottoms of roadbed 6.1 and roadbed body relative displacement monitor 4.1 and roadbed body settlement monitoring device 4.4 behind excavation, then lift the good a plurality of pile cover reinforcing cages of in advance colligation to corresponding prestressed high-strength concrete pile 1.1, connecting reinforcement 2.3 is installed between adjacent pile cover reinforcing cage, perfusion pile cover concrete in the pile cover reinforcing cage, form pile cover 1.2 reach the intensity of designing requirement until the pile cover concrete after, 1.2 filling concrete 2.4 of described adjacent pile cover, preferably select the C25 plain concrete, described pile cover and roadbed body relative displacement monitor 4.1 are between pile cover 1.2 and roadbed 6.1;
Step 3: above pile cover 1.2, lay composite geo-membrane 3.1, this composite geo-membrane 3.1, above composite geo-membrane 3.1, lay the thick medium-sand seam 3.3 of 0.1m, lay first floor graded broken stone layer 2.2 at medium-sand seam 3.3, laying high-strength geo-grid bed course 2.1 on first floor graded broken stone layer 2.2, lay second layer graded broken stone layer 2.5 at high-strength geo-grid bed course 2.1, roadbed body settlement monitoring device 4.4 pre-buried in the step 2 runs through pile cover 1.2, composite geo-membrane 3.1, medium-sand seam 3.3, first floor graded broken stone layer 2.2, high-strength geo-grid bed course 2.1 and second layer graded broken stone layer 2.5, the bottom of described roadbed body settlement monitoring device 4.4 insert in the roadbed 6.1; Above-mentioned high-strength geogrids layer 2.1 design tensile strength are not less than 250kN/m, elongation per unit length≤10%, first floor graded broken stone layer 2.2 and second layer graded broken stone layer 2.5 thickness are 0.4 ~ 0.6m, the CBR(bearing ratio of above-mentioned composite geo-membrane 3.1) bursting strength is not less than 2.5kN;
Step 4: the two ends at described foundation ditch 6.3 arrange the tapping pipe 3.2 that leads to side slope 6.2, this tapping pipe 3.2 is PVC(polyvinylchloride, polyvinyl chloride) tapping pipe, the diameter of this PVC tapping pipe is 10cm, one end of tapping pipe 3.2 inserts medium-sand seam 3.3, the other end of tapping pipe 3.2 leads to side slope 6.2, namely forms the ruggedized construction of the front railway soft soil roadbed settlement of operation.
In the technique scheme, the roadbed of a plurality of prestressed high-strength concrete piles 1.1 behind excavation is evenly arranged, laterally the spacing of 1.1 of adjacent prestressed high-strength concrete piles equates, vertically the spacing of 1.1 of adjacent prestressed high-strength concrete piles also equates.
In the technique scheme, laterally the spacing of 1.1 of adjacent prestressed high-strength concrete piles is 2 ~ 3m; Vertically the spacing of 1.1 of adjacent prestressed high-strength concrete piles is 2 ~ 3m, is approximated to arranged in squares.
In the technique scheme, in step 2, roadbed 6.1 behind excavation is pre-buried pile cover settlement monitoring device 4.2 also, pile cover 1.2 is inserted in the bottom of pile cover settlement monitoring device 4.2, and composite geo-membrane 3.1, medium-sand seam 3.3, first floor graded broken stone layer 2.2, high-strength geo-grid bed course 2.1 and second layer graded broken stone layer 2.5 are run through in the top of pile cover settlement monitoring device 4.2.
Such scheme is in step 1, and excavation roadbed 6.1 1 ~ 2m to the curb forms foundation ditch 6.3, in the step 2, at both sides side slope 6.2 curb positions pre-buried curb settlement monitoring device 4.3.
In the technique scheme, described pile cover and roadbed body relative displacement monitor 4.1 comprise single-point sedimentation joint measurement displacement meter 4.1.1, anchor head 4.1.3, flange 4.1.4 and the first mounting pipe 4.1.5; In the step 2, pre-buried pile cover and roadbed body relative displacement monitor 4.1 front foundation ditch 6.3 bottom excavation monitoring device mounting groove 4.1.2 at roadbed 6.1, bottom at monitor mounting groove 4.1.2 is laid and tamping bottom land medium coarse sand bed course 4.1.7, the first mounting pipe 4.1.5 is set in monitor mounting groove 4.1.2, single-point sedimentation joint measurement displacement meter 4.1.1 is set in the first mounting pipe 4.1.5, insert in the pile cover 1.2 by anchor head 4.1.3 on the top of single-point sedimentation joint measurement displacement meter 4.1.1, the bottom of single-point sedimentation joint measurement displacement meter 4.1.1 is provided with flange 4.1.4, medium coarse sand bed course 4.1.7 at the bottom of the described flange 4.1.4 link slot, Cast-in-situ Piles in Sand-filling 4.1.6 in the filling slot between described the first mounting pipe 4.1.5 and the monitor mounting groove 4.1.2.
In the technique scheme, described roadbed body settlement monitoring device 4.4 comprises settlement plate base 4.4.1, sedimentation measuring staff 4.4.2, the second mounting pipe 4.4.3 and pipe cap 4.4.4, wherein, the top of described the second mounting pipe 4.4.3 connects pipe cap 4.4.4, the bottom of the second mounting pipe 4.4.3 is arranged on the settlement plate base 4.4.1, in described the second mounting pipe 4.4.3 sedimentation measuring staff 4.4.2 is set, the top of described sedimentation measuring staff 4.4.2 is stretched out the second mounting pipe 4.4.3 and is lower than pipe cap 4.4.4, the bottom of sedimentation measuring staff 4.4.2 connects settlement plate base 4.4.1, and described settlement plate base 4.4.1 is connected with roadbed 6.1.
In the technique scheme, described curb settlement monitoring device 4.3 comprises grout injection 4.3.2 in screw thread drill rod 4.3.1 and the hole, the place offers vertical channel at curb, and screw thread drill rod 4.3.1 is set in the described vertical channel, between described vertical channel and the screw thread drill rod 4.3.1 grout injection 4.3.2 is set.
A kind of shown in Fig. 1 ~ 6 runs the ruggedized construction that front railway soft soil roadbed settlement exceeds standard, comprise roadbed 6.1, be opened in the foundation ditch 6.3 at roadbed 6.1 tops, foundation ditch 6.3 is provided with a plurality of prestressed high-strength concrete piles 1.1 of vertical insertion roadbed 6.1 inside, the top of each prestressed high-strength concrete pile 1.1 arranges pile cover 1.2, connecting reinforcement 2.3 and concrete 2.4 are set between the adjacent pile cover 1.2, composite geo-membrane 3.1 is laid at the top of pile cover 1.2, above composite geo-membrane 3.1, lay medium-sand seam 3.3, lay first floor graded broken stone layer 2.2 on the medium-sand seam 3.3, laying high-strength geo-grid bed course 2.1 on the first floor graded broken stone layer 2.2 is laid second layer graded broken stone layer 2.5 on the high-strength geo-grid bed course 2.1;
Pile cover and roadbed body relative displacement monitor 4.1 are set between above-mentioned pile cover 1.2 and the roadbed 6.1, also be provided with the roadbed body settlement monitoring device 4.4 that runs through pile cover 1.2, composite geo-membrane 3.1, medium-sand seam 3.3, first floor graded broken stone layer 2.2, high-strength geo-grid bed course 2.1 and second layer graded broken stone layer 2.5 on the roadbed 6.1, insert in the roadbed 6.1 bottom of roadbed body settlement monitoring device 4.4.
In the technique scheme, the vertical Grouting Pipe 5.1 that foundation ditch 6.3 interior settings are interconnected successively, horizontal Grouting Pipe 5.2 and vertical Grouting Pipe 5.3.
In the technique scheme, the two ends of foundation ditch 6.3 arrange the tapping pipe 3.2 that leads to side slope 6.2, and an end of tapping pipe 3.2 inserts medium-sand seam 3.3, and the other end of tapping pipe 3.2 leads to side slope 6.2.
In the technique scheme, a plurality of prestressed high-strength concrete piles 1.1 are evenly arranged at roadbed 6.1, laterally the spacing of 1.1 of adjacent prestressed high-strength concrete piles equates, vertically the spacing of 1.1 of adjacent prestressed high-strength concrete piles also equates, laterally the spacing of 1.1 of adjacent prestressed high-strength concrete piles is 2 ~ 3m; Vertically the spacing of 1.1 of adjacent prestressed high-strength concrete piles is 2 ~ 3m.
In the technique scheme, curb place, side slope 6.2 both sides is provided with curb settlement monitoring device 4.3;
Pile cover described above and roadbed body relative displacement monitor 4.1 comprise single-point sedimentation joint measurement displacement meter 4.1.1, anchor head 4.1.3, flange 4.1.4 and the first mounting pipe 4.1.5; Offer monitor mounting groove 4.1.2 on the described roadbed 6.1, medium coarse sand bed course 4.1.7 at the bottom of the bottom laying groove of monitor mounting groove 4.1.2, the first mounting pipe 4.1.5 is set in monitor mounting groove 4.1.2, single-point sedimentation joint measurement displacement meter 4.1.1 is set in the first mounting pipe 4.1.5, insert in the pile cover 1.2 by anchor head 4.1.3 on the top of single-point sedimentation joint measurement displacement meter 4.1.1, the bottom of single-point sedimentation joint measurement displacement meter 4.1.1 is provided with flange 4.1.4, medium coarse sand bed course 4.1.7 at the bottom of the described flange 4.1.4 link slot, Cast-in-situ Piles in Sand-filling 4.1.6 in the filling slot between described the first mounting pipe 4.1.5 and the monitor mounting groove 4.1.2;
Above-mentioned roadbed body settlement monitoring device 4.4 comprises settlement plate base 4.4.1, sedimentation measuring staff 4.4.2, the second mounting pipe 4.4.3 and pipe cap 4.4.4, wherein, the top of described the second mounting pipe 4.4.3 connects pipe cap 4.4.4, the bottom of the second mounting pipe 4.4.3 is arranged on the settlement plate base 4.4.1, in described the second mounting pipe 4.4.3 sedimentation measuring staff 4.4.2 is set, the top of described sedimentation measuring staff 4.4.2 is stretched out the second mounting pipe 4.4.3 and is lower than pipe cap 4.4.4, the bottom of sedimentation measuring staff 4.4.2 connects settlement plate base 4.4.1, and described settlement plate base 4.4.1 is connected with roadbed 6.1;
Curb settlement monitoring device 4.3 described above comprises grout injection 4.3.2 in screw thread drill rod 4.3.1 and the hole, described curb place offers vertical channel, screw thread drill rod 4.3.1 is set in the described vertical channel, between described vertical channel and the screw thread drill rod 4.3.1 grout injection 4.3.2 is set.
In the technique scheme, the range of single-point sedimentation joint measurement displacement meter 4.1.1 is selected 15mm, and the diameter of flange 4.1.4 is 10cm, and the first mounting pipe 4.1.5 is pvc pipe, and its diameter is 5cm, and screw thread drill rod 4.3.1 diameter is 28mm,
In the technique scheme, roadbed 6.1, side slope 6.2 and foundation ditch 6.3 consist of road structure 6.
In the technique scheme, prestressed high-strength concrete pile 1.1 and the main bearing structure of pile cover 1.2 formations system 1.
