CN107974876A - Existing railway increases road construction dike multiline pile earth-retaining construction - Google Patents

Existing railway increases road construction dike multiline pile earth-retaining construction Download PDF

Info

Publication number
CN107974876A
CN107974876A CN201711342956.XA CN201711342956A CN107974876A CN 107974876 A CN107974876 A CN 107974876A CN 201711342956 A CN201711342956 A CN 201711342956A CN 107974876 A CN107974876 A CN 107974876A
Authority
CN
China
Prior art keywords
existing railway
web
breast boards
stake
dike
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711342956.XA
Other languages
Chinese (zh)
Inventor
唐第甲
吴沛沛
李安洪
叶世斌
龚建辉
姚裕春
周成
李楚根
曾永红
李宁
田辉
冉令
胡会星
张健
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Eryuan Engineering Group Co Ltd CREEC
Original Assignee
China Railway Eryuan Engineering Group Co Ltd CREEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Eryuan Engineering Group Co Ltd CREEC filed Critical China Railway Eryuan Engineering Group Co Ltd CREEC
Priority to CN201711342956.XA priority Critical patent/CN107974876A/en
Publication of CN107974876A publication Critical patent/CN107974876A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B2/00General structure of permanent way

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)

Abstract

Existing railway increases road construction dike multiline pile earth-retaining construction, effectively to solve the problems, such as that existing railway increases road construction dike earth-retaining closing slope, ensures existing railway operation security, saves reconstruction project investment.Armored concrete supporter is set outside existing railway slope foot, and armored concrete supporter has the rectangle breast boards erect, web, and web is perpendicular to rectangle breast boards front face.Stake after stake, antidumping before basis is set in the stratum below the rectangle breast boards, web, and the upper end of stake is rigidly connected with rectangle breast boards before basis, and the upper end of stake is rigidly connected with web after antidumping.Increase road construction dike to fill out on existing railway in rectangle breast boards plate face rear side.

Description

Existing railway increases road construction dike multiline pile earth-retaining construction
Technical field
The present invention relates to existing railway to increase road construction dike earth-retaining technical field, and more particularly to existing railway increases road construction dike multiline pile Earth-retaining constructs.
Technical background
Currently, as the quick of China railways cause is flourished, when existing railway cannot meet capacity development need, Need to carry out increasing on existing railway to build two wires engineering.Increasing build in rail process, it is necessary to one lateral wall of existing railway it is wide fill it is new Road construction base, since land used is nervous or engineering reasons, often needs closing slope earth-retaining.Traditional Gravity Retaining Wall, embankment pile plate wall Deng rigid earth-retaining construction there are structure height is limited, horizontal earth-retaining scarce capacity, it is high to ground requirement for bearing capacity the problems such as;Reinforcement The flexibility earth-retaining construction such as native barricade, Cantilever Retaining Wall, which is deposited, to be needed to excavate existing railway side slope in the construction process, seriously affects iron The problem of road operation security.Therefore, there is an urgent need to a kind of earth-retaining ability is strong, structure height is big, easy construction, it is applied widely, Ensure that the construction of existing railway operation security solves above-mentioned problem.
The content of the invention
The technical problems to be solved by the invention are to provide a kind of existing railway and increase road construction dike multiline pile earth-retaining construction, to have Effect solves the problems, such as that existing railway increases road construction dike earth-retaining closing slope, ensures existing railway operation security, saves reconstruction project investment.
Technical solution is as follows used by the present invention solves above-mentioned technology:
The existing railway of the present invention increases road construction dike multiline pile earth-retaining construction, including existing railway, it is characterized in that:It is described existing Armored concrete supporter is set outside railway slope foot, and armored concrete supporter has the rectangle breast boards erect, web, web Perpendicular to rectangle breast boards front face;In stratum below the rectangle breast boards, web before setting basis after stake, antidumping , the upper end of stake is rigidly connected with rectangle breast boards before basis, the upper end of stake and web rigid connection after antidumping;Increase road construction dike Filled out in rectangle breast boards plate face rear side on existing railway.
The invention has the advantages that the closing slope earth-retaining problem that existing railway increases road construction dike can be solved effectively, weight is overcome Power formula barricade, embankment pile plate wall, reinforced earth bulkhead, the structure height of Cantilever Retaining Wall be limited, horizontal earth-retaining scarce capacity, serious Influence the problem of railway operation is safe.Earth-retaining ability is strong, and structure height is big, and easy construction is applied widely, it is ensured that existing iron The advantages of road operation security, and engineering land used 30%, construction investment 15% can be saved, there is good economy and ecological benefits.
Brief description of the drawings
This specification includes following three width attached drawing:
Fig. 1 is the sectional drawing that existing railway of the present invention increases road construction dike multiline pile earth-retaining construction;
Fig. 2 is the axonometric drawing that existing railway of the present invention increases road construction dike multiline pile earth-retaining constructed embodiment 1;
Fig. 3 is the axonometric drawing that existing railway of the present invention increases road construction dike multiline pile earth-retaining constructed embodiment 2;
Main member, toponym and corresponding mark are shown in figure:Increase road construction dike A, existing railway B, reinforced concrete Stake 22 after stake 21, antidumping before native supporter 10, rectangle breast boards 11, web 12, basis.
Embodiment
The present invention is further illustrated below by specific embodiment and with reference to attached drawing.
Referring to Figures 1 and 2, existing railway increases road construction dike multiline pile earth-retaining construction, including existing railway B, the existing iron Armored concrete supporter 10 is set outside the B slope foots of road, and armored concrete supporter 10 has the rectangle breast boards 11 erect, web 12, web 12 is perpendicular to 11 front face of rectangle breast boards;Basis is set in stratum below the rectangle breast boards 11, web 12 Stake 22 after preceding stake 21, antidumping, the upper end of stake 21 is rigidly connected with rectangle breast boards 11 before basis, the upper end of stake 22 after antidumping It is rigidly connected with web 12;Increase road construction dike A to fill out on existing railway B in 11 plate face rear side of rectangle breast boards.
With reference to Fig. 1, rectangle breast boards 11, which blocks, increases road construction dike A, and the supporting rectangle of stake 21 breast boards 11 before basis, web 12 carries For the horizontal supporting force to rectangle breast boards 11, stake 22 supports trapezoidal web panels 2 after antidumping, so that the level that will increase road construction dike A Pressure conversion is the vertical pressure to stake after antidumping 22, tries hard to keep what card earth-retaining constructed by the vertical support of stake after antidumping 22 Monolithic stability.Have the characteristics that earth-retaining ability is strong, structure height is big, easy construction and applied widely, and need not excavate The slope foot of existing railway B, can effectively ensure that guarantee existing railway operation security in work progress.
With reference to Fig. 3, to adapt to increase the different situations of road construction dike A, the web 12 can be along between the width of rectangle breast boards 11 Stake 21 can be also arranged at intervals along the width of rectangle breast boards 11 before setting, basis.
With reference to Fig. 1, the web 12 and the cast-in-place formation armored concrete supporter 10 of rectangle breast boards 11, the steel of web 12 Muscle is stretched into rectangle breast boards 11.To save concrete amount, the plate face of the web 12 is in up-small and down-big trapezoidal.The base The reinforcing bar of stake 22 is respectively protruding into rectangle breast boards 11, in web 12 after stake 21, antidumping before plinth.
Some originals described above for simply increasing road construction dike multiline pile earth-retaining using existing railway of the present invention is illustrated and constructing Reason, be not intended to by the present invention be confined to shown in and the concrete structure and the scope of application in, therefore every be possible to sharp Corresponding modification and equivalent, belong to the apllied the scope of the claims of the present invention.

Claims (6)

1. existing railway increases road construction dike multiline pile earth-retaining construction, including existing railway (B), it is characterized in that:The existing railway (B) Setting armored concrete supporter (10) outside slope foot, rectangle breast boards (11) of the armored concrete supporter (10) with setting, Web (12), web (12) is perpendicular to rectangle breast boards (11) front face;Below the rectangle breast boards (11), web (12) Stake (22) after stake (21), antidumping before basis is set in stratum, the upper end of stake (21) and rectangle breast boards (11) rigidity before basis Connection, the upper end of stake (22) is rigidly connected with web (12) after antidumping;Increase road construction dike (A) after rectangle breast boards (11) plate face Side is filled out on existing railway (B).
2. existing railway as claimed in claim 1 increases road construction dike multiline pile earth-retaining construction, it is characterized in that:Web (12) edge The width of rectangle breast boards (11) is arranged at intervals.
3. existing railway as claimed in claim 1 increases road construction dike multiline pile earth-retaining construction, it is characterized in that:The web (12) Plate face in up-small and down-big trapezoidal.
4. the existing railway as described in claim 1,2 or 3 increases road construction dike multiline pile earth-retaining construction, it is characterized in that:The web (12) rectangle breast boards is stretched into the cast-in-place formation armored concrete supporter (10) of rectangle breast boards (11), the reinforcing bar of web (12) (11) in.
5. existing railway as claimed in claim 1 increases road construction dike multiline pile earth-retaining construction, it is characterized in that:Stake before the basis (21) it is arranged at intervals along the width of rectangle breast boards (11).
6. existing railway as claimed in claim 1 increases road construction dike multiline pile earth-retaining construction, it is characterized in that:Stake before the basis (21), the reinforcing bar of stake (22) is respectively protruding into rectangle breast boards (11), web (12) after antidumping.
CN201711342956.XA 2017-12-14 2017-12-14 Existing railway increases road construction dike multiline pile earth-retaining construction Pending CN107974876A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711342956.XA CN107974876A (en) 2017-12-14 2017-12-14 Existing railway increases road construction dike multiline pile earth-retaining construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711342956.XA CN107974876A (en) 2017-12-14 2017-12-14 Existing railway increases road construction dike multiline pile earth-retaining construction

Publications (1)

Publication Number Publication Date
CN107974876A true CN107974876A (en) 2018-05-01

Family

ID=62006546

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711342956.XA Pending CN107974876A (en) 2017-12-14 2017-12-14 Existing railway increases road construction dike multiline pile earth-retaining construction

Country Status (1)

Country Link
CN (1) CN107974876A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110144767A (en) * 2019-04-03 2019-08-20 中铁第四勘察设计院集团有限公司 Help broad way based structures and construction method
CN111945484A (en) * 2020-08-06 2020-11-17 兰州交通大学 Existing-newly-built parallel row pile plate wall retaining structure and construction method

Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20010019548A (en) * 1999-08-27 2001-03-15 이창남 The SEN Retaining Wall
KR20090076688A (en) * 2008-01-09 2009-07-13 코오롱건설주식회사 Prestressed h-pile and soil retaining method for two rows pile using the same
CN202730795U (en) * 2012-06-29 2013-02-13 深圳市工勘岩土工程有限公司 Pile supporting buttressed retaining wall structure
CN202865868U (en) * 2012-09-01 2013-04-10 中铁二院工程集团有限责任公司 Cantilever-type counterfort-type retaining wall of pile foundation
CN103243738A (en) * 2013-01-10 2013-08-14 何成俊 Foundation for open type retaining wall with reinforced concrete frame
JP2013174049A (en) * 2012-02-23 2013-09-05 Taisei Corp Extension method for earth retaining wall and earth retaining wall structure
CN103321243A (en) * 2013-07-09 2013-09-25 中铁第四勘察设计院集团有限公司 Micro pile and retaining wall combined type limited embankment protection structure
JP5490300B1 (en) * 2013-10-15 2014-05-14 株式会社フジコーポレーション Retaining wall structure and retaining wall construction method
CN203782745U (en) * 2014-04-03 2014-08-20 中铁二院工程集团有限责任公司 Structure of earth-retaining wall at high embankment of steep slope at multi-track railway station
JP2015063843A (en) * 2013-09-25 2015-04-09 鹿島建設株式会社 Retaining wall of reinforced concrete
CN104988948A (en) * 2015-06-29 2015-10-21 西南交通大学 Rib plate type retaining wall and construction method thereof
CN104988949A (en) * 2015-07-27 2015-10-21 中铁二院贵阳勘察设计研究院有限责任公司 Soil layer pile plate buttress combined retaining wall
CN107254880A (en) * 2017-07-19 2017-10-17 中铁上海设计院集团有限公司 A kind of curb is combined retaining structure
CN207672345U (en) * 2017-12-14 2018-07-31 中铁二院工程集团有限责任公司 Existing railway increases road construction dike multiline pile earth-retaining construction

Patent Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20010019548A (en) * 1999-08-27 2001-03-15 이창남 The SEN Retaining Wall
KR20090076688A (en) * 2008-01-09 2009-07-13 코오롱건설주식회사 Prestressed h-pile and soil retaining method for two rows pile using the same
JP2013174049A (en) * 2012-02-23 2013-09-05 Taisei Corp Extension method for earth retaining wall and earth retaining wall structure
CN202730795U (en) * 2012-06-29 2013-02-13 深圳市工勘岩土工程有限公司 Pile supporting buttressed retaining wall structure
CN202865868U (en) * 2012-09-01 2013-04-10 中铁二院工程集团有限责任公司 Cantilever-type counterfort-type retaining wall of pile foundation
CN103243738A (en) * 2013-01-10 2013-08-14 何成俊 Foundation for open type retaining wall with reinforced concrete frame
CN103321243A (en) * 2013-07-09 2013-09-25 中铁第四勘察设计院集团有限公司 Micro pile and retaining wall combined type limited embankment protection structure
JP2015063843A (en) * 2013-09-25 2015-04-09 鹿島建設株式会社 Retaining wall of reinforced concrete
JP5490300B1 (en) * 2013-10-15 2014-05-14 株式会社フジコーポレーション Retaining wall structure and retaining wall construction method
CN203782745U (en) * 2014-04-03 2014-08-20 中铁二院工程集团有限责任公司 Structure of earth-retaining wall at high embankment of steep slope at multi-track railway station
CN104988948A (en) * 2015-06-29 2015-10-21 西南交通大学 Rib plate type retaining wall and construction method thereof
CN104988949A (en) * 2015-07-27 2015-10-21 中铁二院贵阳勘察设计研究院有限责任公司 Soil layer pile plate buttress combined retaining wall
CN107254880A (en) * 2017-07-19 2017-10-17 中铁上海设计院集团有限公司 A kind of curb is combined retaining structure
CN207672345U (en) * 2017-12-14 2018-07-31 中铁二院工程集团有限责任公司 Existing railway increases road construction dike multiline pile earth-retaining construction

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110144767A (en) * 2019-04-03 2019-08-20 中铁第四勘察设计院集团有限公司 Help broad way based structures and construction method
CN110144767B (en) * 2019-04-03 2024-06-07 中铁第四勘察设计院集团有限公司 Side-width roadbed structure and construction method
CN111945484A (en) * 2020-08-06 2020-11-17 兰州交通大学 Existing-newly-built parallel row pile plate wall retaining structure and construction method

Similar Documents

Publication Publication Date Title
CN103866694B (en) Deep water silty sand ground geology large span multi-line hardened system and jacking culvert construction method
CN103410156B (en) Support space enclosing structure and application process thereof before a kind of recyclable vertical type steel pipe
CN103437567A (en) Method for supporting existing building underground added storey through original pile foundations
CN203296038U (en) High embankment chair-type sheet-pile retaining wall structure
CN107419731A (en) A kind of board-like double-row pile foundation pit support structure of counterfort and its construction method
CN202865855U (en) Stabilizing plate type anchoring pile retaining structure
CN102839686A (en) Stabilizing plate type anchor pile retaining structure
CN107974876A (en) Existing railway increases road construction dike multiline pile earth-retaining construction
CN203741848U (en) Steel tube plate type retaining structure
CN207525567U (en) A kind of pile plate composite structure suitable for Steep Slope Embankment
CN207672345U (en) Existing railway increases road construction dike multiline pile earth-retaining construction
CN203768914U (en) Foundation pit bracing diagonal support pile structure
CN204456180U (en) Folded plate pile retaining wall
CN103410155B (en) A kind of recyclable preposition assembling braced cuts structure and application process thereof
CN212533575U (en) Waterside hanging wall high retaining wall fill section widen embankment structure
CN203113335U (en) Counterfort type U-type groove retaining structure
CN205617160U (en) Low distributed switch foundation structure of circuit rib post that puts of moderate -low speed magnetic levitation
CN205529734U (en) A U -shaped retaining structure for filling road bed
CN204456182U (en) Vertical anchorage pile retaining wall
CN204940310U (en) A kind of combination retaining structure
CN108130826A (en) A kind of karst railway bed substrate antidumping foundation reinforcing structure
CN207267994U (en) Corrugated sheet steel formula retaining wall
CN104532787B (en) A kind of high-piled slab & girder wharf rear connects the gear indigenous method of bank
CN209339172U (en) A kind of novel peg board composite foundation
CN209603332U (en) Concrete mixing station feed bin net formula fills soft partition wall

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20180501