CN107730142A - Using Quick Response Code in BIM project management system - Google Patents

Using Quick Response Code in BIM project management system Download PDF

Info

Publication number
CN107730142A
CN107730142A CN201711061133.XA CN201711061133A CN107730142A CN 107730142 A CN107730142 A CN 107730142A CN 201711061133 A CN201711061133 A CN 201711061133A CN 107730142 A CN107730142 A CN 107730142A
Authority
CN
China
Prior art keywords
component
quick response
response code
time
module
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711061133.XA
Other languages
Chinese (zh)
Inventor
李洋
张越
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hangzhou Construction Engineering Consulting Co Ltd
Original Assignee
Hangzhou Construction Engineering Consulting Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hangzhou Construction Engineering Consulting Co Ltd filed Critical Hangzhou Construction Engineering Consulting Co Ltd
Priority to CN201711061133.XA priority Critical patent/CN107730142A/en
Publication of CN107730142A publication Critical patent/CN107730142A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06316Sequencing of tasks or work
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06KGRAPHICAL DATA READING; PRESENTATION OF DATA; RECORD CARRIERS; HANDLING RECORD CARRIERS
    • G06K17/00Methods or arrangements for effecting co-operative working between equipments covered by two or more of main groups G06K1/00 - G06K15/00, e.g. automatic card files incorporating conveying and reading operations
    • G06K17/0022Methods or arrangements for effecting co-operative working between equipments covered by two or more of main groups G06K1/00 - G06K15/00, e.g. automatic card files incorporating conveying and reading operations arrangements or provisious for transferring data to distant stations, e.g. from a sensing device
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/08Logistics, e.g. warehousing, loading or distribution; Inventory or stock management
    • G06Q10/087Inventory or stock management, e.g. order filling, procurement or balancing against orders
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Human Resources & Organizations (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Marketing (AREA)
  • Tourism & Hospitality (AREA)
  • General Business, Economics & Management (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Development Economics (AREA)
  • Primary Health Care (AREA)
  • Educational Administration (AREA)
  • General Engineering & Computer Science (AREA)
  • Game Theory and Decision Science (AREA)
  • General Health & Medical Sciences (AREA)
  • Health & Medical Sciences (AREA)
  • Data Mining & Analysis (AREA)
  • Accounting & Taxation (AREA)
  • Finance (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses it is a kind of using Quick Response Code in BIM project management system, solve after later stage component shows up, need staff that corresponding component is installed into corresponding opening position according to actual conditions, and because staff does not know the installation site of each component, staff is needed to find on the spot, more time taking problem, its drip irrigation device are:Including for identifying the two-dimension code recognition device of two-dimension code label, the component information database for being stored with Quick Response Code corresponding informance situation, BIM models, display module and the central processing unit that fit on corresponding component, the BIM models are shown at display module, the a kind of of the present invention quickly finds the installation site of counterpart member using Quick Response Code in BIM project management system, energy ancillary staff.

Description

Using Quick Response Code in BIM project management system
Technical field
The present invention relates to a kind of project management system, it is more particularly to a kind of using Quick Response Code in BIM project management system.
Background technology
With construction speed gradual perfection completion model, it is necessary to which staff is according to actual feelings after in the later stage, component is shown up Corresponding component is installed to corresponding opening position by condition, and the installation site of each component is not known due to staff, it is necessary to Staff finds on the spot, relatively time consuming, also improved space.
The content of the invention
It is an object of the invention to provide a kind of fast in BIM project management system, energy ancillary staff using Quick Response Code The installation site for finding counterpart member of speed.
The present invention above-mentioned technical purpose technical scheme is that:
It is a kind of using Quick Response Code in BIM project management system, including for identifying the two-dimension code label fitted on component Two-dimension code recognition device, the component information database for being stored with Quick Response Code corresponding informance situation, BIM models, display module and Central processing unit, the BIM models are shown at display module;
When two-dimension code recognition device transfer out in component information database using the two-dimension code label identified as querying condition with Corresponding to component information and transmit to central processing unit, the central processing unit controls BIM models high at display module Component acquired in bright display.
, will be so as to understand the component by the Quick Response Code on two-dimension code recognition device identification means using such scheme The installation site of BIM models, and being highlighted for counterpart member is carried out in BIM models by central processing unit, be advantageous to work Personnel understand particular location of the component in BIM models, so as to facilitate staff to quickly find corresponding component installation position Put.
Preferably, storage has redundancy at two-dimension code label, when the two dimension that the two-dimension code recognition device is identified When code does not inquire corresponding informance in component information database, the central processing unit control two-dimension code recognition device obtains Take the redundancy in identified Quick Response Code and be compared with the redundancy of all Quick Response Codes in information database, and will letter The component information situation compared in breath database corresponding to successful Quick Response Code is transmitted into central processing unit.
Using such scheme, by the identification to redundancy in Quick Response Code, quickly discrimination can have the two of part damage Code is tieed up, avoids not being identified when Quick Response Code damages, is improved in general to the accurate of Quick Response Code identification Property.
Preferably, also include the position for being stored with the positional information that each component is corresponding in reality in BIM models The real-time positioning apparatus and route planning module of information database, in real time positioning two-dimension code recognition device position;
Central processing unit transferred using acquired counterpart member in location information data storehouse corresponding to member position information as Terminal, using real-time positioning apparatus position as starting point, pass course planning module planning starting point to the end route and in Shown at display module.
Using such scheme, by positioning of the real-time positioning apparatus to starting point, with reference to transferring in location information data storehouse Counterpart member position, can pass course planning module cook up corresponding route to the position of installation component, consequently facilitating Staff quickly finds the installation site that component is arranged in reality, so as to improve the efficiency to component installation.
Preferably, also include the construction method database for being stored with construction method corresponding to all components, it is fixed when in real time The position that position device is positioned stops route planning module when reaching the position of counterpart member, and using counterpart member as querying condition Corresponding construction method is transferred in construction method database and is shown in display module.
Using such scheme, when component being moved into reality needing the position of installation component, by transferring construction method The installation method of counterpart member in database, in order to which staff quickly understands the installation method of specific component, accelerate The installation effectiveness of framework.
Preferably, also include arrangement of time database, the timing reminder module that storage has the different component engineering time, in Central processor is inquired about in arrangement of time database using the time as querying condition, in the engineering time arrival time arrange number Reminded during the time default according to place by timing reminder module in staff.
Using such scheme, with the set-up time of default each component in arrangement of time database, over time Passage, can quickly remind staff to go to find corresponding component, component is transported into structure in time by timing reminder module Part installed position.
Preferably, also include the initial position data storehouse for means of storage initial position;
Initial position of the central processing unit control using position during real-time positioning apparatus acquisition counterpart member information as component It is stored into initial position data storehouse, and is inquired about using the time as querying condition in arrangement of time database, in construction Between when arrival time when arranging database default time, transfer the component corresponding to the now engineering time, and in initial bit Put and the current position of component is transferred in information database, it is current as starting point, component using the position that real-time positioning apparatus is positioned Corresponding route is planned as terminal, pass course planning module in position;
When route planning module planning route arrival component current position and two-dimension code recognition device identification is corresponding During the Quick Response Code of component, restarting route planning module planning Real-time Component position is to component in positional information database Position route.
Using such scheme, the initial position in initial position data storehouse is transferred by central processing unit, and it is fixed in real time Position device can cook up corresponding route, be advantageous to staff and quickly find need component to be mounted.
Preferably, also include route error prompting module, when real-time positioning apparatus is not advised according to route planning module When drawing route, the central processing unit, which starts route error prompting module, to be reminded in staff.
Using such scheme, pass course error prompting module can be reminded staff, avoid staff not Staff is reminded when walking wrong by programme path, so as to avoid the possibility that staff goes to the wrong way route Property, improve the efficiency of installation component.
Preferably, also including total price computing module and component Pricedata, the central processing unit is with acquired Component corresponding price is transferred in framework Pricedata, and start total price computing module and add up the price of each component And the result of accumulation calculating is shown at display module.
Using such scheme, quickly obtained from component Pricedata by identification of the two-dimension code recognition device to framework The price of each component is taken, and after the price of each component is known, each framework valency can be passed through by total price computing module Cumulative, the corresponding calculating total price of acquisition of lattice.
In summary, the invention has the advantages that:By location information data storehouse, real-time positioning apparatus and Route planning module can planning personnel by component be transported to needed for installation component position, and combining construction method data Storehouse may be notified that in the installation method of staff's counterpart member, and in staff not according to set by route planning module When route is walked, pass course error prompting module reminds staff.
Brief description of the drawings
Fig. 1 is in the system block diagram of BIM project management system using Quick Response Code.
Embodiment
The present invention is described in further detail below in conjunction with accompanying drawing.
Include being used to identify the two of the two-dimension code label fitted on component in BIM project management system using Quick Response Code Tie up code recognition device, the component information database for being stored with Quick Response Code corresponding informance situation, BIM models, display module, Yi Jizhong Central processor, the BIM models are shown at display module;Two-dimension code recognition device is not limited to code reader, mobile phone, in addition to Remaining can obtain the barcode scanning equipment of corresponding information by barcode scanning, and preferably mobile phone, BIM models are mainly three-dimensional building mould herein Type, display module refer to be arranged at the display screen on two-dimension code recognition device, in order to which staff quickly obtains chip, in Centre processing represents CPU accordingly.
When two-dimension code recognition device is transferred in component information database using the two-dimension code label identified as querying condition Go out the information of corresponding component and transmit to central processing unit, the central processing unit controls BIM models in display module Place is highlighted acquired component, and respective members are quickly obtained beneficial to staff in BIM moulds by highlighted showing Position in type, be advantageous to efficiency of the staff in component installation location corresponding to searching.
In addition, storage has redundancy at two-dimension code label, redundancy refers to Quick Response Code to live part again Repeat, can effectively avoid when two-dimension code label damages, can not being scanned, and work as the two-dimension code recognition device When the Quick Response Code identified does not inquire corresponding informance in component information database, the central processing unit control two dimension Code recognition device obtains and identifies the redundancy in Quick Response Code and enter with the redundancy of all Quick Response Codes in information database Row is compared, and the component information situation compared in information database corresponding to successful Quick Response Code is transmitted to central processing unit In, it can be avoided significantly when two-dimension code label live part damages, by obtaining two-dimension code label with above-mentioned setting In redundancy, obtain corresponding label information.
Also include being stored with BIM models each component institute in reality in BIM project management system using Quick Response Code The location information data storehouse of corresponding positional information, the in real time real-time positioning apparatus of positioning two-dimension code recognition device position, And route planning module;Central processing unit transfers corresponding component with acquired counterpart member in location information data storehouse Positional information is as terminal, and using real-time positioning apparatus position as starting point, pass course planning module plans starting point to end The route of point is simultaneously shown at display module, and the side got beneficial to staff up to target is shown by programme path Formula, improve the efficiency of integral replacing component.
And when staff reaches component installation location, staff does not often know corresponding construction method, Therefore the construction method for also including being stored with construction method corresponding to all components in BIM project management system using Quick Response Code Database, stop route planning module when the position that real-time positioning apparatus is positioned reaches the position of counterpart member, and with right Answer component to transfer corresponding construction method in construction method database for querying condition and shown in display module, work people Member can quickly be constructed by the construction method shown at display module.
And due to the particularity in construction regulations, often different components has its specific engineering time, therefore answers Also include depositing arrangement of time database, the timing for having the different component engineering time in BIM project management system with Quick Response Code Prompting module, central processing unit are inquired about in arrangement of time database using the time as querying condition, arrived in the engineering time Reminded during the time default up to arrangement of time database by timing reminder module in staff, herein timing reminder module Alerting pattern be mainly to be reminded by luminous, generation form in staff.
Further, since staff does not often know counterpart member position when time block is reminded, also need The inquiry at the scene of progress is devoted a tremendous amount of time, so also including being used to store in BIM project management system using Quick Response Code The initial position data storehouse of component initial position;Central processing unit control obtains counterpart member information when institute with real-time positioning apparatus It is stored into position as the initial position of component in initial position data storehouse, and is querying condition in arrangement of time number using the time According to being inquired about in storehouse, when arrival time arranges database default time in the engineering time, the now engineering time is transferred Corresponding component, and the current position of component is transferred in initial position message database, determined with real-time positioning apparatus The position of position is starting point, corresponding route is planned in the current position of component as terminal, pass course planning module;Work as route Planning module to when and two-dimension code recognition device identification counterpart member Quick Response Code, start route planning module planning it is real-time Route of the component position to component in the position of positional information database.
Furthermore for, it is existing that route deviation etc. easily occurs during being walked according to route planning module for staff As, therefore also include route error prompting module in BIM project management system using Quick Response Code, when real-time positioning apparatus is not pressed During according to route planning module institute programme path, the central processing unit, which starts route error prompting module, to be reminded in staff, Route error prompting module reminds the mode in staff mainly to be reminded by way of vibrations in staff.
The average price of now all components is obtained for ease of staff, using Quick Response Code in BIM engineering management system System also includes total price computing module and component Pricedata, and the central processing unit is with acquired component in framework valency Corresponding price is transferred in lattice database, and start total price computing module add up each component price and by accumulation calculating As a result shown at display module, being advantageous to staff by the setting of total price computing module, quickly acquisition is corresponding total Valency.
Overall process is as follows:
Two-dimension code label is identified by two-dimension code recognition device first and compared in component information database to obtain component Information, and when the two-dimension code label identified does not inquire in framing information database, central processing can be passed through Device start two-dimension code recognition device will obtain two-dimension code label in Quick Response Code in redundancy, then with component information database Each component Quick Response Code in redundancy information be compared, and successful component will be compared and transmitted to central processing unit, Corresponding central processing unit can control corresponding component in BIM models to be highlighted, and being highlighted by component, and work people Member can obtain the position of installation needed for component accordingly.
And component is transported to the position of required installation by guiding staff preferably, with location information data storehouse Cooked up for terminal and real-time positioning apparatus institute position location as starting point, pass course planning module counterpart member position Corresponding route, and meeting pass course error prompting module is reminded staff when route malfunctions.
And because different component has the different set-up times to arrange, passage time arranges database and timing reminder module Staff is reminded timely to arrange to transport, and it is in place to the initial institute of component to start route planning module booting staff Put, so as to improve the efficiency that staff finds counterpart member.
In addition, staff by required component be transported to counterpart member positioned in positional information database put when, The construction method that counterpart member in construction method database can accordingly be transferred is informed in staff in the method shown.
This specific embodiment is only explanation of the invention, and it is not limitation of the present invention, people in the art Member can make the modification of no creative contribution to the present embodiment as needed after this specification is read, but as long as at this All protected in the right of invention by Patent Law.

Claims (8)

1. it is a kind of using Quick Response Code in BIM project management system, it is characterized in that:Including for identifying fit on component two Tie up the two-dimension code recognition device of code label, the component information database for being stored with Quick Response Code corresponding informance situation, BIM models, aobvious Show module and central processing unit, the BIM models are shown at display module;
When two-dimension code recognition device transfer out in component information database using the two-dimension code label identified as querying condition with Corresponding to component information and transmit to central processing unit, the central processing unit controls BIM models high at display module Component acquired in bright display.
2. it is according to claim 1 using Quick Response Code in BIM project management system, it is characterized in that:At two-dimension code label Storage has redundancy, when the Quick Response Code that the two-dimension code recognition device is identified does not inquire pair in component information database When answering information, central processing unit control two-dimension code recognition device obtain identify redundancy in Quick Response Code and with The redundancy of all Quick Response Codes is compared in information database, and it is right that successful Quick Response Code institute will be compared in information database The component information situation answered is transmitted into central processing unit.
3. it is according to claim 1 using Quick Response Code in BIM project management system, itsIt is characterized in:Also include being stored with The location information data storehouse of each component positional information corresponding in reality, the in real time identification of positioning Quick Response Code in BIM models The real-time positioning apparatus and route planning module of device position;
Central processing unit transferred using acquired counterpart member in location information data storehouse corresponding to member position information as Terminal, using real-time positioning apparatus position as starting point, pass course planning module planning starting point to the end route and in Shown at display module.
4. it is according to claim 3 using Quick Response Code in BIM project management system, it is characterized in that:Also include being stored with The construction method database of construction method corresponding to all components, when the position that real-time positioning apparatus is positioned reaches counterpart member Position when stop route planning module, and corresponding to transferring in construction method database using counterpart member as querying condition Construction method is simultaneously shown in display module.
5. it is according to claim 4 using Quick Response Code in BIM project management system, it is characterized in that:Also have including storage The arrangement of time database of different component engineering time, timing reminder module, central processing unit using the time as querying condition in when Between arrange to be inquired about in database, by regularly carrying when in the engineering time, arrival time arranges database default time Awake module is reminded in staff.
6. it is according to claim 5 using Quick Response Code in BIM project management system, it is characterized in that:Also include being used to deposit Store up the initial position data storehouse of component initial position;
Initial position of the central processing unit control using position during real-time positioning apparatus acquisition counterpart member information as component It is stored into initial position data storehouse, and is inquired about using the time as querying condition in arrangement of time database, in construction Between when arrival time when arranging database default time, transfer the component corresponding to the now engineering time, and in initial bit Put and the current position of component is transferred in information database, it is current as starting point, component using the position that real-time positioning apparatus is positioned Corresponding route is planned as terminal, pass course planning module in position;
When route planning module planning route arrival component current position and two-dimension code recognition device identification is corresponding The Quick Response Code of component, restarting route planning module planning Real-time Component position is to component in positional information database The route of position.
7. it is according to claim 6 using Quick Response Code in BIM project management system, it is characterized in that:It is wrong also to include route False alert module, when real-time positioning apparatus is not according to route planning module institute programme path, the central processing unit starts road Line error prompting module is reminded in staff.
8. it is according to claim 1 using Quick Response Code in BIM project management system, it is characterized in that:Also include total price meter Calculate module and component Pricedata, the central processing unit are transferred with acquired component in framework Pricedata Corresponding price, and start total price computing module add up each component price and by the result of accumulation calculating in display module Place's display.
CN201711061133.XA 2017-11-02 2017-11-02 Using Quick Response Code in BIM project management system Pending CN107730142A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711061133.XA CN107730142A (en) 2017-11-02 2017-11-02 Using Quick Response Code in BIM project management system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711061133.XA CN107730142A (en) 2017-11-02 2017-11-02 Using Quick Response Code in BIM project management system

Publications (1)

Publication Number Publication Date
CN107730142A true CN107730142A (en) 2018-02-23

Family

ID=61221248

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711061133.XA Pending CN107730142A (en) 2017-11-02 2017-11-02 Using Quick Response Code in BIM project management system

Country Status (1)

Country Link
CN (1) CN107730142A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109272421A (en) * 2018-09-12 2019-01-25 浙江三凯工程管理有限公司 A kind of assembled architecture quality control system and its method
CN109740218A (en) * 2018-12-25 2019-05-10 三箭建设工程集团有限公司 A kind of steel construction integral hoisting system based on BIM
CN109886868A (en) * 2019-02-21 2019-06-14 中水北方勘测设计研究有限责任公司 Portable engineering BIM model projection device and method based on augmented reality

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104978696A (en) * 2015-06-09 2015-10-14 广州市水电设备安装有限公司 Electronic acceptance and handover method based on BIM technology
CN105023201A (en) * 2015-07-24 2015-11-04 中建三局第一建设工程有限责任公司 Assembled building detailed design and construction method based on BIM (Building Information Modeling) and large data
US9460479B1 (en) * 2011-09-02 2016-10-04 Trimble Navigation Ltd Dispensable smart target/ re-usable smart target
CN106384200A (en) * 2016-09-27 2017-02-08 朱海涛 BIM (Building Information Modeling) technology-based management and application method of construction multidimensional model
CN106909749A (en) * 2017-03-08 2017-06-30 朱海涛 Mobile terminal is based on the Intelligent Recognition localization method of BIM
CN106919765A (en) * 2017-03-08 2017-07-04 朱海涛 Component processing method based on BIM and mobile terminal
CN107215779A (en) * 2017-07-13 2017-09-29 中联重科股份有限公司 Method, device and system for hoisting assembly type building component

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US9460479B1 (en) * 2011-09-02 2016-10-04 Trimble Navigation Ltd Dispensable smart target/ re-usable smart target
CN104978696A (en) * 2015-06-09 2015-10-14 广州市水电设备安装有限公司 Electronic acceptance and handover method based on BIM technology
CN105023201A (en) * 2015-07-24 2015-11-04 中建三局第一建设工程有限责任公司 Assembled building detailed design and construction method based on BIM (Building Information Modeling) and large data
CN106384200A (en) * 2016-09-27 2017-02-08 朱海涛 BIM (Building Information Modeling) technology-based management and application method of construction multidimensional model
CN106909749A (en) * 2017-03-08 2017-06-30 朱海涛 Mobile terminal is based on the Intelligent Recognition localization method of BIM
CN106919765A (en) * 2017-03-08 2017-07-04 朱海涛 Component processing method based on BIM and mobile terminal
CN107215779A (en) * 2017-07-13 2017-09-29 中联重科股份有限公司 Method, device and system for hoisting assembly type building component

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109272421A (en) * 2018-09-12 2019-01-25 浙江三凯工程管理有限公司 A kind of assembled architecture quality control system and its method
CN109740218A (en) * 2018-12-25 2019-05-10 三箭建设工程集团有限公司 A kind of steel construction integral hoisting system based on BIM
CN109740218B (en) * 2018-12-25 2023-03-24 三箭建设工程集团有限公司 Steel construction integral hoisting system based on BIM
CN109886868A (en) * 2019-02-21 2019-06-14 中水北方勘测设计研究有限责任公司 Portable engineering BIM model projection device and method based on augmented reality

Similar Documents

Publication Publication Date Title
CN107730142A (en) Using Quick Response Code in BIM project management system
CN103186833B (en) Assets management method based on Internet of Things and system
CN103984346A (en) System and method for intelligent warehousing checking
US20160125757A1 (en) Operator support system, operator support method and component mounting apparatus
CN109087048A (en) Two-dimensional code-based assembled building component tracking method
CN106789221A (en) Automobile storage site management system and its management method based on UWB positioning
CN105069590A (en) Factory order goods tracing and monitoring method
CN104484781A (en) Internet of Things technology-based steel cargo fast storage operation device and method
CN206298231U (en) Elevator repair and maintenance managing device based on bluetooth and Mobile Data Communication Technology
JP2015043138A (en) Material management method and material management system
CN103576658A (en) Production tracking control method for lead-acid cells
CN204856612U (en) Steel construction construction management system based on mobile internet
CN113065623A (en) Prefabricated part storage yard management method and device, computer equipment and storage medium thereof
CN102332099A (en) Server property automatic checking information processing method and device in server machine cabinet
CN112684768A (en) MES system-based method and system for automatically associating material information
CN109345171A (en) A kind of information processing method, terminal and server, label
CN111476330A (en) Remote supervision and installation guidance system and method for manufacturing of electrical equipment of transformer substation
CN106312507A (en) Method for controlling assembly line of multi-type cylinder covers and cylinder bodies of engines
JP2006277176A (en) Facility equipment management system
KR101557693B1 (en) Inspection systems of the reinforcement progress, method
CN113537664B (en) Method, device and system for determining vehicle
CN109960231A (en) A kind of production management system and its method based on Internet of Things
CN208636890U (en) A kind of long-range Work attendance device for electric power safety monitoring
JP2017146866A (en) Apparatus monitoring system
CN207115477U (en) Sampling management system and sampling terminal

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180223