CN108179759A - The underwater drill core slotting of driftway is without bottom sealing method - Google Patents

The underwater drill core slotting of driftway is without bottom sealing method Download PDF

Info

Publication number
CN108179759A
CN108179759A CN201711481666.3A CN201711481666A CN108179759A CN 108179759 A CN108179759 A CN 108179759A CN 201711481666 A CN201711481666 A CN 201711481666A CN 108179759 A CN108179759 A CN 108179759A
Authority
CN
China
Prior art keywords
cofferdam
steel
steel pipe
drill core
driftway
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201711481666.3A
Other languages
Chinese (zh)
Other versions
CN108179759B (en
Inventor
于停
曾维军
何树凯
于陆军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chongqing Huali Construction Co Ltd
Original Assignee
Chongqing Huali Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chongqing Huali Construction Co Ltd filed Critical Chongqing Huali Construction Co Ltd
Priority to CN201711481666.3A priority Critical patent/CN108179759B/en
Publication of CN108179759A publication Critical patent/CN108179759A/en
Application granted granted Critical
Publication of CN108179759B publication Critical patent/CN108179759B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/02Restraining of open water
    • E02D19/04Restraining of open water by coffer-dams, e.g. made of sheet piles
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B15/00Supports for the drilling machine, e.g. derricks or masts
    • E21B15/003Supports for the drilling machine, e.g. derricks or masts adapted to be moved on their substructure, e.g. with skidding means; adapted to drill a plurality of wells
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B15/00Supports for the drilling machine, e.g. derricks or masts
    • E21B15/02Supports for the drilling machine, e.g. derricks or masts specially adapted for underwater drilling
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B7/00Special methods or apparatus for drilling
    • E21B7/12Underwater drilling
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0061Production methods for working underwater
    • E02D2250/0076Drilling
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Geology (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Paleontology (AREA)
  • Earth Drilling (AREA)

Abstract

The invention discloses a kind of underwater drill core slotting of driftway without bottom sealing method, including following construction procedure:S1, steel trestle and drill core platform are set up;S2, drill core slotting construction;S3, installation steel cofferdam;S4, cofferdam slot concreting;S5, foundation pit and pile foundation are excavated;S6, pile foundation and bearing platform construction.The beneficial effects of the present invention are:It is cost-effective, without in-place blasting out circle, sealing risk is smaller, speed of application is very fast, the duration is shorter.

Description

The underwater drill core slotting of driftway is without bottom sealing method
Technical field
The present invention relates to highway crash facility technology fields waterborne, and in particular to a kind of underwater drill core slotting of driftway is without envelope Bottom method.
Background technology
Bridge as connection river two sides plays very important effect in modern society.For example it is just built on the Changjiang river If hundreds of bridges, people and Che here reach opposite bank through the Crossing the bridge noodles Congjiang, ship fair current and mistake under bridge.When ship passes through under bridge When, if unexpected knock bridge, huge damage can be caused to bridge.Therefore, general use arranges arc under the bridge of river two sides The anticollision band of shape surrounds bridge to form protection zone on bridge water.In the engineering of construction anticollision band, it is proposed that a variety of to lead The drill core slotting arrangement and method for construction under well water quick-fried has back cover method including boring quick-fried no back cover method under water and boring under water.It is quick-fried using boring under water Excavating load, steel cofferdam periphery and inner circumferential pour curtain concrete, after concrete reaches some strength, are bored under water on curtain concrete Pore pressure starches sealing.Quick-fried in-place blasting out circle cranny development and irregular is bored under water, it is extremely disadvantageous to mud jacking sealing.Boring under water quick-fried has The i.e. lower drill-blast tunnelling of back cover construction method water installs the steel cofferdam of intensification, pours bottom concrete, treat back cover concrete to certain depth Up to after intensity, draw water in cofferdam, dry application work basis.Therefore quick-fried no back cover method is bored under water there are the in-place blasting out circles that underwater demolition generates Sealing dangerous and deep water mud jacking sealing cost more difficult the shortcomings of estimating, bore quick-fried longer and apply with the presence of the back cover method duration under water The shortcomings that work cost is very big.It is therefore desirable to seek it is a kind of it is cost-effective, without in-place blasting out circle, sealing risk is smaller, construction speed The method that degree is very fast and the duration is shorter.
Invention content
In view of this, the purpose of the present invention is to provide a kind of underwater drill core slotting of driftway without bottom sealing method.
In order to achieve the above objectives, the present invention provides following technical solution:A kind of underwater drill core slotting of driftway is without back cover side Method, it is characterised in that, including following construction procedure:
S1, steel trestle and drill core platform are set up, intectate position is using drill core pore-forming in trestle column steel pipe, pouring reinforcement concrete Carry out the footing of upright column steel pipe, top uses I-steel girder;
S2, drill core slotting are constructed, and after the completion of trestle and putting up platform, in cofferdam, surrounding places more engineering core drilling machines;Using more Root is oriented to steel pipe cluster, and top is connected temporarily using reinforcing bar or shaped steel;After the completion of penstock installation is oriented to, you can carry out drill core; It after the completion for the treatment of drill core pore-forming, releases be oriented between steel pipe interim and connecting and removing guiding steel pipe, using jump bit by Kong Yukong Between rock punching be broken into slot, disintegrating slag use dredge pump suction to form cofferdam slot in the slot of cofferdam;
S3, installation steel cofferdam, after cofferdam slot is formed, release the lateral of cofferdam slot Internal and external cycle column steel pipe, reinforce former in cofferdam bore Core steel pipe platform, the platform as installation steel cofferdam;Steel cofferdam is transported to construction site using ship, using crane barge ship entirety merogenesis Section lifting steel cofferdam;After the decentralization of first segment steel cofferdam, cofferdam itself is in floating state, and cofferdam and cofferdam inner platform are done temporarily Connection;Lifting the second section steel cofferdam, is welded with first segment steel cofferdam, after the completion of the welding of cofferdam spelling, water filling sinking in cofferdam, Stop water filling after reaching height, release cofferdam suspension centre, the installation in entire cofferdam is sequentially completed with this;
S4, cofferdam slot concreting, cofferdam are connected outside steel pipe post in cofferdam, at the top of steel cofferdam after installation is complete Platform is formed, Underwater Concrete conduit is laid along cofferdam inside and outside wall, underwater concrete is poured in the slot of cofferdam;Cofferdam is after installation is complete, The water in cofferdam is drained, carries out dry application work, it, can the disposition of localized borehole mud jacking because of the infiltration that the crack of rock mass itself occurs;
S5, foundation pit and pile foundation are excavated;
S6, pile foundation and bearing platform construction.
Further, in S1, steel trestle and drill core platform include holder part and trestle part, one end of trestle part Connecting bracket part;When overlooking holder part, holder part overall structure is rounded, and when overlooking trestle part, trestle part is whole Body structure is in strip-like-shaped;Holder part includes more root post steel pipes, I-steel girder and checkered steel plate, column steel pipe uniform intervals It is located on two concentric circles and column steel pipe vertically extends, the lower end of column steel pipe is fixed on water by reinforced concrete Lower basement rock is fixedly connected in the upper end radially with circumferentially-adjacent two root posts steel pipe by I-steel girder, in I-steel Checkered steel plate is radially equipped with above girder.
Further, four columns steel pipe also is provided in the middle part of holder part, which is square distribution, Basement rock under water is fixed in the lower end of the four columns steel pipe, is consolidated between the upper end of the four columns steel pipe by I-steel girder Fixed, the upper end of the four columns steel pipe passes through I-steel girder and adjacent more root post steel pipes on concentric circle Upper end is fixedly connected.
Further, also including more, vertically fixed column steel pipe, the lower end of column steel pipe are consolidated for trestle part Basement rock is scheduled on, the upper end of column steel pipe is fixedly connected by I-steel girder and is equipped with checkered steel plate;In the another of trestle part One end is equipped with multiple dowels.
Further, it in S2, is oriented to steel pipe and is arranged vertically between two concentric circles, i.e., more guiding Plane tangent forms the circular column steel pipe for being oriented to steel pipe and being arranged on two concentric circles of cluster between steel pipe Between.
Further, basement rock under water is fixed in the lower end for being oriented to steel pipe.
Further, the axis spacing of the adjacent two root posts steel pipe in the inner circle of two concentric circles is 4.6 Rice.
Further, the axis spacing of the adjacent two root posts steel pipe in the outer circle of two concentric circles is 7.4 Rice.
Further, it is oriented to steel pipe and compound steel pipe structure is formed between two concentric circles.
The beneficial effects of the present invention are:It is cost-effective, without in-place blasting out circle, sealing risk is smaller, speed of application is very fast, Duration is shorter.
Description of the drawings
In order to make the purpose of the present invention, technical solution and advantageous effect clearer, the present invention provides drawings described below and carries out Explanation:
Fig. 1 is trestle and platform schematic top plan view of the underwater drill core slotting of driftway of the present invention without bottom sealing method.
Fig. 2 is Fig. 1 along A-A direction structure schematic diagrames.
Fig. 3 arranges schematic diagram for drill core slotting construction part plan.
Fig. 4 is cofferdam traverse drill core bore position layout drawing.
Fig. 5 is punching drilling machine impact grooving schematic diagram.
Fig. 6 is driftway steel cofferdam mounting plane layout drawing.
Fig. 7 is driftway steel cofferdam mounting vertical plane layout drawing.
Fig. 8 is layout drawing inside the slot concrete placings of cofferdam.
In figure, 1 is column steel pipe, and 2 be I-steel girder, and 3 be reinforced concrete, and 4 be dowel, and 5 is are oriented to steel pipe, and 6 be drilling machine, 7 be jump bit, and 8 be cofferdam slot, and 9 be crane barge ship, and 10 be steel cofferdam, and 11 be concrete conduit.
Specific embodiment
The invention will be further described in the following with reference to the drawings and specific embodiments, so that those skilled in the art can be with It is better understood from the present invention and can be practiced, but illustrated embodiment is not as a limitation of the invention.
Embodiment one:A kind of underwater drill core slotting of driftway of the present embodiment is without bottom sealing method, including following construction procedure: S1, steel trestle and drill core platform are set up, intectate position is come steady using drill core pore-forming in trestle column steel pipe, pouring reinforcement concrete Gu the footing of column steel pipe, top uses I-steel girder;S2, drill core slotting are constructed, and after the completion of trestle and putting up platform, are being enclosed Weir surrounding places more engineering core drilling machines;Using more guiding steel pipe clusters, top is connected temporarily using reinforcing bar or shaped steel;When leading After the completion of penstock installation, you can carry out drill core;After the completion for the treatment of drill core pore-forming, connecting and moving temporarily between releasing guiding steel pipe Walk to be oriented to steel pipe, the rock punching between Kong Yukong be broken by slot using jump bit, in the slot of cofferdam disintegrating slag use dredge pump suction with Form cofferdam slot;S3, installation steel cofferdam, after cofferdam slot is formed, release the lateral of cofferdam slot Internal and external cycle column steel pipe, reinforce cofferdam Interior original drill core steel pipe platform, the platform as installation steel cofferdam;Steel cofferdam is transported to construction site using ship, whole using crane barge ship The segmented lifting steel cofferdam of body;After the decentralization of first segment steel cofferdam, cofferdam itself is in floating state, by cofferdam and cofferdam inner platform Do interim connection;Lifting the second section steel cofferdam, welds with first segment steel cofferdam, after the completion of the welding of cofferdam spelling, is noted in cofferdam It is underwater heavy, stop water filling after reaching height, release cofferdam suspension centre, the installation in entire cofferdam is sequentially completed with this;S4, cofferdam slot mix Solidifying soil pours, and outside steel pipe post in cofferdam is connected, platform is formed at the top of steel cofferdam, along cofferdam after installation is complete by cofferdam Inside and outside wall lays Underwater Concrete conduit, and underwater concrete is poured in the slot of cofferdam;The water in cofferdam is drained after installation is complete in cofferdam, Dry application work is carried out, it, can the disposition of localized borehole mud jacking because of the infiltration that the crack of rock mass itself occurs;S5, foundation pit and pile foundation are excavated; S6, pile foundation and bearing platform construction.
In S1, steel trestle and drill core platform include holder part and trestle part, one end connecting bracket of trestle part Part;When overlooking holder part, holder part overall structure is rounded, and when overlooking trestle part, trestle part overall structure is in Strip-like-shaped;Holder part includes more root post steel pipes 1, I-steel girder 2 and checkered steel plate, and 1 uniform intervals of column steel pipe are located at On two concentric circles and column steel pipe 1 vertically extends, and the lower end of column steel pipe 1 is fixed on water by reinforced concrete 3 Lower basement rock is fixedly connected in the upper end radially with circumferentially-adjacent two root posts steel pipe 1 by I-steel girder 2, in I-shaped 2 top of steel girder is radially equipped with checkered steel plate.
Four columns steel pipe 1 also is provided in the middle part of holder part, which is square distribution, this four Basement rock under water is fixed in the lower end of column steel pipe 1, is fixed between the upper end of the four columns steel pipe 1 by I-steel girder 2, should The upper end of four columns steel pipe 1 is upper by I-steel girder 2 and adjacent more root post steel pipes 1 on concentric circle End is fixedly connected.
Trestle part also includes more, and vertically fixed column steel pipe 1, the lower end of column steel pipe 1 are fixed on base Rock, the upper end of column steel pipe 1 are fixedly connected by I-steel girder 2 and are equipped with checkered steel plate;The other end in trestle part Equipped with multiple dowels 4, trestle department is connect with slope surface or basement rock by dowel 4.
In S2, be oriented to steel pipe 5 be arranged vertically between two concentric circles, i.e., more be oriented to steel pipe 5 it Between plane tangent form the circular steel pipe 5 that is oriented to of cluster and be arranged between the column steel pipe 1 on two concentric circles.
Basement rock under water is fixed in the lower end for being oriented to steel pipe 5.
The axis spacing M of adjacent two root posts steel pipe 1 in the inner circle of two concentric circles is 4.6 meters.
The axis spacing L of adjacent two root posts steel pipe 1 in the outer circle of two concentric circles is 7.4 meters.
It is oriented to steel pipe 5 and compound steel pipe structure is formed between two concentric circles.
Embodiment two:The present embodiment by by this method use in Changjiang River Highway Bridge anti-collision facility engineering for.Assuming that The engineering includes 1# driftways, and 1# driftways are located at the long north of the Changjiang River and swim on the bank, 15 meters, elevation of bottom+133.5m of driftway diameter, Elevation of top+180m, foundation bottom connection pile foundation, 2 meters of the diameter pile foundation substrate absolute altitude of pile foundation quantity 9+121.5m.1# driftways Surface geology situation is complex, and more than absolute altitude+138m is rushes diluvial formation, collapses diluvial layer, artificial stack layer, main component sand Soil, block stone soil, plain fill.It is oriented in well area in 1# and big boulder, block stone is distributed with.
In the underwater drill core slotting of driftway used 1# driftways without bottom sealing method, including following construction procedure:S1, it takes If steel trestle and drill core platform, using drill core pore-forming in trestle column steel pipe 1, pouring reinforcement concrete 3 consolidates for intectate position The footing of column steel pipe 1, top use I-steel girder 2.Specifically, as depicted in figs. 1 and 2, steel trestle and drill core platform packet Include holder part and trestle part, one end connecting bracket part of trestle part;When overlooking holder part, holder part is integrally tied Structure is rounded, and when overlooking trestle part, trestle part overall structure is in strip-like-shaped;Holder part includes more root post steel pipes 1, work Word steel girder 2 and checkered steel plate, 1 uniform intervals of column steel pipe are located on two concentric circles and column steel pipe 1 is along vertical side To extension, basement rock under water is fixed in the lower end of column steel pipe 1 by reinforced concrete 3, radially with circumferentially-adjacent two root posts The upper end of steel pipe 1 is fixedly connected by I-steel girder 2, and checkered steel plate is radially equipped with above I-steel girder 2.
Four columns steel pipe 1 also is provided in the middle part of holder part, which is square distribution, this four Basement rock under water is fixed in the lower end of column steel pipe 1, is fixed between the upper end of the four columns steel pipe 1 by I-steel girder 2, should The upper end of four columns steel pipe 1 is upper by I-steel girder 2 and adjacent more root post steel pipes 1 on concentric circle End is fixedly connected.
Trestle part also includes more, and vertically fixed column steel pipe 1, the lower end of column steel pipe 1 are fixed on base Rock, the upper end of column steel pipe 1 are fixedly connected by I-steel girder 2 and are equipped with checkered steel plate;The other end in trestle part Equipped with multiple dowels 4.
S2, drill core slotting are constructed, and after the completion of trestle and putting up platform, in cofferdam, surrounding places 4 QZ engineering core drilling machines.It encloses Weir notch drafts width as 3m, and cofferdam slot bottom absolute altitude is+136m(That is cofferdam groove depth about 3m).As shown in figure 3, it is oriented to 5 edge of steel pipe Vertical direction is arranged between two concentric circles, i.e., the more annular shapes for being oriented to plane tangent formation cluster between steel pipe 5 Steel pipe 5 is oriented to be arranged between the column steel pipe 1 on two concentric circles.The lower end for being oriented to steel pipe 5 is fixed under water Basement rock.The axis spacing M of adjacent two root posts steel pipe 1 in the inner circle of two concentric circles is 4.6 meters.Positioned at two The axis spacing L of adjacent two root posts steel pipe 1 in the outer circle of concentric circle is 7.4 meters.Steel pipe 5 is oriented in two concentric circles Compound steel pipe structure is formed between circumference.In the present embodiment, using 9 guiding 5 clusters of steel pipe, top uses reinforcing bar or type Steel connects temporarily.When 1~9# be oriented to steel pipe 5 installation is complete after, you can carry out drill core, drill through 4#, 5#, 6# hole first, treat 4#, After the completion of 5#, 6# hole drill core, interim connection is released, 1#, 2#, 3# guiding steel pipe 5 are pacified to 10#, 11#, 12#, after installing Do interim connection in top, you can drill through 7#, 8#, 9# hole, cycle drills through according to this.Cofferdam traverse drill core arrangement of boring holes as shown in Figure 4 Figure, in the present embodiment, 182 a diameter of 0.9 is arranged by a diameter of 1 meter of guiding steel pipe 5 altogether in entire cofferdam slot The drill core hole of rice, it is 11.25 meters to excavate outer rabbet line radius R1, and cofferdam outer edge radius R2 is 10.25 meters, cofferdam inner edge Radius R3 is 8.75 meters, and it is 8.25 meters to excavate notch inner edge radius.As shown in figure 5, entire cofferdam slot is applied using four bench drill machines 6 Rock between Kong Yukong after the completion for the treatment of drill core pore-forming, using φ 2.5m jump bits 7 is rushed and is broken into slot by work, disintegrating slag in the slot of cofferdam Dredge pump is used to be sucked out to form cofferdam slot 8(With reference to figure 6).
S3, installation steel cofferdam 10, after cofferdam slot is formed, release the lateral of cofferdam slot Internal and external cycle column steel pipe 1, reinforce cofferdam Interior original drill core steel pipe platform, the platform as installation steel cofferdam;Steel cofferdam is transported to construction site using ship, floating using 300 tons The whole segmented lifting steel cofferdam 10 of ship 9 is hung, as shown in Figure 7.After the decentralization of first segment steel cofferdam, cofferdam itself is in floating shape Interim connection is done in cofferdam and cofferdam inner platform by state;Lifting the second section steel cofferdam, is welded, cofferdam group with first segment steel cofferdam After the completion of welding connects, water filling sinking in cofferdam stops water filling after reaching height, releases cofferdam suspension centre, is completed with this sequence entire The installation in cofferdam.
S4, cofferdam slot concreting, cofferdam are connected outside steel pipe post in cofferdam, in steel cofferdam after installation is complete Platform is formed on top, lays Underwater Concrete conduit 11 along cofferdam inside and outside wall, underwater concrete is poured in the slot of cofferdam, as shown in Figure 8. The water in cofferdam is drained after installation is complete in cofferdam, carries out dry application work, because of the infiltration that the crack of rock mass itself occurs, can locally bore Pore pressure slurry disposition;S5, foundation pit and pile foundation are excavated;S6, pile foundation and bearing platform construction.
For 1# driftways, according to boring quick-fried no back cover method, general 60 days of duration, expense about 5,000,000, mud jacking sealing under water Estimate 3,000,000 yuan;According to bore under water it is quick-fried have 120 days back cover method durations, add it is underwater dig the cubic meter of stone, increase about 18,000,000 yuan of expense, Increase about 1,000,000 yuan of bottom concrete, steel cofferdam deepens about 1,500,000 yuan of increase expense;It is bored under water according to driftway of the present invention Without bottom sealing method, the duration is estimated 60 days for core slotting, and construction platform and trestle etc. increase about 4,000,000 yuan of expense, and foundation trench excavates expense About 500,000 yuan, about 300,000 yuan of foundation pit hand excavation.Therefore, the present invention compared to other two methods there are short time limit, without explosion, The advantages of at low cost.
The beneficial effects of the present invention are:It is cost-effective, without in-place blasting out circle, sealing risk is smaller, speed of application is very fast, Duration is shorter.
Embodiment described above is only to absolutely prove preferred embodiment that is of the invention and being lifted, protection model of the invention It encloses without being limited thereto.The equivalent substitute or transformation that those skilled in the art are made on the basis of the present invention, in the present invention Protection domain within.Protection scope of the present invention is subject to claims.

Claims (9)

1. a kind of underwater drill core slotting of driftway is without bottom sealing method, it is characterised in that, including following construction procedure:
S1, steel trestle and drill core platform are set up, intectate position is using drill core pore-forming in trestle column steel pipe, pouring reinforcement concrete Carry out the footing of upright column steel pipe, top uses I-steel girder;
S2, drill core slotting are constructed, and after the completion of trestle and putting up platform, in cofferdam, surrounding places more engineering core drilling machines;Using more Root is oriented to steel pipe cluster, and top is connected temporarily using reinforcing bar or shaped steel;After the completion of penstock installation is oriented to, you can carry out drill core; It after the completion for the treatment of drill core pore-forming, releases be oriented between steel pipe interim and connecting and removing guiding steel pipe, using jump bit by Kong Yukong Between rock punching be broken into slot, disintegrating slag use dredge pump suction to form cofferdam slot in the slot of cofferdam;
S3, installation steel cofferdam, after cofferdam slot is formed, release the lateral of cofferdam slot Internal and external cycle column steel pipe, reinforce former in cofferdam bore Core steel pipe platform, the platform as installation steel cofferdam;Steel cofferdam is transported to construction site using ship, using crane barge ship entirety merogenesis Section lifting steel cofferdam;After the decentralization of first segment steel cofferdam, cofferdam itself is in floating state, and cofferdam and cofferdam inner platform are done temporarily Connection;Lifting the second section steel cofferdam, is welded with first segment steel cofferdam, after the completion of the welding of cofferdam spelling, water filling sinking in cofferdam, Stop water filling after reaching height, release cofferdam suspension centre, the installation in entire cofferdam is sequentially completed with this;
S4, cofferdam slot concreting, cofferdam are connected outside steel pipe post in cofferdam, at the top of steel cofferdam after installation is complete Platform is formed, Underwater Concrete conduit is laid along cofferdam inside and outside wall, underwater concrete is poured in the slot of cofferdam;Cofferdam is after installation is complete, The water in cofferdam is drained, carries out dry application work, it, can the disposition of localized borehole mud jacking because of the infiltration that the crack of rock mass itself occurs;
S5, foundation pit and pile foundation are excavated;
S6, pile foundation and bearing platform construction.
2. the underwater drill core slotting of driftway according to claim 1 is without bottom sealing method, which is characterized in that in S1, steel stack Bridge and drill core platform include holder part and trestle part, and one end of the trestle part connects the holder part;Overlook institute When stating holder part, the holder part overall structure is rounded, and when overlooking the trestle part, the trestle part is integrally tied Structure is in strip-like-shaped;The holder part includes more root post steel pipes, I-steel girder and checkered steel plate, and the column steel pipe is uniform Interval is located on two concentric circles and the column steel pipe vertically extends, and the lower end of the column steel pipe passes through steel Muscle concrete fixes basement rock under water, is radially being consolidated with the upper end of circumferentially-adjacent two root posts steel pipe by the I-steel girder Fixed connection, checkered steel plate is radially equipped with above the I-steel girder.
3. the underwater drill core slotting of driftway according to claim 2 is without bottom sealing method, it is characterised in that, in the stent Four columns steel pipe also is provided in the middle part of partial, which is square distribution, and the lower end of the four columns steel pipe is consolidated Underwater basement rock is scheduled on, is fixed between the upper end of the four columns steel pipe by the I-steel girder, the four columns steel pipe Upper end is fixedly connected by the I-steel girder with the upper end of adjacent more root post steel pipes on concentric circle.
4. the underwater drill core slotting of driftway according to claim 3 is without bottom sealing method, it is characterised in that, the trestle part Also include more vertically fixed column steel pipe, the lower end of column steel pipe be fixed on basement rock, the upper end of column steel pipe leads to I-steel girder is crossed to be fixedly connected and be equipped with checkered steel plate;The other end in the trestle part is equipped with multiple dowels.
5. the underwater drill core slotting of driftway according to claim 4 is without bottom sealing method, which is characterized in that described in S2 It is oriented to steel pipe to be arranged vertically between two concentric circles, i.e., plane tangent is formed between the more guiding steel pipes The circular steel pipe that is oriented to of cluster is arranged between the column steel pipe on two concentric circles.
6. the underwater drill core slotting of driftway according to claim 5 is without bottom sealing method, it is characterised in that, the guiding steel Basement rock under water is fixed in the lower end of pipe.
7. the underwater drill core slotting of driftway according to claim 6 is without bottom sealing method, it is characterised in that, positioned at described two The axis spacing of adjacent two root posts steel pipe in the inner circle of a concentric circle is 4.6 meters.
8. the underwater drill core slotting of driftway according to claim 7 is without bottom sealing method, it is characterised in that, positioned at described two The axis spacing of adjacent two root posts steel pipe in the outer circle of a concentric circle is 7.4 meters.
9. the underwater drill core slotting of driftway according to claim 8 is without bottom sealing method, it is characterised in that, the guiding steel Pipe forms compound steel pipe structure between described two concentric circles.
CN201711481666.3A 2017-12-29 2017-12-29 Underwater core drilling and undercutting bottomless method for pilot well Expired - Fee Related CN108179759B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711481666.3A CN108179759B (en) 2017-12-29 2017-12-29 Underwater core drilling and undercutting bottomless method for pilot well

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711481666.3A CN108179759B (en) 2017-12-29 2017-12-29 Underwater core drilling and undercutting bottomless method for pilot well

Publications (2)

Publication Number Publication Date
CN108179759A true CN108179759A (en) 2018-06-19
CN108179759B CN108179759B (en) 2020-06-26

Family

ID=62549133

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711481666.3A Expired - Fee Related CN108179759B (en) 2017-12-29 2017-12-29 Underwater core drilling and undercutting bottomless method for pilot well

Country Status (1)

Country Link
CN (1) CN108179759B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110130393A (en) * 2019-05-22 2019-08-16 中铁四局集团有限公司 A kind of underwater foundation pit drilling of soft rock and punching point arrangement method
CN111119212A (en) * 2019-12-18 2020-05-08 中建三局基础设施建设投资有限公司 Construction method for sinking double-wall steel cofferdam under deep clay layer condition
CN111119213A (en) * 2019-12-18 2020-05-08 中建三局基础设施建设投资有限公司 Double-wall steel cofferdam with open edge feet and construction method thereof

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102926355A (en) * 2012-11-21 2013-02-13 重庆交通大学西南水运工程科学研究所 Independent regional anti-collision device adapting to high water-level amplitude
CN103437341A (en) * 2013-07-29 2013-12-11 中铁十六局集团北京轨道交通工程建设有限公司 Effective grooving construction method for underground continuous wall in slightly-weathered limestone with overlying sandy soil
CN104196044A (en) * 2014-09-05 2014-12-10 中铁四局集团有限公司 Cofferdam construction method with grooves milled through limited hole forming of percussion drill combined with steel sheet piles
CN104763324A (en) * 2015-04-01 2015-07-08 上海强劲地基工程股份有限公司 Large-diameter hole forming construction equipment for core drilling rock entering and construction method thereof
CN105804079A (en) * 2016-03-31 2016-07-27 大连久鼎祥瑞特种工程技术研究院有限公司 Tool and method for smashing hard rock in large-diameter pile hole
CN106351241A (en) * 2016-08-28 2017-01-25 中铁二十局集团有限公司 Deep-water foundation construction method for large-span continuous beam adjacent to existing railway line
CN106968176A (en) * 2017-03-24 2017-07-21 中建三局基础设施工程有限公司 A kind of embedding batholith foundation construction of bridge deepwater
CN107503345A (en) * 2017-09-27 2017-12-22 中铁二十局集团有限公司 A kind of deep water foundation pile foundation construction process

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102926355A (en) * 2012-11-21 2013-02-13 重庆交通大学西南水运工程科学研究所 Independent regional anti-collision device adapting to high water-level amplitude
CN103437341A (en) * 2013-07-29 2013-12-11 中铁十六局集团北京轨道交通工程建设有限公司 Effective grooving construction method for underground continuous wall in slightly-weathered limestone with overlying sandy soil
CN104196044A (en) * 2014-09-05 2014-12-10 中铁四局集团有限公司 Cofferdam construction method with grooves milled through limited hole forming of percussion drill combined with steel sheet piles
CN104763324A (en) * 2015-04-01 2015-07-08 上海强劲地基工程股份有限公司 Large-diameter hole forming construction equipment for core drilling rock entering and construction method thereof
CN105804079A (en) * 2016-03-31 2016-07-27 大连久鼎祥瑞特种工程技术研究院有限公司 Tool and method for smashing hard rock in large-diameter pile hole
CN106351241A (en) * 2016-08-28 2017-01-25 中铁二十局集团有限公司 Deep-water foundation construction method for large-span continuous beam adjacent to existing railway line
CN106968176A (en) * 2017-03-24 2017-07-21 中建三局基础设施工程有限公司 A kind of embedding batholith foundation construction of bridge deepwater
CN107503345A (en) * 2017-09-27 2017-12-22 中铁二十局集团有限公司 A kind of deep water foundation pile foundation construction process

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110130393A (en) * 2019-05-22 2019-08-16 中铁四局集团有限公司 A kind of underwater foundation pit drilling of soft rock and punching point arrangement method
CN111119212A (en) * 2019-12-18 2020-05-08 中建三局基础设施建设投资有限公司 Construction method for sinking double-wall steel cofferdam under deep clay layer condition
CN111119213A (en) * 2019-12-18 2020-05-08 中建三局基础设施建设投资有限公司 Double-wall steel cofferdam with open edge feet and construction method thereof

Also Published As

Publication number Publication date
CN108179759B (en) 2020-06-26

Similar Documents

Publication Publication Date Title
CN107524142A (en) A kind of holing with slurry wall protection cast-in-place pile construction method
CN106638640A (en) Modular coffer construction method for concrete without subsealing in the geologic condition of stratum
CN112392400B (en) Hole forming construction process for slope protection pile in complex geological environment
CN109555116A (en) A kind of high density karst intense development area fully-sleeved filled pile construction method
CN106400782A (en) Construction method for construction of foundation pit support bored secant pile walls with rotary drilling rig
CN110735600B (en) Mechanical pore-forming pile construction process for karst geology
CN102953341A (en) Overhead trestle structure built on non-covering steep bare rocks in deep rapids
CN110629747A (en) Full-casing full-rotation construction process for pile foundation under complex geological conditions
CN108166483A (en) Bored pile construction method
CN110939303B (en) Semi-reverse construction method of cyclone pool
CN106930276A (en) The deep hole blasting of rotary digging bored concrete pile and the construction method of conduit rotary digging removing obstacles
CN104264683B (en) Building concave shape ultra-deep foundation pit subregion supporting method is protected for three around literary composition
CN102979039A (en) Elevated trestle bridge construction method on covering-free steep bare rock in deepwater and rapid stream
CN113550340A (en) Construction method of deepwater foundation of double-wall steel cofferdam without sealing bottom under deepwater rock entering condition
CN108179759A (en) The underwater drill core slotting of driftway is without bottom sealing method
CN113174958A (en) Construction method for foundation pit of adjacent road under poor ground condition
CN106758759B (en) A kind of trestle pile foundation and its anchoring process for deep water drift net riverbed
CN110359476A (en) A kind of construction method of steel sheet-pile cofferdam inner support and drilled pile steel pile casting installation operation platform
CN107653878A (en) Cast-in-situ bored pile is reusable to be longitudinally separated formula steel pile casting construction
CN104314071A (en) Construction method of underground diaphragm wall by employing rotary drilling rig
CN112281880A (en) Construction method of complex stratum long spiral hole-leading inserting-driving locking opening steel pipe pile cofferdam
CN105714748A (en) Excavating construction method for surge shaft in gravel and sandy soil layer
CN107059914A (en) A kind of ring-type for being used for shallow overburden or naked rock area in water is embedded to set basis
CN110080779A (en) Tunnel tunnel bottom karst cave treatment construction method
CN207109804U (en) A kind of quick spreading structure configuration of soft soil foundation bored concrete pile

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200626