In the technique scheme, high-strength geo-grid bed course 2.1, first floor graded broken stone layer 2.2, connecting reinforcement 2.3, concrete 2.4 and the reinforced cushion layer structure of second layer graded broken stone layer 2.5 formation system 2.
In the technique scheme, composite geo-membrane 3.1, tapping pipe 3.2 and medium-sand seam 3.3 consist of bedding drainage system 3.
In the technique scheme, pile cover and roadbed body relative displacement monitor 4.1, pile cover settlement monitoring device 4.2, curb settlement monitoring device 4.3, roadbed body settlement monitoring device 4.4 consist of settlement observation system 4.
In the technique scheme, drill rod 4.2.1, steel sleeve 4.2.2 and internal thread pipe cap 4.2.3 consist of pile cover settlement monitoring device 4.2.Wherein, the top of steel sleeve 4.2.2 connects internal thread cap 4.2.3, in the bottom setting and pile cover 1.2 of steel sleeve 4.2.2; Drill rod 4.2.1 top exceeds steel sleeve 4.2.2 and is lower than internal thread pipe cap 4.2.3, and drill rod 4.2.1 stretches into the bottom pile cover 1.2 and welds with the pile cover reinforcing bar.
Adopt the present invention of above-mentioned reinforcement means and structure be easy to engineering construction, to existing roadbed destroy little, can adapt to than casual labourer's phase and require and can thoroughly effect a radical cure the soft soil roadbed settlement problem that exceeds standard.
Structure division of the present invention is mainly by bearing structure system, reinforced cushion layer structure system, bedding drainage system, settlement observation system with reserve filling system five major parts and form.Its main structure construction duration is short, and construction quality is easy to control.This structural requirement is removed track structure, contact net lines and roadway excavation about 1.5m, does not affect contact net column and the facilities such as basis and communicaton and signal cable groove thereof at curb place, to the destruction less of existing roadbed to the curb.Main bearing structure system adopts prestressed high-strength concrete pile 1.1+ reinforced concrete pile cap, enter reliable bearing stratum at the bottom of 1.1 of the prestressed high-strength concrete piles, bear by reinforced cushion layer structure system and be passed to approximately 50% load of the train of pile cover 1.2 and track load and bedding.Because bearing structure intensity is high, settlement is little, has guaranteed the ride comfort of track and the safe operation of train, has higher reliability; In addition, under the effect performance of bearing structure and reinforced cushion layer structure, inter-pile soil carries hardly, has greatly reduced the load that the roadbed body bears; Simultaneously the satisfy the need sedimentation of element body of the efficiency of pile groups of a plurality of prestressed high-strength concrete piles 1.1 can be played effect of contraction again, thereby can effectively control soft soil roadbed settlement.To be arranged at the ground basal plane different from traditional pipe pile network structure, and this new structure is arranged under the road bed about 1.5m, and prestressed high-strength concrete pile 1.1 has been considered the negative skin friction of pile that the sedimentation of roadbed body causes during design.Reinforced cushion layer structure system adopts between graded broken stone layer+high-strength geo-grid bed course 2.1+ pile cover filling C25 plain concrete 2.4 between connecting reinforcement 2.3+ pile cover, has greatly strengthened the Total tune metamorphosis of a clump of piles.The bedding drainage system is composed as follows: 4% two-sided weathering is set by the pile cover end face, on cover the thick medium-sand seam 3.3+ of 0.1m composite geo-membrane 3.1, two ends arrange in the rhone that φ 10cmPVC tapping pipe 3.2 extend out to roadbed both sides side slope under the curb, can effectively get rid of the bedding internal water, prevent Defect of Foundation Bed of Express.The settlement observation system is comprised of pile cover and roadbed body relative displacement monitor 4.1, pile cover settlement monitoring device 4.2 and curb settlement monitoring device 4.3, is respectively applied to monitor relative displacement, pile cover sedimentation and the curb sedimentation of pile cover and roadbed body.Because prestressed high-strength concrete pile 1.1 stretches into reliable bearing stratum, prestressed high-strength concrete pile 1.1 sedimentations are very little, there are settlement difference in roadbed body and prestressed high-strength concrete pile 1.1 structures, although coming to nothing between roadbed body and prestressed high-strength concrete pile 1.1 structures do not affect the safe operation of train, can worsen the stress condition of pile cover.Therefore adopt the reservation filling system that is formed by vertical Grouting Pipe 5.1, horizontal Grouting Pipe 5.2 and vertical Grouting Pipe 5.3, carrying out the after-teeming slurry for the position of being come to nothing in 1.2 times roadbed bodies of pile cover part processes, its after-teeming is carried out after starching and should being chosen in settlement stability according to the settlement observation system data opportunity, thereby avoid pile cover 1.2 stress conditions to worsen, guaranteed the globality of roadbed.
The content that this manual is not described in detail belongs to the known prior art of this area professional and technical personnel.

