CN107724254A - The synchronization of jacking up of construction of bridge T beam changes construction method with making - Google Patents

The synchronization of jacking up of construction of bridge T beam changes construction method with making Download PDF

Info

Publication number
CN107724254A
CN107724254A CN201710730975.3A CN201710730975A CN107724254A CN 107724254 A CN107724254 A CN 107724254A CN 201710730975 A CN201710730975 A CN 201710730975A CN 107724254 A CN107724254 A CN 107724254A
Authority
CN
China
Prior art keywords
jacking
stress
construction
bridge
displacement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710730975.3A
Other languages
Chinese (zh)
Inventor
卢士军
孔庆欣
张印贵
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BEIJING GONGLIAN JIEDA HIGHWAY MAINTENANCE ENGINEERING Co Ltd
Original Assignee
BEIJING GONGLIAN JIEDA HIGHWAY MAINTENANCE ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING GONGLIAN JIEDA HIGHWAY MAINTENANCE ENGINEERING Co Ltd filed Critical BEIJING GONGLIAN JIEDA HIGHWAY MAINTENANCE ENGINEERING Co Ltd
Priority to CN201710730975.3A priority Critical patent/CN107724254A/en
Publication of CN107724254A publication Critical patent/CN107724254A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D22/00Methods or apparatus for repairing or strengthening existing bridges ; Methods or apparatus for dismantling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

A kind of construction of bridge T beam synchronization of jacking up changes construction method with making, and comprises the following steps:Preanalysis and calculating are carried out to the jacking displacement at each girder first;Then to each stress point, stress preanalysis and calculating are carried out.The present invention top lifting power and top lifting height in work progress carry out dual control, based on the highness change between total top lifting height and summit, supplemented by top lift;The preliminary foundation jacked using theoretical top lifting masterpiece as box beam, when close to theoretical top lifting power, take that micro, jack-up method slowly jacks step by step;Fall beam time stage, slowly fall after rise;Tightly monitor the measured stress and deformation at each measuring point, supervision construction;Once there are displacement or overstressing or abnormal conditions, stop construction immediately, search reason in time;Before falling beam, each T soffit and platform cap are monitored according to design requirement(Bracket)Clear height between top surface, so as to ensure that the reliability of construction, reduce difficulty of construction.

Description

The synchronization of jacking up of construction of bridge T beam changes construction method with making
Technical field
The present invention relates to technical field of bridge construction, specially a kind of construction of bridge T beam synchronization of jacking up changes construction party with making Method.
Background technology
After long-term use, former laminated rubber bearing shearing change, aging, cracking disease are serious, lose it for domestic bridge Using concrete rubbish be present in function and beam-ends expansion joint, bridge span structure is caused in the presence of the uniform temperature difference, mobile load, longitudinal direction Deformation suffers restraints.To ensure that superstructure can be freely under the effect of the factors such as load, temperature change and concrete shrinkage and creep Deformation, makes the actual loading of structure, deformation meet design idea, and protects beam-ends, platform cap, bracket injury-free, thus Need to change all bearings at both sides end bay abutment and mid-span both sides bracket.
In the prior art, CN105297643A discloses a kind of hollow slab type Bridge Support Replacement method, the replacing options Including:Calculate jacking displacement:Each cored slab undersetting theory stress size is calculated, according to the modulus of elasticity and stress surface of bearing Product calculates deflection of each bearing under bridge Gravitative Loads, and wherein maximum deformation quantity and the lowest construction needed for replacing time is high Spend sum and jack displacement for the setting of cored slab;Equipment is installed:One jack of each corresponding installation of bearing, according to each hollow The different top lift of plate, corresponding jack is arranged in cored slab with the girt strip of one end, and cored slab is arranged in bearing Same length direction, each jack is arranged on the same width of cored slab, and displacement meter is arranged in the same one end of cored slab Two bearings among, and with jack on the same width of cored slab.
CN104005342A discloses a kind of bridge deformation dynamic synchronization jacking compensation method, and the compensation method includes following Step:Using main control computer, sub- pump and the mutually coordinated work of height sensor, and field monitoring data are combined, using more points Prosecutor formula, to parameters such as pressure value, lifting height, load differences, monitored using electronic system, it is ensured that multiple security protection, LCD Screen display integral construction situation.
CN103410104A discloses a kind of bearing replacement method of overhead road of city, for the overhead column within one The bearing of position is changed, and the replacing options provide unit, and the unit includes setting gradually from bottom to top All-hydraulic load transportation equipment, load-sharing girder, jacking apparatus, slewing equipment, crossbeam and synchronous jacking system, the water of the crossbeam Plane side is provided with operating platform.
However, in construction is changed, beam body jacking and bearing replacement difficulty of construction are very big, because clear height limits at bearing, Can not be directly in beam rib bottom surface and platform cap(Bracket)Lifting Equipment is directly disposed between top surface, especially at mid-span bracket, under bridge For navigable river, and structure stress is complicated at bracket, space is very narrow and small, and difficulty of construction is bigger, particular without synchronous to stress Accurate monitoring, easily forms beam-ends, platform cap, the local damage of bracket, therefore, it is proposed that a kind of construction of bridge T beam synchronization of jacking up with Make and change construction method.
The content of the invention
Construction method is changed with making it is an object of the invention to provide the synchronization of jacking up of construction of bridge T beam, to solve above-mentioned background The problem of being proposed in technology.
To achieve the above object, the present invention provides following technical scheme:A kind of construction of bridge T beam synchronization of jacking up is applied with making replacing Work method, comprises the following steps:Preanalysis and calculating are carried out to the jacking displacement at each girder first;Then to each stress point, Carry out stress preanalysis and calculating, and according to construction experience, form the Reference Stress of each stress point;Then according to each stress point Jacking displacement at Reference Stress and each girder of direction across bridge, the top lift formed at each girder and jacking displacement;Before jacking, Mount stress sensor and displacement transducer at each girder of Reference Stress and direction across bridge of each stress point, and gather static data; The examination top of small stroke is carried out, behind repeatedly examination top, when each concrete numerical value is in term of reference, is formally jacked;Jacking Process should use classification jacking, and the stroke and jacking speed for determining jackings at different levels are calculated according to fixed each girder jacking displacement Degree, maximum displacement and jacking speed to every one-level stroke are controlled;During jacking, exceed ginseng when there is each concrete numerical value When in the range of examining, system automatic alarm, jacking process stops;After adjusted processing, system self-test again;When collection static data is equal When in term of reference, jacking process continues, but jacks speed and the reduction of corresponding stroke;After the completion of every grade of jacking, it is System self-test again;If a few minutes appearance without exception is stood, and when collection static data is in term of reference, next stage Jacking process continues;The decline process after being fully completed is jacked, is also monitored simultaneously, and adjustment in time is handled.
Preferably, need to carry out the stress etc. of whole movement locus, overall posture, structure during the bridge jacking Monitoring in real time.
Preferably, the monitoring content includes bridge entirety posture, displacement, structural stress etc., and monitoring work will be through Jack, hold lotus and fall in the whole work progress of beam.
Preferably, during the jacking, the maximum displacement per one-level stroke is controlled within 1mm, jacks speed control It is more steady within 3 minutes 1mm, after jacking in place, automatic locking jack, not oil return are controlled by computer.
Preferably, need to be monitored the superstructure of bridge during the jacking, the particular content of monitoring is each The vertical and vertical, horizontal displacement of beam body at Jacking point, the stress at each end of main beam diaphragm plate top, bottom and floorings;End bay T The development of diagonal crack near beam beam rib Vertical Cracks disease and beam-ends;Visual examination prison is carried out to expansion joint, deck paving Control, and the dilatation situation at expansion joint.
Compared with prior art, the beneficial effects of the invention are as follows:Top lifting power and top lifting height carry out dual control in work progress, Based on highness change between total top lifting height and summit, supplemented by top lift;Jacked using theoretical top lifting masterpiece as box beam Preliminary foundation, when close to theoretical top lifting power, take that micro, jack-up method slowly jacks step by step;Fall beam time stage, slowly return Fall;Tightly monitor the measured stress and deformation at each measuring point, supervision construction;Once there is displacement or overstressing or exception Situation, stop construction immediately, search reason in time;Before falling beam, each T soffit and platform cap are monitored according to design requirement(Bracket) Clear height between top surface, so as to ensure that the reliability of construction, reduce difficulty of construction.
Brief description of the drawings
Fig. 1 is flow chart of the method for the present invention.
Embodiment
The technical scheme in the embodiment of the present invention is clearly and completely described below, it is clear that described embodiment Only part of the embodiment of the present invention, rather than whole embodiments.Based on the embodiment in the present invention, the common skill in this area The every other embodiment that art personnel are obtained under the premise of creative work is not made, belong to the model that the present invention protects Enclose.
Referring to Fig. 1, the present invention provides a kind of technical scheme:The synchronization of jacking up of construction of bridge T beam changes construction method with making, bag Include following steps:Preanalysis and calculating are carried out to the jacking displacement at each girder first;Then to each stress point, it is pre- to carry out stress Analysis and calculate, and according to construction experience, form the Reference Stress of each stress point;Then according to the Reference Stress of each stress point and Jacking displacement at each girder of direction across bridge, the top lift formed at each girder and jacking displacement;Before jacking, in each stress point Mount stress sensor and displacement transducer at Reference Stress and each girder of direction across bridge, and gather static data;Carry out small stroke Examination top, through repeatedly examination top after, when each concrete numerical value is in term of reference, formally jacked;Jacking process should use Classification jacking, the stroke and jacking speed for determining jackings at different levels are calculated according to fixed each girder jacking displacement, to every one-level The maximum displacement of stroke and jacking speed are controlled;During jacking, when there is each concrete numerical value in term of reference, System automatic alarm, jacking process stop;After adjusted processing, system self-test again;When collection static data is in referring to model When enclosing interior, jacking process continues, but jacks speed and the reduction of corresponding stroke;Every grade jacking after the completion of, system again from Inspection;If stand a few minutes appearance without exception, and when collect static data be in term of reference when, next stage jack process after It is continuous to carry out;The decline process after being fully completed is jacked, is also monitored simultaneously, and adjustment in time is handled.
Embodiment one:
Preanalysis and calculating are carried out to the jacking displacement at each girder first;Then to each stress point, carry out stress preanalysis and Calculate, and according to construction experience, form the Reference Stress of each stress point;Then according to the Reference Stress and direction across bridge of each stress point Jacking displacement at each girder, the top lift formed at each girder and jacking displacement;, should in the reference of each stress point before jacking Mount stress sensor and displacement transducer at power and each girder of direction across bridge, and gather static data;The examination top of small stroke is carried out, Behind repeatedly examination top, when each concrete numerical value is in term of reference, formally jacked;Jacking process should use classification top Rise, the stroke and jacking speed for determining jackings at different levels are calculated according to fixed each girder jacking displacement, to every one-level stroke Maximum displacement and jacking speed are controlled;During jacking, when there is each concrete numerical value in term of reference, system is certainly Dynamic alarm, jacking process stop;After adjusted processing, system self-test again;When collection static data is in term of reference, Jacking process continues, but jacks speed and the reduction of corresponding stroke;After the completion of every grade of jacking, system self-test again;Stand If a few minutes appearance without exception, and when collection static data is in term of reference, next stage jacking process continues; The decline process after being fully completed is jacked, is also monitored simultaneously, and adjustment in time is handled.
Embodiment two:
In embodiment one, along with following processes:
Need to monitor the stress etc. of whole movement locus, overall posture, structure in real time during bridge jacking.
Preanalysis and calculating are carried out to the jacking displacement at each girder first;Then to each stress point, carry out stress and divide in advance Analysis and calculate, and according to construction experience, form the Reference Stress of each stress point;Then according to the Reference Stress and horizontal stroke of each stress point Bridge is to the jacking displacement at each girder, the top lift formed at each girder and jacking displacement;Before jacking, in the ginseng of each stress point Mount stress sensor and displacement transducer at stress and each girder of direction across bridge are examined, and gathers static data;Carry out small stroke Examination top, behind repeatedly examination top, when each concrete numerical value is in term of reference, formally jacked;Jacking process, which should use, divides Level jacking, the stroke and jacking speed for determining jackings at different levels are calculated according to fixed each girder jacking displacement, to every one-level row The maximum displacement of journey and jacking speed are controlled;Wherein, needed during bridge jacking to whole movement locus, overall appearance State, the stress etc. of structure are monitored in real time;During jacking, when there is each concrete numerical value in term of reference, system Automatic alarm, jacking process stop;After adjusted processing, system self-test again;When collection static data is in term of reference When, jacking process continues, but jacks speed and the reduction of corresponding stroke;After the completion of every grade of jacking, system self-test again;It is quiet If put a few minutes appearance without exception, and when collect static data be in term of reference when, next stage jacking process continue into OK;The decline process after being fully completed is jacked, is also monitored simultaneously, and adjustment in time is handled.
Embodiment three:
In embodiment two, along with following processes:
Monitoring content includes bridge entirety posture, displacement, structural stress etc., and monitoring work will be through jacking, hold lotus and Luo Liang Whole work progress in.
Preanalysis and calculating are carried out to the jacking displacement at each girder first;Then to each stress point, carry out stress and divide in advance Analysis and calculate, and according to construction experience, form the Reference Stress of each stress point;Then according to the Reference Stress and horizontal stroke of each stress point Bridge is to the jacking displacement at each girder, the top lift formed at each girder and jacking displacement;Before jacking, in the ginseng of each stress point Mount stress sensor and displacement transducer at stress and each girder of direction across bridge are examined, and gathers static data;Carry out small stroke Examination top, behind repeatedly examination top, when each concrete numerical value is in term of reference, formally jacked;Jacking process, which should use, divides Level jacking, the stroke and jacking speed for determining jackings at different levels are calculated according to fixed each girder jacking displacement, to every one-level row The maximum displacement of journey and jacking speed are controlled;Wherein, needed during bridge jacking to whole movement locus, overall appearance State, the stress etc. of structure are monitored in real time;Wherein, monitoring content includes bridge entirety posture, displacement, structural stress etc., prison Control work will be through jacking, hold lotus and fall in the whole work progress of beam;During jacking, exceed when there is each concrete numerical value When in term of reference, system automatic alarm, jacking process stops;After adjusted processing, system self-test again;When collection static data When being in term of reference, jacking process continues, but jacks speed and the reduction of corresponding stroke;After the completion of every grade of jacking, System self-test again;If a few minutes appearance without exception is stood, and when collection static data is in term of reference, it is next Level jacking process continues;The decline process after being fully completed is jacked, is also monitored simultaneously, and adjustment in time is handled.
Example IV:
In embodiment three, along with following processes:
During jacking, the maximum displacement per one-level stroke is controlled within 1mm, jacking speed control within 3 minutes 1mm more To be steady, after jacking in place, automatic locking jack, not oil return are controlled by computer.
Preanalysis and calculating are carried out to the jacking displacement at each girder first;Then to each stress point, carry out stress and divide in advance Analysis and calculate, and according to construction experience, form the Reference Stress of each stress point;Then according to the Reference Stress and horizontal stroke of each stress point Bridge is to the jacking displacement at each girder, the top lift formed at each girder and jacking displacement;Before jacking, in the ginseng of each stress point Mount stress sensor and displacement transducer at stress and each girder of direction across bridge are examined, and gathers static data;Carry out small stroke Examination top, behind repeatedly examination top, when each concrete numerical value is in term of reference, formally jacked;Jacking process, which should use, divides Level jacking, the stroke and jacking speed for determining jackings at different levels are calculated according to fixed each girder jacking displacement, to every one-level row The maximum displacement of journey and jacking speed are controlled;Wherein, needed during bridge jacking to whole movement locus, overall appearance State, the stress etc. of structure are monitored in real time;Wherein, monitoring content includes bridge entirety posture, displacement, structural stress etc., prison Control work will be through jacking, hold lotus and fall in the whole work progress of beam;During jacking, exceed when there is each concrete numerical value When in term of reference, system automatic alarm, jacking process stops;After adjusted processing, system self-test again;During jacking, Maximum displacement per one-level stroke is controlled within 1mm, and jacking speed control is more steady within 3 minutes 1mm, and jacking is in place Afterwards, automatic locking jack, not oil return are controlled by computer;When collection static data is in term of reference, process is jacked Continue, but jack speed and the reduction of corresponding stroke;After the completion of every grade of jacking, system self-test again;If stand a few minutes Appearance without exception, and when collection static data is in term of reference, next stage jacking process continues;Jacking is all After the completion of decline process, be also monitored simultaneously, and adjustment in time handle.
Embodiment five:
In example IV, along with following processes:
Need to be monitored the superstructure of bridge during jacking, the particular content of monitoring is the perpendicular of beam body at each Jacking point To and vertical, horizontal displacement, at the top of each end of main beam diaphragm plate, the stress of bottom and floorings;End bay T beam beam ribs Vertical Cracks disease The development of diagonal crack near evil and beam-ends;To stretching for expansion joint, deck paving progress visual examination monitoring, and expansion joint Compression deformation situation.
Preanalysis and calculating are carried out to the jacking displacement at each girder first;Then to each stress point, carry out stress and divide in advance Analysis and calculate, and according to construction experience, form the Reference Stress of each stress point;Then according to the Reference Stress and horizontal stroke of each stress point Bridge is to the jacking displacement at each girder, the top lift formed at each girder and jacking displacement;Before jacking, in the ginseng of each stress point Mount stress sensor and displacement transducer at stress and each girder of direction across bridge are examined, and gathers static data;Carry out small stroke Examination top, behind repeatedly examination top, when each concrete numerical value is in term of reference, formally jacked;Jacking process, which should use, divides Level jacking, the stroke and jacking speed for determining jackings at different levels are calculated according to fixed each girder jacking displacement, to every one-level row The maximum displacement of journey and jacking speed are controlled;Wherein, needed during bridge jacking to whole movement locus, overall appearance State, the stress etc. of structure are monitored in real time;Wherein, monitoring content includes bridge entirety posture, displacement, structural stress etc., prison Control work will be through jacking, hold lotus and fall in the whole work progress of beam;During jacking, exceed when there is each concrete numerical value When in term of reference, system automatic alarm, jacking process stops;After adjusted processing, system self-test again;During jacking, Maximum displacement per one-level stroke is controlled within 1mm, and jacking speed control is more steady within 3 minutes 1mm, and jacking is in place Afterwards, automatic locking jack, not oil return are controlled by computer;Need to be monitored the superstructure of bridge during jacking, The particular content of monitoring is the vertical and vertical, horizontal displacement of beam body at each Jacking point, at the top of each end of main beam diaphragm plate, bottom and The stress of floorings;The development of diagonal crack near end bay T beam beam rib Vertical Cracks diseases and beam-ends;To expansion joint, bridge floor Mat formation and carry out visual examination monitoring, and the dilatation situation at expansion joint;When collection static data is in term of reference, Jacking process continues, but jacks speed and the reduction of corresponding stroke;After the completion of every grade of jacking, system self-test again;Stand If a few minutes appearance without exception, and when collection static data is in term of reference, next stage jacking process continues; The decline process after being fully completed is jacked, is also monitored simultaneously, and adjustment in time is handled.
In the present invention, beam body jacking, the main construction procedure of bearing replacement are:Preparation of construction → arrangement jacking the strong point → Jack and synchronous facility → setting monitoring system → traffic control, limiting vehicle speed → in batches by pier synchronization of jacking up beam body are installed → the prefabricated temporary support of installation after jacking is in place → falls beam → bearing replacement construction → synchronization of jacking up again → to put for the first time Put bearing → fall beam.
Top lifting power and top lifting height carry out dual control in work progress, with the highness change between total top lifting height and summit Based on, supplemented by top lift;The preliminary foundation jacked using theoretical top lifting masterpiece as box beam, when close to theoretical top lifting power, take micro- Amount, jack-up method slowly jacks step by step;Fall beam time stage, slowly fall after rise;Tightly monitor the measured stress at each measuring point and deformation Situation, supervision construction;Once there are displacement or overstressing or abnormal conditions, stop construction immediately, search reason in time;Fall beam Before, monitor each T soffit and platform cap according to design requirement(Bracket)Clear height between top surface, so as to ensure that the reliable of construction Property, reduce difficulty of construction.
Although an embodiment of the present invention has been shown and described, for the ordinary skill in the art, can be with A variety of changes, modification can be carried out to these embodiments in the case where not departing from the principle of the present invention and design, replace by understanding And modification, the scope of the present invention is defined by the appended.

Claims (5)

1. the synchronization of jacking up of construction of bridge T beam changes construction method with making, comprise the following steps:First to the jacking displacement at each girder Carry out preanalysis and calculating;Then stress preanalysis and calculating are carried out to each stress point, and according to construction experience, formed respectively by The Reference Stress in force;Then according to the jacking displacement at the Reference Stress of each stress point and each girder of direction across bridge, each master is formed Liang Chu top lift and jacking displacement;Before jacking, the mount stress at each girder of Reference Stress and direction across bridge of each stress point Sensor and displacement transducer, and gather static data;The examination top of small stroke is carried out, behind repeatedly examination top, each concrete numerical value is equal When in term of reference, formally jacked;Jacking process is jacked using classification, and displacement is jacked according to fixed each girder The stroke for determining jackings at different levels and jacking speed are calculated, the maximum displacement and jacking speed to every one-level stroke are controlled;Top During rising, when there is each concrete numerical value in term of reference, system automatic alarm, jacking process stops;Adjusted place After reason, system self-test again;When collection static data is in term of reference, jacking process continues, but jacks speed And corresponding stroke is reduced;After the completion of every grade of jacking, system self-test again;If a few minutes appearance without exception is stood, and when collection When static data is in term of reference, next stage jacking process continues;The decline process after being fully completed is jacked, It is monitored simultaneously, and adjustment in time is handled.
2. construction of bridge T beam synchronization of jacking up according to claim 1 changes construction method with making, it is characterised in that:The bridge Back needs to monitor the stress etc. of whole movement locus, overall posture, structure in real time during rising.
3. construction of bridge T beam synchronization of jacking up according to claim 2 changes construction method with making, it is characterised in that:The prison Controlling content includes bridge entirety posture, displacement, structural stress etc., and monitoring work will be through jacking, hold lotus and fall the whole of beam In work progress.
4. construction of bridge T beam synchronization of jacking up according to claim 1 changes construction method with making, it is characterised in that:The top During rising, the maximum displacement per one-level stroke is controlled within 1mm, and jacking speed control is more flat within 3 minutes 1mm Surely, after jacking in place, automatic locking jack, not oil return are controlled by computer.
5. construction of bridge T beam synchronization of jacking up according to claim 1 changes construction method with making, it is characterised in that:The top Need to be monitored the superstructure of bridge during rising, the particular content of monitoring for beam body vertical at each Jacking point and Vertical, horizontal displacement, the stress at each end of main beam diaphragm plate top, bottom and floorings;End bay T beam beam rib Vertical Cracks diseases and The development of diagonal crack near beam-ends;Visual examination monitoring, and the flexible change at expansion joint are carried out to expansion joint, deck paving Shape situation.
CN201710730975.3A 2017-08-23 2017-08-23 The synchronization of jacking up of construction of bridge T beam changes construction method with making Pending CN107724254A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710730975.3A CN107724254A (en) 2017-08-23 2017-08-23 The synchronization of jacking up of construction of bridge T beam changes construction method with making

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710730975.3A CN107724254A (en) 2017-08-23 2017-08-23 The synchronization of jacking up of construction of bridge T beam changes construction method with making

Publications (1)

Publication Number Publication Date
CN107724254A true CN107724254A (en) 2018-02-23

Family

ID=61205271

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710730975.3A Pending CN107724254A (en) 2017-08-23 2017-08-23 The synchronization of jacking up of construction of bridge T beam changes construction method with making

Country Status (1)

Country Link
CN (1) CN107724254A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108756292A (en) * 2018-09-05 2018-11-06 山东建筑大学 A kind of building synchronization of jacking up control method and system based on technology of Internet of things
CN109235292A (en) * 2018-10-18 2019-01-18 石家庄铁道大学 Railroad bridge changes beam process and changes girder system system
CN110644381A (en) * 2019-10-12 2020-01-03 杭州交投科技工程有限公司 Bridge jacking method
CN110904862A (en) * 2018-10-18 2020-03-24 石家庄铁道大学 Railway bridge beam replacing assembly process and beam replacing process
CN111765997A (en) * 2020-07-22 2020-10-13 中铁二十三局集团第二工程有限公司 Incremental launching beam monitoring and controlling construction method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102966045A (en) * 2011-09-01 2013-03-13 湖南华鼎建筑科技有限公司 Bridge supporting replacement synchronous ejecting device
CN103046767A (en) * 2012-12-20 2013-04-17 浙江省第一水电建设集团股份有限公司 Dual-control synchronous jacking construction method of PLC (Programmable Logic Controller) computer slot body
CN104005342A (en) * 2014-05-28 2014-08-27 北京市政建设集团有限责任公司 Method and device for dynamic synchronous jacking compensation of bridge distortion
CN104988845A (en) * 2015-07-17 2015-10-21 重庆桥都桥梁技术有限公司 Bridge bearer exchanging and newly-installation leveling method
KR101715641B1 (en) * 2016-08-17 2017-03-14 씨에스글로벌 주식회사 Bridge Lifting Up-Down System Using Laser Sensor and Operating Method thereof

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102966045A (en) * 2011-09-01 2013-03-13 湖南华鼎建筑科技有限公司 Bridge supporting replacement synchronous ejecting device
CN103046767A (en) * 2012-12-20 2013-04-17 浙江省第一水电建设集团股份有限公司 Dual-control synchronous jacking construction method of PLC (Programmable Logic Controller) computer slot body
CN104005342A (en) * 2014-05-28 2014-08-27 北京市政建设集团有限责任公司 Method and device for dynamic synchronous jacking compensation of bridge distortion
CN104988845A (en) * 2015-07-17 2015-10-21 重庆桥都桥梁技术有限公司 Bridge bearer exchanging and newly-installation leveling method
KR101715641B1 (en) * 2016-08-17 2017-03-14 씨에스글로벌 주식회사 Bridge Lifting Up-Down System Using Laser Sensor and Operating Method thereof

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
于心然等: "连续T梁同步顶升更换支座的施工监控技术", 《西部交通科技》 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108756292A (en) * 2018-09-05 2018-11-06 山东建筑大学 A kind of building synchronization of jacking up control method and system based on technology of Internet of things
CN109235292A (en) * 2018-10-18 2019-01-18 石家庄铁道大学 Railroad bridge changes beam process and changes girder system system
CN110904862A (en) * 2018-10-18 2020-03-24 石家庄铁道大学 Railway bridge beam replacing assembly process and beam replacing process
CN110644381A (en) * 2019-10-12 2020-01-03 杭州交投科技工程有限公司 Bridge jacking method
CN111765997A (en) * 2020-07-22 2020-10-13 中铁二十三局集团第二工程有限公司 Incremental launching beam monitoring and controlling construction method

Similar Documents

Publication Publication Date Title
CN107724254A (en) The synchronization of jacking up of construction of bridge T beam changes construction method with making
CN100453999C (en) 32m/900t prestressed concrete pretension box beam static loading test method
CN109778721A (en) Synchronization of jacking up bridge top and the bottom structure carries out the method that bridge increases transformation
CN109629461A (en) A method of it does not break off a friendship and carries out cast-in-situ box girder reset and bearing replacement
CN107060105B (en) Lifting construction method for multiple steel galleries between tower buildings
CN108797382A (en) Old bridge Integral synchronous jacks heightening construction method
CN110528678A (en) A kind of multilayer steel frame vestibule installation method between staggered floor high building
CN104099868A (en) Bridge jacking synchronous control integration system
CN110629675A (en) Cast-in-place pier top rotating and cantilever pouring combined construction method for continuous beam support
CN112144406A (en) Construction method for replacing support by integrally and synchronously jacking bridge
CN110230328A (en) Pile foundation underpinning System information construction electronic monitoring method
CN108824210B (en) Prepressing method of bridge support
CN106092629B (en) The ship lift ship compartment compartment Shui Man performance test method
CN109610345A (en) Swivel bridges fall beam construction method
CN111827138B (en) Construction method for replacing disc type support of plate type support in rail transit
CN103758359B (en) A kind of safe and reliable joist post construction system and construction method thereof
CN105155418A (en) Construction method for bridge horizontal movement
CN210216183U (en) Deviation brake for continuous bridge junction pier
Li et al. Analysis and monitoring on jacking construction of continuous box girder bridge
CN104894981B (en) Reaction frame pre-pressing system for bracket of cantilever section
CN103147402A (en) Support device for constructing continuous box girder bridge and elevation adjusting method
CN112761081B (en) Replacement structure and construction method for active ultra-wide beam body support
CN203795884U (en) Safe and reliable construction system for replacing columns by holding beams
CN110158480B (en) Elevation adjusting method for beam body at bridge support
CN110158490A (en) Continuous beam synchronization of jacking up construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180223