CN107730204A - The efficient management system of construction operation and the efficient management terminal of construction operation - Google Patents

The efficient management system of construction operation and the efficient management terminal of construction operation Download PDF

Info

Publication number
CN107730204A
CN107730204A CN201710932248.5A CN201710932248A CN107730204A CN 107730204 A CN107730204 A CN 107730204A CN 201710932248 A CN201710932248 A CN 201710932248A CN 107730204 A CN107730204 A CN 107730204A
Authority
CN
China
Prior art keywords
information
module
construction operation
user
operation information
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710932248.5A
Other languages
Chinese (zh)
Inventor
王成荣
袁公民
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan Migrant Workers Plus Network Technology Co Ltd
Original Assignee
Sichuan Migrant Workers Plus Network Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan Migrant Workers Plus Network Technology Co Ltd filed Critical Sichuan Migrant Workers Plus Network Technology Co Ltd
Priority to CN201710932248.5A priority Critical patent/CN107730204A/en
Publication of CN107730204A publication Critical patent/CN107730204A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Human Resources & Organizations (AREA)
  • Theoretical Computer Science (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Marketing (AREA)
  • Physics & Mathematics (AREA)
  • Tourism & Hospitality (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Economics (AREA)
  • General Health & Medical Sciences (AREA)
  • Health & Medical Sciences (AREA)
  • Data Mining & Analysis (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Primary Health Care (AREA)

Abstract

The invention provides a kind of efficient management system of construction operation and the efficient management terminal of construction operation, the system to include:Information issuing module, for issuing construction operation information;Information-reply module, the return information sent for receiving related personnel according to construction operation information, and show return information;Information storage module, for storing construction operation information and return information.The construction operation information issued in the present invention, contain construction operation photographic intelligence, positional information, remark information, it is able to ensure that the accuracy of the construction operation information of issue, the return information of related personnel's transmission can be received by information-reply module, realize communication rapidly and efficiently, the construction operation information stored by information storage module, foundation is provided for follow-up various disputes, it has been also convenient for the inquiry of related personnel, alleviate in traditional construction operation management, the accuracy of construction operation information is poor, the technical problem that the efficiency of management is low and information is not transparent enough.

Description

The efficient management system of construction operation and the efficient management terminal of construction operation
Technical field
The present invention relates to the technical field of application management, a kind of efficient management system more particularly, to construction operation and apply The efficient management terminal for the industry that works.
Background technology
Construction industry has all had a very important role since development of human history, and it not only meets that people's material and culture is sent out The needs of exhibition, the purpose of the most basic daily routines of the mankind is realized, meanwhile, it can promote social economy constantly to advance. The development direct mark of construction industry constantly advancing for social economy, and therefore, construction industry has very in economic development Important effect.
In construction industry, the content that Engineering Project Construction is related to is a lot, and management is sufficiently complex.In the prior art, for applying The management for the industry that works, various information are passed on generally by artificial oral form, or recorded by the form of paper document, Examine what every job information was carried out.Such as:For the progress situation of job site, the form typically reported by papery is carried out Record, the phenomenon for be usually present false, lying about, can not identifying information authenticity.In addition, when security incident be present, also without Method quickly differentiates the person liable of accident, and the phenomenon to shirk responsibility usually occurs.
To sum up, in existing construction operation management, the accuracy of construction operation information is poor, and the efficiency of management is low, information It is not transparent enough.
The content of the invention
In view of this, it is an object of the invention to provide a kind of efficient management system of construction operation and the height of construction operation Imitate management terminal, to alleviate in the management of existing construction operation, the accuracy of construction operation information is poor, the efficiency of management lowly with And the technical problem that information is not transparent enough.
In a first aspect, the embodiments of the invention provide a kind of efficient management system of construction operation, the system includes:Letter Cease release module, information-reply module, information storage module;
Described information release module, for obtaining the construction operation information uploaded, and in the issue for receiving user's transmission In the case of instruction, the construction operation information is issued, wherein, the construction operation information comprises at least:The photograph of construction operation Piece information, user upload the positional information during construction operation information, remark information;
Described information is replied module and is connected with described information release module, is made for receiving related personnel according to the construction The return information that industry information is sent, and show the return information;
Described information memory module is replied module with described information release module and described information respectively and is connected, for storing The construction operation information and the return information.
With reference in a first aspect, the embodiments of the invention provide the possible embodiment of the first of first aspect, wherein, institute Stating system also includes:Information acquisition module, wherein, described information acquisition module is connected with described information release module, for Described information release module uploads the construction operation information, and described information acquisition module includes:Photo module, position acquisition mould Block, MIM message input module, information uploading module;
The photo module, the construction operation is shot for the trigger action according to the user, obtains institute State the photographic intelligence of construction operation;
The position acquisition module, for obtaining the positional information when user uploads the construction operation information;
Described information input module, the remarks for inputting the construction operation according to the input operation of the user are believed Breath;
Described information uploading module respectively with the photo module, the position acquisition module, described information input module Connection, the construction operation information is uploaded for receiving the construction operation information, and to described information release module, so that institute Information issuing module is stated to issue the construction operation information.
With reference in a first aspect, the embodiments of the invention provide the possible embodiment of second of first aspect, wherein, institute Stating system also includes:Notify release module;
The notice release module, for issuing related announcement bulletin according to the trigger action of the user, so that related Personnel are checked.
With reference in a first aspect, the embodiments of the invention provide the possible embodiment of the third of first aspect, wherein, institute Stating system also includes:Address list introducting interface, address list module;
The information management system of the address list introducting interface and builder connect, and are constructed for obtaining in construction operation The contact method of personnel, and the contact method is preserved to the address list module.
With reference in a first aspect, the embodiments of the invention provide the possible embodiment of the 4th of first aspect kind, wherein, institute Stating information storage module includes:Encrypting module, classification storage module;
The encrypting module, for the construction operation information to be encrypted, the construction operation information after being encrypted;
The classification storage module is connected with the encrypting module, after preserving the encryption according to default classifying rules Construction operation information.
With reference in a first aspect, the embodiments of the invention provide the possible embodiment of the 5th of first aspect kind, wherein, institute Stating system also includes:Data sheet module;
The data sheet module, for automatically generating the data sheet of the construction operation information, so as to the user Operative orientation is formulated according to the data sheet.
With reference in a first aspect, the embodiments of the invention provide the possible embodiment of the 6th of first aspect kind, wherein, institute Stating system also includes:Information inquiry module;
Described information enquiry module, the querying condition for being inputted according to the user inquire about target construction operation information, Wherein, the querying condition includes at least one of:Publisher's information, releasing position information, issuing time information.
With reference in a first aspect, the embodiments of the invention provide the possible embodiment of the 7th of first aspect kind, wherein, institute Stating system also includes:Login module;
The login module, the login authentication request sent for receiving the user, and the login authentication is asked Send to server,
Wherein, the server receives the login authentication request, and whether login authentication request described in interpretation meets default Authentication condition, if the login authentication request meet the default authentication condition, to the login module send log in into The result of work(;
If the login authentication request does not meet the default authentication condition, send to the login module and step on again The result of record.
With reference in a first aspect, the embodiments of the invention provide the possible embodiment of the 8th of first aspect kind, wherein, institute Stating system also includes:Electronic approval module;
The electronic approval module, the approval request sent for receiving the user, and the approval request is transmitted To the approval system corresponding to approving person, so that the approving person examines to the approval request.
Second aspect, the embodiment of the present invention additionally provide a kind of efficient management terminal of construction operation, pacified in the terminal Efficient management system equipped with the construction operation described in above-mentioned first aspect.
The embodiment of the present invention brings following beneficial effect:The efficient management system of construction operation a kind of and construction operation Efficient management terminal, the system include:Information issuing module, information-reply module, information storage module;Information issuing module, For obtaining the construction operation information uploaded, and in the case where receiving the issue instruction of user's transmission, issue construction operation Information, wherein, construction operation information comprises at least:The photographic intelligence of construction operation, user upload position during construction operation information Confidence ceases, remark information;Information-reply module is connected with information issuing module, is believed for receiving related personnel according to construction operation The return information sent is ceased, and shows return information;Information storage module respectively with information issuing module and information-reply module Connection, for storing construction operation information and return information.
In traditional construction operation management, various information are passed on generally by artificial oral form, or pass through paper The form record of matter file, examine every job information.Compared with traditional construction operation management, the construction operation in the present invention Efficient management system construction operation information can be issued by information issuing module, include construction in the construction operation information The photographic intelligence of operation, user upload positional information during construction operation information, and remark information, then, related personnel is according to applying Work job information sends return information by information-reply module, to realize communication rapidly and efficiently, and information storage module In store construction operation information and return information, foundation can be provided for follow-up various disputes.Construction in the present invention is made In the construction operation information of the efficient management system issue of industry, construction operation photographic intelligence is contained, user uploads construction operation Positional information during information, remark information, it can be ensured that the accuracy of the construction operation information of issue, also, returned by information Multiple module can receive the return information of related personnel's transmission, realize communication rapidly and efficiently, deposited by information storage module The construction operation information of storage, foundation is provided for follow-up various disputes, the inquiry of related personnel has been also convenient for, has alleviated traditional In construction operation management, the accuracy of construction operation information is poor, and the technology that the efficiency of management is low and information is not transparent enough is asked Topic.
Other features and advantages of the present invention will illustrate in the following description, also, partly become from specification Obtain it is clear that or being understood by implementing the present invention.The purpose of the present invention and other advantages are in specification, claims And specifically noted structure is realized and obtained in accompanying drawing.
To enable the above objects, features and advantages of the present invention to become apparent, preferred embodiment cited below particularly, and coordinate Appended accompanying drawing, is described in detail below.
Brief description of the drawings
, below will be to specific in order to illustrate more clearly of the specific embodiment of the invention or technical scheme of the prior art The required accompanying drawing used is briefly described in embodiment or description of the prior art, it should be apparent that, in describing below Accompanying drawing is some embodiments of the present invention, for those of ordinary skill in the art, before creative work is not paid Put, other accompanying drawings can also be obtained according to these accompanying drawings.
Fig. 1 is a kind of structured flowchart of the efficient management system of construction operation provided in an embodiment of the present invention;
Fig. 2 is the structure of the efficient management system of the construction operation provided in an embodiment of the present invention comprising information acquisition module Block diagram;
Fig. 3 is the structured flowchart of the efficient management system of another construction operation provided in an embodiment of the present invention;
Fig. 4 is a kind of structured flowchart of the efficient management system of preferable construction operation provided in an embodiment of the present invention.
Icon:
11- information issuing modules;12- information-reply modules;13- information storage modules;14- information acquisition modules;15- leads to Know release module;16- address list introducting interfaces;17- address list modules;18- data sheet modules;131- encrypting modules;132- Classification storage module;141- photo modules;142- position acquisition modules;143- MIM message input modules;144- information uploading modules.
Embodiment
To make the purpose, technical scheme and advantage of the embodiment of the present invention clearer, below in conjunction with accompanying drawing to the present invention Technical scheme be clearly and completely described, it is clear that described embodiment is part of the embodiment of the present invention, rather than Whole embodiments.Based on the embodiment in the present invention, those of ordinary skill in the art are not making creative work premise Lower obtained every other embodiment, belongs to the scope of protection of the invention.
For ease of understanding the present embodiment, first to a kind of the efficient of construction operation disclosed in the embodiment of the present invention Management system describes in detail.
Embodiment one:
A kind of efficient management system of construction operation, with reference to figure 1, the system includes:Information issuing module 11, information-reply Module 12, information storage module 13;
Information issuing module 11, refer to for obtaining the construction operation information uploaded, and in the issue for receiving user's transmission In the case of order, construction operation information is issued, wherein, construction operation information comprises at least:The photographic intelligence of construction operation, user Upload positional information during construction operation information, remark information;
Information-reply module 12 is connected with information issuing module 11, is sent out for receiving related personnel according to construction operation information The return information sent, and show return information;
Information storage module 13 is connected with information issuing module 11 and information-reply module 12 respectively, is made for storing construction Industry information and return information.
In embodiments of the present invention, construction operation information is specially the various information of each link during construction operation, than Such as:Goods and materials are marched into the arena, the inspection of equipment, the control of quality, the supervision of construction speed, inspection of work etc..
It is below to be illustrated in work progress exemplified by produced problem by construction operation information:Information issuing module 11 obtains Produced problem in work progress is taken, receives the issue instruction that user sends, so as to issue produced problem in the work progress, Produced problem contains the photographic intelligence of problem (for example a certain equipment is cast anchor) in the work progress, when user uploads the problem Positional information, the positional information is able to ensure that user is taken pictures what the scene of equipment was carried out, rather than is to practise fraud, ensures The accuracy of information, in addition, also including remark information, the content of remark information is the further explanation to the problem.
User is uploaded in the work progress after produced problem, just can be according to the problem after related personnel sees the problem Return information is sent, to inform measure that user ought to take.This kind of communication way can greatly improve the efficiency of communication.
In addition, in embodiments of the present invention, also comprising information storage module 13, for storing construction operation information and reply Information, foundation can be provided for follow-up various disputes, meanwhile, the inquiry of user has been also convenient for, has improved the transparency of information.
In traditional construction operation management, various information are passed on generally by artificial oral form, or pass through paper The form record of matter file, examine every job information.Compared with traditional construction operation management, the construction operation in the present invention Efficient management system construction operation information can be issued by information issuing module 11, include in the construction operation information and apply Work industry photographic intelligence, user upload construction operation information when positional information, remark information, then, related personnel according to Construction operation information sends return information by information-reply module 12, and to realize communication rapidly and efficiently, and information stores Construction operation information and return information are stored in module 13, foundation can be provided for follow-up various disputes.In the present invention In the construction operation information of the efficient management system issue of construction operation, construction operation photographic intelligence is contained, user uploads and applied Positional information during work job information, remark information, it can be ensured that the accuracy of the construction operation information of issue, also, pass through Information-reply module 12 can receive the return information of related personnel's transmission, realize communication rapidly and efficiently, deposited by information The construction operation information that module 13 stores is stored up, foundation is provided for follow-up various disputes, has been also convenient for the inquiry of related personnel, delay Solve in traditional construction operation management, the accuracy of construction operation information is poor, and the efficiency of management is low and information is not saturating enough Bright technical problem.
Alternatively, also include with reference to figure 2, the system:Information acquisition module 14, wherein, information acquisition module 14 and information Release module 11 connects, and for uploading construction operation information to information issuing module 11, information acquisition module 14 includes:Take pictures mould Block 141, position acquisition module 142, MIM message input module 143, information uploading module 144;
Photo module 141, construction operation is shot for the trigger action according to user, obtain the photograph of construction operation Piece information;
Position acquisition module 142, for obtaining positional information when user uploads construction operation information;
MIM message input module 143, for inputting the remark information of construction operation according to the input operation of user;
Information uploading module 144 connects with photo module 141, position acquisition module 142, MIM message input module 143 respectively, Construction operation information is uploaded for receiving construction operation information, and to information issuing module 11, so that information issuing module 11 is right Construction operation information is issued.
In embodiments of the present invention, information acquisition module 14 includes photo module 141, position acquisition module 142, information Input module 143 and information uploading module 144.Photo module 141 is taken pictures according to the trigger action of user to construction operation, The photo module 141 can be camera.Position acquisition module 142 is used to obtain position when user uploads construction operation information Information, the position acquisition module 142 can be GPS location.MIM message input module 143 is inputted according to the input operation of user and constructed The remark information of operation.
Then, information uploading module 144 receives the photographic intelligence for the construction operation that photo module 141 is sent, receiving position The positional information that acquisition module 142 is sent, and the remark information that receive information input module 143 is sent, and these are constructed Job information is uploaded to information issuing module 11, so that information issuing module 11 is issued to construction operation information.
Alternatively, also include with reference to figure 3, the system:Notify release module 15;
Release module 15 is notified, for issuing related announcement bulletin according to the trigger action of user, so that related personnel enters Row is checked.
In embodiments of the present invention, in order to more user-friendly, inventor is provided with notice issue in systems Module 15, the information for notifying bulletin can be communicated to all apply by notifying release module 15 issues related announcement to announce Worker person, it is convenient and swift, without being passed in turn step by step again.
Alternatively, also include with reference to figure 3, the system:Address list introducting interface 16, address list module 17;
Address list introducting interface 16 is connected with the information management system of builder, for obtaining constructor in construction operation The contact method of member, and contact method is preserved to address list module 17.
In addition, the system in the present invention is additionally provided with address list introducting interface 16, address list introducting interface 16 and building work The information management system connection of people, obtains the contact method of workmen in construction operation, and contact method is preserved to communication Record module 17.So easily user can be caused to find the contact method of related personnel.It will need not work together again, the work of leader Phone is stored in mobile phone so that Work Telephone is not interfere with each other with life phone.
Alternatively, include with reference to figure 4, information storage module 13:Encrypting module 131, classification storage module 132;
Encrypting module 131, for construction operation information to be encrypted, the construction operation information after being encrypted;
Classification storage module 132 is connected with encrypting module 131, for preserving the construction after encryption according to default classifying rules Job information.
Specifically, in order to prevent construction operation information to be stolen so that data are safer, and inventor stores mould in information Encrypting module 131 is provided with block 13, construction operation information can be encrypted for encrypting module 131, applying after being encrypted Work job information, and then, classification storage module 132 is protected according to default classifying rules to the construction operation information after encryption Deposit.Default classifying rules can be in the links in construction operation, and identical link stores as a kind of, can also be according to The construction operation that certain period of time occurs is as a kind of storage (for example the construction operation occurred in one week is classified as one kind), this hair Bright embodiment is not particularly limited to it.
Alternatively, also include with reference to figure 4, the system:Data sheet module 18;
Data sheet module 18, for automatically generating the data sheet of construction operation information, so that user is according to datagram Table formulates operative orientation.
Specifically, data sheet module 18 can generate target data form according to the demand of user, such as, construction operation The form of progress, so so that user easily formulates various operative orientations according to data sheet.
Alternatively, the system also includes:Information inquiry module;
Information inquiry module, the querying condition for being inputted according to user inquire about target construction operation information, wherein, inquiry Condition includes at least one of:Publisher's information, releasing position information, issuing time information.
Specifically, the specific some construction operation information of user's inquiry, inventor are provided with information inquiry mould for convenience Block.The module can inquire target construction operation information according to the querying condition that user inputs, and facilitate checking for user.
Alternatively, the system also includes:Login module;
Login module, sent for receiving the login authentication request of user's transmission, and by login authentication request to server,
Wherein, server receives login authentication request, and whether interpretation login authentication request meets default authentication condition, if Login authentication request meets default authentication condition, then the result logined successfully is sent to login module;
Default authentication condition is not met if logged on certification request, then the result logged in again is sent to login module.
Alternatively, the system also includes:Electronic approval module;
Electronic approval module, for receiving the approval request of user's transmission, and approval request is sent to approving person institute Corresponding approval system, so that approving person examines to approval request.
Specifically, in order to reduce the triviality of traditional approval process, inventor is provided with electronic approval mould in systems Block, for receiving the approval request of user's transmission, so as to which approval request is sent into approval system corresponding to approving person, so that Approving person is examined to approval request, and approval results are sent to electronic approval module, more convenient.
Embodiment two:
The embodiment of the present invention additionally provides a kind of efficient management terminal of construction operation, and above-mentioned implementation is provided with the terminal The efficient management system of construction operation in example one.
A kind of efficient management system for construction operation that the embodiment of the present invention is provided and the efficient management of construction operation are whole The computer program product at end, including the computer-readable recording medium of program code is stored, described program code includes Instruction can be used for performing the method described in previous methods embodiment, and specific implementation can be found in embodiment of the method, no longer superfluous herein State.
It is apparent to those skilled in the art that for convenience and simplicity of description, the system of foregoing description With the specific work process of device, the corresponding process in preceding method embodiment is may be referred to, will not be repeated here.
In addition, in the description of the embodiment of the present invention, unless otherwise clearly defined and limited, term " installation ", " phase Even ", " connection " should be interpreted broadly, for example, it may be being fixedly connected or being detachably connected, or be integrally connected;Can To be mechanical connection or electrical connection;Can be joined directly together, can also be indirectly connected by intermediary, Ke Yishi The connection of two element internals.For the ordinary skill in the art, with concrete condition above-mentioned term can be understood at this Concrete meaning in invention.
If the function is realized in the form of SFU software functional unit and is used as independent production marketing or in use, can be with It is stored in a computer read/write memory medium.Based on such understanding, technical scheme is substantially in other words The part to be contributed to prior art or the part of the technical scheme can be embodied in the form of software product, the meter Calculation machine software product is stored in a storage medium, including some instructions are causing a computer equipment (can be People's computer, server, or network equipment etc.) perform all or part of step of each embodiment methods described of the present invention. And foregoing storage medium includes:USB flash disk, mobile hard disk, read-only storage (ROM, Read-Only Memory), arbitrary access are deposited Reservoir (RAM, Random Access Memory), magnetic disc or CD etc. are various can be with the medium of store program codes.
In the description of the invention, it is necessary to explanation, term " " center ", " on ", " under ", "left", "right", " vertical ", The orientation or position relationship of the instruction such as " level ", " interior ", " outer " be based on orientation shown in the drawings or position relationship, merely to Be easy to the description present invention and simplify description, rather than instruction or imply signified device or element must have specific orientation, With specific azimuth configuration and operation, therefore it is not considered as limiting the invention.In addition, term " first ", " second ", " the 3rd " is only used for describing purpose, and it is not intended that instruction or hint relative importance.
Finally it should be noted that:Embodiment described above, it is only the embodiment of the present invention, to illustrate the present invention Technical scheme, rather than its limitations, protection scope of the present invention is not limited thereto, although with reference to the foregoing embodiments to this hair It is bright to be described in detail, it will be understood by those within the art that:Any one skilled in the art The invention discloses technical scope in, it can still modify to the technical scheme described in previous embodiment or can be light Change is readily conceivable that, or equivalent substitution is carried out to which part technical characteristic;And these modifications, change or replacement, do not make The essence of appropriate technical solution departs from the spirit and scope of technical scheme of the embodiment of the present invention, should all cover the protection in the present invention Within the scope of.Therefore, protection scope of the present invention described should be defined by scope of the claims.

Claims (10)

1. the efficient management system of a kind of construction operation, it is characterised in that the system includes:Information issuing module, information are returned Multiple module, information storage module;
Described information release module, for obtaining the construction operation information uploaded, and receiving the issue instruction of user's transmission In the case of, the construction operation information is issued, wherein, the construction operation information comprises at least:The photo letter of construction operation Breath, user upload the positional information during construction operation information, remark information;
Described information is replied module and is connected with described information release module, is believed for receiving related personnel according to the construction operation The return information sent is ceased, and shows the return information;
Described information memory module is replied module with described information release module and described information respectively and is connected, described for storing Construction operation information and the return information.
2. system according to claim 1, it is characterised in that the system also includes:Information acquisition module, wherein, institute State information acquisition module to be connected with described information release module, believe for uploading the construction operation to described information release module Breath, described information acquisition module include:Photo module, position acquisition module, MIM message input module, information uploading module;
The photo module, the construction operation is shot for the trigger action according to the user, obtain described apply The photographic intelligence for the industry that works;
The position acquisition module, for obtaining the positional information when user uploads the construction operation information;
Described information input module, for inputting the remark information of the construction operation according to the input operation of the user;
Described information uploading module connects with the photo module, the position acquisition module, described information input module respectively, The construction operation information is uploaded for receiving the construction operation information, and to described information release module, so that the letter Breath release module is issued to the construction operation information.
3. system according to claim 1, it is characterised in that the system also includes:Notify release module;
The notice release module, for issuing related announcement bulletin according to the trigger action of the user, so that related personnel Checked.
4. system according to claim 1, it is characterised in that the system also includes:Address list introducting interface, address list Module;
The information management system of the address list introducting interface and builder connect, for obtaining workmen in construction operation Contact method, and the contact method is preserved to the address list module.
5. system according to claim 1, it is characterised in that described information memory module includes:Encrypting module, classification are deposited Store up module;
The encrypting module, for the construction operation information to be encrypted, the construction operation information after being encrypted;
The classification storage module is connected with the encrypting module, for according to applying after the default classifying rules preservation encryption Work job information.
6. system according to claim 1, it is characterised in that the system also includes:Data sheet module;
The data sheet module, for automatically generating the data sheet of the construction operation information, so as to the user according to The data sheet formulates operative orientation.
7. system according to claim 1, it is characterised in that the system also includes:Information inquiry module;
Described information enquiry module, the querying condition for being inputted according to the user inquire about target construction operation information, wherein, The querying condition includes at least one of:Publisher's information, releasing position information, issuing time information.
8. system according to claim 1, it is characterised in that the system also includes:Login module;
The login module, the login authentication request sent for receiving the user, and the login authentication is asked to send To server,
Wherein, the server receives the login authentication request, and whether login authentication request described in interpretation meets pre- setting authentication Condition, if login authentication request meets the default authentication condition, send what is logined successfully to the login module As a result;
If the login authentication request does not meet the default authentication condition, send what is logged in again to the login module As a result.
9. system according to claim 1, it is characterised in that the system also includes:Electronic approval module;
The electronic approval module, the approval request sent for receiving the user, and the approval request is sent to careful Approval system corresponding to the personnel of criticizing, so that the approving person examines to the approval request.
10. the efficient management terminal of a kind of construction operation, it is characterised in that the claim 1 to 9 is provided with the terminal Any one of construction operation efficient management system.
CN201710932248.5A 2017-09-30 2017-09-30 The efficient management system of construction operation and the efficient management terminal of construction operation Pending CN107730204A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710932248.5A CN107730204A (en) 2017-09-30 2017-09-30 The efficient management system of construction operation and the efficient management terminal of construction operation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710932248.5A CN107730204A (en) 2017-09-30 2017-09-30 The efficient management system of construction operation and the efficient management terminal of construction operation

Publications (1)

Publication Number Publication Date
CN107730204A true CN107730204A (en) 2018-02-23

Family

ID=61209331

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710932248.5A Pending CN107730204A (en) 2017-09-30 2017-09-30 The efficient management system of construction operation and the efficient management terminal of construction operation

Country Status (1)

Country Link
CN (1) CN107730204A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109064041A (en) * 2018-08-09 2018-12-21 西安市恒兴市政工程公司 A kind of project in construction management system and method
CN114881549A (en) * 2022-07-12 2022-08-09 深圳市信润富联数字科技有限公司 Job management method, apparatus, terminal device, and storage medium

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN205507878U (en) * 2015-11-18 2016-08-24 邓明晖 Two -way matching of service and transaction system are managed to home decoration internet based on geographical position location
CN106127367A (en) * 2016-06-15 2016-11-16 中邮建技术有限公司 A kind of scene anti-cheating inspection method single with random group based on mobile terminal
CN106408172A (en) * 2016-08-31 2017-02-15 广东达安项目管理股份有限公司 Project management system
CN106779380A (en) * 2016-12-06 2017-05-31 山西省交通科学研究院 A kind of intelligent construction safety checks evaluation system and method
CN107133776A (en) * 2016-08-02 2017-09-05 北京尚优力达科技有限公司 A kind of mobile security supervisory systems

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN205507878U (en) * 2015-11-18 2016-08-24 邓明晖 Two -way matching of service and transaction system are managed to home decoration internet based on geographical position location
CN106127367A (en) * 2016-06-15 2016-11-16 中邮建技术有限公司 A kind of scene anti-cheating inspection method single with random group based on mobile terminal
CN107133776A (en) * 2016-08-02 2017-09-05 北京尚优力达科技有限公司 A kind of mobile security supervisory systems
CN106408172A (en) * 2016-08-31 2017-02-15 广东达安项目管理股份有限公司 Project management system
CN106779380A (en) * 2016-12-06 2017-05-31 山西省交通科学研究院 A kind of intelligent construction safety checks evaluation system and method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109064041A (en) * 2018-08-09 2018-12-21 西安市恒兴市政工程公司 A kind of project in construction management system and method
CN114881549A (en) * 2022-07-12 2022-08-09 深圳市信润富联数字科技有限公司 Job management method, apparatus, terminal device, and storage medium

Similar Documents

Publication Publication Date Title
CN107133776A (en) A kind of mobile security supervisory systems
CN107240165A (en) Security cruising inspection system
CN109034843A (en) A kind of generation method, verification method and the system of article anti-counterfeit information
CN105427211A (en) Legal affair on-line management system
CN108389007A (en) Security risk managing and control system and method
CN106096860A (en) A kind of intelligent risk management and control platform
CN107730204A (en) The efficient management system of construction operation and the efficient management terminal of construction operation
CN103426041A (en) Radiation source real-time monitoring and managing system and method based on Internet of things
CN110233891A (en) One kind being based on 5G network agricultural product ecosystem monitoring system
CN107800589A (en) To the monitoring method of cloud platform access device, device and its cloud platform used
CN111222830A (en) System and method for intelligently managing and monitoring pledge objects based on block chain of Internet of things
CN114219342A (en) Carbon asset management method and device based on non-homogeneous evidence
CN108537065A (en) Reference information processing method
CN104778562B (en) A kind of safe eye supervising platform system in job site
CN102110257A (en) RFID (radio frequency identification) firework firecracker flow direction management system and management method
CN207249677U (en) A kind of construction site safety monitoring system integrated based on RFID and BIM
CN113329066A (en) Building information internet sharing system
CN109918552A (en) Malice group tells tendency personal identification method, server and computer readable storage medium
CN114862417A (en) Block chain-based lead sealing lock system of traceability electronic tag system and interaction method
KR20220087807A (en) Transport logistics system and controlling method of the same
Zhao et al. An analysis of internet of things computer network security and remote control technology
CN114418547A (en) Hazardous chemical substance enterprise information acquisition and management system convenient for government supervision
CN207603691U (en) Mobile place name acquisition system based on safe transmission
CN111913448A (en) Informationized intelligent control system
CN103164763A (en) Radiation source real-time monitoring and managing system and radiation source real-time monitoring and managing method based on Internet of things

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180223