Claims (13)

1. process the reinforcement means that the front railway soft soil roadbed settlement of operation exceeds standard for one kind, it is characterized in that, it comprises the steps:
Step 1: track structure and the contact net lines of removing the soft soil roadbed zone of railway that needs reinforcement, then excavate roadbed (6.1) top bedding, form foundation ditch (6.3), at foundation ditch (6.3) the inner a plurality of prestressed high-strength concrete piles (1.1) of vertical insertion roadbed (6.1) are set;
Step 2: the pre-buried vertical Grouting Pipe (5.1) that is interconnected successively in described foundation ditch (6.3), laterally Grouting Pipe (5.2) and vertically Grouting Pipe (5.3), foundation ditch (6.3) the pre-buried pile cover in bottom and roadbed body relative displacement monitor (4.1) and the roadbed body settlement monitoring device (4.4) of roadbed behind excavation (6.1), then lift the good a plurality of pile cover reinforcing cages of in advance colligation to corresponding prestressed high-strength concrete pile (1.1), connecting reinforcement (2.3) is installed between adjacent pile cover reinforcing cage, perfusion pile cover concrete in the pile cover reinforcing cage, form pile cover (1.2) reach the intensity of designing requirement until the pile cover concrete after, filling concrete (2.4) between described adjacent pile cover (1.2), described pile cover and roadbed body relative displacement monitor (4.1) are positioned between pile cover (1.2) and the roadbed (6.1);
Step 3: composite geo-membrane (3.1) is laid in the top at pile cover (1.2), lay medium-sand seam (3.3) in composite geo-membrane (3.1) top, lay first floor graded broken stone layer (2.2) at medium-sand seam (3.3), at the upper laying high-strength geo-grid bed course (2.1) of first floor graded broken stone layer (2.2), lay second layer graded broken stone layer (2.5) at high-strength geo-grid bed course (2.1), roadbed body settlement monitoring device (4.4) pre-buried in the step 2 runs through pile cover (1.2), composite geo-membrane (3.1), medium-sand seam (3.3), first floor graded broken stone layer (2.2), high-strength geo-grid bed course (2.1) and second layer graded broken stone layer (2.5), the bottom of described roadbed body settlement monitoring device (4.4) insert in the roadbed (6.1);
Step 4: the two ends at described foundation ditch (6.3) arrange the tapping pipe (3.2) that leads to side slope (6.2), one end of described tapping pipe (3.2) inserts medium-sand seam (3.3), the other end of tapping pipe (3.2) leads to side slope (6.2), namely forms the ruggedized construction of the front railway soft soil roadbed settlement of operation.
2. the reinforcement means that the railway soft soil roadbed settlement exceeds standard before the processing operation according to claim 1, it is characterized in that: the roadbed of described a plurality of prestressed high-strength concrete piles (1.1) behind excavation is evenly arranged, laterally the spacing between adjacent prestressed high-strength concrete pile (1.1) equates, vertically the spacing between adjacent prestressed high-strength concrete pile (1.1) also equates.
3. the reinforcement means that the railway soft soil roadbed settlement exceeds standard before the processing operation according to claim 2 is characterized in that: the spacing between described laterally adjacent prestressed high-strength concrete pile (1.1) is 2 ~ 3m; Spacing between described vertically adjacent prestressed high-strength concrete pile (1.1) is 2 ~ 3m.
4. the reinforcement means that exceeds standard of railway soft soil roadbed settlement according to claim 1 and 2 or before the 3 described processing operations, it is characterized in that: in step 2, roadbed behind excavation (6.1) is pre-buried pile cover settlement monitoring device (4.2) also, pile cover (1.2) is inserted in the bottom of described pile cover settlement monitoring device (4.2), and composite geo-membrane (3.1), medium-sand seam (3.3), first floor graded broken stone layer (2.2), high-strength geo-grid bed course (2.1) and second layer graded broken stone layer (2.5) are run through in the top of pile cover settlement monitoring device (4.2).
5. the reinforcement means that exceeds standard of railway soft soil roadbed settlement according to claim 1 and 2 or before the 3 described processing operations, it is characterized in that: in step 1, excavation roadbed (6.1) 1 ~ 2m to the curb, form foundation ditch (6.3), in step 2, at both sides side slope (6.2) curb position pre-buried curb settlement monitoring device (4.3).
6. the reinforcement means that exceeds standard of railway soft soil roadbed settlement according to claim 1 and 2 or before the 3 described processing operations, it is characterized in that: described pile cover and roadbed body relative displacement monitor (4.1) comprise single-point sedimentation joint measurement displacement meter (4.1.1), anchor head (4.1.3), flange (4.1.4) and the first mounting pipe (4.1.5); In the step 2, pre-buried pile cover and the front foundation ditch in roadbed (6.1) of roadbed body relative displacement monitor (4.1) (6.3) bottom excavation monitoring device mounting groove (4.1.2), bottom at monitor mounting groove (4.1.2) is laid and tamping bottom land medium coarse sand bed course (4.1.7), the first mounting pipe (4.1.5) is set in monitor mounting groove (4.1.2), single-point sedimentation joint measurement displacement meter (4.1.1) is set in the first mounting pipe (4.1.5), insert in the pile cover (1.2) by anchor head (4.1.3) on the top of single-point sedimentation joint measurement displacement meter (4.1.1), the bottom of single-point sedimentation joint measurement displacement meter (4.1.1) is provided with flange (4.1.4), medium coarse sand bed course (4.1.7) at the bottom of described flange (4.1.4) link slot, Cast-in-situ Piles in Sand-filling (4.1.6) in the filling slot between described the first mounting pipe (4.1.5) and the monitor mounting groove (4.1.2).
7. the reinforcement means that exceeds standard of railway soft soil roadbed settlement according to claim 1 and 2 or before the 3 described processing operations, it is characterized in that: described roadbed body settlement monitoring device (4.4) comprises settlement plate base (4.4.1), sedimentation measuring staff (4.4.2), the second mounting pipe (4.4.3) and pipe cap (4.4.4), wherein, the top of described the second mounting pipe (4.4.3) connects pipe cap (4.4.4), the bottom of the second mounting pipe (4.4.3) is arranged on the settlement plate base (4.4.1), sedimentation measuring staff (4.4.2) is set in described the second mounting pipe (4.4.3), the top of described sedimentation measuring staff (4.4.2) is stretched out the second mounting pipe (4.4.3) and is lower than pipe cap (4.4.4), the bottom of sedimentation measuring staff (4.4.2) connects settlement plate base (4.4.1), and described settlement plate base (4.4.1) is connected with roadbed (6.1).
