CN107700840A - Formwork structure - Google Patents

Formwork structure Download PDF

Info

Publication number
CN107700840A
CN107700840A CN201710938196.2A CN201710938196A CN107700840A CN 107700840 A CN107700840 A CN 107700840A CN 201710938196 A CN201710938196 A CN 201710938196A CN 107700840 A CN107700840 A CN 107700840A
Authority
CN
China
Prior art keywords
joist
formwork structure
steel bar
fixed
side template
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710938196.2A
Other languages
Chinese (zh)
Inventor
王龙
江华
黄燕
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Baoye Group Corp Ltd
Original Assignee
Shanghai Baoye Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Baoye Group Corp Ltd filed Critical Shanghai Baoye Group Corp Ltd
Priority to CN201710938196.2A priority Critical patent/CN107700840A/en
Publication of CN107700840A publication Critical patent/CN107700840A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G13/00Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills
    • E04G13/06Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills for stairs, steps, cornices, balconies, or other parts corbelled out of the wall
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04DROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
    • E04D13/00Special arrangements or devices in connection with roof coverings; Protection against birds; Roof drainage ; Sky-lights
    • E04D13/04Roof drainage; Drainage fittings in flat roofs, balconies or the like
    • E04D13/064Gutters
    • E04D13/0646Gutters made of concrete or stone-like material

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The invention provides a kind of formwork structure, including:Joist unit, it is encorbelmented in factory building main body;Outside side template, is steel bar truss floor support plate, and the upper surface of the joist unit is fixed in its bottom, and the upper surface of the outside side template and the joist unit forms the outboard template of outer gutter;Bracing piece, it is be arranged in parallel with the outside side template, and runs through and be fixed on steel bar girder therein;Internal side template, it is connected by connecting bolt with the bracing piece.Formwork structure provided by the invention, combine to form formwork structure with steel bar truss floor support plate using the joist unit encorbelmented, without setting up scaffold formwork, cancel form bracing system.Construction cost is low, difficulty of construction bottom, and quality is secure.

Description

Formwork structure
Technical field
The present invention relates to technical field of building construction, is a kind of formwork structure specifically.
Background technology
Gutter refers to the recessed portion between the hip of building roofing two.Roof drainage divides functional in organized water drainage and inorganization draining (certainly By draining), functional in organized water drainage is usually that the ditch for gathering rainwater is thus referred to as day being arranged down again by rain pipe in rainwater collection to gutter Ditch, the interior gutter of gutter point and outer gutter, interior gutter refer to the gutter within exterior wall, typically have parapet, outer gutter is to choose The gutter of exterior wall, does not have parapet typically.
Traditional gutter construction technology is considerably complicated, and scaffold formwork is set up using scene.This method is taken a lot of work, is time-consuming, consumption Material, long construction period, labor intensity are big, construction cost is high and quality is difficult to ensure.Especially to industrialization, the steel of factorial praluction More complicated, problem of being constructed for the gutter in structural construction house is more prominent.
The content of the invention
The technical problem to be solved in the present invention is to provide a kind of formwork structure, without setting up scaffold formwork, cancels template Support system.
In order to solve the above technical problems, the invention provides a kind of formwork structure, including:
Joist unit, it is encorbelmented in factory building main body;
Outside side template, is steel bar truss floor support plate, and the upper surface of the joist unit, the outside are fixed in its bottom The upper surface of side template and the joist unit forms the outboard template of outer gutter;
Bracing piece, it is be arranged in parallel with the outside side template, and runs through and be fixed on steel bar girder therein;
Internal side template, it is connected by connecting bolt with the bracing piece;
Steel bar framework, it is arranged at the bottom of the outer gutter, and both ends are connected with the steel bar girder.
Further, the joist unit includes:
Multiple first joists, in multiple first joists are generally aligned in the same plane, be arranged in parallel between each other, and encorbelment in The factory building main body;
Multiple second joists, each described second joist, its length direction is consistent with the bearing of trend of the outer gutter, It is arranged between two first joists, and its both ends is individually fixed in two first joists;
Multiple bottom plates, be fixed on the upper surface of first joist and the second joist, for block first joist and Breach between second joist.
Further, the bottom plate is fixed on the upper surface of first joist and the second joist by peg.
Further, the bottom plate is firm board, and the bearing of trend of its watt of groove is vertical with the bearing of trend of the outer gutter.
Further, first joist and second joist are " H " shaped steel, also, its edge of a wing is parallel to the ground Place.
Further, in addition to plugging plate, the outside side template and the junction of the joist unit are arranged at, is used for Sealing.
Further, the plugging plate is right angle component.
Further, one side of the plugging plate is fixedly welded on the upper surface of the joist unit, and another side is arranged at Between the bed die and steel bar girder of the outside side template, and be welded and fixed with the contour plate, the steel bar girder with it is described The upper surface of joist unit is welded and fixed.
Further, the commissure of the plugging plate is coated with fluid sealant.
Further, the bracing piece is right angle component.
Formwork structure provided by the invention, combine to form template knot with steel bar truss floor support plate using the joist unit encorbelmented Structure, without setting up scaffold formwork, cancel form bracing system.Construction cost is low, difficulty of construction bottom, and quality is secure.
Brief description of the drawings
Fig. 1 is the schematic diagram of formwork structure of the present invention;
Fig. 2 is the structural representation of joist unit in this practical formwork structure.
In figure, 1. factory building main bodys, 2. first joists, 3. second joists, 4. outside side templates, 41. bed dies, 42. reinforcing bar purlins Frame, 5. bottom plates, 6. inside side templates, 7. plugging plates, 8. bracing pieces, 9. pegs, 10. steel bar frameworks.
Embodiment
The invention will be further described with specific embodiment below in conjunction with the accompanying drawings, so that those skilled in the art can be with More fully understand the present invention and can be practiced, but illustrated embodiment is not as a limitation of the invention.
Steel bar truss floor support plate is that the reinforcing bar in floor is processed into steel bar girder using import equipment in factory, and by steel Muscle truss is with galvanized steel plain sheet in the integrally welded gang form of factory.The template system be by the reinforcing bar in concrete floor with Construction formwork is combined into one, and composition one can bear the load-bearing structure of water-bearing concreae deadweight and construction loads in the construction stage Part, and the component can use in the construction stage as the lateral support of girder steel.In service stage, steel bar girder is total to concrete With work, working load is born.
At the construction field (site), steel bar truss floor support plate can be laid immediately on girder steel, then carries out simple bar bender Journey, can casting concrete.It need not be set up using the template and scaffold, the zinc-plated profiled sheet in bottom only do template use, no The problem of substituting steel bar stress, therefore being not required to consider fire prevention spraying and Corrosion Maintenance, also, arrangement of bar is uniform, upper and lower two layers of steel Muscle spacing and thickness of concrete cover can be fully guaranteed, and advantage is created to improve floor slab construction quality.When pouring After building concrete formation floor, there is Bars In Poured Concrete Slab integral rigidity is big, anti-seismic performance is good, shock resistance is good, water resistance is good etc. Many merits.
A kind of formwork structure, as depicted in figs. 1 and 2, including:
Joist unit, it is encorbelmented in factory building main body 1;
Outside side template 4, it is steel bar truss floor support plate, the upper surface of the joist unit is fixed in its bottom, described outer The upper surface of portion's side template 4 and the joist unit forms the outboard template of outer gutter;
Bracing piece 8, it is be arranged in parallel with the outside side template 4, and runs through and be fixed on steel bar girder 42 therein;
Internal side template 6, it is connected by connecting bolt with the bracing piece 8.
Run through transverse reinforced bar 8 after the installation forming of template 4 in inner and the outer sides, improve the flatness of outside side template 4, private side Template 6 is stepped up by screw rod, is poured to be formed outside concrete and is chosen gutter.Wherein, internal side template 6 can be wooden model.
In one optional embodiment of the present embodiment, in addition to steel bar framework 10, it is arranged at the top of bottom plate 5, both sides with Steel bar girder 42 is connected.
In one optional embodiment of the present embodiment, as shown in Fig. 2 the joist unit includes:
Multiple first joists 2, multiple first joists 2 be arranged in parallel, and encorbelment between each other in being generally aligned in the same plane In the factory building main body 1;
Multiple second joists 3, each described second joist 3, the bearing of trend one of its length direction and the outer gutter Cause, be arranged between two first joists 2, and its both ends is individually fixed in two first joists 2;
Multiple bottom plates 5, the upper surface of the joist 3 of the first joist 2 and second is fixed on, for blocking first joist 2 and the second breach between joist 3.
In one optional embodiment of the present embodiment, the bottom plate 5 is fixed on first joist 2 and by peg 9 The upper surface of two joists 3.
In one optional embodiment of the present embodiment, the bottom plate 5 is firm board, the bearing of trend of its watt of groove with it is described outer The bearing of trend of gutter is vertical.
In one optional embodiment of the present embodiment, first joist 2 and second joist 3 are " H " shaped steel, and And its edge of a wing placement parallel to the ground.
In one optional embodiment of the present embodiment, in addition to plugging plate 7, be arranged at the outside side template 4 with it is described The junction of joist unit, for sealing.The mortar leakage prevention of plugging plate 7 is installed at tie point position.
In one optional embodiment of the present embodiment, the plugging plate 7 is right angle component, preferably Zinc-coated angle steel.
In one optional embodiment of the present embodiment, one side of the plugging plate 7 is fixedly welded on the joist unit Upper surface, another side are arranged between bed die 41 and steel bar girder 42, and are welded and fixed with bed die 41, the steel bar girder 42 with The upper surface of the joist unit is welded and fixed.The reinforcing bar of steel bar girder 42 welds with the upper surface of joist unit totally, increase The resistance to capsizing of outside side template 4.
In one optional embodiment of the present embodiment, the commissure of the plugging plate 7 is coated with fluid sealant.
In one optional embodiment of the present embodiment, the bracing piece 8 is right angle component, preferably angle steel.
Construction method:
Step A:The joist unit in factory building main body 1;
Step B:Elongated plugging plate 7 is welded in joist unit upper surface;
Step C:The outside side template 4 of installation, vertical installation, socket joint is fixed between side template 4 outside polylith, bed die during installation 41 outwardly, and inwardly, the bottom of steel bar girder 42 and joist unit upper surface are welded and fixed for steel bar girder 42, and by the bottom of bed die 41 It is welded and fixed with plugging plate 7 and gluing seals;
Step D:Bracing piece 8 is extended transversely through into steel bar girder 42, and is fixed on steel bar girder 42;
Step E:Assembling reinforcement framework 10, and anchored into the steel bar girder 42 of both sides;
Step F:The internal side template 6 of lifting, back cord use flitch, and support beam uses double steel pipe, and Screw arbor with nut at both-ends inside is with adding The strong overlap joint of bar 8 welding;
Step G:Casting concrete.
Protection scope of the present invention not limited to this.What those skilled in the art were made on the basis of the present invention is equal Substitute or convert, within protection scope of the present invention.Protection scope of the present invention is defined by claims.

Claims (10)

  1. A kind of 1. formwork structure, it is characterised in that including:
    Joist unit, it is encorbelmented in factory building main body;
    Outside side template, is steel bar truss floor support plate, and the upper surface of the joist unit, the outside side form are fixed in its bottom The upper surface of plate and the joist unit forms the outboard template of outer gutter;
    Bracing piece, it is be arranged in parallel with the outside side template, and runs through and be fixed on steel bar girder therein;
    Internal side template, it is connected by connecting bolt with the bracing piece;
    Steel bar framework, it is arranged at the bottom of the outer gutter, and both ends are connected with the steel bar girder.
  2. 2. formwork structure as claimed in claim 1, it is characterised in that the joist unit includes:
    Multiple first joists, multiple first joists be arranged in parallel, and encorbelment in described between each other in being generally aligned in the same plane Factory building main body;
    Multiple second joists, each described second joist, its length direction is consistent with the bearing of trend of the outer gutter, sets Between two first joists, and its both ends is individually fixed in two first joists;
    Multiple bottom plates, the upper surface of first joist and the second joist is fixed on, for blocking first joist and second Breach between joist.
  3. 3. formwork structure as claimed in claim 2, it is characterised in that the bottom plate is fixed on first joist by peg With the upper surface of the second joist.
  4. 4. formwork structure as claimed in claim 2, it is characterised in that the bottom plate is firm board, the bearing of trend of its watt of groove It is vertical with the bearing of trend of the outer gutter.
  5. 5. formwork structure as claimed in claim 2, it is characterised in that first joist and second joist are " H " Shaped steel, also, the placement parallel to the ground of its edge of a wing.
  6. 6. formwork structure as claimed in claim 1, it is characterised in that also including plugging plate, be arranged at the outside side template With the junction of the joist unit, for sealing.
  7. 7. formwork structure as claimed in claim 6, it is characterised in that the plugging plate is right angle component.
  8. 8. formwork structure as claimed in claim 7, it is characterised in that one side of the plugging plate is fixedly welded on the joist The upper surface of unit, another side are arranged between the bed die and steel bar girder of the outside side template, and welded with the contour plate Fixation is connect, the upper surface of the steel bar girder and the joist unit is welded and fixed.
  9. 9. formwork structure as claimed in claim 8, it is characterised in that the commissure of the plugging plate is coated with fluid sealant.
  10. 10. the formwork structure as described in claim 1~9 is any, it is characterised in that the bracing piece is right angle component.
CN201710938196.2A 2017-09-30 2017-09-30 Formwork structure Pending CN107700840A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710938196.2A CN107700840A (en) 2017-09-30 2017-09-30 Formwork structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710938196.2A CN107700840A (en) 2017-09-30 2017-09-30 Formwork structure

Publications (1)

Publication Number Publication Date
CN107700840A true CN107700840A (en) 2018-02-16

Family

ID=61184748

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710938196.2A Pending CN107700840A (en) 2017-09-30 2017-09-30 Formwork structure

Country Status (1)

Country Link
CN (1) CN107700840A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109537822A (en) * 2018-11-28 2019-03-29 中冶建工集团有限公司 Gutter construction technology
CN111561151A (en) * 2020-05-25 2020-08-21 上海宝冶集团有限公司 Corner plate of steel bar truss floor bearing plate and cast-in-place concrete beam
CN112412015A (en) * 2020-12-03 2021-02-26 四川省第六建筑有限公司 Formwork-supporting-free system construction method for irregular concrete gutter

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202090586U (en) * 2011-05-12 2011-12-28 浙江杭萧钢构股份有限公司 Assembly type steel bar truss formwork
CN203684666U (en) * 2014-01-23 2014-07-02 中建八局第四建设有限公司 Reinforcing tool of cornice gutter formwork
CN106121225A (en) * 2016-08-24 2016-11-16 仇国辉 Suspension active erecting device is chosen outside cast-in-place concrete eaves
CN206346473U (en) * 2016-10-31 2017-07-21 中国一冶集团有限公司 A kind of high-altitude overhanging gutter support tripod

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202090586U (en) * 2011-05-12 2011-12-28 浙江杭萧钢构股份有限公司 Assembly type steel bar truss formwork
CN203684666U (en) * 2014-01-23 2014-07-02 中建八局第四建设有限公司 Reinforcing tool of cornice gutter formwork
CN106121225A (en) * 2016-08-24 2016-11-16 仇国辉 Suspension active erecting device is chosen outside cast-in-place concrete eaves
CN206346473U (en) * 2016-10-31 2017-07-21 中国一冶集团有限公司 A kind of high-altitude overhanging gutter support tripod

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109537822A (en) * 2018-11-28 2019-03-29 中冶建工集团有限公司 Gutter construction technology
CN111561151A (en) * 2020-05-25 2020-08-21 上海宝冶集团有限公司 Corner plate of steel bar truss floor bearing plate and cast-in-place concrete beam
CN112412015A (en) * 2020-12-03 2021-02-26 四川省第六建筑有限公司 Formwork-supporting-free system construction method for irregular concrete gutter

Similar Documents

Publication Publication Date Title
CN103821276B (en) A kind of assembled, modular architectural system
CN107143034A (en) A kind of assembly concrete frame structure beam column rigid connection node
CN206016011U (en) A kind of steel plate concrete composite beam panel structure system
CN206859479U (en) A kind of steel bar girder laminated floor slab
CN102251699A (en) Residential building system with cast-in-situ beam columns and prefabricated sandwich concrete wall panels and construction method
CN206903022U (en) A kind of steel bar truss floor support plate
CN109577539A (en) Build inclined roof fabricated construction technique
CN106567458A (en) Assembly type steel-concrete combined beam column frame structure system
CN114658219B (en) Construction method for single-side assembled formwork support
CN108005410A (en) A kind of assembled Residential System of Steel-concrete Composite Structure and its construction method
CN109403545B (en) High-assembly-rate steel pipe concrete frame structure system and connection method
CN108301545A (en) A kind of big module overlapping contignation of the assembled with space truss temporary support
CN108612315A (en) A kind of assembled mixed structure Frame-Shear Wall building system and construction method
CN107700840A (en) Formwork structure
CN111851825A (en) Fabricated form-removal-free prefabricated steel bar truss floor and construction method thereof
CN207739674U (en) A kind of assembled Residential System of Steel-concrete Composite Structure
CN108005264A (en) A kind of steel framework constraint precast reinforced concrete shear wall structure and preparation and installation method
CN112942574A (en) Prefabricated reinforced concrete full-fabricated roof cornice and construction method thereof
CN202125104U (en) Residential building system formed by cast-in-place beam columns and prefabricated sandwich concrete wall slabs
CN205875394U (en) Antidetonation concrete beam column that dry process is connected
CN105275087A (en) A prefabricated assembled type concrete beam-column connecting structure
CN2846567Y (en) Steel net structure concrete composite building
CN100451257C (en) Concrete complex building of steel meshwork framework, and construction procedure
CN207633655U (en) Outer gutter formwork structure
CN111851827A (en) Assembly type prefabricated steel bar truss disassembly-free template system and manufacturing method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information
CB02 Change of applicant information

Address after: 201900 Qing'an Road, Baoshan District, Shanghai 77

Applicant after: Shanghai Baoye Group Corp., Ltd.

Address before: 201900 Fujin Industrial Development Zone, Baoshan District, Shanghai, 8 East Road.

Applicant before: Shanghai Baoye Group Corp., Ltd.

RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180216