CN107767973A - 核电厂乏燃料水池补充冷却装置 - Google Patents
核电厂乏燃料水池补充冷却装置 Download PDFInfo
- Publication number
- CN107767973A CN107767973A CN201610692265.1A CN201610692265A CN107767973A CN 107767973 A CN107767973 A CN 107767973A CN 201610692265 A CN201610692265 A CN 201610692265A CN 107767973 A CN107767973 A CN 107767973A
- Authority
- CN
- China
- Prior art keywords
- power plant
- spent
- nuclear
- cooling
- cooling device
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- G—PHYSICS
- G21—NUCLEAR PHYSICS; NUCLEAR ENGINEERING
- G21C—NUCLEAR REACTORS
- G21C15/00—Cooling arrangements within the pressure vessel containing the core; Selection of specific coolants
- G21C15/02—Arrangements or disposition of passages in which heat is transferred to the coolant; Coolant flow control devices
-
- G—PHYSICS
- G21—NUCLEAR PHYSICS; NUCLEAR ENGINEERING
- G21C—NUCLEAR REACTORS
- G21C15/00—Cooling arrangements within the pressure vessel containing the core; Selection of specific coolants
- G21C15/18—Emergency cooling arrangements; Removing shut-down heat
- G21C15/182—Emergency cooling arrangements; Removing shut-down heat comprising powered means, e.g. pumps
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E30/00—Energy generation of nuclear origin
- Y02E30/30—Nuclear fission reactors
Landscapes
- Physics & Mathematics (AREA)
- Engineering & Computer Science (AREA)
- Plasma & Fusion (AREA)
- General Engineering & Computer Science (AREA)
- High Energy & Nuclear Physics (AREA)
- Structure Of Emergency Protection For Nuclear Reactors (AREA)
Abstract
本发明公开了一种核电厂乏燃料水池补充冷却装置,其包括位于核岛厂房内的一回路和位于核岛厂房外的二回路,乏燃料水池中的乏池水能够在一回路中循环流动,一回路通过中间热交换器将热量输送至二回路,二回路中的流体通过冷却塔将热量排出。与现有技术相比,本发明通过双回路冷链设计,将乏池水限制在核岛厂房内,防止放射性物质发生意外在核岛厂房外泄漏,提升了装置的安全可靠性,显著提升了乏燃料水池的冷却能力,同时,本发明采用双模供电,并新增独立热阱,提高了乏燃料水池对全厂断电事故和热阱丧失事故的应急处理能力。
Description
技术领域
本发明属于核电领域,更具体地说,本发明涉及一种核电厂乏燃料水池补充冷却装置。
背景技术
核电厂中的乏燃料水池,用于存放历次换料中从堆芯卸出的乏燃料组件。乏燃料组件在乏燃料水池中产生一定的衰变热,需要乏燃料水池冷却***对其进行冷却,维持乏池水水温在一定温度以下,正常工况下防止水池温度过高损坏设备,事故工况下抑制乏池水沸腾,防止乏池水蒸干、燃料组件裸露融化而造成大量放射性物质外泄。
在压水堆核电厂中,已公开的乏燃料水池冷却***如图1虚线部分所示,其由两列冷却子***组成,每列子***包含1台循环冷却泵和1台管壳式换热器。核电厂换料大修时,两列冷却子***均投入运行,保持乏燃料水池水温低于某一限定值。这种乏燃料水池冷却***的工艺配置设计基准为:反应堆以12个月为换料周期,每次换料有1/3堆芯乏燃料组件卸入乏燃料水池。
然而,随着燃料管理技术的改进,核电厂换料模式升级为以18个月为周期换料、每次换料时全堆芯燃料组件卸入乏燃料水池。新换料模式下,乏燃料水池中燃料组件的衰变热负荷更高,原有冷却***冷却能力不能满足新换料模式的要求,核电厂只能在冷却水温度较低(低于设计基准温度一定范围)的冬季进行换料,换料运行策略、核电厂正常运行受到很大影响。
此外,已公开的乏燃料水池冷却***的热量排出依赖于“设备冷却水/海水”这一冷链,当这一冷链由于设备故障不可用时,或者核电厂发生全厂断电时,乏燃料水池冷却即告中断,若乏池水长期沸腾,则会导致乏燃料厂房内部分设备损坏,部分放射性物质外泄,影响公众人身安全。
有鉴于此,有必要提供一种能够解决上述问题的核电厂乏燃料水池补充冷却装置。
发明内容
本发明的目的在于:克服现有技术的不足,提供一种具有理想的冷却能力、安全可靠性强的核电厂乏燃料水池补充冷却装置。
为了实现上述目的,本发明提供一种核电厂乏燃料水池补充冷却装置,其包括位于核岛厂房内的一回路和位于核岛厂房外的二回路,乏燃料水池中的乏池水能够在一回路中循环流动,一回路通过中间热交换器将热量输送至二回路,二回路中的流体通过冷却塔将热量排出。
作为本发明核电厂乏燃料水池补充冷却装置的一种改进,所述一回路中除乏燃料水池外,其其他部分中的流体封闭运行,所述二回路为闭式回路。
作为本发明核电厂乏燃料水池补充冷却装置的一种改进,所述核电厂乏燃料水池补充冷却装置中的所有动力设备均采用双模供电方式。
作为本发明核电厂乏燃料水池补充冷却装置的一种改进,所述双模供电的其中一模为柴油发电机供电。
作为本发明核电厂乏燃料水池补充冷却装置的一种改进,所述冷却塔为逆流闭式冷却塔。
作为本发明核电厂乏燃料水池补充冷却装置的一种改进,所述冷却塔包括四台小冷却塔,当核电厂乏燃料水池补充冷却装置运行时,其中三台小冷却塔投运,另一台小冷却塔备用。
作为本发明核电厂乏燃料水池补充冷却装置的一种改进,所述二回路中的流体通过两台并联的冷却泵输送,当核电厂乏燃料水池补充冷却装置运行时,一台冷却泵投运,另一台冷却泵备用。
作为本发明核电厂乏燃料水池补充冷却装置的一种改进,所述中间热交换器为板式热交换器。
作为本发明核电厂乏燃料水池补充冷却装置的一种改进,所述二回路中设置有容积控制波动箱。
作为本发明核电厂乏燃料水池补充冷却装置的一种改进,所述二回路中的流体介质为非放射性冷却水。
与现有技术相比,本发明核电厂乏燃料水池补充冷却装置至少具有以下技术效果:
(1)显著提升了乏燃料水池的冷却能力,使核电厂能够适应以18个月为周期换料、每次换料时全堆芯燃料组件卸入乏燃料水池为特征的燃料管理模式运行要求,保证核电厂正常运作。
(2)动力设备预留外部柴油机供电接口,当核电厂发生全厂断电事故时,乏燃料水池可正常冷却,防止放射性物质外泄引起安全事故。
(3)以大气环境为热阱,为乏燃料水池提供新的独立的冷链***,当核电厂发生热阱丧失事故时,乏燃料水池可正常冷却,防止放射性物质外泄引起安全事故。
(4)通过双回路冷链设计,将乏池水限制在核岛厂房内,防止放射性物质发生意外在核岛厂房外泄漏,提升了装置的安全可靠性。
附图说明
下面结合附图和具体实施方式,对本发明核电厂乏燃料水池补充冷却装置及其有益技术效果进行详细说明。
图1为本发明核电厂乏燃料水池补充冷却装置的结构示意图。
具体实施方式
为了使本发明的目的、技术方案和技术效果更加清晰明白,以下结合附图和具体实施方式,对本发明进行进一步详细说明。应当理解的是,本说明书中描述的具体实施方式仅仅是为了解释本发明,并不是为了限定本发明。
请参阅图1,图1中虚线所示回路为已公开的核电厂乏燃料水池冷却装置,实线所示回路为本发明核电厂乏燃料水池补充冷却装置。
本发明核电厂乏燃料水池补充冷却装置包括位于核岛厂房内的一回路和位于核岛厂房外的二回路,乏燃料水池中的乏池水能够在一回路中循环流动,一回路通过中间热交换器将热量输送至二回路,二回路中的流体通过冷却塔将热量排出。
一回路包括一回路管道、乏燃料水池、中间热交换器和一回路冷却泵。乏燃料水池中容纳有温度较高的乏池水。中间热交换器为板式热交换器。乏燃料水池、中间热交换器和一回路冷却泵串联在一回路管道中。包括中间热交换器、一回路冷却泵在内,一回路中所有的动力设备均采用双模供电方式,即采用核电厂厂用电源和外部应急柴油发电机供电两路供电的方式。在正常运行期间使用核电厂厂用电源供电,发生全厂断电事故时使用外部应急柴油发电机供电,从而提高供电的灵活性和***运行的独立性。
在一回路中,乏池水在一回路冷却泵的输送下,流经中间热交换器,在中间热交换器中被二回路中的流体冷却后,不与已公开的冷却回路汇合,直接返回乏燃料水池。乏池水在一回路中经过多次循环,其热量传递给二回路的流体。乏池水在一回路中除乏燃料水池外的其他部分中封闭运行,具有放射性的乏池水限制在核岛厂房内流动,避免放射性物质排放到核岛厂房外的环境中。
二回路包括二回路管道、冷却塔、容积控制波动箱,以及两台并联的二回路冷却泵。冷却塔为逆流闭式冷却塔,其盘管外循环喷淋水,吸收盘管内流体热量,喷淋水蒸发并将热量最终传递到大气环境中。冷却塔通风方式为引风式机械通风。冷却塔采用4×33%的配置模式,即冷却塔包括四台小冷却塔。正常运行时,三台小冷却塔投入使用,另一台小冷却塔备用。两台并联的二回路冷却泵容量为2×100%。正常运行时只有一台二回路冷却泵投入运行,另一台二回路冷却泵备用。二回路的能动设备冷却塔和冷却泵设置冗余配置,能够增强冷却装置的设备总体可靠性,提高***可用率。容积控制波动箱用于应对二回路的流体容积变化。冷却塔、容积控制波动箱、两台并联的二回路冷却泵串联在二回路中。二回路经过中间热交换器。包括冷却塔、二回路冷却泵、容积控制波动箱在内,二回路中所有的动力设备均采用双模供电方式,即采用核电厂厂用电源和外部应急柴油发电机供电两路供电的方式。在正常运行期间使用核电厂厂用电源供电,发生全厂断电事故时使用外部应急柴油发电机供电,从而提高供电的灵活性和***运行的独立性。
在二回路中,流体通过中间热交换器在不与一回路乏池水接触的情况下接收乏池水的热量、冷却乏池水,之后流体在二回路冷却泵的输送下,进入冷却塔的盘管内,冷却塔通过在盘管外表面布水蒸发和通风对流等换热方式对管内热流体进行冷却。流体在二回路中经过多次循环,其热量最终传递到大气环境中。二回路的流体介质为非放射性冷却水,且二回路为闭式回路、与一回路不相交,因此放射性物质不会泄漏至核岛厂房外。
结合以上对本发明的详细描述可以看出,相对于现有技术,本发明核电厂乏燃料水池补充冷却装置的有益技术效果包括但不限于:
(1)通过双回路冷链设计,将乏池水限制在核岛厂房内,防止放射性物质发生意外在核岛厂房外泄漏,提升了装置的安全可靠性。
(2)显著提升了乏燃料水池的冷却能力,使核电厂能够适应以18个月为周期换料、每次换料时全堆芯燃料组件卸入乏燃料水池为特征的燃料管理模式运行要求,保证了核电厂的正常运作。
(3)动力设备预留外部柴油机供电接口,当核电厂发生全厂断电事故时,乏燃料水池可正常冷却,防止放射性物质外泄引起安全事故。
(4)以大气环境为热阱,为乏燃料水池提供新的独立的冷链***,当核电厂发生热阱丧失事故时,乏燃料水池可正常冷却,防止放射性物质外泄引起安全事故。
根据上述原理,本发明还可以对上述实施方式进行适当的变更和修改。因此,本发明并不局限于上面揭示和描述的具体实施方式,对本发明的一些修改和变更也应当落入本发明的权利要求的保护范围内。此外,尽管本说明书中使用了一些特定的术语,但这些术语只是为了方便说明,并不对本发明构成任何限制。
Claims (10)
1.一种核电厂乏燃料水池补充冷却装置,其特征在于:所述核电厂乏燃料水池补充冷却装置包括位于核岛厂房内的一回路和位于核岛厂房外的二回路,乏燃料水池中的乏池水能够在一回路中循环流动,一回路通过中间热交换器将热量输送至二回路,二回路中的流体通过冷却塔将热量排出。
2.根据权利要求1所述的核电厂乏燃料水池补充冷却装置,其特征在于:所述一回路中除乏燃料水池外,其其他部分中的流体封闭运行,所述二回路为闭式回路。
3.根据权利要求1所述的核电厂乏燃料水池补充冷却装置,其特征在于:所述核电厂乏燃料水池补充冷却装置中的所有动力设备均采用双模供电方式。
4.根据权利要求3所述的核电厂乏燃料水池补充冷却装置,其特征在于:所述双模供电的其中一模为柴油发电机供电。
5.根据权利要求1所述的核电厂乏燃料水池补充冷却装置,其特征在于:所述冷却塔为逆流闭式冷却塔。
6.根据权利要求5所述的核电厂乏燃料水池补充冷却装置,其特征在于:所述冷却塔包括四台小冷却塔,当核电厂乏燃料水池补充冷却装置运行时,其中三台小冷却塔投运,另一台小冷却塔备用。
7.根据权利要求1所述的核电厂乏燃料水池补充冷却装置,其特征在于:所述二回路中的流体通过两台并联的冷却泵输送,当核电厂乏燃料水池补充冷却装置运行时,一台冷却泵投运,另一台冷却泵备用。
8.根据权利要求1所述的核电厂乏燃料水池补充冷却装置,其特征在于:所述中间热交换器为板式热交换器。
9.根据权利要求1所述的核电厂乏燃料水池补充冷却装置,其特征在于:所述二回路中设置有容积控制波动箱。
10.根据权利要求1所述的核电厂乏燃料水池补充冷却装置,其特征在于:所述二回路中的流体介质为非放射性冷却水。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610692265.1A CN107767973B (zh) | 2016-08-19 | 2016-08-19 | 核电厂乏燃料水池补充冷却装置 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610692265.1A CN107767973B (zh) | 2016-08-19 | 2016-08-19 | 核电厂乏燃料水池补充冷却装置 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN107767973A true CN107767973A (zh) | 2018-03-06 |
CN107767973B CN107767973B (zh) | 2020-05-05 |
Family
ID=61261979
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610692265.1A Active CN107767973B (zh) | 2016-08-19 | 2016-08-19 | 核电厂乏燃料水池补充冷却装置 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107767973B (zh) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108492899A (zh) * | 2018-03-29 | 2018-09-04 | 深圳中广核工程设计有限公司 | 核电站乏燃料水池的移动式应急冷却装置 |
CN109524132A (zh) * | 2018-10-12 | 2019-03-26 | 岭澳核电有限公司 | 应用于乏燃料水池冷却支路的控制方法及其控制*** |
CN109599191A (zh) * | 2018-10-16 | 2019-04-09 | 中国科学院合肥物质科学研究院 | 一种基于全超导托卡马克装置的冷却环路*** |
CN112361948A (zh) * | 2020-10-29 | 2021-02-12 | 中国核动力研究设计院 | 模拟燃料棒-乏池不同控温的加热装置 |
CN113345608A (zh) * | 2021-04-28 | 2021-09-03 | 中广核研究院有限公司 | 乏燃料水池冷却和净化*** |
CN113409968A (zh) * | 2021-05-18 | 2021-09-17 | 中国核电工程有限公司 | 一种用于核电厂丧失热阱工况下的制冷*** |
CN113871044A (zh) * | 2021-08-12 | 2021-12-31 | 中广核研究院有限公司 | 冷却控制方法及其相关设备 |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5488642A (en) * | 1994-08-22 | 1996-01-30 | Consolidated Edison Company Of New York, Inc. | Cooling system for spent fuel pool |
CN102842349A (zh) * | 2011-06-22 | 2012-12-26 | 上海核工程研究设计院 | 核电厂冷却水***的检修备用*** |
CN104347124A (zh) * | 2013-07-26 | 2015-02-11 | 中广核工程有限公司 | 核电厂安全壳及乏燃料水池事故后中长期冷却*** |
CN205177415U (zh) * | 2015-11-06 | 2016-04-20 | 中广核工程有限公司 | 核电厂乏燃料水池非能动热管冷却*** |
CN205211425U (zh) * | 2015-12-03 | 2016-05-04 | 中广核工程有限公司 | 核电站乏燃料水池冷却*** |
CN205334971U (zh) * | 2015-11-26 | 2016-06-22 | 中广核工程有限公司 | 一种用安全壳喷淋***补充冷却乏池的*** |
CN105825900A (zh) * | 2015-01-06 | 2016-08-03 | 中国科学院工程热物理研究所 | 一种高温液态金属两级冷却设备和方法 |
-
2016
- 2016-08-19 CN CN201610692265.1A patent/CN107767973B/zh active Active
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5488642A (en) * | 1994-08-22 | 1996-01-30 | Consolidated Edison Company Of New York, Inc. | Cooling system for spent fuel pool |
CN102842349A (zh) * | 2011-06-22 | 2012-12-26 | 上海核工程研究设计院 | 核电厂冷却水***的检修备用*** |
CN104347124A (zh) * | 2013-07-26 | 2015-02-11 | 中广核工程有限公司 | 核电厂安全壳及乏燃料水池事故后中长期冷却*** |
CN105825900A (zh) * | 2015-01-06 | 2016-08-03 | 中国科学院工程热物理研究所 | 一种高温液态金属两级冷却设备和方法 |
CN205177415U (zh) * | 2015-11-06 | 2016-04-20 | 中广核工程有限公司 | 核电厂乏燃料水池非能动热管冷却*** |
CN205334971U (zh) * | 2015-11-26 | 2016-06-22 | 中广核工程有限公司 | 一种用安全壳喷淋***补充冷却乏池的*** |
CN205211425U (zh) * | 2015-12-03 | 2016-05-04 | 中广核工程有限公司 | 核电站乏燃料水池冷却*** |
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108492899A (zh) * | 2018-03-29 | 2018-09-04 | 深圳中广核工程设计有限公司 | 核电站乏燃料水池的移动式应急冷却装置 |
WO2019184432A1 (zh) * | 2018-03-29 | 2019-10-03 | 深圳中广核工程设计有限公司 | 核电站乏燃料水池的移动式应急冷却装置 |
CN108492899B (zh) * | 2018-03-29 | 2020-11-10 | 深圳中广核工程设计有限公司 | 核电站乏燃料水池的移动式应急冷却装置 |
CN109524132A (zh) * | 2018-10-12 | 2019-03-26 | 岭澳核电有限公司 | 应用于乏燃料水池冷却支路的控制方法及其控制*** |
CN109524132B (zh) * | 2018-10-12 | 2020-04-24 | 岭澳核电有限公司 | 应用于乏燃料水池冷却支路的控制方法及其控制*** |
CN109599191A (zh) * | 2018-10-16 | 2019-04-09 | 中国科学院合肥物质科学研究院 | 一种基于全超导托卡马克装置的冷却环路*** |
CN112361948A (zh) * | 2020-10-29 | 2021-02-12 | 中国核动力研究设计院 | 模拟燃料棒-乏池不同控温的加热装置 |
CN112361948B (zh) * | 2020-10-29 | 2022-02-22 | 中国核动力研究设计院 | 模拟燃料棒-乏池不同控温的加热装置 |
CN113345608A (zh) * | 2021-04-28 | 2021-09-03 | 中广核研究院有限公司 | 乏燃料水池冷却和净化*** |
CN113409968A (zh) * | 2021-05-18 | 2021-09-17 | 中国核电工程有限公司 | 一种用于核电厂丧失热阱工况下的制冷*** |
CN113871044A (zh) * | 2021-08-12 | 2021-12-31 | 中广核研究院有限公司 | 冷却控制方法及其相关设备 |
CN113871044B (zh) * | 2021-08-12 | 2024-06-21 | 中广核研究院有限公司 | 冷却控制方法及其相关设备 |
Also Published As
Publication number | Publication date |
---|---|
CN107767973B (zh) | 2020-05-05 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107767973A (zh) | 核电厂乏燃料水池补充冷却装置 | |
CN103295656B (zh) | 用于核反应堆的多样化专设安全*** | |
KR101242746B1 (ko) | 원자력 발전소의 격납건물 외부 통합피동안전계통 시스템 | |
US20180350472A1 (en) | Passive safe cooling system | |
CN102831942B (zh) | 核电站乏燃料水池应急冷却*** | |
GB2521549A (en) | Combined active and passive secondary-side reactor core heat removal apparatus | |
US10134493B2 (en) | Reactor and operating method for the reactor | |
US20160247585A1 (en) | Passive safety equipment and nuclear power plant including same | |
CN104508753A (zh) | 用于核反应堆的深度防御安全范例 | |
CN102903402A (zh) | 一种先进的二次侧堆芯热量导出装置 | |
CN204242601U (zh) | 非能动安全冷却*** | |
KR20140126187A (ko) | 피동안전설비 및 이를 구비하는 원전 | |
CN111081399B (zh) | 核电厂应急堆芯冷却*** | |
WO2014048290A1 (zh) | 一种能动与非能动相结合的堆腔注水冷却*** | |
CN106328223A (zh) | 一种新型非能动安全壳能量控制*** | |
CN107665742A (zh) | 能动与非能动相结合的船用反应堆应急余热排出*** | |
KR20180047849A (ko) | 중간열침원 냉각설비를 구비하는 원전 | |
CN202887749U (zh) | 一种能动与非能动相结合的二次侧堆芯热量导出装置 | |
KR19980069816A (ko) | 원자력발전소를 위한 드레인시스템 | |
CN210271804U (zh) | 一种注水式铅铋快堆应急余热排出*** | |
CN202887750U (zh) | 一种先进的二次侧堆芯热量导出装置 | |
CN104078086A (zh) | 一种能动、非能动结合的安全壳地坑水冷却*** | |
CN103295657A (zh) | 核反应堆余热排出*** | |
KR101628170B1 (ko) | 피동격납부냉각계통 및 이를 구비하는 원전 | |
CN115240880B (zh) | 一种可实现持续排热的非能动余热排出***及方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |