CN108252215A - Connection structure of the board-like Suo-tower of trepanning and preparation method thereof - Google Patents

Connection structure of the board-like Suo-tower of trepanning and preparation method thereof Download PDF

Info

Publication number
CN108252215A
CN108252215A CN201810206828.0A CN201810206828A CN108252215A CN 108252215 A CN108252215 A CN 108252215A CN 201810206828 A CN201810206828 A CN 201810206828A CN 108252215 A CN108252215 A CN 108252215A
Authority
CN
China
Prior art keywords
steel
suo
concrete
trepanning
board
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810206828.0A
Other languages
Chinese (zh)
Inventor
裴炳志
刘明虎
张门哲
徐国平
刘玉擎
陈虎成
唐守峰
刘磊
董钊
吴威
吕香华
贾伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hubei Shishou Yangtze River Highway Bridge Co Ltd
CCCC Highway Consultants Co Ltd
Original Assignee
Hubei Shishou Yangtze River Highway Bridge Co Ltd
CCCC Highway Consultants Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hubei Shishou Yangtze River Highway Bridge Co Ltd, CCCC Highway Consultants Co Ltd filed Critical Hubei Shishou Yangtze River Highway Bridge Co Ltd
Priority to CN201810206828.0A priority Critical patent/CN108252215A/en
Publication of CN108252215A publication Critical patent/CN108252215A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/14Towers; Anchors ; Connection of cables to bridge parts; Saddle supports

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

Present disclose provides board-like Sarasota connection structure of a kind of trepanning and preparation method thereof, the board-like Sarasota connection structure of trepanning includes:Steel panel (3), it is fixedly connected on the Concrete-filled steel tube (1) of the Cable-stayed Bridge Pylon, it is flushed with Concrete-filled steel tube (1), perforated plate connector (5), it is welded on the tower wall side of steel panel (3), the perforated plate connector (5) includes the steel plate with trepanning, and steel and concrete are combined into one by the dowel action of reinforcing bar in concrete in hole and hole.The board-like Sarasota connection structure reasonable stress of trepanning, easy for construction that the disclosure provides can be suitable for the cable-stayed bridge of different across footpaths, different rope face forms, especially suitable for long span stayed-cable bridge.

Description

Connection structure of the board-like Suo-tower of trepanning and preparation method thereof
Technical field
This disclosure relates to bridge structure technical field more particularly to a kind of board-like Suo of trepanning-tower connection structure and its making Method.
Background technology
The bridge tower anchoring structure of cable-stayed bridge is as Design of Cable-Stayed Bridge method and theoretical, steel construction are promoted and are applied and numerous Practical bridge practice and continuous optimized development.At present, common bridge tower anchoring structure be broadly divided into prestressed anchor fixing structure, Steel anchor beam anchor structure and steel anchor box anchor structure three types.
Steel anchor beam type combines Sarasota anchorage style, and referring to suspension cable being anchored at along bridge on the steel anchor beam of arrangement, makes Steel anchor beam is primarily subjected to the horizontal component of Suo Li, and Concrete-filled steel tube is primarily subjected to a kind of suspension cable anchoring of the vertical force component of Suo Li Mode.In the steel anchor beam designing scheme of early stage, steel anchor beam multi-support is being constructed on the concrete steel bracket of Sarasota inner wall There is the shortcomings that being unfavorable for slding form operation and serious stress concentration with discovery concrete steel bracket during use.It is in recent years to adopt more The structure type of concrete steel bracket is replaced with steel corbel:Anchor beam along bridge to being placed on the steel corbel of concrete cable inner wall of tower, Anchor-hold is on anchoring piece, and horizontal force is mainly undertaken by steel anchor beam, and vertical force component is by steel corbel via steel panel and steel reinforced concrete Engaging portion is transmitted to king-post and undertakes.As a result, steel corbel with which kind of combine cage structure could by Suo Li safely, be delivered evenly to Sarasota Just become critical problem.
Since weldering nail connector shearing resistance does not have directionality and easy for construction, in traditional steel anchor beam-steel corbel synthetic rope Mostly using the scheme that nail group's connector is welded in steel panel external welding in the design of tower anchorage zone steel reinforced concrete engaging portion.And in actual loading In, siding out-of-plane deformation caused by Concrete-filled steel tube subjects top-down cumulative vertical pressure and Suo Li wobbler actions makes It obtains the weldering in bridge tower anchoring structure and follows closely connector other than undertaking vertical shear, also in the state of longitudinal tensile.Weldering nail by Larger pulling capacity, and this pulling capacity and shearing distribution are extremely uneven, so as to make Concrete-filled steel tube locally in tension shape State easily generates crack and then influences the durability and bearing capacity of combination bridge tower anchoring structure.
Therefore, in the steel reinforced concrete engaging portion of steel anchor beam-steel corbel combination Sarasota anchoring, it is desirable that connector has more superior Anti-pull-out property to transmit caused by the eccentric power transmission of steel corbel along bridge to moment of flexure and more superior vertical shear resistance It can be to transmit the vertical force component of Suo Li.It is necessary to propose that one kind can either ensure even to improve vertical shear-carrying capacity, and can be into One step promotes steel-mixed engaging portion anti-pulling ability, not only economical durable, but also novel Suo-tower combination portion connecting structure convenient for construction.
Invention content
(1) technical problems to be solved
Present disclose provides the board-like Suo of a kind of trepanning-tower connection structure and preparation method thereof, more than at least partly solving The technical issues of proposed.
(2) technical solution
According to one aspect of the disclosure, a kind of board-like Suo of trepanning-tower connection structure is provided, including:Steel panel, it is fixed It is connected on the Concrete-filled steel tube of Cable-stayed Bridge Pylon, is flushed with Concrete-filled steel tube;Perforated plate connector is welded on the tower of steel panel Wall side, the perforated plate connector include the steel plate with trepanning, will by the dowel action of reinforcing bar in concrete in hole and hole Steel is combined into one with concrete.
In the disclosure some embodiments, the board-like Suo of trepanning-tower connection structure side is welded with steel corbel 7, opposite side with Cast-in-place Concrete-filled steel tube is strong bonded, and the board-like Suo of the trepanning-tower connection structure is directly embedded into tower wall concrete, with mixing Solidifying soil tower wall works together, and bears the Suo Li by steel anchor beam and steel corbel transmission.
In the disclosure some embodiments, the perforated plate connector is big in the tower wall insert depth of steel corbel corresponding position Tension plate is welded in other positions, and in its end.
In the disclosure some embodiments, the perforated plate connector wears regular reinforcement in hole, puts more energy into steel panel.
In the disclosure some embodiments, the perforated plate connector according to different-stiffness and requirement for bearing capacity type selecting, and Meet the detailing requiments of perforated plate connector, be welded in steel panel by preset space length, bear Suo Li vertical force component and due to Along bridge to moment of flexure caused by eccentricity.
In the disclosure some embodiments, the steel panel opens up the reserved through hole passed through for suspension cable, with being cast in out Orifice plate connector and the Concrete-filled steel tube on tension plate periphery work together, and bear the Suo Li transmitted by steel anchor beam and steel corbel.
In the disclosure some embodiments, the steel panel is fixed on corresponding mixed by perforated plate connector and tension plate In solidifying soil tower wall.
In the disclosure some embodiments, perforated plate connector, tension plate are combined with Concrete-filled steel tube, the concrete towers Wall is a complete frame structure, and the steel panel is fixed on the corresponding concrete by perforated plate connector and tension plate In tower wall.
In the disclosure some embodiments, the board-like Suo of the trepanning-tower connection structure, trepanning described in adjacent two layers is board-like Suo-tower connection structure is separated in segment, and the vertical force component of Suo Li is made to be born completely by Concrete-filled steel tube.
The disclosure additionally provides a kind of method for making the board-like Suo of trepanning-tower connection structure, including:
Step S1, processing steel anchor beam, steel corbel and the board-like Suo of trepanning-tower connection structure steel panel perforated plate connector and Tension plate;Wherein, first perforated plate connector is welded in steel panel, the rear tension plate that welds forms the disclosure;Again by steel corbel It is welded in steel panel, and completes application;
Step S2, it is first that four steel corbels are prefabricated closely connected after steel anchor beam completion of processing, and temporarily after connection again by steel ox Leg is welded with embedded board;
The board-like Suo of the trepanning of multiple segments-tower connection structure is transported to construction site and completes to lift, positions by step S3 And stacking, so as to form main body steel construction;Wherein, the steel panel of the board-like Suo of the trepanning of two neighboring segment-tower connection structure is mutual It is not connected to;
Step S4, using steel panel as needed for casting concrete segment template, using tension plate as construction when stent, Regular reinforcement assembling reinforcement is worn in perforated plate connector, is laid with prestress pipe, segmented casting concrete is timely when pouring It vibrates with the density for ensureing concrete in perforated plate connector hole, ultimately forms Concrete-filled steel tube;
Step S5, after Concrete-filled steel tube reaches target strength, in perforated plate connector and the faying face of Concrete-filled steel tube 1 Prestressed reinforcement of tensioning positions and draws suspension cable, completes inclined guy cable stretching work, is then set on steel corbel and steel panel The limiting device of steel anchor beam;After inclined guy cable stretching and secondary dead load are constructed, the high-strength bolt at steel anchor beam both ends is tightened.
(3) advantageous effect
It can be seen from the above technical proposal that the board-like Suo of disclosure trepanning-tower connection structure and preparation method thereof at least has There is one of following advantageous effect:
(1) since steel panel is closely connect by perforated plate connector and tension plate with Concrete-filled steel tube, perforated panel connection For part based on vertically being sheared, stress is clear and definite, is not in larger pulling capacity, avoids pulling capacity to perforated plate connector shearing resistance The weakening of rigidity and bearing capacity, so as to make perforated plate connector and tower wall stress all in favo(u)red state.Concrete-filled steel tube is opened The area that orifice plate is cut down is smaller, is a complete frame structure, ensure that the globality of Concrete-filled steel tube, therefore structure is with good Good overall stiffness and crack resistance, and then improve the durability of structure;
(2) because the weight of the board-like Suo of single segmental trepanning-tower connection structure is smaller, the board-like Suo of single-unit trepanning-tower connection knot Structure can be again transported after factory process to the whole segment lifting in construction site, so as to improve construction efficiency;On the other hand, more piece For the board-like Suo of Duan Kaikong-tower connection structure in segmental construction, the segment constructed can be each to save as the construction platform of next segment The board-like Suo of Duan Kaikong-tower connection structure mass action is strong, improves overall stability during construction;
(3) since steel panel can double as the formwork for placing of tower wall concrete, tension plate can as the stent of formwork erection, from And reduce the formwork erection work of tower wall concreting.
Description of the drawings
Fig. 1 is embodiment of the present disclosure combination bridge tower anchoring structure single segmental schematic diagram.
Fig. 2 is the exploded view of the board-like Suo of the trepanning of the embodiment of the present disclosure-tower connection structure.
Fig. 3 is the vertical view of the board-like Suo of the trepanning of the embodiment of the present disclosure-tower connection structure.
【Embodiment of the present disclosure critical piece symbol description in attached drawing】
1st, Concrete-filled steel tube;2nd, steel anchor beam
3rd, steel panel;4th, suspension cable
5th, perforated plate connector;6th, tension plate
7th, steel corbel;8th, steel panel hole
Specific embodiment
The disclosure be designed to provide a kind of power transmission clearly, high capacity, economic security, trepanning easy for construction it is board-like Suo-tower connection structure belongs to the key components of combination bridge tower anchoring structure, is applicable to the cable-stayed bridge of different across footpaths.
Purpose, technical scheme and advantage to make the disclosure are more clearly understood, below in conjunction with specific embodiment, and reference The disclosure is further described in attached drawing.
Disclosure some embodiments will be done with reference to appended attached drawing in rear and more comprehensively describe to property, some of but not complete The embodiment in portion will be shown.In fact, the various embodiments of the disclosure can be realized in many different forms, and should not be construed To be limited to this several illustrated embodiment;Relatively, these embodiments are provided so that the disclosure meets applicable legal requirement.
In first exemplary embodiment of the disclosure, a kind of board-like Suo of trepanning-tower connection structure is provided.The disclosure The board-like Suo of trepanning-tower connection structure, including steel panel 3, perforated plate connector 5 and tension plate 6.Disclosure Sarasota anchors engaging portion Connection structure side is welded with steel corbel 7, and side and cast-in-place Concrete-filled steel tube 1 are strong bonded, and the trepanning of the present embodiment is board-like Suo-tower connection structure is directly embedded into tower wall concrete, is worked together with tower wall, is born to be transmitted by steel anchor beam 2 and steel corbel 7 Suo Li.
In 7 support steel anchor beam of steel corbel, 2 type combines cable-pylon anchorage zone, steel corbel 7 is welded on the steel panel 3 of the disclosure On, play the role of huge Suo Li being transmitted to perforated plate connector 5 and Concrete-filled steel tube 1.
The steel panel 3 is fixedly connected on the Concrete-filled steel tube 1 of the Cable-stayed Bridge Pylon, is opened up for the suspension cable 4 The reserved through hole passed through, the Concrete-filled steel tube 1 with being cast in 6 periphery of perforated plate connector 5 and tension plate work together, bear by The Suo Li that steel anchor beam 2 and steel corbel 7 transmit.Steel panel 3 is flushed with Concrete-filled steel tube 1, is directly born steel corbel 7 and is transmitted the lotus of coming It carries, opens up the through-hole passed through for suspension cable 4 thereon.Above-mentioned steel panel 3 is fixed on pair by perforated plate connector 5 and tension plate 6 On the Concrete-filled steel tube 1 answered.
The perforated plate connector 5 is main steel-concrete faying face Force transmission parts, is a kind of trepanning on the steel plate, leads to The novel connector that steel and concrete are combined into one by the dowel action of reinforcing bar in concrete and hole in via.The perforated panel Connector 5 is more than other positions perforated panel, and weld tension plate in its end in the tower wall insert depth of 7 corresponding position of steel corbel 6, further enhance the anti-pulling ability of structure.
Perforated plate connector 5 is welded on the tower wall side of steel panel 3, and regular reinforcement is worn in hole, further improves it and holds Performance and deformation performance are carried, in addition to this, perforated plate connector 5 can also play distortion to steel panel 3.
Further, it is strong bonded by perforated plate connector 5, tension plate 6 and Concrete-filled steel tube 1, the concrete towers Wall 1 is a complete frame structure.
The depth of 7 corresponding position perforated plate connector 5 of steel corbel insertion tower wall is more than other perforated panels, and is welded in its end Tension plate 6 is connect, further enhances the anti-pulling ability of structure.
The above-mentioned board-like Suo of trepanning-tower connection structure is an opening section structure, is connected by the perforated panel being embedded in tower wall Fitting 5, tension plate 6 and Concrete-filled steel tube 1 are strong bonded.The area that the Concrete-filled steel tube 1 is cut down by the disclosure is smaller, is one Complete frame structure ensure that the globality of Concrete-filled steel tube 1.The guy anchor that the steel anchor beam 2 directly bears Suo Li for one Gu mechanism, the steel corbel 7 mainly transmits vertical force and eccentric bending moment to the Force transmission parts of the disclosure for one, can be according to reality The variation of the rope face form of bridge, drag-line angle etc. and change.
Further, perforated plate connector 5 can be selected according to different-stiffness and requirement for bearing capacity, and should meet perforated panel company The detailing requiments of fitting 5 are welded on along a determining deviation in steel panel 3, bear the vertical force component of Suo Li and since eccentricity causes Suitable bridge to moment of flexure.Tension plate 6 can be used as the reinforcement plate of anti-pulling, also can be as stent when constructing.
The board-like Suo of trepanning described in adjacent two layers-tower connection structure is disconnected in internode, makes the vertical force component of Suo Li completely by mixing Solidifying soil tower wall 1 is born, and the disclosure only plays intermal force.It certainly, also can be vertically integrally welded by the disclosure when needing.
The disclosure is further described below in conjunction with the embodiment shown in that figure.
Embodiment
The board-like Suo of trepanning-tower connection structure in the embodiment of the present disclosure be apply cable-stayed bridge combination anchor structural area steel- A kind of new Joining Structure of mixed engaging portion, is made of, and steel panel 3, perforated plate connector 5 and tension plate 6 with being cast in out Concrete-filled steel tube 1 around orifice plate connector 5 works together, and bears 4 Suo Li of suspension cable.
Fig. 1 is the 2 type anchor structure single segmental schematic diagram of steel anchor beam for employing the disclosure.It can be seen that the board-like Suo-tower of trepanning Connection structure side is welded with steel corbel 7, and side is strong bonded with Concrete-filled steel tube 1, common stress, is combination cable-pylon anchorage zone The key constructs of engaging portion.The area that Concrete-filled steel tube 1 is weakened by perforated plate connector 5 is smaller, is a complete frame knot Structure ensure that the globality of Concrete-filled steel tube 1.
Fig. 2 is the exploded view of the board-like Suo of trepanning-tower connection structure.The board-like Suo of trepanning-tower connection in the embodiment of the present disclosure Structure is made of steel panel 3, perforated plate connector 5 and tension plate 6, and the concrete with being cast in around perforated plate connector 5 Tower wall 1 bears Suo Li jointly.Perforated plate connector 5 and tension plate 6 are embedded in concreting in concrete, steel panel 3 It is flushed with Concrete-filled steel tube 1.The end of steel anchor beam 2 is equipped with the anchor-hold mechanism for installing suspension cable 4.When suspension cable 4 with When perforated plate connector 5 conflicts, perforated plate connector 5 need to be blocked in the range of suspension cable 4 passes through.
Fig. 3 is the vertical view of the board-like Suo of trepanning-tower connection structure.The present embodiment is applied in a double plane cable stayed bridge, is needed Support two steel anchor beams 2.However the board-like Suo of trepanning-tower connection structure also can be by adjusting detail structure to adapt to different rope faces The requirement of form and bearing capacity.
Distance in the board-like Suo of any one trepanning-tower connection structure between two steel panels 3 is slightly larger than the length of steel anchor beam 2 Degree.Steel anchor beam 2 is allowed to be relatively moved longitudinally in tensioning suspension cable 4, equilibrium water is undertaken so as to give full play to steel anchor beam 2 The ability of Ping Suoli.
The lateral surface of every piece of steel panel 3 has welded multiple perforated plate connectors 5.Steel panel 3 mainly passes through these trepannings Plate connector 5 is fixed on the Concrete-filled steel tube 1 of Cable-stayed Bridge Pylon.Perforated plate connector 5 is that one kind sets trepanning on the steel plate, The novel connector that steel and concrete are combined into one by concrete dowel action in hole.In addition to bearing to provide vertical shear Outside pulling capacity, above-mentioned perforated plate connector 5 or steel panel 3 provide distortion, prevent it excessive in local pressure There is unstability.According to the angle of inclination of suspension cable 4, the steel panel hole passed through for the suspension cable 4 of cable-stayed bridge is offered in steel panel 3 8.When suspension cable 4 conflicts with perforated plate connector 5, perforated plate connector 5 need to be blocked in the range of suspension cable 4 passes through, Ensure the continuity of suspension cable 4.
Based on Fig. 1 to the board-like Suo of trepanning shown in Fig. 3-tower connection structure, embodiment of the disclosure additionally provides making and opens The method of orifice-plate type Suo-tower connection structure, specifically includes following steps:
Step S1 processes the board-like Suo-Ta Lian of trepanning in steel anchor beam 2, steel corbel 7 and the embodiment of the present disclosure in factory respectively Each plate of binding structure.Wherein, first perforated plate connector 5 can be welded in steel panel 3, the rear tension plate 6 that welds forms this public affairs It opens.Steel corbel 7 is welded in steel panel 3 afterwards, and completes application;
Step S2, it is first that four steel corbels 7 are prefabricated closely connected after steel 2 completion of processing of anchor beam, and temporarily after connection again by steel Bracket 7 is welded with embedded board;
The board-like Suo of the trepanning of multiple segments-tower connection structure is transported to construction site and completes to lift, positions by step S3 And stacking, so as to form main body steel construction.Wherein, the steel panel 3 of the board-like Suo of the trepanning of two neighboring segment-tower connection structure is mutual It is not connected to;
Step S4, using steel panel 3 as needed for casting concrete segment template, using tension plate 6 as construction when branch Frame wears regular reinforcement assembling reinforcement in perforated plate connector 5, is laid with prestress pipe, segmented casting concrete, when pouring It should vibrate in time with the density for ensureing concrete in 5 hole of perforated plate connector, ultimately form Concrete-filled steel tube 1;
Step S5, after Concrete-filled steel tube 1 reaches target strength, in the combination of perforated plate connector 5 and Concrete-filled steel tube 1 Face prestressed reinforcement of tensioning positions and draws suspension cable 4,4 tensioning of suspension cable work is completed, then in steel corbel 7 and steel panel 3 The limiting device of upper setting steel anchor beam 2.After 4 tensioning of suspension cable and secondary dead load are constructed, the institute at 2 both ends of steel anchor beam is tightened There is high-strength bolt.
In above-mentioned steps S4, coagulation is poured at once after the board-like Suo of trepanning-tower connection structure of several segments is usually laminated Native tower wall 1 repeats previous process after concrete reaches expected intensity.
In above-mentioned steps S5, can setting be selected according to design calculation result or be not provided with deformed bar.
In above-mentioned steps S5, the limiting device of steel anchor beam 2 is set on steel corbel 7 and steel panel 3 can ensure imbalance Horizontal Suo Li is smoothly transmitted to the disclosure and Concrete-filled steel tube 1.
In above-mentioned steps S5, the board-like Suo of trepanning-tower connection structure when 4 tensioning of suspension cable and secondary dead load are constructed, due to One end slip is fixed in 2 one end of steel anchor beam, therefore mainly transmits vertical force.It is opposite between anchor beam and steel corbel 7 after Second Construction Slide it is restrained, in addition to vertical force, the disclosure also with the unbalanced horizontal Suo Li of tower wall shared
The board-like Suo of trepanning-tower connection structure reasonable stress, easy for construction that the disclosure provides, can be suitable for it is different across The cable-stayed bridge of diameter, different rope face forms, especially suitable for long span stayed-cable bridge.
So far, the board-like Suo of embodiment of the present disclosure trepanning-tower connection structure introduction finishes.
So far, attached drawing is had been combined the embodiment of the present disclosure is described in detail.It should be noted that it in attached drawing or says In bright book text, the realization method that is not painted or describes is form known to a person of ordinary skill in the art in technical field, and It is not described in detail.In addition, the above-mentioned definition to each element and method be not limited in mentioning in embodiment it is various specific Structure, shape or mode, those of ordinary skill in the art simply can be changed or replaced to it.
It should also be noted that, the direction term mentioned in embodiment, for example, " on ", " under ", "front", "rear", " left side ", " right side " etc. is only the direction of refer to the attached drawing, is not used for limiting the protection domain of the disclosure.Through attached drawing, identical element by Same or similar reference numeral represents.When understanding of this disclosure may be caused to cause to obscure, conventional structure will be omitted Or construction.
And the shape and size of each component do not reflect actual size and ratio in figure, and only illustrate the embodiment of the present disclosure Content.In addition, in the claims, any reference mark between bracket should not be configured to the limit to claim System.
Furthermore word "comprising" does not exclude the presence of element or step not listed in the claims.Before element Word "a" or "an" does not exclude the presence of multiple such elements.
In addition, unless specifically described or the step of must sequentially occur, there is no restriction in more than institute for the sequence of above-mentioned steps Row, and can change or rearrange according to required design.And above-described embodiment can be based on the considerations of design and reliability, that This mix and match is used using or with other embodiment mix and match, i.e., the technical characteristic in different embodiments can be freely combined Form more embodiments.
Those skilled in the art, which are appreciated that, to carry out adaptively the module in the equipment in embodiment Change and they are arranged in one or more equipment different from the embodiment.It can be the module or list in embodiment Member or component be combined into a module or unit or component and can be divided into addition multiple submodule or subelement or Sub-component.Other than such feature and/or at least some of process or unit exclude each other, it may be used any Combination is disclosed to all features disclosed in this specification (including adjoint claim, abstract and attached drawing) and so to appoint Where all processes or unit of method or equipment are combined.Unless expressly stated otherwise, this specification is (including adjoint power Profit requirement, abstract and attached drawing) disclosed in each feature can be by providing the alternative features of identical, equivalent or similar purpose come generation It replaces.If also, in the unit claim for listing equipment for drying, several in these devices can be by same hard Part item embodies.
Similarly, it should be understood that in order to simplify the disclosure and help to understand one or more of each open aspect, Above in the description of the exemplary embodiment of the disclosure, each feature of the disclosure is grouped together into single implementation sometimes In example, figure or descriptions thereof.However, the method for the disclosure should be construed to reflect following intention:I.e. required guarantor The disclosure of shield requires features more more than the feature being expressly recited in each claim.More precisely, as following Claims reflect as, open aspect is all features less than single embodiment disclosed above.Therefore, Thus the claims for following specific embodiment are expressly incorporated in the specific embodiment, wherein each claim is in itself All as the separate embodiments of the disclosure.
Particular embodiments described above has carried out the purpose, technical solution and advantageous effect of the disclosure further in detail It describes in detail bright, it should be understood that the foregoing is merely the specific embodiment of the disclosure, is not limited to the disclosure, it is all Within the spirit and principle of the disclosure, any modification, equivalent substitution, improvement and etc. done should be included in the guarantor of the disclosure Within the scope of shield.

Claims (10)

1. a kind of board-like Suo of trepanning-tower connection structure, including:
Steel panel (3) is fixedly connected on the Concrete-filled steel tube (1) of Cable-stayed Bridge Pylon, is flushed with Concrete-filled steel tube (1);
Perforated plate connector (5), is welded on the tower wall side of the steel panel (3), and the perforated plate connector (5) is opened including band Steel and concrete are combined into one by the steel plate in hole by the dowel action of reinforcing bar in concrete in hole and hole.
2. the board-like Suo of trepanning-tower connection structure according to claim 1, the board-like Suo of trepanning-tower connection structure side and steel Bracket (7) welds, and opposite side is combined with cast-in-place Concrete-filled steel tube (1), and the board-like Suo of the trepanning-tower connection structure is directly embedded into It into tower wall concrete, is worked together with Concrete-filled steel tube (1), bears the Suo Li by steel anchor beam (2) and steel corbel (7) transmission.
3. the board-like Suo of trepanning-tower connection structure according to claim 2, the perforated plate connector (5) is in steel corbel (7) The tower wall insert depth of corresponding position is more than other positions, and in its end welding tension plate (6).
4. the board-like Suo of trepanning-tower connection structure according to claim 2, the perforated plate connector (5) are worn general in hole Logical reinforcing bar, puts more energy into steel panel (3).
5. the board-like Suo of trepanning-tower connection structure according to claim 2, the perforated plate connector (5) is according to different firm Degree and requirement for bearing capacity type selecting, and meet the detailing requiments of perforated plate connector, it is welded in steel panel, bears by preset space length The vertical force component of Suo Li and due to caused by eccentricity along bridge to moment of flexure.
6. the board-like Suo of trepanning-tower connection structure according to claim 3, the steel panel (3) opens up wears for suspension cable (4) The reserved through hole crossed, the Concrete-filled steel tube (1) with being cast in perforated plate connector (5) and tension plate (6) periphery are worked together, are held By the Suo Li transmitted by steel anchor beam (2) and steel corbel (7).
7. the board-like Suo of trepanning-tower connection structure according to claim 3, the steel panel (3) pass through perforated plate connector (5) it is fixed on corresponding Concrete-filled steel tube (1) with tension plate (6).
8. the board-like Suo of trepanning-tower connection structure according to claim 3, perforated plate connector (5), tension plate (6) are with mixing Solidifying soil tower wall (1) combines, and the Concrete-filled steel tube (1) is a complete frame structure, and the steel panel (3) is connected by perforated panel Fitting (5) and tension plate (6) are fixed on the corresponding Concrete-filled steel tube (1).
9. the board-like Suo of trepanning-tower connection structure according to claim 1, the board-like Suo of trepanning described in adjacent two layers-tower connection Structure is separated in segment, and the vertical force component of Suo Li is made to be born completely by Concrete-filled steel tube.
10. a kind of method of the board-like Suo of trepanning-tower connection structure made described in any one of claim 1-9, including:
Step S1, steel panel (3) perforated panel of processing steel anchor beam (2), steel corbel (7) and the board-like Suo of trepanning-tower connection structure connect Fitting (5) and tension plate (6);Wherein, first perforated plate connector (5) is welded in steel panel (3), it is rear to weld tension plate (6) Form the disclosure;Steel corbel (7) is welded in steel panel (3) again, and completes application;
Step S2, it is first that four steel corbels (7) are prefabricated closely connected after steel anchor beam (2) completion of processing, and temporarily after connection again by steel Bracket (7) is welded with embedded board;
The board-like Suo of the trepanning of multiple segments-tower connection structure is transported to construction site and completing and lifts, positions and layer by step S3 It is folded, so as to form main body steel construction;Wherein, the steel panel (3) of the board-like Suo of the trepanning of two neighboring segment-tower connection structure is mutual not Connection;
Step S4, using steel panel (3) as needed for casting concrete segment template, using tension plate (6) as construction when branch Frame wears regular reinforcement assembling reinforcement in perforated plate connector (5), is laid with prestress pipe, and segmented casting concrete pours When vibrated in time with the density for ensureing concrete in perforated plate connector (5) hole, ultimately form Concrete-filled steel tube (1);
Step S5, after Concrete-filled steel tube (1) reaches target strength, in perforated plate connector (5) and the knot of Concrete-filled steel tube (1) Conjunction face prestressed reinforcement of tensioning positions and draws suspension cable (4), inclined guy cable stretching work is completed, then in steel corbel (7) and steel The limiting device of steel anchor beam (2) is set on siding (3);After inclined guy cable stretching and secondary dead load are constructed, steel anchor beam is tightened (2) high-strength bolt at both ends.
CN201810206828.0A 2018-03-13 2018-03-13 Connection structure of the board-like Suo-tower of trepanning and preparation method thereof Pending CN108252215A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810206828.0A CN108252215A (en) 2018-03-13 2018-03-13 Connection structure of the board-like Suo-tower of trepanning and preparation method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810206828.0A CN108252215A (en) 2018-03-13 2018-03-13 Connection structure of the board-like Suo-tower of trepanning and preparation method thereof

Publications (1)

Publication Number Publication Date
CN108252215A true CN108252215A (en) 2018-07-06

Family

ID=62746717

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810206828.0A Pending CN108252215A (en) 2018-03-13 2018-03-13 Connection structure of the board-like Suo-tower of trepanning and preparation method thereof

Country Status (1)

Country Link
CN (1) CN108252215A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115341467A (en) * 2022-08-04 2022-11-15 中铁四局集团有限公司 Highway-railway dual-purpose river-crossing A-type stay cable anchoring structure and construction method thereof
CN118241546A (en) * 2024-05-28 2024-06-25 福建省高速公路科技创新研究院有限公司 Structure for connecting steel corbel and concrete tower wall in cable tower anchoring area

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100779766B1 (en) * 2006-07-11 2007-11-27 삼성물산 주식회사 Construction method for tower of bridge
CN101629408A (en) * 2009-08-14 2010-01-20 同济大学 Composite anchoring structure on guyed tower end of cable-stayed bridge
CN202131566U (en) * 2011-05-31 2012-02-01 浙江省交通规划设计研究院 Bridge tower anchoring structure combined by corrugated steel plates and concrete
JP2014047489A (en) * 2012-08-30 2014-03-17 Sumitomo Mitsui Construction Co Ltd Anchorage structure of oblique cable
CN203768811U (en) * 2014-02-21 2014-08-13 同济大学 Embedded steel anchor beam combined pylon anchoring structure
CN105297613A (en) * 2015-10-27 2016-02-03 中交第二公路勘察设计研究院有限公司 Compact stay cable steel anchor beam and construction method thereof

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100779766B1 (en) * 2006-07-11 2007-11-27 삼성물산 주식회사 Construction method for tower of bridge
CN101629408A (en) * 2009-08-14 2010-01-20 同济大学 Composite anchoring structure on guyed tower end of cable-stayed bridge
CN202131566U (en) * 2011-05-31 2012-02-01 浙江省交通规划设计研究院 Bridge tower anchoring structure combined by corrugated steel plates and concrete
JP2014047489A (en) * 2012-08-30 2014-03-17 Sumitomo Mitsui Construction Co Ltd Anchorage structure of oblique cable
CN203768811U (en) * 2014-02-21 2014-08-13 同济大学 Embedded steel anchor beam combined pylon anchoring structure
CN105297613A (en) * 2015-10-27 2016-02-03 中交第二公路勘察设计研究院有限公司 Compact stay cable steel anchor beam and construction method thereof

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
吴鸣主编: "《桥梁工程》", 武汉大学出版社, pages: 375 - 376 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115341467A (en) * 2022-08-04 2022-11-15 中铁四局集团有限公司 Highway-railway dual-purpose river-crossing A-type stay cable anchoring structure and construction method thereof
CN118241546A (en) * 2024-05-28 2024-06-25 福建省高速公路科技创新研究院有限公司 Structure for connecting steel corbel and concrete tower wall in cable tower anchoring area

Similar Documents

Publication Publication Date Title
CN107542190B (en) Composite structural wall and method of construction thereof
CN107476476B (en) Combined construction method of long-span steel bar truss floor bearing plate and reinforced concrete beam
JP5497713B2 (en) Steel structures for reinforced concrete structures
CN104988844B (en) Two times tensioning prestressing force assembled Wavelike steel webplate combination beam
CN102086677A (en) Prefabricated reinforced concrete beam and connection joint of reinforced concrete column and beam
CN108330831A (en) Steel locker format Suo-tower connection structure and preparation method thereof
CN107514083B (en) Side-hung reinforced bar concrete composite floor slab structure with shear key and connecting method
CN106906748A (en) Based on the construction method for mixing prestressed assembled corrugated steel web plate composite box girder
JP2001027005A (en) Connection structure of steel member and concrete in a composite structure
CN210316185U (en) Prefabricated shear wall, connected node
CN108252215A (en) Connection structure of the board-like Suo-tower of trepanning and preparation method thereof
CN110630032A (en) Node connecting device for newly adding beam on existing reinforced concrete column beam
KR20130075995A (en) Lateral supporter, composite concrete column structure having the same, and constructing method thereeof
CN205741871U (en) There is the prestressed reinforced concrete box beam of double limb corrugated steel web
CN208415101U (en) The board-like Suo of aperture-tower connection structure
JP5607384B2 (en) Construction method for beam-column joints
JP7158231B2 (en) Composite column, bridge pier using same, construction method
CN104264782B (en) Assembled integral pre-stressed concrete frame structure and construction method thereof
JP3999591B2 (en) Seismic control structure of concrete structure with fiber reinforced cementitious material
CN105951984A (en) High-ductility assembled integral type frame exterior joint connection structure and construction method thereof
CN206769150U (en) After pour teeth groove and be linked and packed formula building roof system
CN215977671U (en) Large-span prestressed concrete assembled frame connected node
JP2007077628A (en) Joint structure of joint and its construction method
CN211369156U (en) Assembled steel concrete shear force wall
JP3931635B2 (en) Composite box girder and its construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination