CN107881891A
CN107881891A CN201711262968.1A CN201711262968A CN107881891A CN 107881891 A CN107881891 A CN 107881891A CN 201711262968 A CN201711262968 A CN 201711262968A CN 107881891 A CN107881891 A CN 107881891A
Authority
CN
China
Prior art keywords
soft soil
concrete
construction method
bed course
layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711262968.1A
Other languages
Chinese (zh)
Inventor
陈庆君
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changchun Municipal Construction (group) Co Ltd
Original Assignee
Changchun Municipal Construction (group) Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changchun Municipal Construction (group) Co Ltd filed Critical Changchun Municipal Construction (group) Co Ltd
Priority to CN201711262968.1A priority Critical patent/CN107881891A/en
Publication of CN107881891A publication Critical patent/CN107881891A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C21/00Apparatus or processes for surface soil stabilisation for road building or like purposes, e.g. mixing local aggregate with binder
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C3/00Foundations for pavings
    • E01C3/04Foundations produced by soil stabilisation
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/12Consolidating by placing solidifying or pore-filling substances in the soil

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Architecture (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Soil Sciences (AREA)
  • General Engineering & Computer Science (AREA)
  • Agronomy & Crop Science (AREA)
  • Road Paving Structures (AREA)

Abstract

The invention discloses a kind of soft soil roadbed construction method of municipal administration,Including Soft Soil Layer,Basic unit's groove is provided with the top of the Soft Soil Layer,Basic unit's bottom land end is extended in Soft Soil Layer,It is bottom-up in basic unit's groove to be disposed with hard stratum,Bed course,Concrete strengthening layer and diaphragm,The concrete strengthening layer is provided with the cross reinforcing that a row uniformly arranges and the vertical strengthening ribs that a row uniformly arranges,The cross reinforcing bottom is provided with load bearing support muscle,The load bearing support muscle runs through concrete strengthening layer,Bed course and hard stratum,And extend in Soft Soil Layer,The present invention to soft soil roadbed by carrying out distributed back-up coat setting,Improve the bearing capacity of roadbed,And roadbed is set to be not easy and cave in,Improve the service life of roadbed,And when injecting concrete,Concrete and addition coagulator of each back-up coat from varying strength,So as to effectively raise the quality of roadbed,And this construction method is simple,Easily implement.

