- CN107673205A CN107673205A CN201710915883.2A CN201710915883A CN107673205A CN 107673205 A CN107673205 A CN 107673205A CN 201710915883 A CN201710915883 A CN 201710915883A CN 107673205 A CN107673205 A CN 107673205A
- Authority
- CN
- China
- Prior art keywords
- level
- part hanging
- prefabricated part
- prefabricated
- ing device
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C13/00—Other constructional features or details
- B66C13/04—Auxiliary devices for controlling movements of suspended loads, or preventing cable slack
- B66C13/08—Auxiliary devices for controlling movements of suspended loads, or preventing cable slack for depositing loads in desired attitudes or positions
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C13/00—Other constructional features or details
- B66C13/16—Applications of indicating, registering, or weighing devices
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
- E04G21/16—Tools or apparatus
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
本发明提供了一种预制构件吊装的构件重心姿态自动调整装置及方法,本发明中塔机与预制构件吊装自动调平装置连接,预制构件吊装自动调平装置连接预制构件,预制构件起吊后,预制构件吊装自动调平装置根据水平仪的角度信号进行构件重心姿态的水平调整,在构件吊装安装到达楼层指定标高前完成整个调整工作,直接进入构件安装工序,实现预制构件水平位置快速自动化调整。采用本发明的预制构件吊装的构件重心姿态自动调整装置,预制构件吊装水平位置调节工序大大简化,实现预制构件起吊后水平位置自动调整,形成一种新型预制构件吊装安装方式,提高预制装配式建筑施工效率与质量。
Description
技术领域
本发明涉及一种预制构件吊装的构件重心姿态自动调整装置及方法。
背景技术
装配式混凝土结构构件吊装安装施工过程中,构件起吊后的水平位置影响构件重心位置调整以及吊具、构件在吊装过程中的受力,同时影响后续楼层构件安装施工,并且目前施工现场所采用的构件起吊后水平位置均为人工目测手动调节,调整时间长,重心姿态不稳。
发明内容
本发明的目的在于提供一种预制构件吊装的构件重心姿态自动调整装置及方法,能够精确、高效地将预制构件的重心姿态调整至水平位置。
为解决上述问题,本发明提供一种预制构件吊装的构件重心姿态自动调整装置,包括:
塔机;
预制构件吊装自动调平装置,所述预制构件吊装自动调平装置一端与所述塔机连接,另一端与预制构件连接;
设置于所述预制构件上的水平仪,所述水平仪与所述预制构件吊装自动调平装置通信连接。
进一步的,在上述装置中,所述水平仪与所述预制构件吊装自动调平装置有线或无线连接。
进一步的,在上述装置中,所述塔机上连接有钢丝绳,所述预制构件吊装自动调平装置一端通过所述钢丝绳与所述塔机连接。
进一步的,在上述装置中,所述水平仪为一角度传感器。
进一步的,在上述装置中,所述预制构件吊装自动调平装置用于从所述水平仪接收角度信号,并根据从水平仪接收的角度信号将所述预制构件的重心姿态调整至水平位置。
根据本发明的另一面,提供一种预制构件吊装的构件重心姿态自动调整方法,包括:
在预制构件上安装水平仪;
将预制构件吊装自动调平装置一端与塔机连接,另一端与所述预制构件连接;
将所述水平仪与所述预制构件吊装自动调平装置通信连接;
通过所述塔机起吊连接于所述预制构件吊装自动调平装置上的所述预制构件;
所述预制构件吊装自动调平装置从所述水平仪接收角度信号,并根据从水平仪接收的角度信号将所述预制构件的重心姿态调整至水平位置。
进一步的,在上述方法中,所述水平仪与所述预制构件吊装自动调平装置有线或无线连接。
进一步的,在上述方法中,所述塔机上连接有钢丝绳,所述预制构件吊装自动调平装置一端通过所述钢丝绳与所述塔机连接。
进一步的,在上述方法中,所述水平仪为一角度传感器。
与现有技术相比,本发明中塔机与预制构件吊装自动调平装置连接,预制构件吊装自动调平装置连接预制构件,预制构件起吊后,预制构件吊装自动调平装置根据水平仪的角度信号进行构件重心姿态的水平调整,在构件吊装安装到达楼层指定标高前完成整个调整工作,直接进入构件安装工序,实现预制构件水平位置快速自动化调整。本发明由原粗犷式人工调整转化为自适应精细化电脑***调节,改变以往使用人工调节构件水平位置的吊装方式,采用本发明的预制构件吊装的构件重心姿态自动调整装置,预制构件吊装水平位置调节工序大大简化,实现预制构件起吊后水平位置自动调整,形成一种新型预制构件吊装安装方式,提高预制装配式建筑施工效率与质量。
附图说明
图1是本发明一实施例的预制构件吊装的构件重心姿态自动调整装置的结构图;
图2是本发明一实施例的预制构件吊装的构件重心姿态自动调整方法的流程图。
具体实施方式
为使本发明的上述目的、特征和优点能够更加明显易懂,下面结合附图和具体实施方式对本发明作进一步详细的说明。
如图1所示,本发明提供一种预制构件吊装的构件重心姿态自动调整装置,包括:
塔机1;
预制构件吊装自动调平装置2,预制构件吊装自动调平装置2一端与塔机1连接,另一端与预制构件3连接;
设置于预制构件3上的水平仪4,水平仪4与预制构件吊装自动调平装置2通信连接。
在此,随着装配式混凝土结构大面积应用,预制装配式建筑建造过程中,构件从起吊、就位、临时固定、微调到最终就位,吊装过程构件水平调整控制至关重要,但是效率也是关键点。
本实施例中,塔机1与预制构件吊装自动调平装置2连接,预制构件吊装自动调平装置2连接预制构件3,预制构件3起吊后,预制构件吊装自动调平装置2根据水平仪4的角度信号进行构件重心姿态的水平调整,在预制构件3吊装安装到达楼层指定标高前完成整个调整工作,直接进入构件安装工序,实现预制构件水平位置快速自动化调整。
本发明针对装配式混凝土结构中构件吊装安装施工方法进行研发优化,由原粗犷式人工调整转化为自适应精细化电脑***调节,改变以往使用人工调节构件水平位置的吊装方式,采用本发明的预制构件吊装的构件重心姿态自动调整装置,预制构件吊装水平位置调节工序大大简化,实现预制构件起吊后水平位置自动调整,形成一种新型预制构件吊装安装方式,提高预制装配式建筑施工效率与质量。
本发明的预制构件吊装的构件重心姿态自动调整装置一实施例中,所述水平仪4与预制构件吊装自动调平装置2有线或无线连接,从而可以根据实际应用场景通过有线可无线的方式进行两者之间的通信。
如图1所示,本发明的预制构件吊装的构件重心姿态自动调整装置一实施例中,所述塔机上连接有钢丝绳,所述预制构件吊装自动调平装置2一端通过所述钢丝绳5与塔机1连接,从而实现预制构件吊装自动调平装置2与塔机的可靠连接。
本发明的预制构件吊装的构件重心姿态自动调整装置一实施例中,所述水平仪4为一角度传感器,从而可以通过角度传感器精确获取预制构件的角度信号。
本发明的预制构件吊装的构件重心姿态自动调整装置一实施例中,预制构件吊装自动调平装置2用于从所述水平仪4接收角度信号,并根据从水平仪4接收的角度信号将所述预制构件3的重心姿态调整至水平位置。
如图1和2所示,根据本发明的另一面,还提供一种预制构件吊装的构件重心姿态自动调整方法,包括:
步骤S1,在预制构件3上安装水平仪4;
步骤S2,将预制构件吊装自动调平装置2一端与塔机1连接,另一端与预制构件3连接;
步骤S3,将水平仪4与所述预制构件吊装自动调平装置2通信连接;
步骤S4,通过塔机1起吊连接于预制构件吊装自动调平装置2上的预制构件3;
步骤S5,所述预制构件吊装自动调平装置2从水平仪4接收角度信号,并根据从水平仪4接收的角度信号将所述预制构件3的重心姿态调整至水平位置。
本发明针对装配式混凝土结构中构件吊装安装施工方法进行研发优化,由原粗犷式人工调整转化为自适应精细化电脑***调节,改变以往使用人工调节构件水平位置的吊装方式,采用本发明的预制构件吊装的构件重心姿态自动调整装置,预制构件吊装水平位置调节工序大大简化,实现预制构件起吊后水平位置自动调整,形成一种新型预制构件吊装安装方式,提高预制装配式建筑施工效率与质量。
本发明的预制构件吊装的构件重心姿态自动调整方法一实施例中,所述水平仪4与预制构件吊装自动调平装置2有线或无线连接,从而可以根据实际应用场景通过有线可无线的方式进行两者之间的通信。
如图2所示,本发明的预制构件吊装的构件重心姿态自动调整方法一实施例中,所述塔机1上连接有钢丝绳5,所述预制构件吊装自动调平装置2一端通过钢丝绳5与塔机1连接,从而实现预制构件吊装自动调平装置2与塔机1的可靠连接。
本发明的预制构件吊装的构件重心姿态自动调整方法一实施例中,水平仪4为一角度传感器,从而可以通过角度传感器精确获取预制构件的角度信号。
综上所述,本发明中塔机与预制构件吊装自动调平装置连接,预制构件吊装自动调平装置连接预制构件,预制构件起吊后,预制构件吊装自动调平装置根据水平仪的角度信号进行构件重心姿态的水平调整,在构件吊装安装到达楼层指定标高前完成整个调整工作,直接进入构件安装工序,实现预制构件水平位置快速自动化调整。本发明由原粗犷式人工调整转化为自适应精细化电脑***调节,改变以往使用人工调节构件水平位置的吊装方式,采用本发明的预制构件吊装的构件重心姿态自动调整装置,将预制构件吊装水平位置调节工序大大简化,实现预制构件起吊后水平位置自动调整,形成一种新型预制构件吊装安装方式,提高预制装配式建筑施工效率与质量。
本说明书中各个实施例采用递进的方式描述,每个实施例重点说明的都是与其他实施例的不同之处,各个实施例之间相同相似部分互相参见即可。
显然,本领域的技术人员可以对发明进行各种改动和变型而不脱离本发明的精神和范围。这样,倘若本发明的这些修改和变型属于本发明权利要求及其等同技术的范围之内,则本发明也意图包括这些改动和变型在内。
Claims (9)
1.一种预制构件吊装的构件重心姿态自动调整装置,其特征在于,包括:
塔机;
预制构件吊装自动调平装置,所述预制构件吊装自动调平装置一端与所述塔机连接,另一端与预制构件连接;
设置于所述预制构件上的水平仪,所述水平仪与所述预制构件吊装自动调平装置通信连接。
2.如权利要求1所述的预制构件吊装的构件重心姿态自动调整装置,其特征在于,所述水平仪与所述预制构件吊装自动调平装置有线或无线连接。
3.如权利要求1所述的预制构件吊装的构件重心姿态自动调整装置,其特征在于,所述塔机上连接有钢丝绳,所述预制构件吊装自动调平装置一端通过所述钢丝绳与所述塔机连接。
4.权利要求1所述的预制构件吊装的构件重心姿态自动调整装置,其特征在于,所述水平仪为一角度传感器。
5.权利要求1至4任一项所述的预制构件吊装的构件重心姿态自动调整装置,其特征在于,所述预制构件吊装自动调平装置用于从所述水平仪接收角度信号,并根据从水平仪接收的角度信号将所述预制构件的重心姿态调整至水平位置。
6.一种预制构件吊装的构件重心姿态自动调整方法,其特征在于,包括:
在预制构件上安装水平仪;
将预制构件吊装自动调平装置一端与塔机连接,另一端与所述预制构件连接;
将所述水平仪与所述预制构件吊装自动调平装置通信连接;
通过所述塔机起吊连接于所述预制构件吊装自动调平装置上的所述预制构件;
所述预制构件吊装自动调平装置从所述水平仪接收角度信号,并根据从水平仪接收的角度信号将所述预制构件的重心姿态调整至水平位置。
7.如权利要求6所述的预制构件吊装的构件重心姿态自动调整方法,其特征在于,所述水平仪与所述预制构件吊装自动调平装置有线或无线连接。
8.如权利要求6所述的预制构件吊装的构件重心姿态自动调整装置,其特征在于,所述塔机上连接有钢丝绳,所述预制构件吊装自动调平装置一端通过所述钢丝绳与所述塔机连接。
9.权利要求6至8任一项所述的预制构件吊装的构件重心姿态自动调整装置,其特征在于,所述水平仪为一角度传感器。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710915883.2A CN107673205A (zh) | 2017-09-30 | 2017-09-30 | 预制构件吊装的构件重心姿态自动调整装置及方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710915883.2A CN107673205A (zh) | 2017-09-30 | 2017-09-30 | 预制构件吊装的构件重心姿态自动调整装置及方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107673205A true CN107673205A (zh) | 2018-02-09 |
Family
ID=61138073
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710915883.2A Pending CN107673205A (zh) | 2017-09-30 | 2017-09-30 | 预制构件吊装的构件重心姿态自动调整装置及方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107673205A (zh) |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109291033A (zh) * | 2018-10-26 | 2019-02-01 | 广州圣安环保科技有限公司 | 一种基于机器人的建筑构件安装***及其控制方法 |
CN110482392A (zh) * | 2019-08-09 | 2019-11-22 | 中建三局第一建设工程有限责任公司 | 用于预制构件吊装的调平装置及调平方法 |
CN111335356A (zh) * | 2020-04-01 | 2020-06-26 | 北京建工土木工程有限公司 | 管涵预制构件自动化装配***及施工方法 |
CN112249898A (zh) * | 2020-09-14 | 2021-01-22 | 广东博智林机器人有限公司 | 钢筋骨架构件的吊装姿态调整方法、装置及电子设备 |
CN112252734A (zh) * | 2020-10-30 | 2021-01-22 | 东南大学 | 应用于装配式建筑预制构件吊装就位辅助工装及吊装方法 |
CN112607588A (zh) * | 2021-01-25 | 2021-04-06 | 河南恒远恒山工业有限公司 | 一种具备调平功能的吊具 |
CN112912567A (zh) * | 2019-07-03 | 2021-06-04 | 广州建筑股份有限公司 | 一种l型双向悬挑结构整体提升施工方法 |
CN113233355A (zh) * | 2021-04-15 | 2021-08-10 | 大连海事大学 | 安装在船用起重机上的绳驱式auv回收装置的控制*** |
CN117403912A (zh) * | 2023-11-20 | 2024-01-16 | 重庆大学溧阳智慧城市研究院 | 一种装配式建筑预制构件装配装置及其方法 |
Citations (14)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH05162972A (ja) * | 1991-12-18 | 1993-06-29 | Hitachi Ltd | 自動水平度調整装置 |
JPH06321485A (ja) * | 1993-04-12 | 1994-11-22 | Nissei Eng:Yugen | コンクリート製品の吊り上げ寄せ集め装置 |
JPH082875A (ja) * | 1994-06-20 | 1996-01-09 | Babcock Hitachi Kk | 自動調芯天秤 |
JPH08277094A (ja) * | 1995-04-05 | 1996-10-22 | Babcock Hitachi Kk | 自動調芯吊具 |
CN101633478A (zh) * | 2008-07-23 | 2010-01-27 | 中国科学院自动化研究所 | 绳索牵引自动水平调节吊具及方法 |
CN101704470A (zh) * | 2009-10-28 | 2010-05-12 | 中北大学 | 一种自动调平与调姿吊具及其控制方法 |
CN101891109A (zh) * | 2010-07-16 | 2010-11-24 | 北京卫星制造厂 | 一种双自由度调节自动水平式吊具及调节方法 |
CN202054551U (zh) * | 2011-03-23 | 2011-11-30 | 长沙中联重工科技发展股份有限公司 | 塔式起重机及其吊钩调平装置 |
CN104058334A (zh) * | 2014-06-05 | 2014-09-24 | 上海卫星装备研究所 | 一种自调平式吊具装置 |
CN105110189A (zh) * | 2015-10-06 | 2015-12-02 | 华北理工大学 | 自动平衡吊具及其使用方法 |
CN205076703U (zh) * | 2015-10-06 | 2016-03-09 | 华北理工大学 | 自动平衡吊具 |
CN205675990U (zh) * | 2016-06-15 | 2016-11-09 | 北京城建建设工程有限公司 | 一种建筑预制构件吊装装置 |
CN106865399A (zh) * | 2017-03-20 | 2017-06-20 | 四川行之智汇知识产权运营有限公司 | 自动找平的核电站施工配套吊运结构 |
CN207451453U (zh) * | 2017-09-30 | 2018-06-05 | 上海建工五建集团有限公司 | 预制构件吊装的构件重心姿态自动调整装置 |
-
2017
- 2017-09-30 CN CN201710915883.2A patent/CN107673205A/zh active Pending
Patent Citations (14)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH05162972A (ja) * | 1991-12-18 | 1993-06-29 | Hitachi Ltd | 自動水平度調整装置 |
JPH06321485A (ja) * | 1993-04-12 | 1994-11-22 | Nissei Eng:Yugen | コンクリート製品の吊り上げ寄せ集め装置 |
JPH082875A (ja) * | 1994-06-20 | 1996-01-09 | Babcock Hitachi Kk | 自動調芯天秤 |
JPH08277094A (ja) * | 1995-04-05 | 1996-10-22 | Babcock Hitachi Kk | 自動調芯吊具 |
CN101633478A (zh) * | 2008-07-23 | 2010-01-27 | 中国科学院自动化研究所 | 绳索牵引自动水平调节吊具及方法 |
CN101704470A (zh) * | 2009-10-28 | 2010-05-12 | 中北大学 | 一种自动调平与调姿吊具及其控制方法 |
CN101891109A (zh) * | 2010-07-16 | 2010-11-24 | 北京卫星制造厂 | 一种双自由度调节自动水平式吊具及调节方法 |
CN202054551U (zh) * | 2011-03-23 | 2011-11-30 | 长沙中联重工科技发展股份有限公司 | 塔式起重机及其吊钩调平装置 |
CN104058334A (zh) * | 2014-06-05 | 2014-09-24 | 上海卫星装备研究所 | 一种自调平式吊具装置 |
CN105110189A (zh) * | 2015-10-06 | 2015-12-02 | 华北理工大学 | 自动平衡吊具及其使用方法 |
CN205076703U (zh) * | 2015-10-06 | 2016-03-09 | 华北理工大学 | 自动平衡吊具 |
CN205675990U (zh) * | 2016-06-15 | 2016-11-09 | 北京城建建设工程有限公司 | 一种建筑预制构件吊装装置 |
CN106865399A (zh) * | 2017-03-20 | 2017-06-20 | 四川行之智汇知识产权运营有限公司 | 自动找平的核电站施工配套吊运结构 |
CN207451453U (zh) * | 2017-09-30 | 2018-06-05 | 上海建工五建集团有限公司 | 预制构件吊装的构件重心姿态自动调整装置 |
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109291033A (zh) * | 2018-10-26 | 2019-02-01 | 广州圣安环保科技有限公司 | 一种基于机器人的建筑构件安装***及其控制方法 |
CN112912567A (zh) * | 2019-07-03 | 2021-06-04 | 广州建筑股份有限公司 | 一种l型双向悬挑结构整体提升施工方法 |
CN112912567B (zh) * | 2019-07-03 | 2022-11-01 | 广州建筑股份有限公司 | 一种l型双向悬挑结构整体提升施工方法 |
CN110482392A (zh) * | 2019-08-09 | 2019-11-22 | 中建三局第一建设工程有限责任公司 | 用于预制构件吊装的调平装置及调平方法 |
CN111335356A (zh) * | 2020-04-01 | 2020-06-26 | 北京建工土木工程有限公司 | 管涵预制构件自动化装配***及施工方法 |
CN112249898A (zh) * | 2020-09-14 | 2021-01-22 | 广东博智林机器人有限公司 | 钢筋骨架构件的吊装姿态调整方法、装置及电子设备 |
CN112252734A (zh) * | 2020-10-30 | 2021-01-22 | 东南大学 | 应用于装配式建筑预制构件吊装就位辅助工装及吊装方法 |
CN112252734B (zh) * | 2020-10-30 | 2024-05-31 | 东南大学 | 应用于装配式建筑预制构件吊装就位辅助工装及吊装方法 |
CN112607588A (zh) * | 2021-01-25 | 2021-04-06 | 河南恒远恒山工业有限公司 | 一种具备调平功能的吊具 |
CN113233355A (zh) * | 2021-04-15 | 2021-08-10 | 大连海事大学 | 安装在船用起重机上的绳驱式auv回收装置的控制*** |
CN113233355B (zh) * | 2021-04-15 | 2024-06-07 | 大连海事大学 | 安装在船用起重机上的绳驱式auv回收装置的控制*** |
CN117403912A (zh) * | 2023-11-20 | 2024-01-16 | 重庆大学溧阳智慧城市研究院 | 一种装配式建筑预制构件装配装置及其方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107673205A (zh) | 预制构件吊装的构件重心姿态自动调整装置及方法 | |
CN105735657B (zh) | 适用于竖向预制构件的自适应斜撑调垂装置 | |
CN106315389B (zh) | 一种大型预制板调姿吊架及其方法 | |
CN107585683A (zh) | 预制构件自动调平装置及方法 | |
CN107700360B (zh) | 一种桁架桥节段的拼装方法 | |
CN204675610U (zh) | 曲轴吊具的辅助吊链工装 | |
CN101284628B (zh) | 大吨位压力机架的吊装方法 | |
CN207451453U (zh) | 预制构件吊装的构件重心姿态自动调整装置 | |
CN107476581B (zh) | 一种钢结构双层悬挑结构吊装安装方法 | |
CN106121145A (zh) | 一种分片式装配楼梯及其制作方法与装配方法 | |
CN104895335B (zh) | 一种吊柱的安装方法 | |
CN108249275A (zh) | 一种预制构件吊装工具及吊装调姿方法 | |
CN104032967A (zh) | 预制装配式框架结构构件吊装施工方法 | |
CN105776011B (zh) | 高炉炉顶吊车梁安装方法 | |
CN208964364U (zh) | 一种装配式叠合楼板自动吊具 | |
CN101769076B (zh) | 高楼用避振器的框架顶升吊挂安装方法 | |
CN109518614A (zh) | 一种钢桥梁悬空施工机构及施工方法 | |
CN108103936B (zh) | 预制盖梁安装于立柱的方法 | |
CN110552510B (zh) | 装配式曲面吊顶的施工方法 | |
GB2544513A (en) | Controller and method of controlling a load | |
CN205838313U (zh) | 装配式构件吊具 | |
CN110080083A (zh) | 安装提篮式钢桁拱主弦杆的方法 | |
CN209652762U (zh) | 一种钢桥梁悬空定位施工机构 | |
CN207434888U (zh) | 预制构件自动调平装置 | |
CN107879239A (zh) | 一种外挂墙板吊装方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |