CN107401219B - The node of column and beam and its construction method of the anti-buckling energy-consumption component of replacement easy to install - Google Patents

The node of column and beam and its construction method of the anti-buckling energy-consumption component of replacement easy to install Download PDF

Info

Publication number
CN107401219B
CN107401219B CN201710810371.XA CN201710810371A CN107401219B CN 107401219 B CN107401219 B CN 107401219B CN 201710810371 A CN201710810371 A CN 201710810371A CN 107401219 B CN107401219 B CN 107401219B
Authority
CN
China
Prior art keywords
connection sleeve
concrete
energy consumption
flange
sleeve
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201710810371.XA
Other languages
Chinese (zh)
Other versions
CN107401219A (en
Inventor
王昆
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wanpin Architectural Design (Shanghai) Co., Ltd.
Original Assignee
Wanpin Architectural Design (shanghai) Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wanpin Architectural Design (shanghai) Co Ltd filed Critical Wanpin Architectural Design (shanghai) Co Ltd
Priority to CN201710810371.XA priority Critical patent/CN107401219B/en
Publication of CN107401219A publication Critical patent/CN107401219A/en
Application granted granted Critical
Publication of CN107401219B publication Critical patent/CN107401219B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/20Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of concrete, e.g. reinforced concrete, or other stonelike material
    • E04B1/21Connections specially adapted therefor
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H9/00Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate
    • E04H9/02Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate withstanding earthquake or sinking of ground
    • E04H9/021Bearing, supporting or connecting constructions specially adapted for such buildings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H9/00Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate
    • E04H9/02Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate withstanding earthquake or sinking of ground
    • E04H9/025Structures with concrete columns

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Business, Economics & Management (AREA)
  • Emergency Management (AREA)
  • Environmental & Geological Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Mechanical Engineering (AREA)
  • Joining Of Building Structures In Genera (AREA)

Abstract

The present invention relates to the node of column and beam and its construction method of a kind of anti-buckling energy-consumption component of replacement easy to install, with energy consumption bar member connection between the vertical muscle of the subsidiary short beam of beams of concrete and column side, the first screwed assembly that energy consumption bar member is connect with the first vertical muscle includes: the 5th connection sleeve, the 6th connection sleeve, and the second screwed assembly that energy consumption bar member is connect with the second vertical muscle includes: the first connection sleeve, the second connection sleeve, third connection sleeve, the 4th connection sleeve.Using the node of column and beam and its construction method of the anti-buckling energy-consumption component of present invention replacement easy to install, it can quickly install and restore anti-buckling energy-consumption component.

Description

The node of column and beam and its construction method of the anti-buckling energy-consumption component of replacement easy to install
Technical field
The invention patent relates to the seismic resistance field of building structure, in particular to a kind of anti-buckling energy-consumption structure of replacement easy to install The node of column and beam and its construction method of part.
Background technique
The anti-seismic performance of bean column node is always that field is given priority in building structure.For bean column node, generally By moving on on beam plastic hinge region outside cylinder, the thought of strong column and weak beam is realized.
105780960 A of CN provides a kind of fully-prefabricated assembled column-beam anti-buckling energy-consumption node, the anti-buckling energy-consumption Node includes two anti-buckling edge of a wing metal plate energy-consumption dampers, two high-strength web connecting plates, one first pre-buried girder steel and one the Two pre-buried girder steels;One end of the first pre-buried girder steel is embedded in the concrete column, the protruding cylinder of the other end;Described One end of two pre-buried girder steels is embedded in the beams of concrete, the protruding beam-ends face of the other end;The first pre-buried girder steel and The upper lower flange of two pre-buried girder steels is connected by the two anti-buckling edge of a wing metal plate energy-consumption dampers;First pre-buried steel Beam is connected with the two sides in the middle part of the second pre-buried girder steel by the two high-strength web connecting plates.The advantage is that: can pass through The anti-buckling energy-consumption node realizes that plastic hinge is moved out from cylinder, to reduce the damage to anti-buckling energy-consumption joint cores Wound realizes the anti-seismic performance requirement of " strong column and weak beam " and " strong shear capacity and weak bending capacity ".
And CN103556780A also provides a kind of anti-buckling shape steel-concrete combined beam in the edge of a wing, including pillar and the edge of a wing are prevented Buckling fashioned iron portion.The anti-buckling fashioned iron portion in the edge of a wing is installed on pillar, the anti-buckling fashioned iron portion in the edge of a wing include girder steel, floor, Peg, bolt and anti-buckling steel bushing plate, the floor are fixed on girder steel by peg, and the anti-buckling steel bushing plate passes through bolt It is anchored at girder steel lower flange and lower part web.It has construct it is convenient, from heavy and light, intensity is high, rigidity is big, positive and negative Moment The symmetrical advantage of lower performance.
The mechanical mechanism of above-mentioned document is, for girder steel, plastic hinge turns to be moved to Liang Shanghou, due to the upper and lower wing Edge undertakes " drawing-pressure " cyclic reverse loading, may generate buckling when being pressurized, therefore, anti-buckling support is designed as on the edge of a wing Form, the energy-dissipating property of Lai Tigao bean column node.
CN104088375A discloses a kind of buckling-restrained reinforcement constitution, upper reinforcement, lower rebar, buckling-restrained steel Muscle, confinement sleeve, threaded coupling sleeve and closed material composition, the advantage is that: in the reciprocal of the accidental loads such as earthquake load Under effect, constraint of the Reinforcement in compressive buckling by external constraint casing, to improve Reinforcement Axially compression bearing capacity, had both been able to maintain the power transmission load-carrying properties of Reinforcement itself under cyclic reverse loading, while can be with It prevents the buckling of Reinforcement from failing, improves entire pier stud component or pier stud-girder connection energy dissipation capacity. The method of CN104088375A is similar with the principle of CN 105780960 A, CN103556780A, is to set reinforcing bar, the steel edge of a wing Confining part is set, its compressive buckling is prevented.Similar scheme is arranged also just like CN105525679A also between beam-column Energy consumption stick consume energy.
However, how anti-buckling component is quickly installed there is also certain damage and restores anti-buckling after geological process Dissipative member becomes a urgent problem to be solved.In the prior art, also not mixed to bean column node, especially beams of concrete- This problem of anti-buckling energy-consumption component quick-replaceable in solidifying earth pillar carries out the analysis and solution of system.
Summary of the invention
The object of the present invention is to provide the node of column and beam and its construction party of a kind of anti-buckling energy-consumption component of replacement easy to install Method solves how quickly to install the technical issues of restoring anti-buckling energy-consumption component.
A kind of node of column and beam of the anti-buckling energy-consumption component of replacement easy to install, comprising: concrete column 1, the second beams of concrete 2-2, concrete column 1 are also prefabricated with the first short beam 2-1, the second beams of concrete 2-2 for prefabricated and cylinder;First short beam 2-1 It is embedded with the first vertical muscle 3-1 of prominent first end face short beam 2-1, the upper and lower side of the end of the second beams of concrete 2-2 is provided with enterprise Mouth 2-3, the vertical muscle 3-2 of the second of the second beams of concrete 2-2 stretch out tongue and groove end face, and the first vertical muscle 3-1 and the second vertical muscle 3-2 are mutually right It answers;Energy consumption bar member 4 is connected between the first vertical vertical muscle 3-2 of muscle 3-1 and second;
Pre-buried first position-limiting tube 9 in the first short beam 2-1;
Energy consumption bar member 4 includes: the 5th connection sleeve 10- with the first vertical muscle 3-1 the first screwed assembly 10 connecting 1, the 6th connection sleeve 10-2, the 5th connection sleeve 10-1 includes third flange, the 4th flange and gear conjunction portion, third flange, the Four flange inners have screw thread;There is screw thread on the inside of 6th connection sleeve, the outside spiral shell with energy consumption bar member 4 and the 4th flange Line connection;
Vertical plate 6-2 is arranged in second beams of concrete 2-2 at tongue and groove;
Energy consumption bar member 4 and the second vertical muscle 3-2 the second screwed assembly 7 connecting include: the first connection sleeve 7-1, Second connection sleeve 7-2, third connection sleeve 7-3, the 4th connection sleeve 7-4;The 4th connection sleeve 7-4 includes first convex Edge, the second flange and gear conjunction portion, are provided with screw thread on the inside of the first flange and the second flange and connect with the second vertical muscle 3-2, the Two flanges are inserted into the through-hole 6-3 of vertical plate 6-2, are also equipped with screw thread in the outer surface of the first flange;The third connector sleeve The inner surface of cylinder 7-3 is threadedly coupled the outer surface for the first flange for connecting sleeve 7-4 with the 4th;Second connection sleeve 7-2's is interior Surface is threadedly coupled the end of energy consumption bar member 4;The inner surface of the first connection sleeve 7-1 is threadedly connected to the second connector sleeve Cylinder 7-2 and third connect sleeve 7-3.
Further, using the connection side of Alveolus type or shaped-steel joint between the first short beam 2-1 and the second beams of concrete 2-2 Formula connection.
Further, the first position-limiting tube 9 is steel pipe, the 5th connection third flange of sleeve 10-1 and connecing for the first position-limiting tube 9 Contacting surface is shiny surface.
Further, the two sides of tongue and groove 2-3 and the second beams of concrete 2-2 it is affixed have block 2-4;Steel plate is constrained first Screw rod 8-3 is connected on the bottom plate of 8-1, the outside of the energy consumption bar member 4 in tongue and groove is provided with concrete restraining plate, and second about The outside of concrete restraining plate is arranged in beam steel plate 8-2, and by concrete restraining plate and the second constraint steel plate 8-2 is provided with and spiral shell The corresponding hole bar 8-3.
A kind of construction method of the node of column and beam of the anti-buckling energy-consumption component of replacement easy to install, installation energy consumption bar member 4, Installation steps are as follows:
First, the 4th connection sleeve 7-4 is passed through into the second vertical muscle 3-2 and is entered in through-hole 6-3, third is connected into sleeve 7- 3 are threaded on the first flange of the 4th connection sleeve 7-4, and the first connection sleeve set 7-1 is covered on energy consumption bar member 4, In the second connection of end thread connection sleeve 7-2 of energy consumption stick;
Second, energy consumption bar member 4 is connect with the first screwed assembly;
Third, with second connect sleeve 7-2 for the first connection sleeve 7-1 and connect sleeve 7-3 with third and link together.
Further, before energy consumption bar member 4 is installed, at the vertical plate 6-2 of beams of concrete and other positions of tongue and groove One layer of elastic fluid of surface mount, on elastic fluid install first constraint steel plate 8-1, first constraint steel plate 8-1 include bottom Portion's plate and two sides vertical plate.
Further, after energy consumption bar member 4 is installed, the hole of concrete restraining plate is corresponded into screw rod, is placed in tongue and groove In, screw rod 8-3 passes through the surface of the second constraint steel plate 8-2, then uses nut tightening.
Further, the step of energy consumption stick is connect with the first screwed assembly is as follows: firstly, the 5th connection sleeve 10-1 rotation Enter the first reinforcing bar, the 5th connection sleeve 10-1 third flange enters in the first position-limiting tube 9 until its gear conjunction portion connects with the first short beam Touching, secondly, the 6th connection sleeve 10-2 is threaded on the 4th flange of the 5th connection sleeve 10-1, finally, will energy consumption Bar member 4 is threaded in the 6th connection sleeve 10-2.
By adopting the above technical scheme, compared with prior art, advantage includes the following.
First, by installing energy consumption bar member in tongue and groove, in order to installation and replacement energy consumption bar member.
Second, energy consumption bar member connect with vertical muscle to be connected using the means for connecting sleeve, from one~embodiment of comparative example one, It successively solves following problems: how to connect the end of energy consumption bar member, the stretching for how avoiding the first vertical muscle and the second vertical muscle How buckling avoids the screw-in of sleeve from screwing out.
Block is arranged in third on concrete tongue-and-groove, is the positioning in order to limit the concrete in tongue and groove;And it will be in tongue and groove It is concrete prefabricated connected at plate by bolt and nut, can easily install energy consumption bar member concrete constraint.
Detailed description of the invention:
Fig. 1: the first short beam of one~embodiment of comparative example one and the design drawing of the second beams of concrete.
Fig. 2: the vertical muscle of comparative example one connect design drawing with energy consumption bar member.
Fig. 3: the vertical muscle of comparative example two connect design drawing with energy consumption stick.
Fig. 4: the vertical muscle of comparative example three connect design drawing with energy consumption stick.
Fig. 5: the schematic diagram of the vertical plate 6-2 of comparative example three.
Fig. 6: the vertical muscle of embodiment one connect design drawing with energy consumption bar member.
Fig. 7: the schematic diagram of the first constraint steel plate 8-1 of embodiment one and the second constraint steel plate 8-2.
Fig. 8: the first short beam of embodiment two and the design drawing of the second beams of concrete.
Fig. 9: the limited block of the tongue and groove of the secondth beams of concrete of embodiment three and the design drawing of screw rod.
Appended drawing reference: 1 concrete column, the first short beam of 2-1, the second beams of concrete of 2-2,2-3 tongue and groove, 3-1 first indulge muscle, 3- 2 second vertical muscle, 4 energy consumption bar members, the first taper of 4-1 steel bushing, 4-2 the second taper steel bushing, the first connection component of 5-1,5-2 Second connection component, 5-2-1 energy consumption stick connect sleeve, and 5-2-2 indulges muscle connecting elements, 6-2 vertical plate, 6-3 through-hole, 7 second spiral shells Line connection component, the connection sleeve of 7-1 first, the connection sleeve of 7-2 second, 7-3 third connect sleeve, the connection sleeve of 7-4 the 4th, 7- The first flange of 4-1, the second flange of 7-4-2,8-1 first constrain steel plate, and 8-2 second constrains steel plate, 8-3 screw rod, 9 first limits Pipe, 10 first screwed assemblies, the connection sleeve of 10-1 the 5th, the connection sleeve of 10-2 the 6th.
Specific embodiment
Comparative example one can consume for prefabricated assembled concrete beam-concrete column connecting node for the ease of replacement Energy connection component, the first selection is the pre-buried fashioned iron in beam such as CN105780960A, and the fashioned iron of prominent beam is utilized to connect energy consumption Component.This mode, can also apply and girder steel.Above scheme is excessive in the moment capacity decline of beam-ends, and only fashioned iron is held Moment of flexure is carried on a shoulder pole, and concrete does not undertake moment of flexure.For this purpose, inventor, which has abandoned, utilizes the edge of a wing replacement dissipative member on structural steel connecting member Thought.Second of selection is such as CN105525679A, the setting energy consumption stick between beams of concrete-column, using energy consumption stick come real Now consume energy.But energy consumption stick is cast in composite beam, replaces inconvenience;And more importantly, in mechanical mechanism On, energy consumption stick is in tension and compression Cyclic Loading, is actually the fixing iron member using energy consumption stick two sides when consuming energy stick tension Shearing force between concrete transmits the pulling force of energy consumption stick, this is higher for the intensity requirement of concrete and fixing iron member, And when consuming energy stick compressive buckling, it is also possible to generate destruction to concrete.
As shown in Figure 1, being the scheme of comparative example 1, comprising: concrete column 1, the second beams of concrete 2-2, concrete column 1 Cylinder has the first short beam 2-1, using Alveolus type or shaped-steel joint between the first short beam 2-1 and the second beams of concrete 2-2 Connection type connection;First short beam 2-1 is embedded with the first vertical muscle 3-1, the second beams of concrete 2- of prominent first end face short beam 2-1 The upper and lower side of 2 end is provided with tongue and groove 2-3, and the vertical muscle 3-2 of the second of the second beams of concrete 2-2 stretches out tongue and groove end face, and first is vertical Muscle 3-1 is corresponded to each other with the second vertical muscle 3-2;Energy consumption bar member 4 is connected between the first vertical vertical muscle 3-2 of muscle 3-1 and second.
After energy consumption bar member 4 is installed, the fill concrete in tongue and groove;The concrete and the first short beam filled in tongue and groove Flexible dielectric layer is provided between 2-1, the second beams of concrete 2-2.
As shown in Fig. 2, the first taper steel bushing is respectively adopted in energy consumption bar member 4 and the first vertical muscle 3-1, the second vertical muscle 3-2 4-1, the second taper steel bushing 4-2 connection;Consume energy bar member 4 both ends have shape of threads, sectional area muscle 3-1 vertical compared with first, Second vertical muscle 3-2 is big;First taper steel bushing 4-1, the shape of the second taper steel bushing 4-2 are identical.When installation, first by the first cone The vertical muscle of shape steel bushing 4-1 and first is threaded togather, the second taper steel bushing 4-2 and the second vertical muscle are threaded in one It rises, and the second taper steel bushing 4-2 is first mobile to the direction of the second vertical muscle, it then will energy consumption bar member and the first taper steel bushing The other end of 4-1 is threadedly coupled, and is then rotated the second taper steel bushing, is moved to the direction of dissipative member,
First, combine advantage of both CN105780960A, CN105525679A: the stick that will consume energy is directly vertical with beam Muscle connection does not need the anchoring piece that energy consumption stick is arranged again.
Second, in the effect of the upper and lower surfaces setting tongue and groove of the second beams of concrete 2-2, first is that in order to weaken the anti-of beam-ends Curved rigidity, so that plastic hinge moves on on beams of concrete from cylinder, so that energy consumption stick energy consumption;Second is that energy consumption stick is arranged in upper and lower table In the tongue and groove in face, in order to the installation and replacement of the stick that consumes energy.
Third, energy consumption stick compressive buckling energy consumption, if the bending deformation of energy consumption stick is excessive, concrete can be also crushed.If The concrete of energy consumption stick is connect with beams of concrete, is crushed meeting so that beams of concrete loses bearing capacity.And the application is to energy consumption stick Anti-buckling concrete is not involved in stress, broken to have an impact to the bearing capacity of beams of concrete.And in order to mention energy consumption Steel plate can be arranged in the outside of concrete in the anti-buckling performance of stick.
4th, the connection of energy consumption stick and the first vertical muscle, the second vertical muscle is a difficult point.Energy consumption stick and the first vertical muscle pass through first After taper steel bushing is connected through a screw thread, energy consumption stick cannot rotate again, pass through second the preparatory second vertical muscle spiral shell of taper steel bushing Line connection, and the second taper steel bushing screws in the second vertical muscle, after consume energy stick and the first taper steel bushing are installed, then by the Two taper steel bushings reversely rotate, so that the second taper steel bushing links together with energy consumption stick.
The problem of comparative example one is: the second taper steel bushing needs mobile distance larger in connection, and the second cone Shape steel bushing is moved on the second vertical muscle, and therefore, the distance that the second vertical muscle stretches out beams of concrete is also longer.
In view of the above deficiencies, comparative example two is proposed: as shown in figure 3, the first, second taper steel bushing is changed to One, the second connection component 5-1, the structure of 5-2, the two are identical, are made of two components: energy consumption stick connection sleeve 5-2-1 and Vertical muscle connecting elements 5-2-2, indulging muscle connecting elements is flanged screwed part, and the inner end and outer end of flange are equipped with screw thread, The inner end of flange is threadedly coupled with the first or second vertical muscle, and the outer end of flange connect the inner end spiral shell of sleeve 5-2-1 with energy consumption stick Line connection.When installation, energy consumption bar member is first connect with the first vertical muscle, first will consumption when the bar member that consumes energy is connect with the second vertical muscle Energy stick connection sleeve 5-2-1 is threadedly coupled, and vertical muscle connecting elements 5-2-2 is rotated in advance on the second vertical muscle, in place in energy consumption stick Afterwards, vertical muscle connecting elements 5-2-2 is rotated to energy consumption stick direction, so that the flange of vertical muscle connecting elements 5-2-2 and energy consumption stick connect Female connector cylinder 5-2-1 links together, until energy consumption stick connection sleeve 5-2-1 encounters the gear conjunction portion of vertical muscle connecting elements 5-2-2.
The advantages of comparative example two, is, is set as 2 components for what the bar member that consumes energy was threadedly coupled with the second vertical muscle, can Greatly facilitate the installation of energy consumption stick.But during the test, find: the end of the stretching of the first vertical muscle and the second vertical muscle has There is buckling phenomenon.
Comparative example three: as illustrated in figures 4-5, vertical plate 6- is fixedly installed in the upper and lower tongue and groove of the second beams of concrete 2-2 2, in the first short beam 2-1 pre-buried first position-limiting tube 9, its use metal material and protrude from the first short beam 2-1, will when installation Energy consumption bar member is threadedly coupled with the first connection component 5-1 of the first vertical muscle;It is arranged on vertical plate 6-2 corresponding with the second vertical muscle Through-hole 6-3, when installation, energy consumption stick connection sleeve 5-2-1 is first screwed in into energy consumption bar member first, then by the second vertical muscle connection The gear conjunction portion of component 5-2-2 is inserted into through-hole 6-3, and when the bar member that finally consumes energy positions, energy consumption stick connection sleeve 5-2-1 is screwed out, With the threaded connection of the flange of the second vertical muscle connecting elements 5-2-2.The vertical muscle connecting elements of the through-hole 6-3 of vertical plate 6-2 and second The gear conjunction portion of 5-2-2 is simultaneously not fixed, same to design, and the connection component 5-1 of the first vertical muscle is not also fixed with the first position-limiting tube 9, So that energy consumption bar member is given in vertical muscle power transmission.
Embodiment one: although arriving several improvement of comparative example three by comparative example one, three schemes have one Problem: being exactly the component screw-in back-out for being required to connection therein.Since above-mentioned component will play transmitting " drawing-pressure " load Effect, it is general using being more closely threadedly coupled, that is, it is larger to screw in dynamics required for screwing out.On the basis of comparative example three On, how to avoid screwing in back-out, is to continue with improved key point.
The first screwed assembly 10 for connecting with the first vertical muscle of energy consumption bar member 4 includes: the 5th to connect sleeve 10-1, the Six connection sleeve 10-2, the 5th connection sleeve 10-1 include third flange, the 4th flange and gear conjunction portion, including third flange, the Four flange inners have screw thread;There is screw thread on the inside of 6th connection sleeve, the outside spiral shell with energy consumption bar member 4 and the 4th flange Line connection;When installation, the 5th connection sleeve 10-1 screws in the first reinforcing bar, the 5th connection sleeve 10-1 third flange enters the first limit Until its gear conjunction portion is contacted with the first short beam in the pipe 9 of position, the 6th connection sleeve 10-2 is then threaded in the 5th connector sleeve On the 4th flange of cylinder 10-1, then energy consumption bar member 4 is threaded in the 6th connection sleeve 10-2.
Energy consumption bar member 4 and the second vertical muscle 3-2 the second screwed assembly 7 connecting include: the first connection sleeve 7-1, Second connection sleeve 7-2, third connection sleeve 7-3, the 4th connection sleeve 7-4;
4th connection sleeve 7-4 includes the first flange 7-4-1, the second flange and gear conjunction portion, the inside of the second flange 7-4-2 It is provided with screw thread and its through-hole 6-3 for being inserted into vertical plate 6-2, is arranged with screw thread in the surfaces externally and internally of the first flange;
The inner surface of third connection sleeve 7-3 is threadedly coupled the outer surface for the first flange for connecting sleeve 7-4 with the 4th;The The inner surface of two connection sleeve 7-2 is threadedly coupled the end of energy consumption bar member 4;
The inner surface of first connection sleeve 7-1 is threadedly connected to the second connection sleeve 7-2 and third connection sleeve 7-3. When installation, the first connection sleeve since its inner surface is not contacted with energy consumption bar member, do not need to need as comparative example 1-3 by Sleeve, which screws in, to be screwed out.
The outer surface of second connection sleeve 7-2 is in step-like, and the inner surface of the first connection sleeve is in step-like.Step is set Meter, the installation between component convenient for determining screwed assembly 7.
The installation steps of energy consumption bar member are as follows: first, the 4th connection sleeve 7-4 is passed through into the second vertical muscle 3-2 and entrance In through-hole 6-3, third connection sleeve 7-3 is threaded on the first flange of the 4th connection sleeve 7-4, by the first connector sleeve Cylinder set 7-1 covers on energy consumption bar member 4, in the second connection of end thread connection sleeve 7-2 of energy consumption stick;Second, by the stick that consumes energy Component 4 is connect with the first screwed assembly;First connection sleeve 7-1 is connect sleeve 7-2 with second and connect with third by third Sleeve 7-3 links together.
Before energy consumption bar member 4 is installed, on the surface at other positions of the vertical plate 6-2 and tongue and groove of beams of concrete Paste one layer of elastic fluid, on elastic fluid install first constraint steel plate 8-1, first constraint steel plate 8-1 include bottom plate and Two sides vertical plate constrains steel plate 8-1 after the first constraint steel plate 8-1 casting concrete, then by the second constraint steel plate 8-2 and first Connection, so that the anti-buckling concrete to energy consumption bar member constrains.This design is similar to anti-buckling support.
The first short beam 2-1 in embodiment one is identical as the cross-sectional sizes shape of the second beams of concrete 2-2 and uses rectangle, Its depth of section is h, and the length of the first short beam is between 0.5-0.7h, and the length of tongue and groove is between 0.15h-0.3h.It is above-mentioned to set The purpose of meter is to limit the position of beam-ends plastic hinge, sufficiently to improve the ductility of bean column node.
Embodiment two: as shown in figure 8, the upper and lower sides of the first short beam are also provided with tongue and groove;First vertical muscle and the bar member that consumes energy Connection type is identical as embodiment one.When using such design, the length of the first short beam is between 0.7-1.2h, the first short beam And second beams of concrete tongue and groove total length between 0.15h-0.6h.
Embodiment three: the problem of embodiment one is, casting concrete in tongue and groove, and the bar member 4 that thus causes to consume energy is not easy Transformation.For the ease of replacement, concrete in tongue and groove is using prefabricated, in order to the replacement for the board member 4 that consumes energy.As shown in figure 9, The two sides of tongue and groove and the second beams of concrete 2-2 it is affixed have block 2-4;Spiral shell is connected on the bottom plate of the first constraint steel plate 8-1 Bar 8-3, the outside of the energy consumption bar member 4 in tongue and groove are provided with concrete restraining plate, and the second constraint steel plate 8-2 is arranged in coagulation Concrete restraining plate and the second constraint steel plate 8-2 are provided with hole corresponding with screw rod 8-3 by the outside of native restraining plate;? When installation, after energy consumption bar member is installed, the hole of concrete restraining plate is corresponded into screw rod, is placed in tongue and groove, screw rod 8-3 Across the surface of the second constraint steel plate 8-2, nut tightening is then used.
The preferred embodiment of present aspect has already been described in detail above, it is understood that having read of the invention above-mentioned say After awarding content, those skilled in the art can make various modifications or changes to the present invention.Such equivalent forms equally fall into this Shen It please be in the protection scope of the appended claims.

Claims (8)

1. a kind of node of column and beam of the anti-buckling energy-consumption component of replacement easy to install, comprising: concrete column (1), the second beams of concrete (2-2), concrete column (1) are that prefabricated and cylinder has the first short beam (2-1), and the second beams of concrete (2-2) is also prefabricated;The One short beam (2-1) is embedded with the first vertical muscle (3-1) of prominent end face first short beam (2-1), the end of the second beams of concrete (2-2) Upper and lower side be provided with tongue and groove (2-3), the vertical muscle (3-2) of the second of the second beams of concrete (2-2) stretches out tongue and groove end face, and first is vertical Muscle (3-1) is corresponded to each other with the second vertical muscle (3-2);Energy consumption stick structure is connected between first vertical muscle (3-1) and the second vertical muscle (3-2) Part (4);
It is characterized by:
Pre-buried first position-limiting tube (9) in the first short beam (2-1);
The first screwed assembly (10) that energy consumption bar member (4) is connect with the first vertical muscle (3-1) includes: the 5th connection sleeve (10-1), the 6th connection sleeve (10-2), the 5th connection sleeve (10-1) they include third flange, the 4th flange and keep off conjunction portion, the Three flanges, the 4th flange inner have screw thread;There is screw thread on the inside of 6th connection sleeve, with energy consumption bar member (4) and the 4th The outside screw of flange connects;
Vertical plate (6-2) is arranged in second beams of concrete (2-2) at tongue and groove;
The second screwed assembly (7) that energy consumption bar member (4) is connect with the second vertical muscle (3-2) includes: the first connection sleeve (7- 1), the second connection sleeve (7-2), third connection sleeve (7-3), the 4th connection sleeve (7-4);The 4th connection sleeve (7- 4) include the first flange, the second flange and gear conjunction portion, screw thread is provided on the inside of the first flange and the second flange and is indulged with second Muscle (3-2) connection, the second flange are inserted into the through-hole (6-3) of vertical plate (6-2), are also equipped with spiral shell in the outer surface of the first flange Line;The inner surface of third connection sleeve (7-3) is threadedly coupled the appearance for the first flange for connecting sleeve (7-4) with the 4th Face;The inner surface of second connection sleeve (7-2) is threadedly coupled the end of energy consumption bar member (4);First connection sleeve (7-1) Inner surface be threadedly connected to the second connection sleeve (7-2) and third connection sleeve (7-3).
2. a kind of node of column and beam of the anti-buckling energy-consumption component of replacement easy to install as described in claim 1, which is characterized in that It is connect between first short beam (2-1) and the second beams of concrete (2-2) using the connection type of Alveolus type or shaped-steel joint.
3. a kind of node of column and beam of the anti-buckling energy-consumption component of replacement easy to install as described in claim 1, which is characterized in that the One position-limiting tube (9) is steel pipe, and the third flange of the 5th connection sleeve (10-1) is smooth with the contact surface of the first position-limiting tube (9) Face.
4. special such as a kind of described in any item node of column and beam of the anti-buckling energy-consumption component of replacement easy to install of claim 1 or 3 Sign is, the two sides of tongue and groove (2-3) and the second beams of concrete (2-2) it is affixed have block (2-4);Steel plate is constrained first It is connected with screw rod (8-3) on the bottom plate of (8-1), is provided with concrete restraining plate outside the energy consumption bar member (4) in tongue and groove, The outside of concrete restraining plate is arranged in second constraint steel plate (8-2), by concrete restraining plate and the second constraint steel plate (8-2) It is provided with hole corresponding with screw rod (8-3).
5. a kind of construction method of the node of column and beam of the anti-buckling energy-consumption component of replacement easy to install as described in claim 1, It is characterized in that:
Installation energy consumption bar member (4), installation steps include:
First, the 4th connection sleeve (7-4) is passed through into the second vertical muscle (3-2) and is entered in through-hole (6-3), third is connected into sleeve (7-3) is threaded on the first flange of the 4th connection sleeve (7-4), and the first connection sleeve set (7-1) is covered in energy consumption stick On component (4), in the second connection sleeve (7-2) of end thread connection of energy consumption stick;
Second, energy consumption bar member (4) is connect with the first screwed assembly;
Third, with second connect sleeve (7-2) for the first connection sleeve (7-1) and connect sleeve (7-3) with third and link together.
6. a kind of construction method of the node of column and beam of the anti-buckling energy-consumption component of replacement easy to install as claimed in claim 5, It is characterized in that, before energy consumption bar member (4) installation, at other positions of the vertical plate (6-2) and tongue and groove of beams of concrete One layer of elastic fluid of surface mount, installs the first constraint steel plate (8-1) on elastic fluid, and the first constraint steel plate (8-1) includes Bottom plate and two sides vertical plate.
7. a kind of construction method of the node of column and beam of the anti-buckling energy-consumption component of replacement easy to install as claimed in claim 5, It is characterized in that, after energy consumption bar member (4) installation, the hole of concrete restraining plate is corresponded into screw rod, is placed in tongue and groove, spiral shell Bar (8-3) passes through the surface of the second constraint steel plate (8-2), then uses nut tightening.
8. a kind of construction method of the node of column and beam of the anti-buckling energy-consumption component of replacement easy to install as claimed in claim 5, It is characterized in that, energy consumption stick the step of connect with the first screwed assembly is as follows: firstly, the 5th connects sleeve (10-1) screw-in the One reinforcing bar, the 5th connection sleeve (10-1) third flange enter in the first position-limiting tube (9) until its gear conjunction portion connects with the first short beam Touching, secondly, the 6th connection sleeve (10-2) is threaded on the 4th flange of the 5th connection sleeve (10-1), finally, will Energy consumption bar member (4) is threaded in the 6th connection sleeve (10-2).
CN201710810371.XA 2017-09-09 2017-09-09 The node of column and beam and its construction method of the anti-buckling energy-consumption component of replacement easy to install Expired - Fee Related CN107401219B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710810371.XA CN107401219B (en) 2017-09-09 2017-09-09 The node of column and beam and its construction method of the anti-buckling energy-consumption component of replacement easy to install

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710810371.XA CN107401219B (en) 2017-09-09 2017-09-09 The node of column and beam and its construction method of the anti-buckling energy-consumption component of replacement easy to install

Publications (2)

Publication Number Publication Date
CN107401219A CN107401219A (en) 2017-11-28
CN107401219B true CN107401219B (en) 2019-06-14

Family

ID=60397018

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710810371.XA Expired - Fee Related CN107401219B (en) 2017-09-09 2017-09-09 The node of column and beam and its construction method of the anti-buckling energy-consumption component of replacement easy to install

Country Status (1)

Country Link
CN (1) CN107401219B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108035607B (en) * 2017-12-25 2023-07-07 杭州市电力设计院有限公司 Buckling-restrained replacement device and method for rush repair, replacement and maintenance of steel truss tower
CN108560706A (en) * 2018-06-20 2018-09-21 中国矿业大学 A kind of friction energy-dissipating Self-resetting fully assembled joint
CN108868008B (en) * 2018-08-19 2024-06-18 中国矿业大学 Ductile steel bar connecting device with replaceable threaded sleeve and installation and replacement method
CN111335146B (en) * 2020-03-10 2021-05-18 青岛理工大学 Frame type replaceable buckling-restrained damping energy dissipation device and using method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012207389A (en) * 2011-03-29 2012-10-25 Fujita Corp Seismic strengthening construction method for existing building
CN104088375A (en) * 2014-06-19 2014-10-08 北京工业大学 Buckling restriction steel bar structure
CN104878948A (en) * 2015-04-07 2015-09-02 淮海工学院 Reinforced concrete frame beam hogging moment region reinforcing method and reinforcing device
CN105780960A (en) * 2016-04-27 2016-07-20 福建工程学院 Fully-prefabricated assembled concrete column-concrete beam buckling-restrained energy-consuming joint
CN106499247A (en) * 2016-10-21 2017-03-15 东南大学 The replaceable power consumption coupling assembly of assembling frame beam-to-column joint
CN106759879A (en) * 2016-12-12 2017-05-31 福州大学 Precast prestressed concrete frame is from rehabilitation energy dissipation node and its construction method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012207389A (en) * 2011-03-29 2012-10-25 Fujita Corp Seismic strengthening construction method for existing building
CN104088375A (en) * 2014-06-19 2014-10-08 北京工业大学 Buckling restriction steel bar structure
CN104878948A (en) * 2015-04-07 2015-09-02 淮海工学院 Reinforced concrete frame beam hogging moment region reinforcing method and reinforcing device
CN105780960A (en) * 2016-04-27 2016-07-20 福建工程学院 Fully-prefabricated assembled concrete column-concrete beam buckling-restrained energy-consuming joint
CN106499247A (en) * 2016-10-21 2017-03-15 东南大学 The replaceable power consumption coupling assembly of assembling frame beam-to-column joint
CN106759879A (en) * 2016-12-12 2017-05-31 福州大学 Precast prestressed concrete frame is from rehabilitation energy dissipation node and its construction method

Also Published As

Publication number Publication date
CN107401219A (en) 2017-11-28

Similar Documents

Publication Publication Date Title
CN107401219B (en) The node of column and beam and its construction method of the anti-buckling energy-consumption component of replacement easy to install
CN104847052B (en) A kind of damaged replaceable composite column structure
CN107313540B (en) Fireproof and buckling-restrained fabricated composite beam and construction method
CN102852244B (en) Detachable self-resetting type energy-dissipation coupling beam
US20120180423A1 (en) Yielding Rod to Counter Seismic Activity
EP3234277A1 (en) Method for producing prestressed structures and structural parts by means of sma tension elements, and structure and structural part equipped therewith
CN103669570A (en) Special-shaped steel column-prestress central supporting frame easy to restore after earthquake
Takamatsu et al. Non-slip-type restoring force characteristics of an exposed-type column base
CN203284969U (en) Bamboo-plastic composite pipe-restrained section steel high-strength concrete structure
CN208633269U (en) A kind of detachable assembling type column and basic ductility joint connection type
CN208363267U (en) A kind of full assembled Self-resetting Column Joint of unilateral prestressing force
CN110700082A (en) Column base node of SMA-ECC self-resetting circular steel tube restrained reinforced concrete pier
CN204753830U (en) Multilayer assembled concrete panel connecting piece
Zeynalian et al. Structural performance of cold-formed steel trusses used in electric power substations
Kim et al. Design limits for RC slabs strengthened with hybrid FRP–HPC retrofit system
CN110924566A (en) Steel frame infilled CLT plate constraint steel plate shear wall combined structure
CN203905298U (en) Superimposed component of reinforced concrete filled FRP pipe and concrete filled steel pipe
CN110670937A (en) Interval reinforcing device and method for service power transmission tower
CN104294963A (en) Novel precast concrete shearing wall plate with bottom provided with holes with energy consumption devices
CN204212285U (en) A kind of novel bottom punches and is with the precast concrete shear wall plate of energy-dissipating device
CN107605064A (en) A kind of anti-buckling support coupling beam of assembled X-shaped
CN205577153U (en) Installation node of wallboard connecting piece and wallboard
CN204326301U (en) A kind of bottom punches containing the fabricated assembly overall concrete shear wallboard of many coupling beams
CN110616855A (en) Steel bar mechanical connection structure and connection method for prefabricated concrete structure
CN202831237U (en) Shaft flange joint structure for assembly-type cold rolled section steel structure connection

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20190409

Address after: 100086 room 1302, block B, casting tower, 6 South Avenue, Haidian District, Beijing, 6

Applicant after: BEIJING ZHITAO SCIENCE & TECHNOLOGY CO., LTD.

Address before: 234101 2 Tong Jie Road, Fu Li Town, Anhui City, Suzhou.

Applicant before: Wang Kun

TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20190509

Address after: 201414 Guangming Yangwang Village, Qingcun Town, Fengxian District, Shanghai

Applicant after: Wanpin Architectural Design (Shanghai) Co., Ltd.

Address before: 100086 room 1302, block B, casting tower, 6 South Avenue, Haidian District, Beijing, 6

Applicant before: BEIJING ZHITAO SCIENCE & TECHNOLOGY CO., LTD.

TA01 Transfer of patent application right
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190614

Termination date: 20200909

CF01 Termination of patent right due to non-payment of annual fee