Description

A kind of soft soil roadbed construction method of municipal administration
Technical field
The present invention relates to a kind of soft soil roadbed technical field of construction of municipal administration, more particularly to a kind of municipal administration is soft soil roadbed to be applied Work method.
Background technology
The complicated component of weak soil, contain the Chemical Genesis such as substantial amounts of carbonate and evaporite material and humic soil chip etc. Biogenesis material, soft scholar are usually to deposit to form in flowing water environment, with silt particle and obvious stratification are presented, area Otherness is larger, soft soil roadbed mainly to have following several respects feature:It is soft soil roadbed that there is the spy that water content is higher, hole is bigger Point;Weak soil has obvious structural;With obvious rheological characteristic;Compressibility is high, bad hydraulic permeability;Shear strength is very low.
Road is built in soft clay area, the problems such as road settlement deforms often occurs, the use of road is had a strong impact on, and And huge economic loss is therefore caused, or even irreparable consequence is caused, in recent years, with expanding economy, city rule Mould constantly expands, and the urban road that China is completed and built at present, the roadbed in many regions is soft soil roadbed, Soft Soil Layer Thicker, distributed more widely, soft soil roadbed processing work turns into the emphasis of road construction research, generally, soft soil roadbed to city road The adverse effect on road is mainly due to soft soil roadbed shearing strength deficiency, it is difficult to the load action of road surface transmission is born, in lotus It is soft soil roadbed under load effect to produce locally or globally failure by shear, so as to produce road surface embankment landslide, unstability, cause road The destruction of structure sheaf, therefore, it is necessary to solve the above problems to invent a kind of soft soil roadbed construction method of municipal administration.
The content of the invention
It is an object of the invention to provide a kind of soft soil roadbed construction method of municipal administration, to solve to carry in above-mentioned background technology The problem of going out.
To achieve the above object, the present invention provides following technical scheme:A kind of soft soil roadbed construction method of municipal administration, including Soft Soil Layer, the Soft Soil Layer top are provided with basic unit's groove, and basic unit's bottom land end is extended in Soft Soil Layer, in basic unit's groove certainly It is disposed with hard stratum, bed course, concrete strengthening layer and diaphragm upwards down, it is equal that the concrete strengthening layer is provided with a row The vertical strengthening ribs that the cross reinforcing of even arrangement and a row uniformly arrange, the cross reinforcing bottom are provided with load bearing support Muscle, the load bearing support muscle runs through concrete strengthening layer, bed course and hard stratum, and extends in Soft Soil Layer, the bed course both sides Top is provided with breast boards, and the breast boards side is provided with limiting plate, and described limiting plate one end is extended in Soft Soil Layer;
The construction method installation following steps are carried out:
Step 1:Grooving flattens:Grooving is carried out with digging machine on Soft Soil Layer, and after grooving terminates, enters walking along the street with road roller The flat processing of face pressure;
Step 2:The processing of pre-buried and bed course:It is pre-buried some with vertical strengthening ribs in hard stratum after pressing, and vertically add Strengthening tendons bottom extends in Soft Soil Layer and fixed, and then tentatively pours into concrete to pan soil layer surface;
Step 3:Breast boards and reinforcement arrangement:It is artificial to carry out breast boards arrangement and add when mat surface concrete layer solidifies Strengthening tendons is arranged;
Step 4:Back-up coat is set:After reinforcement and breast boards arrange, a certain amount of concrete stirring is poured into bed course Liquid;
Step 5:Manually smooth out with the fingers gentle protection:After concrete stirring liquid injection terminates, manually progress surface is smoothed out with the fingers flat, after smoothing out with the fingers flat, In concrete stirring liquid surface laying diaphragm.
Preferably, grooving depth is arranged between 20cm-30cm in step 1.
Preferably, cushion thickness is arranged between 5cm-8cm in step 2, and vertical strengthening ribs top is pre- apart from bed course top Staying height, concrete uses C15 standard concretes between 7cm-10cm, and according to its component and the mass fraction of each component For cement:Stone:Gravel:Water:Coagulator=1:4:2:0.6:0.02 match ratio.
Preferably, the breast boards in step 3 is the smooth wooden boards in surface, the earth-retaining plate thickness be 2cm-4cm it Between, the breast boards is highly between 40cm-50cm.
Preferably, the concrete stirring liquid employed in step 4 is arranged to C25 standard concretes, and according to its component And the mass fraction of each component is cement:Stone:Gravel:Water:Coagulator=1:1.7:1:0.4:0.01 match ratio.
Preferably, antifreeze is also contained in the C25 standard concretes, and its component accounts for the match ratio of mixed liquor and is 0.008。
Preferably, also contain later maintenance in step 5, when concrete tentatively solidifies, raise diaphragm every three days, And sprinkled water toward concrete surface, after this process is until carry out 3-4 times, remove diaphragm.
The technique effect and advantage of the present invention:The present invention is carried by carrying out distributed back-up coat setting to soft soil roadbed The high bearing capacity of roadbed, and roadbed is not easy and is caved in, the service life of roadbed is improved, and in injection concrete When, each back-up coat selects the concrete and addition coagulator of varying strength, so as to effectively raise the quality of roadbed, and This construction method is simple, easily implements.
Brief description of the drawings
Fig. 1 is road structure schematic diagram of the present invention.
Figure:1 Soft Soil Layer, 2 basic unit's grooves, 3 hard stratums, 4 bed courses, 5 concrete strengthening layers, 6 diaphragms, 7 cross reinforcings, 8 Vertical strengthening ribs, 9 load bearing support muscle, 10 breast boards, 11 limiting plates.
Embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clear, complete Site preparation describes, it is clear that described embodiment is only part of the embodiment of the present invention, rather than whole embodiments, is based on Embodiment in the present invention, those of ordinary skill in the art are obtained every other under the premise of creative work is not made Embodiment, belong to the scope of protection of the invention.
A kind of soft soil roadbed construction method of municipal administration according to Fig. 1, including Soft Soil Layer 1, the top of Soft Soil Layer 1 are set Basic unit's groove 2 is equipped with, the bottom of basic unit's groove 2 is extended in Soft Soil Layer 1, bottom-up in basic unit's groove 2 to be disposed with firmly Soil layer 3, bed course 4, concrete strengthening layer 5 and diaphragm 6, the concrete strengthening layer 5 are provided with the transverse direction that a row uniformly arranges The vertical strengthening ribs 8 that the row of reinforcement 7 and one uniformly arranges, the bottom of cross reinforcing 7 is provided with load bearing support muscle 9, described Load bearing support muscle 9 runs through concrete strengthening layer 5, bed course 4 and hard stratum 3, and extends in Soft Soil Layer 1, the both sides of bed course 4 top End is provided with breast boards 10, and the side of breast boards 10 is provided with limiting plate 11, and described one end of limiting plate 11 extends to Soft Soil Layer 1 It is interior.
During hot environment:
A kind of soft soil roadbed construction method of municipal administration, specific preparation process are as follows:
Step 1:Groove flattens:Grooving is carried out with digging machine on Soft Soil Layer 1, institute's grooving depth is arranged between 20cm-30cm, and And after grooving terminates, road surface pressing processing is carried out with road roller;
Step 2:Pre-buried and bed course 4 is handled:It is pre-buried some with vertical strengthening ribs 8 in hard stratum 3 after pressing, and erect Extended to the bottom of reinforcement 8 in Soft Soil Layer 1 fixed, the thickness of bed course 4 is arranged between 5cm-8cm, the top of vertical strengthening ribs 8 away from From the reserved height in the top of bed course 4 between 7cm-10cm, then tentatively pour into using C15 standard concretes, and according to its group Divide and the mass fraction of each component is cement:Stone:Gravel:Water:Coagulator=1:4:2:0.6:0.02 match ratio pours into pan soil 3 surface of layer;
Step 3:Breast boards 10 and reinforcement arrangement:It is artificial to carry out the cloth of breast boards 10 when the surface concrete layer of bed course 4 solidifies Put and arranged with reinforcement, selected breast boards 10 is the smooth wooden boards in surface, and the thickness of breast boards 10 is 2cm-4cm Between, the height of breast boards 10 avoids the weak soil pollution concrete solution in Soft Soil Layer 1 between 40cm-50cm, so as to Roadbed is impacted;
Step 4:Back-up coat is set:After reinforcement and breast boards 10 arrange, a certain amount of C25 standards are poured into bed course 4 Concrete, and be cement according to the mass fraction of its component and each component:Stone:Gravel:Water:Coagulator=1:1.7:1: 0.4:0.01 match ratio concrete stirring liquid;
Step 5:Manually smooth out with the fingers gentle protection:After concrete stirring liquid injection terminates, manually progress surface is smoothed out with the fingers flat, after smoothing out with the fingers flat, In concrete stirring liquid surface laying diaphragm 6, when concrete tentatively solidifies, diaphragm 6 is raised every three days, and it is past mixed Coagulate native surface to be sprinkled water, avoid in solidification, water deficient in concrete, cause to crack, so as to influence the quality of roadbed, After this process is until carry out 3-4 times, diaphragm 6 is removed, so as to reach the purpose of the present invention.
During high/low temperature temperature environment:
A kind of soft soil roadbed construction method of municipal administration, specific preparation process are as follows:
Step 1:Groove flattens:Grooving is carried out with digging machine on Soft Soil Layer 1, institute's grooving depth is arranged between 20cm-30cm, and And after grooving terminates, road surface pressing processing is carried out with road roller;
Step 2:Pre-buried and bed course 4 is handled:It is pre-buried some with vertical strengthening ribs 8 in hard stratum 3 after pressing, and erect Extended to the bottom of reinforcement 8 in Soft Soil Layer 1 fixed, the thickness of bed course 4 is arranged between 5cm-8cm, the top of vertical strengthening ribs 8 away from From the reserved height in the top of bed course 4 between 7cm-10cm, then tentatively pour into using C15 standard concretes, and according to its group Divide and the mass fraction of each component is cement:Stone:Gravel:Water:Coagulator=1:4:2:0.6:0.02 match ratio pours into pan soil 3 surface of layer;
Step 3:Breast boards 10 and reinforcement arrangement:It is artificial to carry out the cloth of breast boards 10 when the surface concrete layer of bed course 4 solidifies Put and arranged with reinforcement, selected breast boards 10 is the smooth wooden boards in surface, and the thickness of breast boards 10 is 2cm-4cm Between, the height of breast boards 10 avoids the weak soil pollution concrete solution in Soft Soil Layer 1 between 40cm-50cm, so as to Roadbed is impacted;
Step 4:Back-up coat is set:After reinforcement and breast boards 10 arrange, a certain amount of C25 standards are poured into bed course 4 Concrete, and be cement according to the mass fraction of its component and each component:Stone:Gravel:Water:Coagulator:Antifreeze=1: 1.7:1:0.4:0.01:0.008 match ratio concrete stirring liquid, the addition of antifreeze, is avoided in arctic weather, low temperature Frostbite is caused to concrete;
Step 5:Manually smooth out with the fingers gentle protection:After concrete stirring liquid injection terminates, manually progress surface is smoothed out with the fingers flat, after smoothing out with the fingers flat, In concrete stirring liquid surface laying diaphragm 6, when concrete tentatively solidifies, diaphragm 6 is raised every three days, and it is past mixed Coagulate native surface to be sprinkled water, avoid in solidification, water deficient in concrete, cause to crack, so as to influence the quality of roadbed, After this process is until carry out 3-4 times, diaphragm 6 is removed, so as to reach the purpose of the present invention.
Finally it should be noted that:The preferred embodiments of the present invention are the foregoing is only, are not intended to limit the invention, Although the present invention is described in detail with reference to the foregoing embodiments, for those skilled in the art, it still may be used To be modified to the technical scheme described in foregoing embodiments, or equivalent substitution is carried out to which part technical characteristic, Within the spirit and principles of the invention, any modification, equivalent substitution and improvements made etc., it should be included in the present invention's Within protection domain.

Claims (7)

  1. A kind of 1. soft soil roadbed construction method of municipal administration, it is characterised in that:Including Soft Soil Layer(1), the Soft Soil Layer(1)Top is set It is equipped with basic unit's groove(2), basic unit's groove(2)Bottom extends to Soft Soil Layer(1)It is interior, basic unit's groove(2)It is interior it is bottom-up successively It is provided with hard stratum(3), bed course(4), concrete strengthening layer(5)And diaphragm(6), the concrete strengthening layer(5)It is provided with The cross reinforcing that one row uniformly arranges(7)The vertical strengthening ribs uniformly arranged with a row(8), the cross reinforcing(7)Bottom End is provided with load bearing support muscle(9), the load bearing support muscle(9)Through concrete strengthening layer(5), bed course(4)And hard stratum (3), and extend to Soft Soil Layer(1)It is interior, the bed course(4)Both sides top is provided with breast boards(10), the breast boards(10)One Side is provided with limiting plate(11), the limiting plate(11)One end extends to Soft Soil Layer(1)It is interior;
    The construction method installation following steps are carried out:
    Step 1:Grooving flattens:In Soft Soil Layer(1)On with digging machine carry out grooving, and after grooving terminates, carried out with road roller Road surface pressing processing;
    Step 2:Pre-buried and bed course(4)Processing:Hard stratum after pressing(3)It is interior pre-buried some with vertical strengthening ribs(8), And vertical strengthening ribs(8)Bottom extends to Soft Soil Layer(1)Interior fixation, concrete is then tentatively poured into hard stratum(3)Surface;
    Step 3:Breast boards(10)Arranged with reinforcement:Work as bed course(4)When surface concrete layer solidifies, breast boards is manually carried out (10)Arrangement and reinforcement arrangement;
    Step 4:Back-up coat is set:When reinforcement and breast boards(10)After arranging, to bed course(4)Inside pour into a certain amount of mixed Solidifying soil stirring liquid;
    Step 5:Manually smooth out with the fingers gentle protection:After concrete stirring liquid injection terminates, manually progress surface is smoothed out with the fingers flat, after smoothing out with the fingers flat, In concrete stirring liquid surface laying diaphragm(6).
  2. A kind of 2. soft soil roadbed construction method of municipal administration according to claim 1, it is characterised in that:Grooving is deep in step 1 Degree is arranged between 20cm-30cm.
  3. A kind of 3. soft soil roadbed construction method of municipal administration according to claim 1, it is characterised in that:Bed course in step 2 (4)Thickness is arranged between 5cm-8cm, vertical strengthening ribs(8)Top is apart from bed course(4)The reserved height in top for 7cm-10cm it Between, concrete uses C15 standard concretes, and is cement according to the mass fraction of its component and each component:Stone:Gravel: Water:Coagulator=1:4:2:0.6:0.02 match ratio.
  4. A kind of 4. soft soil roadbed construction method of municipal administration according to claim 1, it is characterised in that:Earth-retaining in step 3 Plate(10)For the wooden boards that surface is smooth, the breast boards(10)Thickness is between 2cm-4cm, the breast boards(10)Highly Between 40cm-50cm.
  5. A kind of 5. soft soil roadbed construction method of municipal administration according to claim 1, it is characterised in that:Employed in step 4 Concrete stirring liquid be arranged to C25 standard concretes, and be cement according to the mass fraction of its component and each component:Stone Son:Gravel:Water:Coagulator=1:1.7:1:0.4:0.01 match ratio.
  6. A kind of 6. soft soil roadbed construction method of municipal administration according to claim 1 or 5, it is characterised in that:The C25 standards Also contain antifreeze in concrete, and it is 0.008 that its component, which accounts for the match ratio of mixed liquor,.
  7. A kind of 7. soft soil roadbed construction method of municipal administration according to claim 1, it is characterised in that:Also contain in step 5 Later maintenance, when concrete tentatively solidifies, diaphragm is raised every three days(6), and sprinkled water toward concrete surface, this After process is until carry out 3-4 times, diaphragm is removed(6).
CN201711262968.1A 2017-12-04 2017-12-04 A kind of soft soil roadbed construction method of municipal administration Pending CN107881891A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711262968.1A CN107881891A (en) 2017-12-04 2017-12-04 A kind of soft soil roadbed construction method of municipal administration

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711262968.1A CN107881891A (en) 2017-12-04 2017-12-04 A kind of soft soil roadbed construction method of municipal administration

Publications (1)

Publication Number Publication Date
CN107881891A true CN107881891A (en) 2018-04-06

Family

ID=61773090

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711262968.1A Pending CN107881891A (en) 2017-12-04 2017-12-04 A kind of soft soil roadbed construction method of municipal administration

Country Status (1)

Country Link
CN (1) CN107881891A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109183539A (en) * 2018-09-05 2019-01-11 辽宁工程技术大学 A kind of soft soil roadbed construction method
CN109295821A (en) * 2018-09-27 2019-02-01 王默 A kind of subgrade road reinforcing support construction
CN109577124A (en) * 2018-12-27 2019-04-05 舜元建设(集团)有限公司 Roadbed reinforcement means on the spot under a kind of saturated soft soil geological conditions
CN110331713A (en) * 2019-05-31 2019-10-15 浙江振升建设有限公司 A kind of reinforcement of foundation for soft ground
CN110735373A (en) * 2019-10-09 2020-01-31 北京夏都水利工程有限公司 field road construction method
CN112813756A (en) * 2019-11-18 2021-05-18 浙江金业建设有限公司 Roadbed based on municipal soft soil and construction method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0121003A1 (en) * 1983-03-31 1984-10-10 Sosrohadikoesoemo, Soearto, Ir. R. Ng. Ground plate
NL2003159C2 (en) * 2009-07-09 2011-01-12 Dijk Maasland B V Van METHOD FOR RENOVATING A ROAD CONSTRUCTION
CN106120523A (en) * 2016-07-05 2016-11-16 河海大学 A kind of integrated application stake and vertical earth working material process the construction method of highway soft foundation
CN106592363A (en) * 2016-11-29 2017-04-26 昆山顶牛市政建设有限公司 Construction method for municipal soft soil roadbed

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0121003A1 (en) * 1983-03-31 1984-10-10 Sosrohadikoesoemo, Soearto, Ir. R. Ng. Ground plate
NL2003159C2 (en) * 2009-07-09 2011-01-12 Dijk Maasland B V Van METHOD FOR RENOVATING A ROAD CONSTRUCTION
CN106120523A (en) * 2016-07-05 2016-11-16 河海大学 A kind of integrated application stake and vertical earth working material process the construction method of highway soft foundation
CN106592363A (en) * 2016-11-29 2017-04-26 昆山顶牛市政建设有限公司 Construction method for municipal soft soil roadbed

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109183539A (en) * 2018-09-05 2019-01-11 辽宁工程技术大学 A kind of soft soil roadbed construction method
CN109295821A (en) * 2018-09-27 2019-02-01 王默 A kind of subgrade road reinforcing support construction
CN109295821B (en) * 2018-09-27 2021-05-14 王默 Soft foundation road reinforcing and supporting structure
CN109577124A (en) * 2018-12-27 2019-04-05 舜元建设(集团)有限公司 Roadbed reinforcement means on the spot under a kind of saturated soft soil geological conditions
CN110331713A (en) * 2019-05-31 2019-10-15 浙江振升建设有限公司 A kind of reinforcement of foundation for soft ground
CN110735373A (en) * 2019-10-09 2020-01-31 北京夏都水利工程有限公司 field road construction method
CN112813756A (en) * 2019-11-18 2021-05-18 浙江金业建设有限公司 Roadbed based on municipal soft soil and construction method

Similar Documents

Publication Publication Date Title
CN107881891A (en) A kind of soft soil roadbed construction method of municipal administration
CN101368383B (en) Method for treating soft soil roadbed by artificial composite crust layer
CN102296507B (en) Treatment method of subgrade cracks
CN100439600C (en) Treatment method of newly built high way railway engineering soft foundation
CN105155510B (en) Method capable of carrying out microorganism solidifying and crusting on super soft foundation surface and matching device
CN109736291A (en) One kind owing consolidation and blows on the base of alluvial plain that biological cement is reinforcing road bed and its construction method
CN105586818A (en) Light foam layer for widening roadbed of road and construction process of light foam layer
CN107805987A (en) The hassock layer Foam lightweight soil road structure and construction method in deep soft foundation section
CN107700435A (en) The cementing rock-fill dams of rock-fill concrete core-wall and its construction method
CN101487254A (en) Construction method of vibrating immersed tube gravel slip-casting pile
CN101250868A (en) Precipitation prepressing association motivation induration deep densification method
CN106560559B (en) A kind of leakage preventing structure and construction method for city river
WO2019007176A1 (en) Foam light soil railway subgrade structure and construction method
CN108442724B (en) Earthen site crack repairing method
CN106592363B (en) A kind of construction method that municipal administration is soft soil roadbed
CN104674842B (en) Solidified earth barricade and constructional method thereof
CN103061224A (en) Method for thawing and strengthening permafrost foundations by quicklime-sand piles
CN104480956B (en) A kind of minor diameter mold-bagged concrete pile composite foundation
CN206015452U (en) A kind of Municipal Road Engineering roadbed
CN107724364A (en) A kind of construction technology of soft soil foundation
CN213772779U (en) Concrete road surface structure permeates water
CN207452609U (en) A kind of hassock layer Foam lightweight soil road structure in deep soft foundation section
CN104790282B (en) A kind of road surface with soft subgrade whitewashing processing means
CN104499394B (en) A kind of zero padding black cotton regur soil roadbed Treatment Methods
CN207878440U (en) A kind of reinforcement composite foundation structure suitable for soft soil foundation

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180406