CN107354946A - A kind of supporting construction of encorbelmenting for foundation pit steel support - Google Patents

A kind of supporting construction of encorbelmenting for foundation pit steel support Download PDF

Info

Publication number
CN107354946A
CN107354946A CN201710703106.1A CN201710703106A CN107354946A CN 107354946 A CN107354946 A CN 107354946A CN 201710703106 A CN201710703106 A CN 201710703106A CN 107354946 A CN107354946 A CN 107354946A
Authority
CN
China
Prior art keywords
coupling beam
steel
encorbelmenting
stand column
bracing members
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710703106.1A
Other languages
Chinese (zh)
Inventor
朱炎兵
赵星
罗会平
余玉琴
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Siyuan Survey and Design Group Co Ltd
Original Assignee
China Railway Siyuan Survey and Design Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Siyuan Survey and Design Group Co Ltd filed Critical China Railway Siyuan Survey and Design Group Co Ltd
Priority to CN201710703106.1A priority Critical patent/CN107354946A/en
Publication of CN107354946A publication Critical patent/CN107354946A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Foundations (AREA)

Abstract

The invention discloses a kind of supporting construction of encorbelmenting for foundation pit steel support, it includes:It is vertically arranged in foundation ditch and perpendicular to the stand column pile for the bracing members being respectively set up in parallel;The steel coupling beam being fixedly mounted through the stand column pile and its middle part with stand column pile, its both ends stretches out in the stand column pile and forms cantilever design, and the steel coupling beam be arranged at below each bracing members and with each bracing members traversed by, to be supported to each bracing members;And more drag-lines, one end of each drag-line is fixedly connected with the position being located in stand column pile above steel coupling beam, the other end is each individually fixed in the diverse location on two cantilever ends of steel coupling beam, and the support of encorbelmenting to steel coupling beam is realized in a manner of this is with steel coupling beam formation oblique pull suspension cable.Steel coupling beam and the lattice column in stand column pile are connected by the supporting construction of encorbelmenting of the present invention using multiple zips, and encorbelmenting for long length can be realized in the case where not increasing stand column pile, reliable and stable support is formed to more bracing members.

Description

A kind of supporting construction of encorbelmenting for foundation pit steel support
Technical field
The invention belongs to base pit engineering technical field, and in particular to a kind of supporting construction of encorbelmenting for foundation pit steel support.
Background technology
In Metro station excavation engineering, bracing members are often designed and needed as a kind of conventional supporting member, its stability The key factor of consideration.Generally, can be vertical by increasing in bracing members stability deficiency to ensure bracing members stability The vertical supporting system of stanchion and steel coupling beam composition meets bracing members stability requirement, that is, sets stand column pile and lattice column, will Firm coupling beam is erected on lattice column and with this cross-brace bracing members, keeps it stable.
Above-mentioned support scheme usually occurs that steel coupling beam is encorbelmented the situations of bracing members, i.e. lattice column two in design and construction The steel coupling beam at end forms cantilever design, and bracing members are arranged on the cantilever of the steel coupling beam.By steel coupling beam inherently safe and stably The requirement of property, steel coupling beam cantilever span be not easy it is long, typically no more than 2m, and the single bracing members that can only encorbelment.To overcome Drawbacks described above, common solution method are in one end increase stand column pile of encorbelmenting, and reduce cantilever span, still, this increase column On the one hand the scheme of stake adds engineering cost and construction period, on the other hand, excessive stand column pile is unfavorable for base in foundation ditch The excavation operation in hole, and there is also problem for the assembly connection between excessive stand column pile or lattice column and steel coupling beam.Therefore, have Necessity proposes a kind of supporting construction of encorbelmenting suitable for foundation pit steel support, the defects of to overcome existing supporting construction to bring.
The content of the invention
For the disadvantages described above or Improvement requirement of prior art, the invention provides a kind of encorbelmenting for foundation pit steel support Supporting construction, it is improved and optimizated by structure, and steel coupling beam and the lattice column in stand column pile are connected using multiple zips, The structure type of similar suspension bridge is formed, so as to realize encorbelmenting for long length in the case where not increasing stand column pile, to more More bracing members form reliable and stable support, avoid traditional foundation ditch that the stability hidden danger of support and excessive stand column pile are brought of encorbelmenting Construction trouble and assembly connection problem.
To achieve the above object, according to one aspect of the present invention, there is provided a kind of support of encorbelmenting for foundation pit steel support Structure, it is characterised in that including:
It is vertically arranged in foundation ditch and perpendicular to the stand column pile for the bracing members being respectively set up in parallel;
Steel coupling beam, it is fixedly mounted through the stand column pile and its middle part with stand column pile, and its both ends stretches out in the column Stake simultaneously forms cantilever design, and the steel coupling beam be arranged at below each bracing members and with each bracing members traversed by, to each bracing members It is supported;And
Drag-line, it is more, and one end of each drag-line is fixedly connected with the position being located in stand column pile above steel coupling beam, separately One end is each individually fixed in the diverse location on two cantilever ends of steel coupling beam, real in a manner of this is with steel coupling beam formation oblique pull suspension cable Now to the support of encorbelmenting of steel coupling beam.
As a further improvement on the present invention, more than two bracing members are supported by each cantilever end of steel coupling beam.
As a further improvement on the present invention, it is provided with drawing between any two bracing members on each cantilever end of steel coupling beam Rope.
As a further improvement on the present invention, the drag-line is steel strand wires.
As a further improvement on the present invention, the drag-line is connected by fixed angle steel with steel coupling beam.
As a further improvement on the present invention, the drag-line is connected by fixed angle steel with stand column pile.
As a further improvement on the present invention, the stand column pile upper end is provided with lattice column, the steel coupling beam and the lattice Structure post is fixedly mounted.
As a further improvement on the present invention, shown steel coupling beam is vertically arranged with each bracing members.
In general, by the contemplated above technical scheme of the present invention compared with prior art, have below beneficial to effect Fruit:
(1) supporting construction of encorbelmenting of the invention, it leads to its cantilever end by setting drag-line to the both ends cantilever of steel coupling beam Cross drag-line and stand column pile fixed strain, use for reference the principle of cable-stayed bridge stress, vertical load load being converted into stand column pile, most The bearing capacity for the performance stand column pile changed greatly, not only considerably increases the cantilever span of steel coupling beam, while it is more with steel branch to encorbelment Support;
(2) supporting construction of encorbelmenting of the invention, solves the problems, such as that steel coupling beam cantilever span is small, optimizes the cloth of stand column pile Put, the principle for using for reference cable-stayed bridge has played the vertical bearing capacity of stand column pile to greatest extent, and reliable in quality, construction is convenient, peace It is complete economical, there are all engineerings of stand column pile support bracing members suitable for foundation ditch.
Brief description of the drawings
Fig. 1 is the overlooking the structure diagram of the supporting construction of encorbelmenting of one embodiment of the invention;
Fig. 2 is diagrammatic cross-section of the supporting construction along A-A directions of encorbelmenting in Fig. 1;
In all of the figs, same reference represents identical technical characteristic, is specially:1- stand column pile, 2- lattices Post, 3- steel coupling beams, 4- bracing members, 5- drag-lines, 6- fix angle steel.
Embodiment
In order to make the purpose , technical scheme and advantage of the present invention be clearer, it is right below in conjunction with drawings and Examples The present invention is further elaborated.It should be appreciated that the specific embodiments described herein are merely illustrative of the present invention, and It is not used in the restriction present invention.
In addition, as long as technical characteristic involved in each embodiment of invention described below is each other not Conflict can is formed to be mutually combined.
Fig. 1 is the overlooking the structure diagram of the supporting construction of encorbelmenting of one embodiment of the invention;Fig. 2 is encorbelmenting in Fig. 1 Diagrammatic cross-section of the supporting construction along A-A directions, wherein 1- stand column pile, 2- lattice columns, 3- steel coupling beams, 4- bracing members, 5- drag-lines, 6- fixes angle steel.
As illustrated in fig. 1 and 2, the supporting construction of encorbelmenting for foundation pit steel support of the embodiment of the present invention, it includes stand column pile 1st, steel coupling beam 3 and drag-line 5.Wherein, stand column pile 1 is vertically arranged in foundation ditch, and perpendicular to being disposed in parallel on foundation ditch absolute altitude face Each bracing members 4.
In a preferred embodiment, the top of stand column pile 1 sets lattice column 2, and it is similarly vertical direction arrangement, with this from base Cheat it is protruding under on bracing members 4, for the pillar as steel coupling beam 3.
As illustrated in fig. 1 and 2, steel coupling beam 3 passes through lattice column 2, and middle part and the lattice column 2 of lattice column 2 are fixedly mounted, steel coupling beam 3 both ends stretch out in lattice column 2 and form cantilever design (or being cantilevered structure).The steel coupling beam 3 is in strip, positioned at each steel branch The lower section of support 4, and its upper surface contacts with each bottom surface of bracing members 4 and intersected, and is preferably mutually perpendicular to, to enter to each bracing members 4 Row support.
As illustrated in fig. 1 and 2, more than two bracing members are supported by each cantilever end of steel coupling beam 3, i.e., each cantilever end On have at least two bracing members being set up in parallel, such as two, three, four, or more.
For preferably stable support, the supporting construction in this programme also includes more drag-lines 5, and drag-line is preferably steel strand Line, naturally it is also possible to be the various ropes or other elements for meeting corresponding tensile strength.One end of each drag-line 5 is consolidated with lattice column Fixed, fixing point is located at the top of steel coupling beam 3, pulling force, drag-line quantity and the cantilever design that its specific height is born according to drag-line Bracing members quantity supported etc. is calculated.
The other end of drag-line 5 is fixedly connected with the cantilever end of steel coupling beam 3, in this way by steel coupling beam 3 and drag-line 5 and column The similar stayed bridge structure of the composition of stake 1, so as to effectively supporting steel coupling beam, the stress of transmission steel coupling beam 3, so as to effectively Support more bracing members 4.
In a preferred embodiment, the quantity of drag-line 5 is even number root, at least two, or four, the six roots of sensation, eight Root or more even number root, particular number determine according to factors such as the length of cantilever end, bracing members quantity.More preferably, both ends The quantity of drag-line 5 is identical and is symmetrical arranged.
In preferred embodiment, the position between any two bracing members 4 on each cantilever end of steel coupling beam 3 is all connected with There is drag-line 5.In a more preferred embodiment, the outside of the outermost bracing members 4 of each cantilever end is also connected with drag-line 5.
The supporting construction of encorbelmenting of this programme, by setting stayed structure, the cantilever span of steel coupling beam can be increased, use for reference oblique pull The principle of bridge stress, vertical load load being converted into stand column pile, the maximized bearing capacity for playing stand column pile, not only The cantilever span of steel coupling beam is considerably increased, while it is more with bracing members to encorbelment, solve that conventional solution method is a series of to ask Topic.
In a preferred embodiment, drag-line 5 is connected with lattice column 2 and steel coupling beam 3 respectively by fixed angle steel 6, certainly Fixation can also be attached using other connectors.
As it will be easily appreciated by one skilled in the art that the foregoing is merely illustrative of the preferred embodiments of the present invention, not to The limitation present invention, all any modification, equivalent and improvement made within the spirit and principles of the invention etc., all should be included Within protection scope of the present invention.

Claims (8)

  1. A kind of 1. supporting construction of encorbelmenting for foundation pit steel support, it is characterised in that including:
    It is vertically arranged in foundation ditch and perpendicular to the stand column pile for the bracing members being respectively set up in parallel;
    Steel coupling beam, it is fixedly mounted through the stand column pile and its middle part with stand column pile, and its both ends stretches out in the stand column pile simultaneously Form cantilever design, and the steel coupling beam be arranged at below each bracing members and with each bracing members traversed by, to be carried out to each bracing members Support;And
    Drag-line, it is more, and one end of each drag-line is fixedly connected with the position being located in stand column pile above steel coupling beam, the other end Diverse location on two cantilever ends of steel coupling beam is each individually fixed in, is realized in a manner of this forms oblique pull suspension cable with steel coupling beam pair The support of encorbelmenting of steel coupling beam.
  2. 2. the supporting construction of encorbelmenting according to claim 1 for foundation pit steel support, wherein, each cantilever of steel coupling beam More than two bracing members are supported by end.
  3. 3. the supporting construction of encorbelmenting according to claim 1 or 2 for foundation pit steel support, wherein, each of steel coupling beam is hanged On arm end drag-line is provided between any two bracing members.
  4. 4. the supporting construction of encorbelmenting according to any one of claim 1 to 3 for foundation pit steel support, wherein, the drawing Rope is steel strand wires.
  5. 5. the supporting construction of encorbelmenting according to any one of claim 1 to 4 for foundation pit steel support, wherein, the drawing Rope is connected by fixed angle steel with steel coupling beam.
  6. 6. the supporting construction of encorbelmenting according to any one of claim 1 to 5 for foundation pit steel support, wherein, the drawing Rope is connected by fixed angle steel with stand column pile.
  7. 7. the supporting construction of encorbelmenting according to any one of claim 1 to 6 for foundation pit steel support, wherein, it is described vertical Stanchion upper end is provided with lattice column, and the steel coupling beam is fixedly mounted with the lattice column.
  8. 8. the supporting construction of encorbelmenting according to any one of claim 1 to 7 for foundation pit steel support, wherein, shown steel Coupling beam is vertically arranged with each bracing members.
CN201710703106.1A 2017-08-16 2017-08-16 A kind of supporting construction of encorbelmenting for foundation pit steel support Pending CN107354946A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710703106.1A CN107354946A (en) 2017-08-16 2017-08-16 A kind of supporting construction of encorbelmenting for foundation pit steel support

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710703106.1A CN107354946A (en) 2017-08-16 2017-08-16 A kind of supporting construction of encorbelmenting for foundation pit steel support

Publications (1)

Publication Number Publication Date
CN107354946A true CN107354946A (en) 2017-11-17

Family

ID=60287596

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710703106.1A Pending CN107354946A (en) 2017-08-16 2017-08-16 A kind of supporting construction of encorbelmenting for foundation pit steel support

Country Status (1)

Country Link
CN (1) CN107354946A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108316315A (en) * 2018-03-29 2018-07-24 中铁第四勘察设计院集团有限公司 It is a kind of to exempt to set up the vertical stability structure of stanchion suitable for foundation pit
CN109024611A (en) * 2018-08-16 2018-12-18 中船勘察设计研究院有限公司 Across support of tunnel large span stand column device
CN111691546A (en) * 2020-04-30 2020-09-22 海南大学 Anti-seismic cantilever structure
CN111764406A (en) * 2020-08-19 2020-10-13 中国五冶集团有限公司 Adjustable inhaul cable
CN112575789A (en) * 2020-11-30 2021-03-30 广西大学 Diagonal space truss foundation pit inner support system
CN114544872A (en) * 2022-02-11 2022-05-27 清华大学 Be used for open-air simulation of forest to heat device

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103291116A (en) * 2013-05-20 2013-09-11 中国十五冶金建设集团有限公司 Grid-type formwork supporting and operating platform for construction of water tank on top of inverted-cone water tower
CN103321410A (en) * 2013-06-26 2013-09-25 青岛建安建设集团有限公司 Overhang diagonal form at exposed corner and method for erecting form
CN203403422U (en) * 2013-06-06 2014-01-22 广西建工集团第五建筑工程有限责任公司 Long-span reinforced concrete inner support structure of rectangular deep foundation pit
CN103967018A (en) * 2014-05-09 2014-08-06 深圳市工勘岩土集团有限公司 Deep and large foundation pit angle supporting horizontal shearing resistance structure
CN204040436U (en) * 2014-08-07 2014-12-24 龙元建设集团股份有限公司 For the self-balancing steel builder's jack of overlength cantilevered structure framed bent construction
US20150052694A1 (en) * 2012-06-01 2015-02-26 Ihi Infrastructure Systems Co., Ltd. Method for replacing sloped cables, and temporary hanger for replacing sloped cables
CN104389419A (en) * 2014-11-18 2015-03-04 杭州江润科技有限公司 Cantilevered formwork platform installation structure and construction method
CN205347899U (en) * 2016-02-23 2016-06-29 四川中德空铁科技有限公司 Monorail train pillar construction
CN105862878A (en) * 2016-05-30 2016-08-17 建研地基基础工程有限责任公司 Supporting system for deep foundation pit
CN207176694U (en) * 2017-08-16 2018-04-03 中铁第四勘察设计院集团有限公司 A kind of supporting construction of encorbelmenting for foundation pit steel support

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20150052694A1 (en) * 2012-06-01 2015-02-26 Ihi Infrastructure Systems Co., Ltd. Method for replacing sloped cables, and temporary hanger for replacing sloped cables
CN103291116A (en) * 2013-05-20 2013-09-11 中国十五冶金建设集团有限公司 Grid-type formwork supporting and operating platform for construction of water tank on top of inverted-cone water tower
CN203403422U (en) * 2013-06-06 2014-01-22 广西建工集团第五建筑工程有限责任公司 Long-span reinforced concrete inner support structure of rectangular deep foundation pit
CN103321410A (en) * 2013-06-26 2013-09-25 青岛建安建设集团有限公司 Overhang diagonal form at exposed corner and method for erecting form
CN103967018A (en) * 2014-05-09 2014-08-06 深圳市工勘岩土集团有限公司 Deep and large foundation pit angle supporting horizontal shearing resistance structure
CN204040436U (en) * 2014-08-07 2014-12-24 龙元建设集团股份有限公司 For the self-balancing steel builder's jack of overlength cantilevered structure framed bent construction
CN104389419A (en) * 2014-11-18 2015-03-04 杭州江润科技有限公司 Cantilevered formwork platform installation structure and construction method
CN205347899U (en) * 2016-02-23 2016-06-29 四川中德空铁科技有限公司 Monorail train pillar construction
CN105862878A (en) * 2016-05-30 2016-08-17 建研地基基础工程有限责任公司 Supporting system for deep foundation pit
CN207176694U (en) * 2017-08-16 2018-04-03 中铁第四勘察设计院集团有限公司 A kind of supporting construction of encorbelmenting for foundation pit steel support

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108316315A (en) * 2018-03-29 2018-07-24 中铁第四勘察设计院集团有限公司 It is a kind of to exempt to set up the vertical stability structure of stanchion suitable for foundation pit
CN109024611A (en) * 2018-08-16 2018-12-18 中船勘察设计研究院有限公司 Across support of tunnel large span stand column device
CN111691546A (en) * 2020-04-30 2020-09-22 海南大学 Anti-seismic cantilever structure
CN111764406A (en) * 2020-08-19 2020-10-13 中国五冶集团有限公司 Adjustable inhaul cable
CN112575789A (en) * 2020-11-30 2021-03-30 广西大学 Diagonal space truss foundation pit inner support system
CN114544872A (en) * 2022-02-11 2022-05-27 清华大学 Be used for open-air simulation of forest to heat device
CN114544872B (en) * 2022-02-11 2023-03-10 清华大学 Be used for open-air simulation of forest to heat device

Similar Documents

Publication Publication Date Title
CN107354946A (en) A kind of supporting construction of encorbelmenting for foundation pit steel support
CN204662661U (en) The two rope truss string structure system of the two case beam of large span
CN106498837B (en) A kind of bridge and its construction method
CN105256813A (en) Lenticular balance beam section steel supporting system
CN105463979B (en) Space trident beam string foot bridge
US6343445B1 (en) Tower structure
CN207176694U (en) A kind of supporting construction of encorbelmenting for foundation pit steel support
CN212460966U (en) Detachable bridge model for teaching
CN213572385U (en) Umbrella-shaped building structure
US5134821A (en) Trussed structure
CN214245436U (en) High stability sound barrier steel stand
CN101368366A (en) Cantilever beam external anchor stayed-cable bridge
CN212082851U (en) Vertical static load test structure of bridge floor crane
CN210374121U (en) Self-balancing flexible photovoltaic panel support
US5070566A (en) Hybrid bridge structure
CN208235714U (en) A kind of assembled light steel construction structure
CN216699321U (en) Transformer substation framework adopting cantilever beam structure
CN103174087B (en) A kind of suspension cable-oblique pull co-operative system comprising inclination hoist cable and variable cross-section main push-towing rope
CN206233085U (en) A kind of secondary suspension rod combined type long-span bridge structure of suspension cable oblique pull
CN219181101U (en) Bridge cantilever type cable frame structure
CN206655486U (en) A kind of elongated steel column temporary fixing structure
CN219316153U (en) Light steel greenhouse with self-anchored suspension cable structure
CN111719756A (en) Stay cable fairway of cable dome structure
CN219643446U (en) Crossing rack
CN215107235U (en) High-altitude cantilever structure formwork support platform

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20171117