8. the reinforcement means that the railway soft soil roadbed settlement exceeds standard before the processing operation according to claim 5, it is characterized in that: described curb settlement monitoring device (4.3) comprises grout injection (4.3.2) in screw thread drill rod (4.3.1) and the hole, the place offers vertical channel at curb, screw thread drill rod (4.3.1) is set in the described vertical channel, between described vertical channel and the screw thread drill rod (4.3.1) grout injection (4.3.2) is set.
9. the ruggedized construction that the railway soft soil roadbed settlement exceeds standard before the operation, comprise roadbed (6.1), be opened in the foundation ditch (6.3) at roadbed (6.1) top, it is characterized in that: described foundation ditch (6.3) is provided with the inner a plurality of prestressed high-strength concrete piles (1.1) of vertical insertion roadbed (6.1), the top of described each prestressed high-strength concrete pile (1.1) arranges pile cover (1.2), connecting reinforcement (2.3) and concrete (2.4) are set between the described adjacent pile cover (1.2), composite geo-membrane (3.1) is laid at the top of described pile cover (1.2), lay medium-sand seam (3.3) in composite geo-membrane (3.1) top, the upper first floor graded broken stone layer (2.2) of laying of described medium-sand seam (3.3), the upper laying high-strength geo-grid bed course (2.1) of described first floor graded broken stone layer (2.2), the upper second layer graded broken stone layer (2.5) of laying of described high-strength geo-grid bed course (2.1);
Pile cover and roadbed body relative displacement monitor (4.1) are set between described pile cover (1.2) and the roadbed (6.1), also be provided with the roadbed body settlement monitoring device (4.4) that runs through pile cover (1.2), composite geo-membrane (3.1), medium-sand seam (3.3), first floor graded broken stone layer (2.2), high-strength geo-grid bed course (2.1) and second layer graded broken stone layer (2.5) on the described roadbed (6.1), insert in the roadbed (6.1) bottom of described roadbed body settlement monitoring device (4.4).
10. the ruggedized construction that the railway soft soil roadbed settlement exceeds standard before the operation according to claim 9 is characterized in that: the vertical Grouting Pipe (5.1) that the interior setting of described foundation ditch (6.3) is interconnected successively, horizontal Grouting Pipe (5.2) and vertical Grouting Pipe (5.3).
11. the ruggedized construction that the railway soft soil roadbed settlement exceeds standard before the operation according to claim 9, it is characterized in that: the two ends of described foundation ditch (6.3) arrange the tapping pipe (3.2) that leads to side slope (6.2), one end of described tapping pipe (3.2) inserts medium-sand seam (3.3), and the other end of tapping pipe (3.2) leads to side slope (6.2).
12. the ruggedized construction that the railway soft soil roadbed settlement exceeds standard before the operation according to claim 9, it is characterized in that: described a plurality of prestressed high-strength concrete piles (1.1) are evenly arranged at roadbed (6.1), laterally the spacing between adjacent prestressed high-strength concrete pile (1.1) equates, vertically the spacing between adjacent prestressed high-strength concrete pile (1.1) also equates, the spacing between described laterally adjacent prestressed high-strength concrete pile (1.1) is 2 ~ 3m; Spacing between described vertically adjacent prestressed high-strength concrete pile (1.1) is 2 ~ 3m.
13. the ruggedized construction that the railway soft soil roadbed settlement exceeds standard before the operation according to claim 9, it is characterized in that: curb place, described side slope (6.2) both sides is provided with curb settlement monitoring device (4.3);
Described pile cover and roadbed body relative displacement monitor (4.1) comprise single-point sedimentation joint measurement displacement meter (4.1.1), anchor head (4.1.3), flange (4.1.4) and the first mounting pipe (4.1.5); Offer monitor mounting groove (4.1.2) on the described roadbed (6.1), medium coarse sand bed course (4.1.7) at the bottom of the bottom laying groove of monitor mounting groove (4.1.2), the first mounting pipe (4.1.5) is set in monitor mounting groove (4.1.2), single-point sedimentation joint measurement displacement meter (4.1.1) is set in the first mounting pipe (4.1.5), insert in the pile cover (1.2) by anchor head (4.1.3) on the top of single-point sedimentation joint measurement displacement meter (4.1.1), the bottom of single-point sedimentation joint measurement displacement meter (4.1.1) is provided with flange (4.1.4), medium coarse sand bed course (4.1.7) at the bottom of described flange (4.1.4) link slot, Cast-in-situ Piles in Sand-filling (4.1.6) in the filling slot between described the first mounting pipe (4.1.5) and the monitor mounting groove (4.1.2);
Described roadbed body settlement monitoring device (4.4) comprises settlement plate base (4.4.1), sedimentation measuring staff (4.4.2), the second mounting pipe (4.4.3) and pipe cap (4.4.4), wherein, the top of described the second mounting pipe (4.4.3) connects pipe cap (4.4.4), the bottom of the second mounting pipe (4.4.3) is arranged on the settlement plate base (4.4.1), sedimentation measuring staff (4.4.2) is set in described the second mounting pipe (4.4.3), the top of described sedimentation measuring staff (4.4.2) is stretched out the second mounting pipe (4.4.3) and is lower than pipe cap (4.4.4), the bottom of sedimentation measuring staff (4.4.2) connects settlement plate base (4.4.1), and described settlement plate base (4.4.1) is connected with roadbed (6.1);
Described curb settlement monitoring device (4.3) comprises grout injection (4.3.2) in screw thread drill rod (4.3.1) and the hole, described curb place offers vertical channel, screw thread drill rod (4.3.1) is set in the described vertical channel, between described vertical channel and the screw thread drill rod (4.3.1) grout injection (4.3.2) is set.
CN201210495038.1A 2012-11-28 2012-11-28 Reinforcement method and reinforcement structure for treating railway soft soil roadbed settlement overweight before operation Active CN102926304B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210495038.1A CN102926304B (en) 2012-11-28 2012-11-28 Reinforcement method and reinforcement structure for treating railway soft soil roadbed settlement overweight before operation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210495038.1A CN102926304B (en) 2012-11-28 2012-11-28 Reinforcement method and reinforcement structure for treating railway soft soil roadbed settlement overweight before operation

Publications (2)

Publication Number Publication Date
CN102926304A true CN102926304A (en) 2013-02-13
CN102926304B CN102926304B (en) 2015-02-04

Family

ID=47641221

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210495038.1A Active CN102926304B (en) 2012-11-28 2012-11-28 Reinforcement method and reinforcement structure for treating railway soft soil roadbed settlement overweight before operation

Country Status (1)

Country Link
CN (1) CN102926304B (en)

Cited By (21)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103276639A (en) * 2013-06-07 2013-09-04 中铁第四勘察设计院集团有限公司 Roadbed structure for deep soft soil region
CN103290827A (en) * 2013-06-17 2013-09-11 中国水利水电第十四工程局有限公司 Mounting, burying and grouting method for multi-point displacement meter
CN103321118A (en) * 2013-07-09 2013-09-25 中铁第四勘察设计院集团有限公司 Bridge road transition section roadbed structure of deep layer yielding ground regions
CN103334357A (en) * 2013-06-07 2013-10-02 上海嘉实(集团)有限公司 Viaduct road embankment structure with lower pile foundation bearing platform extending in roadbed, and construction method
CN103790151A (en) * 2014-01-23 2014-05-14 江苏中瑞路桥建设有限公司 Soft soil roadbed drainage prepressing rear blocking structure and construction method
CN104988815A (en) * 2015-07-03 2015-10-21 河海大学 Method for treating post-construction settlement disease of railroad bed
CN106049196A (en) * 2016-06-08 2016-10-26 杭州江润科技有限公司 Construction method of ballastless track subgrade with combined flexible piles and pile rafts at same fracture surfaces
CN106835878A (en) * 2017-01-24 2017-06-13 华中科技大学 A kind of embankment structure and construction method
WO2017125018A1 (en) * 2016-01-21 2017-07-27 中铁第四勘察设计院集团有限公司 Device for monitoring void value of settlement of rail support beam and roadbed of medium-low-speed magnetic suspension low line
CN107419630A (en) * 2017-06-13 2017-12-01 华中科技大学 A kind of the soft soil foundation high-filled embankment and construction method of effectively control settlement after construction
CN107964843A (en) * 2017-12-06 2018-04-27 中铁二院工程集团有限责任公司 A kind of high-speed railway Karst Subgrade construction and its restorative procedure for having warning function
CN108411714A (en) * 2018-05-09 2018-08-17 中铁工程设计咨询集团有限公司 The high peg board of roadbed and its construction method
CN108824097A (en) * 2018-07-25 2018-11-16 中铁七局集团第工程有限公司 Prefabricated GFRP pipe concrete stake and armoured concrete slab overhead type roadbed pile slab structure
CN108999046A (en) * 2018-09-14 2018-12-14 中铁十四局集团有限公司 A kind of backfilled roadbed supported cavity beneath slab monitoring and board bottom separation in reducing subsidence by grouting system and method
CN109281239A (en) * 2018-10-25 2019-01-29 浙江省交通规划设计研究院有限公司 Ribbed abutments in road operation state bore slope cutting method
CN110080232A (en) * 2019-04-04 2019-08-02 程桂香 A kind of deep basal pit earth-filling method of underground high water level
CN110644311A (en) * 2019-10-30 2020-01-03 贵州大学 Anti-settlement roadbed structure and construction method
CN110924251A (en) * 2019-12-03 2020-03-27 武汉市武昌市政建设(集团)有限公司 Road structure with pipe gallery arranged at bottom
CN111021172A (en) * 2019-12-18 2020-04-17 诚通凯胜生态建设有限公司 Road construction process
CN111289351A (en) * 2020-03-23 2020-06-16 中铁二院工程集团有限责任公司 Composite light pile group pile bearing capacity detection device, system and method
CN113186768A (en) * 2021-04-21 2021-07-30 中铁六局集团太原铁路建设有限公司 Construction method for improving roadbed backfill quality after existing line demolition of frame structure

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10317307A (en) * 1997-05-19 1998-12-02 Dia Consultant:Kk Construction method for road
DE10333613A1 (en) * 2003-07-24 2005-02-24 Keller Grundbau Gmbh Process to enhance railway line soil load bearing characteristics by insertion of concrete columns
CN101476325A (en) * 2008-11-28 2009-07-08 华南理工大学 Rigid gridding and pile combined foundation and its use in soft soil foundation reinforcement
NL2003159C2 (en) * 2009-07-09 2011-01-12 Dijk Maasland B V Van METHOD FOR RENOVATING A ROAD CONSTRUCTION
CN101967824A (en) * 2010-09-27 2011-02-09 浙江大学 Large-diameter thin-wall cylindrical pile mesh combined structure with pile cap and construction method thereof
CN201952698U (en) * 2011-03-07 2011-08-31 冯守中 Roadbed structure reinforced by geotextile discrete material piles
CN102650128A (en) * 2012-04-26 2012-08-29 浙江大学城市学院 Cement mixing pile with stiffness core capable of draining and pre-pressing firstly and then grouting as well as construction method thereof
CN102704488A (en) * 2012-04-24 2012-10-03 王军 Novel soft soil foundation pit excavation method

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10317307A (en) * 1997-05-19 1998-12-02 Dia Consultant:Kk Construction method for road
DE10333613A1 (en) * 2003-07-24 2005-02-24 Keller Grundbau Gmbh Process to enhance railway line soil load bearing characteristics by insertion of concrete columns
CN101476325A (en) * 2008-11-28 2009-07-08 华南理工大学 Rigid gridding and pile combined foundation and its use in soft soil foundation reinforcement
NL2003159C2 (en) * 2009-07-09 2011-01-12 Dijk Maasland B V Van METHOD FOR RENOVATING A ROAD CONSTRUCTION
CN101967824A (en) * 2010-09-27 2011-02-09 浙江大学 Large-diameter thin-wall cylindrical pile mesh combined structure with pile cap and construction method thereof
CN201952698U (en) * 2011-03-07 2011-08-31 冯守中 Roadbed structure reinforced by geotextile discrete material piles
CN102704488A (en) * 2012-04-24 2012-10-03 王军 Novel soft soil foundation pit excavation method
CN102650128A (en) * 2012-04-26 2012-08-29 浙江大学城市学院 Cement mixing pile with stiffness core capable of draining and pre-pressing firstly and then grouting as well as construction method thereof

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
秦文权: "客运专线复合地基上无碴轨道路基沉降的控制与计算分析", 《中国优秀硕士学位论文全文数据库工程科学Ⅱ辑》, no. 12, 15 December 2008 (2008-12-15) *

Cited By (32)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103334357B (en) * 2013-06-07 2015-07-15 上海嘉实(集团)有限公司 Viaduct road embankment structure with lower pile foundation bearing platform extending in roadbed, and construction method
CN103334357A (en) * 2013-06-07 2013-10-02 上海嘉实(集团)有限公司 Viaduct road embankment structure with lower pile foundation bearing platform extending in roadbed, and construction method
CN103276639A (en) * 2013-06-07 2013-09-04 中铁第四勘察设计院集团有限公司 Roadbed structure for deep soft soil region
CN103276639B (en) * 2013-06-07 2015-06-10 中铁第四勘察设计院集团有限公司 Roadbed structure for deep soft soil region
CN103290827A (en) * 2013-06-17 2013-09-11 中国水利水电第十四工程局有限公司 Mounting, burying and grouting method for multi-point displacement meter
CN103290827B (en) * 2013-06-17 2015-01-07 中国水利水电第十四工程局有限公司 Mounting, burying and grouting method for multi-point displacement meter
CN103321118A (en) * 2013-07-09 2013-09-25 中铁第四勘察设计院集团有限公司 Bridge road transition section roadbed structure of deep layer yielding ground regions
CN103321118B (en) * 2013-07-09 2015-07-08 中铁第四勘察设计院集团有限公司 Bridge road transition section roadbed structure of deep layer yielding ground regions
CN103790151A (en) * 2014-01-23 2014-05-14 江苏中瑞路桥建设有限公司 Soft soil roadbed drainage prepressing rear blocking structure and construction method
CN103790151B (en) * 2014-01-23 2016-08-31 神州建设集团有限公司 Plugging structure and construction method after a kind of soft soil roadbed draining precompressed
CN104988815A (en) * 2015-07-03 2015-10-21 河海大学 Method for treating post-construction settlement disease of railroad bed
WO2017125018A1 (en) * 2016-01-21 2017-07-27 中铁第四勘察设计院集团有限公司 Device for monitoring void value of settlement of rail support beam and roadbed of medium-low-speed magnetic suspension low line
CN106049196A (en) * 2016-06-08 2016-10-26 杭州江润科技有限公司 Construction method of ballastless track subgrade with combined flexible piles and pile rafts at same fracture surfaces
CN106049196B (en) * 2016-06-08 2018-04-06 杭州江润科技有限公司 Flexible pile combines ballastless track roadbed construction method with stake raft with section
CN106835878A (en) * 2017-01-24 2017-06-13 华中科技大学 A kind of embankment structure and construction method
CN107419630A (en) * 2017-06-13 2017-12-01 华中科技大学 A kind of the soft soil foundation high-filled embankment and construction method of effectively control settlement after construction
CN107419630B (en) * 2017-06-13 2023-06-20 华中科技大学 Soft soil foundation high-filling embankment capable of effectively controlling post-construction settlement and construction method
CN107964843A (en) * 2017-12-06 2018-04-27 中铁二院工程集团有限责任公司 A kind of high-speed railway Karst Subgrade construction and its restorative procedure for having warning function
CN108411714A (en) * 2018-05-09 2018-08-17 中铁工程设计咨询集团有限公司 The high peg board of roadbed and its construction method
CN108824097A (en) * 2018-07-25 2018-11-16 中铁七局集团第工程有限公司 Prefabricated GFRP pipe concrete stake and armoured concrete slab overhead type roadbed pile slab structure
CN108999046A (en) * 2018-09-14 2018-12-14 中铁十四局集团有限公司 A kind of backfilled roadbed supported cavity beneath slab monitoring and board bottom separation in reducing subsidence by grouting system and method
CN108999046B (en) * 2018-09-14 2019-10-01 中铁十四局集团建筑工程有限公司 A kind of backfilled roadbed supported cavity beneath slab monitoring and board bottom separation in reducing subsidence by grouting system and method
CN109281239B (en) * 2018-10-25 2021-03-26 浙江省交通规划设计研究院有限公司 Rib type abutment taper slope cutting method in road operation state
CN109281239A (en) * 2018-10-25 2019-01-29 浙江省交通规划设计研究院有限公司 Ribbed abutments in road operation state bore slope cutting method
CN110080232A (en) * 2019-04-04 2019-08-02 程桂香 A kind of deep basal pit earth-filling method of underground high water level
CN110644311A (en) * 2019-10-30 2020-01-03 贵州大学 Anti-settlement roadbed structure and construction method
CN110924251A (en) * 2019-12-03 2020-03-27 武汉市武昌市政建设(集团)有限公司 Road structure with pipe gallery arranged at bottom
CN111021172A (en) * 2019-12-18 2020-04-17 诚通凯胜生态建设有限公司 Road construction process
CN111021172B (en) * 2019-12-18 2021-08-10 诚通凯胜生态建设有限公司 Road construction process
CN111289351A (en) * 2020-03-23 2020-06-16 中铁二院工程集团有限责任公司 Composite light pile group pile bearing capacity detection device, system and method
CN111289351B (en) * 2020-03-23 2022-12-30 中铁二院工程集团有限责任公司 Composite light pile group pile bearing capacity detection device, system and method
CN113186768A (en) * 2021-04-21 2021-07-30 中铁六局集团太原铁路建设有限公司 Construction method for improving roadbed backfill quality after existing line demolition of frame structure

Also Published As

Publication number Publication date
CN102926304B (en) 2015-02-04

Similar Documents

Publication Publication Date Title
CN102926304B (en) Reinforcement method and reinforcement structure for treating railway soft soil roadbed settlement overweight before operation
CN105350584B (en) A kind of construction method of anti-float anchor rod
CN102071607B (en) Railroad bed repair method without affecting existing running conditions
CN107503257B (en) One kind being close to mountain high-filled subgrade stabilization and Deformation control structure and construction method
CN103276639B (en) Roadbed structure for deep soft soil region
CN107190602B (en) River erosion section pile-supported foam concrete light embankment structure and construction method
CN104674802B (en) Prestressing force rubble anchorage pile and landslide control construction method thereof
CN105274922B (en) A kind of antiskid key steel-pipe pile composite construction and method for repairing landslide roadbed
CN106089244A (en) Frame props up arched tunnel lining structure
CN207109475U (en) It is close to mountain high-filled subgrade stabilization and Deformation control structure
CN205387720U (en) Tertiary light -duty retaining structure of double circular pile pile foundation of superelevation embankment
CN108867200A (en) A kind of Resistant heave high-speed railway rock chasm structuref and design method
CN106676993B (en) Reinforced broken stone frame structure roadbed reinforcing system and reinforcing method thereof
CN106702840A (en) Anchored pile reinforced earth retaining wall embankment for treating shoreside soft soil roadbed
CN106640096A (en) Construction method for penetrating through tunnel of backfilling soil section and transition section
CN207878473U (en) Layer depth foundation pit hangs foot stake supporting construction to Tu Yan in combination
CN111395060A (en) Karst area existing cutting widened roadbed structure and design and construction method
CN205116204U (en) Roadbed structure of crowded native bored concrete pile stake board of two -way spiral
CN111441372A (en) Landslide foundation treatment embankment structure and construction method
CN108914954A (en) Slope support method of the pre support in conjunction with permanent support
CN206625096U (en) A kind of reinforced rubble frame structure subgrade strengthening system
CN205954638U (en) Half semi -rigid flexible supporting construction of deep basal pit lateral wall
CN110805049B (en) Construction method of mountain slope ultra-thickness spray anchor permanent supporting structure
CN105821902B (en) The light-duty armored concrete Ecological Retaining Wall construction method of vertical lattice
CN203034326U (en) Reinforced structure for treating excessive railway soft soil subgrade settlement before operation

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant