CN107524213A CN201610445190.7A CN201610445190A CN107524213A CN 107524213 A CN107524213 A CN 107524213A CN 201610445190 A CN201610445190 A CN 201610445190A CN 107524213 A CN107524213 A CN 107524213A
Authority
CN
China
Prior art keywords
sump
steel pipe
draining
protection net
pipeline
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610445190.7A
Other languages
Chinese (zh)
Inventor
邱战武
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC5 Group Shanghai Corp Ltd
Original Assignee
MCC5 Group Shanghai Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC5 Group Shanghai Corp Ltd filed Critical MCC5 Group Shanghai Corp Ltd
Priority to CN201610445190.7A priority Critical patent/CN107524213A/en
Publication of CN107524213A publication Critical patent/CN107524213A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F1/00Methods, systems, or installations for draining-off sewage or storm water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/12Manhole shafts; Other inspection or access chambers; Accessories therefor
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Health & Medical Sciences (AREA)
  • Water Supply & Treatment (AREA)
  • Public Health (AREA)
  • Hydrology & Water Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Paleontology (AREA)
  • Mining & Mineral Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

A kind of job site water discharge method using sump, it is characterised in that comprise the following steps:Draining steel pipe is set a,(5)Pipeline, b, sump is made, c, make sump protection net, d, excavate draining steel pipe(5)Pipeline trench, e, draining steel pipe(5)The embedded and installation of pipeline and sump, f, the installation of sump protection net, g, dismounting are simultaneously reused:According to engineering ground needs, recovery can be dug out after the completion of flowing line and sump project to be onstructed, is re-used in next project under construction.The job site water discharge method using sump of the present invention has sump apparatus structure simple, easy to make, utilize complete water discharge method, can effectively solve live drainage problem, ensure that draining is unimpeded, reduce unnecessary drainage channel scarfing cinder, dredging work, save artificial, the saving construction period, the advantages of can reusing and reduce engineering cost.

Description

A kind of job site water discharge method using sump
Technical field
The present invention relates to a kind of job site water discharge method, is that a kind of job site using sump is arranged specifically Water method.
Background technology
In building engineering construction, particularly in large-scale floor space building engineering construction, live draining is as existing The important content of field plane management.In general water discharge method uses open cut gutter and sump, brick gutter and collection substantially Well etc.:Though cut and cover method simple economy, everywhere soil raceway groove, and easily blocking, it is unfavorable for job site markization management and text Bright construction requirement;Though brick method is advantageous to markization management, essentially nonrecurring cost input and use, it is impossible to reuse, It is unfavorable for construction cost saving, uneconomical practicality.
Therefore known job site water discharge method there are problems that above-mentioned a variety of inconvenience and.
The content of the invention
The purpose of the present invention, it is to propose a kind of job site markization management and civilized construction and saves making for construction cost With the job site water discharge method of sump.
To achieve the above object, technical solution of the invention is:
A kind of job site water discharge method using sump, it is characterised in that comprise the following steps:
Draining steel pipe pipeline is set a,:Using steel pipe manufacturing, draining steel pipe pipeline in job site is set, steel pipe pipe joint uses It is welded to connect;
B, sump is made:Sump is external diameter >=1020mm circle steel drums, and circular steel drum is suitable for reading to be opened wide, under circular steel drum mouth by Circular steel sole plate welds back cover;Circular steel drum height >=1.8m, two corresponding side walls of circular steel drum set through hole, through hole and draining Steel-pipe welding;Through hole from a distance from steel sole plate >=1200mm;Through hole is 5-8mm bigger than draining outer diameter of steel pipes hole;
C, sump protection net is made:Sump protection net is square reinforcing bar protection net, and protection net can cover in Circular steel drum is suitable for reading;The lower floor of square reinforcing bar protection net be reinforcement welding into reinforcing bar grid, full paving gold on reinforcing bar grid Belong to mesh sheet;
D, draining steel pipe pipeline trench is excavated:Using excavating pipeline after position of the excavator along engineering Floorplanning and buried depth unwrapping wire Groove and the well that catchments;
E, the embedded and installation of draining steel pipe pipeline and sump:Sump is placed in using truck crane hand fit and excavated Catchment in well, drainpipe is laid in the groove excavated, the hole of draining steel pipe pipeline and sump is connected using welding Connect, draining steel pipe pipeline and sump it is embedded after the completion of, trench backfill is smooth;
F, sump protection net is installed:After the completion of sump Embedment and installation, protection net is positioned over and catchmented on well head, to prevent Only personnel and bulk debris are fallen into well;
G, dismounting and reuse:According to engineering ground needs, can be dug out after the completion of flowing line and sump project to be onstructed Recovery, is re-used in next project under construction.
The job site water discharge method using sump of the present invention can also be using following technical measures come further Realize.
Foregoing method, wherein the draining steel pipe is DN300*4mm.
Foregoing method, wherein the draining steel pipe on the two side of the circular steel bucket(5)In horizontally disposed.
Foregoing method, wherein the protection net center weld has some pins, pin hangs down with protection net plane Directly.
After adopting the above technical scheme, the present invention's has advantages below using the job site water discharge method of sump:
1st, sump apparatus structure is simple, easy to make;
2nd, with common steel tube, steel, reinforcement fabrication drainpipe, sump and protection network, gather materials on the spot, make simply, without special Industry personnel can make, and save construction cost;
3rd, using complete water discharge method, can effectively solve live drainage problem, ensure that draining is unimpeded, favourable civilized construction and Safety post management
3rd, unnecessary drainage channel scarfing cinder, dredging work can be reduced, saves artificial, the saving construction period, profit can be repeated With reduction engineering cost.
Brief description of the drawings
Fig. 1 is the sump structural representation of the embodiment of the present invention;
Fig. 2 is the sump and drainpipe connection diagram of the embodiment of the present invention;
Fig. 3 is the sump reinforcing bar protective net cover structure schematic diagram of the embodiment of the present invention;
Fig. 4 is the sump and reinforcing bar protection net single unit system schematic diagram of the embodiment of the present invention.
In figure:The 1 sump borehole wall, 2 through holes, 3 steel sole plates, 4 sumps, 5 draining steel pipes, 6 protection nets, 7 pins.
Embodiment
With reference to embodiments and its accompanying drawing illustrates further to the present invention.
Embodiment 1
The job site water discharge method using sump of the present invention, comprises the following steps:
Referring now to Fig. 1, Fig. 1 is the sump structural representation of the embodiment of the present invention.
The pipeline of draining steel pipe 5 is set a,:By the use of constructing, waste and old steel pipe DN300*4mm connects as flowing line, steel pipe pipeline Head is used and is welded to connect.
B, sump is made:Using large diameter pipeline DN1000*8mm, cut one section of 1.8m length and be used as the sump borehole wall, cut Diameter 8mm bigger 100mm, thick than large diameter pipeline DN1000 circular steel plate is cut, as the bottom plate of sump, by steel plate bottom Plate and steel pipe borehole wall weld all around, drainpipe is compared using gas cutting or the diameter of plasma cut one at 500mm below steel pipe borehole wall well head The big 5-8mm of external diameter hole, a same hole, the connection as drainage pipeline are cut in the straight offside steel pipe borehole wall of this hole Hole.Fig. 2 is the sump and drainpipe connection diagram of the embodiment of the present invention.
C, sump protection net is made:It is bigger than sump diameter using diameter 18mm or other specification reinforcing bars, length and width 200mm, two-way spacing 100mm, is welded into mesh sheet, and the long reinforcing bar pins of 100mm are welded on four sides of mesh sheet.In the protection net The heart is welded with four pins, and pin is vertical with protection net plane.
D, flowing line groove is excavated:Using excavating pipeline after position of the excavator along engineering Floorplanning and buried depth unwrapping wire Groove and the well that catchments.
E, the embedded and installation of the pipeline of draining steel pipe 5 and sump:Sump is placed in using truck crane hand fit That has excavated is catchmented in well, and drainpipe is laid in the groove excavated, and the hole of drainpipe and sump is connected using welding Connect, after laying pipe laying and sump, groove etc. is backfilled smooth.Draining steel pipe 5 on the two side of the circular steel drum In horizontally disposed.Fig. 4 is the sump and reinforcing bar protection net single unit system schematic diagram of the embodiment of the present invention.
F, sump protective cover is installed:After the completion of sump Embedment and installation, to prevent personnel and bulk debris from falling into well, Bar-mat reinforcement protective cover is put into and catchmented on well head, pin is positioned at catchmenting in the borehole wall, to prevent protective cover horizontal hunting.Fig. 3 is this The sump reinforcing bar protective net cover structure schematic diagram of inventive embodiments.Fig. 4 is sump and the reinforcing bar protection of the embodiment of the present invention Guard single unit system schematic diagram.
G, dismounting and reuse:According to engineering ground needs, energy after the completion of flowing line and sump project to be onstructed Recovery is dug out, is re-used in next project under construction.
The present invention has substantive distinguishing features and significant technological progress, the job site draining of the invention using sump Method has made a kind of steel drainpipe and steel sump, easy to make, quick, and installation facility, this method is than traditional open cut ditch Well, brick ditch well, can guarantee that draining is unimpeded, non-leakage, are advantageous to job site civilized construction and markization management, improve construction shape As saving construction cost.
The job site water discharge method of the invention using sump of the present invention is in the Cold-roller of Baosteel Zhanjiang steel 1550 Used in journey, construction site area reaches 120000m2, it is located in that region rainy season is more, rainfall is big, the draining of job site is The midpoint of plane management, though taking cut and cover method simple economy, soil raceway groove, and easily blocking everywhere, it is unfavorable for job site Markization manages and civilized construction requirement, though taking brick method to be advantageous to markization management, essentially nonrecurring cost puts into and made With, it is impossible to reuse, be unfavorable for construction cost saving, uneconomical practicality.The applying using sump of the invention of the present invention Work scene water discharge method utilizes live common steel tube, steel, reinforcement fabrication drainpipe, sump and protection network, fabrication and installation and It is embedded, complete draining is formed, its is easy to make, quick, installation facility, can guarantee that draining is unimpeded, non-leakage, it is existing to be advantageous to construction Civilized construction and markization management, improve construction image, its safe effect is good, less investment, strong applicability, repeat utilization, save About construction cost.
Above example is used for illustrative purposes only, rather than limitation of the present invention, the technology people about technical field Member, without departing from the spirit and scope of the present invention, can also make various conversion or change.Therefore, it is all equivalent Technical scheme should also belong to scope of the invention, should be limited by each claim.

Claims (4)

1. a kind of job site water discharge method using sump, it is characterised in that comprise the following steps:
Draining steel pipe is set a,(5)Pipeline:Using steel pipe manufacturing, job site draining steel pipe pipeline, steel pipe pipe joint are set Using being welded to connect;
B, sump is made:Sump is external diameter >=1020mm circle steel drums, and circular steel drum is suitable for reading to be opened wide, under circular steel drum mouth by Circular steel sole plate(3)Weld back cover;Circular steel drum height >=1.8m, two corresponding side walls of circular steel drum set through hole(2), through hole With draining steel pipe(5)Welding;Through hole(2)From steel sole plate(3)Distance >=1200mm;Through hole is than draining steel pipe(5)External diameter is big 5-8mm hole;
C, sump protection net is made:Sump protection net is square reinforcing bar protection net, and protection net can cover in Circular steel drum is suitable for reading;The lower floor of square reinforcing bar protection net be reinforcement welding into reinforcing bar grid, full paving gold on reinforcing bar grid Belong to mesh sheet;
D, draining steel pipe is excavated(5)Pipeline trench:Using being excavated after position of the excavator along engineering Floorplanning and buried depth unwrapping wire Pipeline trench and the well that catchments;
E, draining steel pipe(5)The embedded and installation of pipeline and sump:Sump is placed in out using truck crane hand fit That has dug is catchmented in well, and drainpipe is laid in the groove excavated, draining steel pipe(5)The hole of pipeline and sump uses It is welded to connect, draining steel pipe(5)Pipeline and sump it is embedded after the completion of, trench backfill is smooth;
F, sump protection net is installed:After the completion of sump Embedment and installation, protection net is positioned over and catchmented on well head, to prevent Only personnel and bulk debris are fallen into well;
G, dismounting and reuse:According to engineering ground needs, can be dug out after the completion of flowing line and sump project to be onstructed Recovery, is re-used in next project under construction.
2. the job site water discharge method of sump is used as claimed in claim 1, it is characterised in that the draining steel pipe (5)For DN300*4mm.
3. the job site water discharge method of sump is used as claimed in claim 1, it is characterised in that the circular steel drum Draining steel pipe on two side(5)In horizontally disposed.
4. the job site water discharge method of sump is used as claimed in claim 1, it is characterised in that in the protection net The heart is welded with some pins, and pin is vertical with protection net plane.
CN201610445190.7A 2016-06-21 2016-06-21 A kind of job site water discharge method using sump Pending CN107524213A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610445190.7A CN107524213A (en) 2016-06-21 2016-06-21 A kind of job site water discharge method using sump

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610445190.7A CN107524213A (en) 2016-06-21 2016-06-21 A kind of job site water discharge method using sump

Publications (1)

Publication Number Publication Date
CN107524213A true CN107524213A (en) 2017-12-29

Family

ID=60734538

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610445190.7A Pending CN107524213A (en) 2016-06-21 2016-06-21 A kind of job site water discharge method using sump

Country Status (1)

Country Link
CN (1) CN107524213A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108797761A (en) * 2018-07-04 2018-11-13 福建江夏学院 A kind of integrate draining system construction method

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10114954A (en) * 1997-10-30 1998-05-06 Chiken Kogyo Kk Manhole body block applied to small-bore pipe jacking and method of manhole construction
JP2007231734A (en) * 2004-10-15 2007-09-13 Erudekku:Kk Infiltrating structure
CN101381999A (en) * 2008-10-14 2009-03-11 沈阳骅飞管业有限公司 Glass fibre reinforced plastic sand inclusion well chamber
CN103046639A (en) * 2011-10-13 2013-04-17 肖玉光 Checking and catch basin for drainage pipeline and production method thereof
CN203546882U (en) * 2013-10-24 2014-04-16 无锡市政设计研究院有限公司 Novel catch basin for draining road surface accumulated water
CN104563271A (en) * 2015-01-22 2015-04-29 山西二建集团有限公司 Plastic inspection well and construction method thereof
CN204401764U (en) * 2015-01-13 2015-06-17 曹萍 A kind of Multifunction catch-basin
CN204435531U (en) * 2015-01-22 2015-07-01 山西二建集团有限公司 Plastic inspection well
CN204753784U (en) * 2015-04-28 2015-11-11 中机国能电力工程有限公司 Composite beam grate sump pit
CN205134481U (en) * 2015-10-14 2016-04-06 山东省交通规划设计院 Highway superelevation excavation highway section hydrocone type drainage system

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10114954A (en) * 1997-10-30 1998-05-06 Chiken Kogyo Kk Manhole body block applied to small-bore pipe jacking and method of manhole construction
JP2007231734A (en) * 2004-10-15 2007-09-13 Erudekku:Kk Infiltrating structure
CN101381999A (en) * 2008-10-14 2009-03-11 沈阳骅飞管业有限公司 Glass fibre reinforced plastic sand inclusion well chamber
CN103046639A (en) * 2011-10-13 2013-04-17 肖玉光 Checking and catch basin for drainage pipeline and production method thereof
CN203546882U (en) * 2013-10-24 2014-04-16 无锡市政设计研究院有限公司 Novel catch basin for draining road surface accumulated water
CN204401764U (en) * 2015-01-13 2015-06-17 曹萍 A kind of Multifunction catch-basin
CN104563271A (en) * 2015-01-22 2015-04-29 山西二建集团有限公司 Plastic inspection well and construction method thereof
CN204435531U (en) * 2015-01-22 2015-07-01 山西二建集团有限公司 Plastic inspection well
CN204753784U (en) * 2015-04-28 2015-11-11 中机国能电力工程有限公司 Composite beam grate sump pit
CN205134481U (en) * 2015-10-14 2016-04-06 山东省交通规划设计院 Highway superelevation excavation highway section hydrocone type drainage system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108797761A (en) * 2018-07-04 2018-11-13 福建江夏学院 A kind of integrate draining system construction method

Similar Documents

Publication Publication Date Title
CN109680716B (en) Method for double in-situ protection of electric power culvert by adopting upper suspension and lower support
CN112502777B (en) Method for treating tunnel inrush roof collapse and door closing
CN102434717B (en) Construction method of joist steel pipe-jacking work pit
CN101503882A (en) Construction method for underground continuous wall with conjoined reinforcing cage by topdown construction method
WO2023077552A1 (en) Construction method for foundation pit enclosure and earth excavation
CN107869351A (en) A kind of method of the high narrow large-scale solution cavity Cavity treatment security protection of type
CN107964976A (en) Steel pipe-conversion steel platform tower crane top-down construction method
CN106245654A (en) Deposited reinforced concrete pile exempts from inter-pile soil excavation construction method
CN112095644A (en) Deep foundation pit water intercepting and draining device and construction method thereof
CN111765318A (en) Pipeline flow guide structure for pipeline repair
CN108708284A (en) A kind of steel trestle construction method for resisting flood discharge bed scour
CN206189454U (en) Piping lane
CN209652936U (en) A kind of artificial push pipe inspection shaft steel plate box pattern foundation pit supporting structure
CN110616719B (en) Quick construction method for U-shaped groove of upper-span existing culvert
CN212900365U (en) Pipeline flow guide structure for pipeline repair
CN101994314A (en) Longhole rectangular terraced antiskid pile jump-preventing excavating construction
CN212272234U (en) High-strength combined template for open groove section of large-section inclined shaft
CN105332382A (en) River-adjacent-foundation-pit island-building cofferdam clay sealing construction method
CN107524213A (en) A kind of job site water discharge method using sump
CN107503354A (en) A kind of tower crane goes along with sb. to guard him bracing reinforcement and excavation method
CN205954632U (en) Pipeline crosses supporting construction of foundation ditch department in rich water sand layer
CN111648373B (en) Excavation supporting construction process for water-rich deep foundation pit fender pile gap
CN211900696U (en) Karst tunnel groundwater open type drainage structure
CN203891013U (en) Simple manual hole digging pile concrete wall protecting formwork
CN107816068B (en) Construction method of underground diaphragm wall brushing concrete bypass flow detection and treatment device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20171229