CN107476599A - Tile type overlaps packway and its construction method - Google Patents

Tile type overlaps packway and its construction method Download PDF

Info

Publication number
CN107476599A
CN107476599A CN201710623785.1A CN201710623785A CN107476599A CN 107476599 A CN107476599 A CN 107476599A CN 201710623785 A CN201710623785 A CN 201710623785A CN 107476599 A CN107476599 A CN 107476599A
Authority
CN
China
Prior art keywords
bonding jumper
tread portion
hook part
packway
skewback
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710623785.1A
Other languages
Chinese (zh)
Inventor
杨俱玮
宫健翔
段忠伟
迟鹏骋
李帛谦
邓蓉
李晓曦
姜鹤
马鹏飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN201710623785.1A priority Critical patent/CN107476599A/en
Publication of CN107476599A publication Critical patent/CN107476599A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G27/00Temporary arrangements for giving access from one level to another for men or vehicles, e.g. steps, ramps
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/08Scaffold boards or planks

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Paving Structures (AREA)

Abstract

The present invention relates to a kind of tile type to overlap packway, is erected on scaffold, the packway includes multiple bonding jumpers, and adjacent two bonding jumpers mutually overlap;The bonding jumper includes tread portion and the bending hook part being connected with the tread portion, is hooked the bonding jumper on the cross bar of the scaffold by the bending hook part, so as to which the tread portion forms aisle face at the cross bar;The surface of the tread portion is provided with the first bulge-structure positioned at two sides, and first bulge-structure moves towards to set along the tread portion.Tile type overlap joint packway provided by the invention is erected on scaffold using bonding jumper, and on-site consolidation is convenient, and speed is fast, and turnover rate is high, the advantage such as installation coefficient height.The bonding jumper is hooked by bending hook part and is located on the cross bar of scaffold, and the berm structure formed is solid and reliable, is unlikely to deform, and not limited by the field, and flexibility is strong, is not easy to topple, and the turnover of the bonding jumper is flexible, without receiving the limitation of lifting machine and place space.

Description

Tile type overlaps packway and its construction method
Technical field
The present invention relates to the realm of building construction, refers in particular to a kind of tile type overlap joint packway and its construction method.
Background technology
Packway, also known as escape way, it is specially to set up to enter operating surface for workmen in constructure construction procedure Passage, 2 races or 3 races are typically set, scaffold is generally set up by steel pipe, bamboo splint is laid on scaffold, wood is followed closely on bamboo splint Bar does step-like, and foot guard plate, handrail and plug-in safety net are set up in both sides.Also useful wooden springboard or steel springboard replace in the prior art For bamboo splint, there is transport of materials inconvenience in such mode of setting up, it is low that worker sets up time-consuming efficiency;Wooden springboard is relatively Weight, sets up that process is relatively elaborate, and steel springboard is generally sheetmetal plate, lighter weight, is easily toppled when trampling, and in use Easily deform upon.
(number of patent application is one first patent of applicant:201620722104.8 invention and created name is determined for a kind of light steel Type can be used in turn people's packway on scaffold) a kind of upper people's packway being used in turn is disclosed, the light upper people's packway of steel sizing It can be used in turn, and integral forming is set up and more facilitated, but because the light upper people's packway of steel sizing is needed according to reality Story height and the number of plies are processed, and flexibility is poor, and needs integral hoisting when setting up assembly, by lifting machine with And the limitation in place space.
The content of the invention
The defects of it is an object of the invention to overcome prior art, there is provided a kind of tile type overlap joint packway and its construction party Method, solve wooden springboard or steel springboard packway in the prior art and set up that existing laborious time-consuming efficiency is low and that easily topples asks Topic, and very flexible existing for steel packway and the problem of limited by lifting machine and place space.
Realizing the technical scheme of above-mentioned purpose is:
The invention provides a kind of tile type to overlap packway, is erected on scaffold, and the packway includes multiple bonding jumpers, Two adjacent bonding jumpers mutually overlap;
The bonding jumper includes tread portion and the bending hook part being connected with the tread portion, is taken by the bending hook part by described Contact pin is hooked on the cross bar of the scaffold, so as to which the tread portion forms aisle face at the cross bar;
The surface of the tread portion is provided with the first bulge-structure positioned at two sides, and first bulge-structure is along described Tread portion is moved towards to set.
Tile type overlap joint packway provided by the invention is erected on scaffold using bonding jumper, and on-site consolidation is convenient, speed It hurry up, turnover rate is high, the advantage such as installation coefficient height.The bonding jumper is hooked by bending hook part and is located on the cross bar of scaffold, is formed Berm structure is solid and reliable, is unlikely to deform, and not limited by the field, can monolithic use, can multi-disc splicing, flexibility is strong, no Easily topple, the turnover of the bonding jumper is flexible, without receiving the limitation of lifting machine and place space.
Tile type of the present invention overlap joint packway further improvement is that, the bending hook part is formed at the end of the tread portion Portion, including the arc-shaped limit section being connected with the end of the tread portion and straight spacing section be connected with the arc-shaped limit section, The surface of described straight spacing section and the end of the tread portion be arranged in parallel, the section radian of the arc-shaped limit section and institute The radian for stating cross bar is adapted.
Tile type of the present invention overlap joint packway further improvement is that, the end of the tread portion is set at the cross bar Limited location neck, the cross bar is limited in the bending hook part by the limit card slot.
Tile type of the present invention overlap joint packway further improvement is that, the tread portion is flat board, the first of the flat board End is provided with the bending hook part, and the second end corresponding with the first end of the flat board is placed on the tread portion of another bonding jumper And be erected on together on another cross bar, so as to which the flat board forms the packway together with the tread portion of another bonding jumper.
Tile type of the present invention overlap joint packway further improvement is that, the tread portion is provided with the hook including first end First skewback in portion, the arc linkage section being connected with the second end of first skewback and with the arc linkage section connect The second skewback connect;
First skewback is in the low skewed setting in high second end of first end;
The arc linkage section is adapted with the bending hook part;
Second skewback is adapted with the angle of inclination of first skewback;
The arc linkage section of the first bonding jumper in two adjacent bonding jumpers is attached at the bending hook part of the second bonding jumper Surface, the second skewback of the first bonding jumper are attached on the first skewback of second bonding jumper close to the portion of its bending hook part Point, so as to form continuous packway together by the first skewback, arc linkage section and the second skewback of multiple bonding jumpers.
Tile type of the present invention overlap joint packway further improvement is that, the tread portion include tread plate, with the tread Plate riser plate connected vertically and the spacing hook section for stepping on panel end is connected to, the end of the riser plate is provided with institute State bending hook part;
The spacing hook section is adapted with the bending hook part;
The spacing hook section of the first bonding jumper in two adjacent bonding jumpers is attached at the bending hook part of the second bonding jumper Surface, and part is attached on the riser plate of second bonding jumper, so as to form the packway of step by multiple bonding jumpers.
Present invention also offers a kind of construction method of tile type overlap joint packway, comprise the following steps:
Multiple bonding jumpers are provided, the bonding jumper includes tread portion and the bending hook part being connected with the tread portion, described to step on The surface of plate portion is provided with the first bulge-structure positioned at two sides, and trend of first bulge-structure along the tread portion is set Put;
The bonding jumper is hooked on the cross bar of scaffold by bending hook part, and by the pedal of two adjacent bonding jumpers Portion mutually overlaps, so as to form the aisle face of packway by the tread portion.
Construction method of the present invention further improvement is that, the tread portion is flat board, and the first end of the flat board is provided with The bending hook part;
The first bonding jumper in two adjacent bonding jumpers is hooked on the scaffold by the bending hook part of its own On corresponding cross bar, the second bonding jumper is hooked on corresponding cross bar on the scaffold by the bending hook part of its own;
The second end section at the second end of the flat board of first bonding jumper and the flat board of second bonding jumper is overlapped And be erected on together on the cross bar between the bending hook part of the first bonding jumper and the second bonding jumper, so as to pass through the flat of two bonding jumpers Plate forms the packway together.
Construction method of the present invention further improvement is that, the tread portion includes that first end is provided with the bending hook part One skewback, the arc linkage section being connected with the second end of first skewback and be connected with the arc linkage section Two skewbacks;
First skewback is set in the low heeling condition in high second end of first end, by inclining for second skewback Rake angle is arranged to be adapted with the angle of inclination of first skewback, and the arc linkage section is mutually fitted with the bending hook part Match somebody with somebody;
The arc linkage section of the first bonding jumper in two adjacent bonding jumpers is attached to the bending hook part of the second bonding jumper Surface;
Second skewback of first bonding jumper is attached on the first skewback of second bonding jumper close to it The part of bending hook part, so as to be formed together by the first skewback, arc linkage section and the second skewback of multiple bonding jumpers Continuous packway.
Construction method of the present invention further improvement is that, the tread portion includes tread plate, vertical with the tread plate The riser plate of connection and the spacing hook section for stepping on panel end is connected to, the end of the riser plate is provided with the hook Portion;
The spacing hook section is adapted with the bending hook part;
The spacing hook section of the first bonding jumper in two adjacent bonding jumpers is attached to the bending hook part of the second bonding jumper Surface, and part be attached on the riser plate of the second bonding jumper, so as to pass through multiple bonding jumpers formed step packway.
Brief description of the drawings
Fig. 1 is the structural representation of the first embodiment of the bonding jumper in tile type of the present invention overlap joint packway.
Fig. 2 is Fig. 1 side view.
Fig. 3 is the structural representation of the second embodiment of the bonding jumper in tile type of the present invention overlap joint packway.
Fig. 4 is Fig. 3 side view.
Fig. 5 is the structural representation of the 3rd embodiment of the bonding jumper in tile type of the present invention overlap joint packway.
Fig. 6 is Fig. 5 side view.
Fig. 7 is the cross-sectional view of the tread portion of the bonding jumper in tile type of the present invention overlap joint packway.
Fig. 8 is that the first embodiment of the bonding jumper in tile type of the present invention overlap joint packway forms the structural representation of packway.
Fig. 9 is that the second embodiment of the bonding jumper in tile type of the present invention overlap joint packway forms the structural representation of packway.
Figure 10 is that the 3rd embodiment of the bonding jumper in tile type of the present invention overlap joint packway forms the structural representation of packway.
Embodiment
The invention will be further described with specific embodiment below in conjunction with the accompanying drawings.
Refering to Fig. 1, the invention provides a kind of tile type to overlap packway, existing using wooden springboard making packway for solving Set up arduously because wooden springboard is relatively heavy, and need to additionally follow closely tread plate and cause cumbersome;Using template construct step Packway and the problem of low existing turnover rate;The problem of packway is made using steel springboard and easily topples and deforms;Using steel horse Road needs to be designed according to actual floor height and mechanical hoisting need to be used when assembled and is asked by what machinery and site area were limited Topic.The tile type overlap joint packway of the present invention is formed by multiple overlap joint oblique cut graftings, is overlapped on the cross bar of scaffold, the bonding jumper Structure is unified, factory can be used to produce in batches, versatile;On-site consolidation is convenient, and speed is fast, and turnover rate is high, and safety coefficient is high; Suitable for the operating environment of small space, do not limited by place, flexibility is strong;The berm structure of formation is firmly unlikely to deform, no Easily topple.Packway is overlapped to tile type of the present invention below in conjunction with the accompanying drawings and its construction method illustrates.
As shown in Fig. 1, Fig. 3 and Fig. 5, a kind of tile type overlap joint packway provided by the invention is erected on scaffold, the horse Road includes multiple bonding jumpers 20, and adjacent two bonding jumpers 20 mutually overlap, and bonding jumper 20 includes tread portion 21 and and tread portion The bending hook part 22 of 21 connections, bonding jumper 20 are hooked on the cross bar of scaffold by bending hook part 22, so as to stepping on for the bonding jumper 20 Plate portion 21 forms the aisle face of packway at cross bar, so that staff walks.The surface of tread portion 21, which is provided with, is located at two sides The first bulge-structure 211, first bulge-structure 211 along tread portion 21 move towards set.With reference to shown in Fig. 7, first is convex Two sides that structure 211 is located at tread portion 21 are played, and are set along the length direction of tread portion 211, first bulge-structure 211 Anti-crawl agentdefiection effect is served, prevents the deformation of tread portion 21, the first bulge-structure prevents two sides of tread portion 21 to produce crimping The deformation upwarped, it ensure that the structural stability and structural strength of tread portion 21.
As the better embodiment of the present invention, bending hook part 22 is formed at the end of tread portion 21, and the bending hook part 22 wraps The arc-shaped limit section 221 being connected with the end of tread portion 21 and straight spacing section 222 be connected with arc-shaped limit section 221 are included, is put down The surface of straight spacing section 222 and the end of tread portion 21 be arranged in parallel, the section radian of arc-shaped limit section 221 and the arc of cross bar Degree is adapted, and horizontal stroke is fastened in so as to which the end of the arc-shaped limit section 221, straight spacing section 222 and tread portion 21 encloses to form Neck on bar, it is preferred that straight spacing section 222 of the length is more than twice of cross bar diameter.Straight spacing section 222 serves The effect of mousing-hook, to ensure being connected firmly for bending hook part 22 and cross bar.With reference to shown in Fig. 8, horizontal stroke is located at bending hook part 22 is hooked When on bar 11, outer surface and the arc-shaped limit section 221 of the cross bar 11 fit, and are connected by the cutting ferrule of bending hook part 22 and cross bar 11 Connect so that bonding jumper 20 can be fixedly mounted on scaffold.
Further, to ensure fastness that bonding jumper 20 is connected with pin hand, the end of tread portion 21 is at cross bar 11 Provided with limit card slot 213, the limit card slot 213 is recessed to be formed downwards for the surface of tread portion 21, will by the limit card slot 213 Cross bar is limited in bending hook part 22, namely the setting due to limit card slot 213 so that cross bar is steadily placed in bending hook part 22. Limit card slot 213 serves spacing effect to cross bar, improves the structural stability of bonding jumper 20.
As depicted in figs. 1 and 2, it is shown that the structure of the first embodiment of bonding jumper 20 of the invention, in first embodiment In, the tread portion 21 of the bonding jumper 20 is flat board 21a, and flat board 21a includes relative first end 214a and the second end 215a, should Flat board 21a first end 214a is provided with bending hook part 22, and limit card slot 213 is provided with flat board 21a first end 214a.Flat board 2a First end 214a be connected with the arc-shaped limit section 221 of bending hook part 22, with reference to shown in Fig. 8, flat board 21a the second end 215a is placed in It is erected on the tread portion of another bonding jumper and together on another cross bar 11, so as to the tread portion of flat board and another bonding jumper It together form packway.
Further, can by the first embodiment structure composition packway of two bonding jumpers, in two bonding jumpers 20 One bonding jumper is hooked by the bending hook part 22 of itself and is located on a cross bar 11, and the second bonding jumper is hooked by the bending hook part 22 of itself and set On another cross bar 11, two cross bars 11 are oppositely arranged, and between be additionally provided with another cross bar 11, the of the first bonding jumper Second end 215a of two end 215a and the second bonding jumper is superimposed with each other on the cross bar 11 being placed between two cross bars 11, from And formd on three cross bars 11 and overlap the packway formed by two bonding jumpers 20.Packway direction of travel is flat with bonding jumper 20 Plate 21a length direction is perpendicular, so that and the one side of the first bulge-structure 211 serves anti-crawl agentdefiection effect to bonding jumper 20, On the other hand the anti-skid bulge also as packway.
As shown in Figure 3 and Figure 4, it is shown that the structure of the second embodiment of bonding jumper 20 of the invention, in second embodiment In, the step plate 21 of the bonding jumper 20 includes the first skewback 21b and the first skewback 21b that first end is provided with bending hook part 22 The connection of the second end arc linkage section 23b and the second skewback 25b for being connected with arc linkage section 23b, this is first oblique Panel 21b is adapted in the low skewed setting in high second end of first end, arc linkage section 23b with bending hook part 22, the second inclined-plane Plate 25b is adapted with the first skewback 21b angle of inclination.With reference to shown in Fig. 9, first in adjacent two bonding jumpers 20 takes The arc linkage section 23b of contact pin is sticked in the surface of the bending hook part 22 of the second bonding jumper, the second skewback 25b of the first bonding jumper Be sticked on the first skewback 21b of the second bonding jumper close to the second bonding jumper bending hook part 22 part, so as to by multiple The first skewback 21b, the arc linkage section 23b and the second skewback 25b of bonding jumper 20 form continuous packway together.
When overlapping to form packway using the second embodiment of bonding jumper, trend of the bonding jumper along packway is overlapped successively Set, the arc linkage section 23b of first bonding jumper is ridden upon on a cross bar 11, then successively by the arc of the latter bonding jumper Shape linkage section 23b and the second skewback 25b is ridden upon on the skewback 21b of bending hook part 22 and first of previous bonding jumper, so as to The second skewback 25b, the arc linkage section 23b and the first skewback 21b of lap connection together are formd on cross bar 11, So as to which those second skewbacks 25b, arc linkage section 23b and the first skewback 21b surface form the aisle face of packway.
Further, in a second embodiment, the second bulge-structure 212 is additionally provided with bonding jumper 20, the second raised knot Structure 212 is vertically arranged, second bulge-structure between two the first bulge-structures 211 with the first bulge-structure 211 212 serve anti-skidding effect, and aisle face interval of second bulge-structure 212 along packway is laid, and prevents operating personnel from existing Walking such as is slipped at the fortuitous event on the face of aisle.
As shown in Figure 5 and Figure 6, it is shown that the structure of the 3rd embodiment of bonding jumper 20 of the invention, in 3rd embodiment In, the tread portion 21 of bonding jumper 20 includes tread plate 21c, riser plate 23c connected vertically with tread plate 21c and is connected to step on The spacing hook section 25c of panel 21c ends, the riser plate 23c end are provided with bending hook part 22.Spacing hook section 25c therein It is adapted with bending hook part 22.With reference to shown in Figure 10, the spacing hook section 25c of the first bonding jumper in adjacent two bonding jumpers 20 It is sticked and is sticked on the surface of the bending hook part 22 of the second bonding jumper and part on the riser plate 23c in the second bonding jumper, so as to passes through Multiple bonding jumpers form the packway of step.Treads of the tread plate 21c therein as step aisle, riser plate 23c make For the riser in step aisle, tread is walked for operating personnel.
Further, in the third embodiment, tread plate 21c is provided with the second bulge-structure 212, second bulge-structure 212 between two the first bulge-structures 211, and are vertically arranged with the first bulge-structure 211, second bulge-structure 212 Serve anti-skidding effect.
The scaffold that the packway of the present invention is set up includes multiple vertical rods, the cross bar being connected laterally in vertical rod, Yi Jilian Cross bar and the vertical pole of vertical rod are connect, the length of cross bar is more than vertical pole, and the cross bar for setting bonding jumper 20 is long transverse lever, and vertical pole is quarter butt. The length of cross bar of the length adaptation of bonding jumper 20 between two vertical rods, the bending hook part 22 of bonding jumper 20, which hooks, is located at two vertical rods Between cross bar on, so as on cross bar pass through tread portion 21 formed packway aisle face.
Present invention also offers a kind of construction method of tile type overlap joint packway, overlaps horse to the tile type of the present invention below The construction method in road illustrates.
The construction method of the tile type overlap joint packway of the present invention comprises the following steps:
As shown in Fig. 1, Fig. 3 and Fig. 5, there is provided multiple bonding jumpers 20, bonding jumper 20 include tread portion 21 and with tread portion 21 The bending hook part 22 of connection, the surface of tread portion 21 are provided with the first bulge-structure 211 positioned at two sides, first bulge-structure 211 move towards to set along tread portion 21.With reference to shown in Fig. 7, the first bulge-structure 211 is located at two sides of tread portion 21, and Set along the length direction of tread portion 211, first bulge-structure 211 serves anti-crawl agentdefiection effect, prevents the change of tread portion 21 Shape, the first bulge-structure prevent two sides of tread portion 21 to produce the deformation that crimping upwarps, ensure that the structure of tread portion 21 Stability and structural strength.
Bonding jumper 20 is hooked on the cross bar of scaffold by bending hook part 22, and stepping on two adjacent bonding jumpers 20 Plate portion 21 mutually overlaps, so as to form the aisle face of packway by tread portion 21.
As the better embodiment of the present invention, bending hook part 22 is formed at the end of tread portion 21, and the bending hook part 22 wraps The arc-shaped limit section 221 being connected with the end of tread portion 21 and straight spacing section 222 be connected with arc-shaped limit section 221 are included, is put down The surface of straight spacing section 222 and the end of tread portion 21 be arranged in parallel, the section radian of arc-shaped limit section 221 and the arc of cross bar Degree is adapted, and horizontal stroke is fastened in so as to which the end of the arc-shaped limit section 221, straight spacing section 222 and tread portion 21 encloses to form Neck on bar, it is preferred that straight spacing section 222 of the length is more than twice of cross bar diameter.Straight spacing section 222 serves The effect of mousing-hook, to ensure being connected firmly for bending hook part 22 and cross bar.With reference to shown in Fig. 8, horizontal stroke is located at bending hook part 22 is hooked When on bar 11, outer surface and the arc-shaped limit section 221 of the cross bar 11 fit, and are connected by the cutting ferrule of bending hook part 22 and cross bar 11 Connect so that bonding jumper 20 can be fixedly mounted on scaffold.
Further, to ensure fastness that bonding jumper 20 is connected with pin hand, the end of tread portion 21 is at cross bar 11 Provided with limit card slot 213, the limit card slot 213 is recessed to be formed downwards for the surface of tread portion 21, will by the limit card slot 213 Cross bar is limited in bending hook part 22, namely the setting due to limit card slot 213 so that cross bar is steadily placed in bending hook part 22. Limit card slot 213 serves spacing effect to cross bar, improves the structural stability of bonding jumper 20.
As depicted in figs. 1 and 2, it is shown that the structure of the first embodiment of bonding jumper 20, in the first embodiment, the overlap joint The tread portion 21 of piece 20 is flat board 21a, and flat board 21a includes relative first end 214a and the second end 215a, flat board 21a's First end 214a is provided with bending hook part 22, and limit card slot 213 is provided with flat board 21a first end 214a.Flat board 2a first end 214a is connected with the arc-shaped limit section 221 of bending hook part 22, and with reference to shown in Fig. 8, first in two adjacent bonding jumpers 20 is taken Contact pin is hooked on corresponding cross bar on scaffold by the bending hook part 22 of its own, and the second bonding jumper is passed through into the curved of its own Hook part is hooked on corresponding cross bar on scaffold;
By the flat board 21a of the first bonding jumper the second end 215a and flat board 21a of the second bonding jumper the second end 215a portions Divide on the cross bar for overlapping and being erected on together between the first bonding jumper and the bending hook part 22 of the second bonding jumper, so as to be taken by two The flat board 21a of contact pin forms packway together.
Further, the length direction of packway direction of travel and the flat board 21a of bonding jumper 20 is perpendicular, so that first The one side of bulge-structure 211 serves anti-crawl agentdefiection effect to bonding jumper 20, on the other hand the anti-skid bulge also as packway.
As shown in Figure 3 and Figure 4, it is shown that the structure of the second embodiment of bonding jumper 20, in a second embodiment, the overlap joint The step plate 21 of piece 20 includes first end and is provided with the first skewback 21b of bending hook part 22, the second end company with the first skewback 21b The arc linkage section 23b connect and the second skewback 25b being connected with arc linkage section 23b.With reference to shown in Fig. 9, by first Skewback 21b is set in the low heeling condition in high second end of first end, and the second skewback 25b angle of inclination is arranged to and the One skewback 21b angle of inclination is adapted, and arc linkage section 23b is adapted with bending hook part 22;By two adjacent overlap joints The arc linkage section 23b of the first bonding jumper in piece 20 is attached at the surface of the bending hook part 22 of the second bonding jumper;By the first overlap joint Second skewback 25b of piece is attached on the first skewback 21b of the second bonding jumper close to the part of its bending hook part 22, so as to logical The first skewback, arc linkage section and the second skewback for crossing multiple bonding jumpers form continuous packway together.By bonding jumper Setting is overlapped successively along the trend of packway, and the arc linkage section 23b of first bonding jumper is ridden upon on a cross bar 11, then The arc linkage section 23b of the latter bonding jumper and the second skewback 25b are ridden upon to the bending hook part 22 of previous bonding jumper successively On the first skewback 21b, connect so as to form the second skewback 25b, the arc of lap connection together on cross bar 11 Section 23b and the first skewback 21b are met, so as to those second skewbacks 25b, arc linkage section 23b and the first skewback 21b table Face forms the aisle face of packway.
Further, in a second embodiment, the second bulge-structure 212 is additionally provided with bonding jumper 20, the second raised knot Structure 212 is vertically arranged, second bulge-structure between two the first bulge-structures 211 with the first bulge-structure 211 212 serve anti-skidding effect, and aisle face interval of second bulge-structure 212 along packway is laid, and prevents operating personnel from existing Walking such as is slipped at the fortuitous event on the face of aisle.
As shown in Figure 5 and Figure 6, it is shown that the structure of the 3rd embodiment of bonding jumper 20, in the third embodiment, the overlap joint The tread portion 21 of piece 20 includes tread plate 21c and tread plate 21c riser plate 23c connected vertically and is connected to tread plate 21c ends The spacing hook section 25c in portion, the riser plate 23c end are provided with bending hook part 22.Spacing hook section 25c and the phase of bending hook part 22 are fitted Match somebody with somebody.With reference to shown in Figure 10, the spacing hook section 25c of the first bonding jumper in two adjacent bonding jumpers is attached at the second overlap joint The surface of the bending hook part 22 of piece, and part is attached on the riser plate 23c of the second bonding jumper, so as to be formed by multiple bonding jumpers The packway of step.Further, tread plate 21c is provided with the second bulge-structure 212, and second bulge-structure 212 is located at two Between individual first bulge-structure 211, and it is vertically arranged with the first bulge-structure 211, second bulge-structure 212 serves anti-skidding Effect.
The present invention is described in detail above in association with accompanying drawing embodiment, those skilled in the art can be according to upper State and bright many variations example is made to the present invention.Thus, some details in embodiment should not form limitation of the invention, this Invention will be used as protection scope of the present invention using the scope that appended claims define.

Claims (10)

1. a kind of tile type overlaps packway, it is erected on scaffold, it is characterised in that the packway includes multiple bonding jumpers, phase Two adjacent bonding jumpers mutually overlap;
The bonding jumper includes tread portion and the bending hook part that is connected with the tread portion, by the bending hook part by the bonding jumper Hook on the cross bar of the scaffold, so as to which the tread portion forms aisle face at the cross bar;
The surface of the tread portion is provided with the first bulge-structure positioned at two sides, and first bulge-structure is along the pedal Portion moves towards to set.
2. tile type as claimed in claim 1 overlaps packway, it is characterised in that the bending hook part is formed at the tread portion End, including the arc-shaped limit section that is connected with the end of the tread portion and be connected with the arc-shaped limit section straight spacing Section, the surface of described straight spacing section and the end of the tread portion be arranged in parallel, the section radian of the arc-shaped limit section It is adapted with the radian of the cross bar.
3. tile type as claimed in claim 2 overlaps packway, it is characterised in that the end of the tread portion is close to the cross bar Place is provided with limit card slot, and the cross bar is limited in the bending hook part by the limit card slot.
4. tile type as claimed any one in claims 1 to 3 overlaps packway, it is characterised in that the tread portion is flat board, The first end of the flat board is provided with the bending hook part, and the second end corresponding with the first end of the flat board is placed in another overlap joint It is erected on the tread portion of piece and together on another cross bar, so as to flat board shape together with the tread portion of another bonding jumper Into the packway.
5. tile type as claimed any one in claims 1 to 3 overlaps packway, it is characterised in that the tread portion includes the One end be provided with the first skewback of the bending hook part, the arc linkage section that is connected with the second end of first skewback and with Second skewback of the arc linkage section connection;
First skewback is in the low skewed setting in high second end of first end;
The arc linkage section is adapted with the bending hook part;
Second skewback is adapted with the angle of inclination of first skewback;
The arc linkage section of the first bonding jumper in two adjacent bonding jumpers is attached at the surface of the bending hook part of the second bonding jumper, Second skewback of the first bonding jumper is attached on the first skewback of second bonding jumper close to the part of its bending hook part, from And continuous packway is formed by the first skewback, arc linkage section and the second skewback of multiple bonding jumpers together.
6. tile type as claimed any one in claims 1 to 3 overlaps packway, it is characterised in that the tread portion includes stepping on Panel, with tread plate riser plate connected vertically and being connected to the spacing hook section for stepping on panel end, it is described to kick The end of panel is provided with the bending hook part;
The spacing hook section is adapted with the bending hook part;
The spacing hook section of the first bonding jumper in two adjacent bonding jumpers is attached at the surface of the bending hook part of the second bonding jumper, And part is attached on the riser plate of second bonding jumper, so as to form the packway of step by multiple bonding jumpers.
7. a kind of construction method of tile type overlap joint packway, it is characterised in that comprise the following steps:
Multiple bonding jumpers are provided, the bonding jumper includes tread portion and the bending hook part being connected with the tread portion, the tread portion Surface be provided with positioned at two sides the first bulge-structure, first bulge-structure along the tread portion move towards set;
The bonding jumper is hooked on the cross bar of scaffold by bending hook part, and by the tread portion phase of two adjacent bonding jumpers Mutually overlap joint, so as to form the aisle face of packway by the tread portion.
8. construction method as claimed in claim 7, it is characterised in that the tread portion is flat board, the first end of the flat board Provided with the bending hook part;
The first bonding jumper in two adjacent bonding jumpers is hooked by the bending hook part of its own and corresponded on the scaffold Cross bar on, the second bonding jumper is hooked on the scaffold on corresponding cross bar by the bending hook part of its own;
The second end section at the second end of the flat board of first bonding jumper and the flat board of second bonding jumper is overlapped and one Rise and be erected on the cross bar between the bending hook part of the first bonding jumper and the second bonding jumper, so as to pass through the flat board one of two bonding jumpers Rise and form the packway.
9. construction method as claimed in claim 7, it is characterised in that the tread portion is provided with the bending hook part including first end The first skewback, the arc linkage section that is connected with the second end of first skewback and be connected with the arc linkage section The second skewback;
First skewback is set in the low heeling condition in high second end of first end, by the inclination angle of second skewback Degree is arranged to be adapted with the angle of inclination of first skewback, and the arc linkage section is adapted with the bending hook part;
The arc linkage section of the first bonding jumper in two adjacent bonding jumpers is attached to the table of the bending hook part of the second bonding jumper Face;
Second skewback of first bonding jumper is attached on the first skewback of second bonding jumper close to its hook The part in portion, so as to be formed together continuously by the first skewback, arc linkage section and the second skewback of multiple bonding jumpers Packway.
10. construction method as claimed in claim 7, it is characterised in that the tread portion includes tread plate and the tread plate Riser plate connected vertically and the spacing hook section for stepping on panel end is connected to, the end of the riser plate is provided with described Bending hook part;
The spacing hook section is adapted with the bending hook part;
The spacing hook section of the first bonding jumper in two adjacent bonding jumpers is attached to the table of the bending hook part of the second bonding jumper Face, and part is attached on the riser plate of the second bonding jumper, so as to form the packway of step by multiple bonding jumpers.
CN201710623785.1A 2017-07-27 2017-07-27 Tile type overlaps packway and its construction method Pending CN107476599A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710623785.1A CN107476599A (en) 2017-07-27 2017-07-27 Tile type overlaps packway and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710623785.1A CN107476599A (en) 2017-07-27 2017-07-27 Tile type overlaps packway and its construction method

Publications (1)

Publication Number Publication Date
CN107476599A true CN107476599A (en) 2017-12-15

Family

ID=60597073

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710623785.1A Pending CN107476599A (en) 2017-07-27 2017-07-27 Tile type overlaps packway and its construction method

Country Status (1)

Country Link
CN (1) CN107476599A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110512849A (en) * 2019-07-29 2019-11-29 南昌大学 A kind of scaffold being easily installed scaffold board and setting method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2916236A1 (en) * 1979-04-21 1980-10-23 Gerhard Dobersch Scaffolding working platform board - has brackets at one end supporting mutually offset end hooks gripping crossbars
WO1994012745A1 (en) * 1992-11-27 1994-06-09 Bricaud Jean Paul Gangway for crossing obstacles
FR2899911A1 (en) * 2006-04-14 2007-10-19 Jean Paul Bricaud Protective part i.e. guard rail, and floor unit connecting node for forming e.g. urban usage foot bridge, has support base plate surmounted with guide receiving vertical tubular post of protective part by insertion
CN101680231A (en) * 2007-03-30 2010-03-24 蒂森克虏伯萨夫维公司 Erector scaffold deck fall arrest assembly
CN103883111A (en) * 2014-03-04 2014-06-25 袁士风 Folding scaffold

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2916236A1 (en) * 1979-04-21 1980-10-23 Gerhard Dobersch Scaffolding working platform board - has brackets at one end supporting mutually offset end hooks gripping crossbars
WO1994012745A1 (en) * 1992-11-27 1994-06-09 Bricaud Jean Paul Gangway for crossing obstacles
FR2899911A1 (en) * 2006-04-14 2007-10-19 Jean Paul Bricaud Protective part i.e. guard rail, and floor unit connecting node for forming e.g. urban usage foot bridge, has support base plate surmounted with guide receiving vertical tubular post of protective part by insertion
CN101680231A (en) * 2007-03-30 2010-03-24 蒂森克虏伯萨夫维公司 Erector scaffold deck fall arrest assembly
CN103883111A (en) * 2014-03-04 2014-06-25 袁士风 Folding scaffold

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110512849A (en) * 2019-07-29 2019-11-29 南昌大学 A kind of scaffold being easily installed scaffold board and setting method

Similar Documents

Publication Publication Date Title
JP6703477B2 (en) Work platform system including suspended panel unit and method for mounting work platform system
CN206053274U (en) The external scaffolding device of the perpendicular BAIYE outer visor of skyscraper and glass curtain wall dual-purpose
CN104060844A (en) Sliding device and lifting device for truss frame of steel structural transfer floor of the high-rise building and construction method thereof
KR102029907B1 (en) Prefabricated shoring system
KR101556968B1 (en) Suspension pedestrian bridge integrated with parapet using parapet cable and constructing method thereof
US10465393B1 (en) Apparatus, system and method for panelizing and installing wall and roof panels
CN106150057B (en) A kind of split blade type hydraulic pressure lift climbing frame
CN107476599A (en) Tile type overlaps packway and its construction method
CN207144549U (en) Tile type overlaps packway
CN209011528U (en) A kind of all steel attachment type raise scaffold
CN105090613B (en) A kind of hanging method of high-rise building exterior wall gas pipeline
CN106948603A (en) Wall plate member switching mechanism and its method for turning
CN107816209B (en) The large-scale Roof Truss construction technology of installation is lifted across outer two sides
CN105839907A (en) Suspension type steel platform scaffold foundation and method for mounting same
KR100818863B1 (en) Lift and installing method of preassembled truss decks at ground level
CN102852280B (en) The prestressing force precast beam of head shelved by a kind of band
CN110359696B (en) Adjustable attached lifting scaffold and inclined climbing method thereof
CN205348731U (en) Core section of thick bamboo reinforcing bar post is from promoting formula operation platform
CN208604959U (en) Assembled protection shed frame integrating safety protection of construction elevator and ramp
CN104863344B (en) The assemble method of elevator erecting device and the erecting device
CN207633735U (en) The tower soft platform of lighting roof
JP3398833B2 (en) Escalator step turning method and turning device
CN113137072A (en) Construction method of high-altitude track mobile steel platform
CN105781092A (en) Single-guide-frame and multi-stage lifting working platform with adjustable interval and construction method thereof
CN202913705U (en) Large curtain wall unit plate track lifting device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination