CN108193684A - Cast-in-situ bored pile pile crown detaches removing method - Google Patents

Cast-in-situ bored pile pile crown detaches removing method Download PDF

Info

Publication number
CN108193684A
CN108193684A CN201711364256.0A CN201711364256A CN108193684A CN 108193684 A CN108193684 A CN 108193684A CN 201711364256 A CN201711364256 A CN 201711364256A CN 108193684 A CN108193684 A CN 108193684A
Authority
CN
China
Prior art keywords
pile
pile crown
main reinforcement
crown
removing method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711364256.0A
Other languages
Chinese (zh)
Inventor
董雅廷
王小宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Original Assignee
China MCC20 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC20 Group Corp Ltd filed Critical China MCC20 Group Corp Ltd
Priority to CN201711364256.0A priority Critical patent/CN108193684A/en
Publication of CN108193684A publication Critical patent/CN108193684A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D9/00Removing sheet piles bulkheads, piles, mould-pipes or other moulds or parts thereof

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The present invention relates to a kind of hole pouring pile pile crowns to detach removing method, including step 1:Pile crown reinforcing bar is isolated:After pile body pore-forming, installation PVC disrance sleeves in main reinforcement, ultrasound detection pipe and Grouting Pipe are vertically placed more than design of pile top absolute altitude, swelling agent is sprayed into from its base opening, and shut set base opening with band, filler is poured into casing, it fills to the rear sleeve doubling suitable for reading of main reinforcement top and shuts, and casing discount flattening iron wire and main reinforcement top are bound securely;Two:Pile crown integrally blocks:After excavation of foundation pit, cut stake face bore perpendicular to pile body postpone a circumferential direction be uniformly distributed brill four bore division holes;Three:Pile crown removes:Hangs muscle and main reinforcement are disconnected in Hydraulic splitter applies press process, four, top hangs muscle is formed a branch of and can handling appointed place higher than main reinforcement top certain distance as suspension centre, the vertical-lift of pile crown entirety after being locked or welded by the use of lockset.Pile crown separation of the present invention removes quick, the cost-effective and duration.

Description

Cast-in-situ bored pile pile crown detaches removing method
Technical field
The present invention relates to a kind of pile crowns to detach removing method, specifically cast-in-situ bored pile pile crown separation removing method.
Background technology
At present, the cast-in-situ bored pile foundation construction form more ripe as a kind of technique, since it is simple using equipment, It is easy to operate, it is widely applied in the pile foundation constructions such as skyscraper, high-rise building and large bridge at present.But in reality Work progress in, design of pile top absolute altitude cuts link with upper bit and occupies more time, labour after forming pile, influence Foundation construction progress, and being abolished using big machinery influences pile quality, it is easy to there is a series of problems, such as broken pile.
Invention content
The defects of the present invention is directed to overcome the prior art, provides a kind of cast-in-situ bored pile pile crown separation removing method, operation Simplicity, pile crown separation remove quick, the cost-effective and duration.
In order to solve the above-mentioned technical problem, the invention is realized in this way:
A kind of cast-in-situ bored pile pile crown detaches removing method, it is characterised in that it includes the following steps:
Step 1:Pile crown reinforcing bar is isolated:
After pile body pore-forming, at the top of pile body steel reinforcement cage at decentralization to aperture, main reinforcement, ultrasound are vertically placed more than design of pile top absolute altitude PVC disrance sleeves in detection pipe and Grouting Pipe are installed, swelling agent is sprayed into, and set base opening is shut with band from its base opening, then from its Top opening pours into filler into casing, fills to the rear sleeve doubling suitable for reading of main reinforcement top and shuts, and by casing discount flattening iron wire Secured with the binding of main reinforcement top, the control of discount length is in 200-300mm, conduit liter when preventing steel reinforcement cage decentralization, concreting Drop hangs casing;
Step 2:Pile crown integrally blocks:
After excavation of foundation pit, cut stake face bore perpendicular to pile body postpone a circumferential direction be uniformly distributed brill four bore division holes, using liquid Pressure splitter is inserted into division hole and blocks pile crown;
Step 3:Pile crown removes:
Hangs muscle and main reinforcement are disconnected in Hydraulic splitter applies press process, using steel reinforcement cage hanging steel bar secondary use, by top Four hangs muscles formed it is a branch of and after being locked or welded by the use of lockset as suspension centre, the vertical-lift of pile crown entirety is certain higher than main reinforcement top Distance can handling appointed place.
The cast-in-situ bored pile pile crown separation removing method, it is characterised in that:Division hole depth described in step 2 For 200mm, a diameter of 50mm.
The cast-in-situ bored pile pile crown separation removing method, it is characterised in that:Filler described in step 1 is sand Or granular polystyrene.
The beneficial effects of the invention are as follows:Easy to operate, pile crown separation removes quickly, and do mechanization operation is more, greatly saves Cost, duration etc..
Description of the drawings
The present invention is described in further detail with embodiment below in conjunction with the accompanying drawings:
Fig. 1 is schematic structural view of the invention.
Fig. 2 is diagrammatic cross-section at A-A in Fig. 1.
Specific embodiment
As shown in Figure 1, 2:A kind of cast-in-situ bored pile pile crown detaches removing method, it includes the following steps:
Step 1:Pile crown reinforcing bar is isolated:
After pile body pore-forming, at the top of pile body steel reinforcement cage at decentralization to aperture, main reinforcement 1, super is vertically placed in more than 5 design of pile top absolute altitude PVC disrance sleeves 2 on sound detection pipe and Grouting Pipe are installed, swelling agent is sprayed into from its base opening, and set base opening is shut with band, then from Its top opening pours into filler into casing 2, and the filler is husky or granular polystyrene;It fills suitable for reading to 1 top rear sleeve 2 of main reinforcement Doubling is shut, and 2 discount flattening iron wire of casing and 1 top of main reinforcement are bound securely, and discount length is controlled in 200-300mm, Prevent conduit lifting when steel reinforcement cage decentralization, concreting from hanging casing;
Step 2:Pile crown integrally blocks:
After excavation of foundation pit, cut stake face bore perpendicular to pile body postpone a circumferential direction be uniformly distributed brill four bore division holes 4, divide hole 4 depth are 200mm, a diameter of 50mm;Division hole is inserted into using Hydraulic splitter and blocks pile crown;
Step 3:Pile crown removes:
Hangs muscle and main reinforcement are disconnected in Hydraulic splitter applies press process, using 3 secondary use of steel reinforcement cage hanging steel bar, by top Four hangs muscles 3 form a branch of and are higher than 1 top one of main reinforcement as suspension centre, the vertical-lift of pile crown entirety after being locked or welded by the use of lockset Set a distance can handling appointed place.

Claims (3)

1. a kind of cast-in-situ bored pile pile crown detaches removing method, it is characterised in that it includes the following steps:
Step 1:Pile crown reinforcing bar is isolated:
After pile body pore-forming, at the top of pile body steel reinforcement cage at decentralization to aperture, main reinforcement, ultrasound are vertically placed more than design of pile top absolute altitude PVC disrance sleeves in detection pipe and Grouting Pipe are installed, swelling agent is sprayed into, and set base opening is shut with band from its base opening, then from its Top opening pours into filler into casing, fills to the rear sleeve doubling suitable for reading of main reinforcement top and shuts, and by casing discount flattening iron wire Secured with the binding of main reinforcement top, the control of discount length is in 200-300mm, conduit liter when preventing steel reinforcement cage decentralization, concreting Drop hangs casing;
Step 2:Pile crown integrally blocks:
After excavation of foundation pit, cut stake face bore perpendicular to pile body postpone a circumferential direction be uniformly distributed brill four bore division holes, using liquid Pressure splitter is inserted into division hole and blocks pile crown;
Step 3:Pile crown removes:
Hangs muscle and main reinforcement are disconnected in Hydraulic splitter applies press process, using steel reinforcement cage hanging steel bar secondary use, by top Four hangs muscles formed it is a branch of and after being locked or welded by the use of lockset as suspension centre, the vertical-lift of pile crown entirety is certain higher than main reinforcement top Distance can handling appointed place.
2. cast-in-situ bored pile pile crown according to claim 1 detaches removing method, it is characterised in that:Described in step 2 Division hole depth is 200mm, a diameter of 50mm.
3. cast-in-situ bored pile pile crown according to claim 2 detaches removing method, it is characterised in that:Described in step 1 Filler is husky or granular polystyrene.
CN201711364256.0A 2017-12-18 2017-12-18 Cast-in-situ bored pile pile crown detaches removing method Pending CN108193684A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711364256.0A CN108193684A (en) 2017-12-18 2017-12-18 Cast-in-situ bored pile pile crown detaches removing method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711364256.0A CN108193684A (en) 2017-12-18 2017-12-18 Cast-in-situ bored pile pile crown detaches removing method

Publications (1)

Publication Number Publication Date
CN108193684A true CN108193684A (en) 2018-06-22

Family

ID=62576944

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711364256.0A Pending CN108193684A (en) 2017-12-18 2017-12-18 Cast-in-situ bored pile pile crown detaches removing method

Country Status (1)

Country Link
CN (1) CN108193684A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109629557A (en) * 2018-12-18 2019-04-16 五冶集团上海有限公司 A kind of cast-in-situ bored pile pile crown isolating device and its application method
CN110158581A (en) * 2019-05-30 2019-08-23 武汉中力岩土工程有限公司 Pile base construction method
CN110185037A (en) * 2019-06-27 2019-08-30 中铁五局集团建筑工程有限责任公司 A kind of bored concrete pile is without mechanical broken pile head method and structure

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102312429A (en) * 2011-07-12 2012-01-11 中铁西北科学研究院有限公司 Rapid separation and integral hoisting method for pile head of cast-in-place concrete pile
CN102587380A (en) * 2012-02-08 2012-07-18 湖南省第二工程有限公司 Construction method for wholly removing drilling pile head
CN104343115A (en) * 2014-11-13 2015-02-11 中交隧道工程局有限公司 Structure and method for integrally breaking pile head of pile foundation
CN104480931A (en) * 2014-12-10 2015-04-01 大连三川建设集团股份有限公司 Fast file head removing method for mechanical pore forming pouring pile
CN105297729A (en) * 2015-11-23 2016-02-03 中国葛洲坝集团第六工程有限公司 Bridge pile foundation pile head breaking device and method
CN106400803A (en) * 2016-10-31 2017-02-15 中国葛洲坝集团第六工程有限公司 Integral cast-in-situ bored pile head breaking process

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102312429A (en) * 2011-07-12 2012-01-11 中铁西北科学研究院有限公司 Rapid separation and integral hoisting method for pile head of cast-in-place concrete pile
CN102587380A (en) * 2012-02-08 2012-07-18 湖南省第二工程有限公司 Construction method for wholly removing drilling pile head
CN104343115A (en) * 2014-11-13 2015-02-11 中交隧道工程局有限公司 Structure and method for integrally breaking pile head of pile foundation
CN104480931A (en) * 2014-12-10 2015-04-01 大连三川建设集团股份有限公司 Fast file head removing method for mechanical pore forming pouring pile
CN105297729A (en) * 2015-11-23 2016-02-03 中国葛洲坝集团第六工程有限公司 Bridge pile foundation pile head breaking device and method
CN106400803A (en) * 2016-10-31 2017-02-15 中国葛洲坝集团第六工程有限公司 Integral cast-in-situ bored pile head breaking process

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109629557A (en) * 2018-12-18 2019-04-16 五冶集团上海有限公司 A kind of cast-in-situ bored pile pile crown isolating device and its application method
CN110158581A (en) * 2019-05-30 2019-08-23 武汉中力岩土工程有限公司 Pile base construction method
CN110185037A (en) * 2019-06-27 2019-08-30 中铁五局集团建筑工程有限责任公司 A kind of bored concrete pile is without mechanical broken pile head method and structure

Similar Documents

Publication Publication Date Title
CN205975626U (en) Strut integrated configuration with stagnant water unification in soft soil layer foundation ditch
CN101705687B (en) Deep foundation pit reinforced concrete waist rail detaching device and construction method
CN204039921U (en) A kind of Construction Support without support bent cap
CN108612086B (en) Construction method of fractured geological cast-in-situ bored pile
CN110042844B (en) Construction method of cast-in-situ large-diameter foundation pit supporting tubular pile
CN104988915B (en) A kind of prefabricated installation method of detachable steel casing and under water connection beam
CN103410564A (en) Tunnel water gushing treatment structure and construction method thereof
CN104480931B (en) Fast file head removing method for mechanical pore forming pouring pile
CN108951431A (en) Bridge concrete earth cofferdam and bridge pier building technology
CN108193684A (en) Cast-in-situ bored pile pile crown detaches removing method
CN111395330A (en) Construction method for concrete cast-in-situ bored pile complete steel casing penetrating through underground gallery
CN107653878A (en) Cast-in-situ bored pile is reusable to be longitudinally separated formula steel pile casting construction
CN106285032B (en) Basement reconstruction construction with raft foundation building
CN107237339A (en) A kind of concrete cut increases leakage preventing structure and its construction method
CN107489284A (en) Basement locally increases the construction method in deeper subsurface garage newly
CN110206071A (en) A kind of diaphram wall seam reinforcement means and device
CN106284428A (en) A kind of concrete column method for supporting of building structure post-cast strip
CN207260378U (en) A kind of assembled frame-shear structure curved scissors type combines keyway connection structure
CN108179759A (en) The underwater drill core slotting of driftway is without bottom sealing method
CN209066508U (en) Cross the existing electric power piping lane protection structure of tunnel foundation pit
CN206889866U (en) A kind of pipeline for avoiding seepage wears pool wall device
JP5288356B2 (en) How to connect existing piping and new piping in the manhole
CN107476293A (en) A kind of quick spreading structure of soft soil foundation bored concrete pile configures and its spreading method
CN105970961B (en) A kind of bored concrete pile goes along with sb. to guard him deep pit monitor and cuts piling method
CN105970972A (en) Novel secant pile supporting structure and construction method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180622

RJ01 Rejection of invention patent application after publication