CN107269013A - A kind of across active service highway continuous beam protection booth structure and its construction method - Google Patents

A kind of across active service highway continuous beam protection booth structure and its construction method Download PDF

Info

Publication number
CN107269013A
CN107269013A CN201710552095.1A CN201710552095A CN107269013A CN 107269013 A CN107269013 A CN 107269013A CN 201710552095 A CN201710552095 A CN 201710552095A CN 107269013 A CN107269013 A CN 107269013A
Authority
CN
China
Prior art keywords
column
steel
distribution beam
lifting
bolt
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201710552095.1A
Other languages
Chinese (zh)
Inventor
王新泉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hangzhou Jiangrun Technology Co Ltd
Original Assignee
Hangzhou Jiangrun Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hangzhou Jiangrun Technology Co Ltd filed Critical Hangzhou Jiangrun Technology Co Ltd
Priority to CN201710552095.1A priority Critical patent/CN107269013A/en
Publication of CN107269013A publication Critical patent/CN107269013A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/32Safety or protective measures for persons during the construction of buildings
    • E04G21/3204Safety or protective measures for persons during the construction of buildings against falling down
    • E04G21/3209Temporary tunnels specially adapted against falling objects

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses across the active service highway continuous beam protection booth structure of one kind and its construction method, including strip footing, the column being fixedly installed in strip footing and ride upon transverse distribution beam on column, the transverse distribution beam is provided with one group of longitudinal distribution beam, longitudinal distribution beam is provided with splash guard, steel-pipe pile is fixedly installed on the ground of the side position of transverse distribution beam two, the steel-pipe pile is provided with cable wind rope, described cable wind rope one end is fixedly connected with steel-pipe pile, is fixedly connected at the top of other end column corresponding with transverse distribution beam both sides.The characteristics of present invention has following and beneficial effect:The problem of difficulty of construction is big is solved using the method for basis, crossbeam, longeron top layer integral hoisting splicing, auxiliary equipment is set up and solves the problem of safety coefficient requires high, with preferable technical economic benefit;Crossbeam removes the method using traction lifting, reduces dismounting difficulty.

Description

A kind of across active service highway continuous beam protection booth structure and its construction method
Technical field
The present invention relates to subgrade engineering technical field, and in particular to a kind of across active service highway continuous beam protection booth structure and its Construction method.
Background technology
In current construction of the highway, prestressed concrete continuous box girder technology is based on that its Mechanical Builds is attractive in appearance, easy construction And be widely applied in construction of the highway.In order to avoid the construction high and medium pendant thing influence of highway prestress box beam is both wired Normal operation, prevents accident, during both wired main structure constructions, sets up safe guarding shed put up in order to avoid thing Therefore occur one of maximally effective measure, it is widely used in road construction construction.
The Box Beam Bridge built in recent years is extremely more, and the safety prevention measure in work progress is of crucial importance, protection Frame is as a kind of safety prevention measure, and difficulty of construction is big, and safety coefficient requires high.The protecting canopy frame of across active service highway continuous beam Waterproof, anti-electric, fire prevention, anti-falling from high altitude thing are not required nothing more than, resistance typhoon is also needed and lightning-arrest, and the country is available for using for reference what is referred to Construction experience is few.
In consideration of it, big in order to solve protection canopy difficulty of construction, it is desirable to the problems such as high, it would be highly desirable to invention it is a kind of it is simple and effective across Active service highway continuous beam protects booth structure.Construction hardly possible is solved using the method for basis, crossbeam, longeron top layer integral hoisting splicing The problem of spending big, sets up auxiliary equipment and solves the problem of safety coefficient requires high, with preferable technical economic benefit.
The content of the invention
For problems of the prior art, the invention provides easy and effective and with preferable technical economic benefit One kind across active service highway continuous beam protection booth structure and its construction method.
Technical scheme is as follows:
A kind of across active service highway continuous beam protection booth structure, it is characterised in that including strip footing, be fixedly installed on strip footing On column and ride upon transverse distribution beam on column, the transverse distribution beam is described vertical provided with one group of longitudinal distribution beam It is provided with to distribution beam on splash guard, the ground of the side position of transverse distribution beam two and steel-pipe pile, the steel-pipe pile is fixedly installed Cable wind rope is provided with, described cable wind rope one end is fixedly connected with steel-pipe pile, other end column corresponding with transverse distribution beam both sides Top be fixedly connected.
Across the active service highway continuous beam protection booth structure of described one kind, it is characterised in that the side of the strip footing is set There is steel pipe preformed hole, strip footing, which is set up in parallel between two groups, and the corresponding strip footing in two groups of positions, passes through steel pipe and steel The cooperation of pipe preformed hole is fixed;The top end positions of the strip footing are provided with lifting preformed hole.
Across the active service highway continuous beam protection booth structure of described one kind, it is characterised in that in the top of the strip footing Meta has installed and pre-embedded bolt is provided with reserved hole, the reserved hole, and the pre-embedded bolt is provided with fixation steel plate, the column Terminal pad is provided with, column is fixed with strip footing by pre-embedded bolt for the terminal pad.
Across the active service highway continuous beam protection booth structure of described one kind, it is characterised in that the longitudinal distribution beam and waterproof Damping plank is provided between plate, the splash guard is provided with one group of strap bolt pulley, the splash guard and slided positioned at strap bolt It is provided with two side positions of wheel on bolt, the transverse distribution beam and is being provided with band silk braid cylinder with bolt corresponding position, it is described vertical Overall structure is fixedly connected as with the cooperation with silk braid cylinder by bolt to distribution beam, damping plank and splash guard.
A kind of described across active service highway continuous beam protects the construction method of booth structure, it is characterised in that including following step Suddenly:
1)Lift strip footing:Strip footing uses prefabricated in advance, and wooden handcart is transported to behind job site and lifted;
2)Hoisting upright column:Before lifting fixation steel plate is put in the reserved hole of strip footing in advance;It is hung to by column in strip footing Column, is fixedly connected by side by terminal pad with strip footing using pre-embedded bolt;
3)Construction of beam:Two transverse distribution beams are placed at the top of column side by side;Transverse distribution beam and steel plate at the top of column is two-sided Welding;
4)Longeron top layer integral slipping is lifted:Longitudinal distribution beam is molded by prior spreading is designed;By damping plank and splash guard it Between with iron wire bundle connect, be connected integral using Rebar rod type between longitudinal distribution beam;Band is filled on splash guard Bolt pulley, and the prepared screw-bolt hole on the splash guard of the side position of strap bolt pulley two;Carry out integral slip type lifting, sliding After the completion of put down strap bolt pulley, will be bolted to band silk braid cylinder on;
5)Affiliated facility is constructed:Twice cable wind rope is respectively set in protection canopy frame both sides, cable wind rope one end is fixed at the top of column, separately One end is fixed on ground with steel-pipe pile, and ensures cable wind rope by tension uniform;The steel pipe two ends of strip footing will be connected simultaneously Connect ground connection facility;
6)The lifting of longeron top layer integral slipping is removed:Bolt is unclamped, longitudinal distribution beam, damping plank and splash guard are integrally used Two cranes coordinate unloading, integrally hang to ground, then removed;
7)Crossbeam traction lifting is removed:Will be on box beam flange plate with the reserved lifting hole of pvc pipe, bottom in constructing continuous beam Suspender belt hole is opened up on plate;Steel wire rope is worn at reserved lifting hole and suspender belt hole, and coordinates crane to be lifted with hoist engine Dismounting;
8)Column is removed:The terminal pad on column is first unclamped, recycles ground crane to be removed;
9)Strip footing is removed:Strip footing is removed by reserving hole for hoist using ground crane.
A kind of described across active service highway continuous beam protects the construction method of booth structure, it is characterised in that the step 2) Neutral column length is adjusted accordingly according to road gradient.
A kind of described across active service highway continuous beam protects the construction method of booth structure, it is characterised in that the steel-pipe pile Embedded depth is 7-9m.
A kind of described across active service highway continuous beam protects the construction method of booth structure, it is characterised in that the step 7) Middle cross beam traction lifting is removed by the way of crane is drawn plus is lifted, and is comprised the following steps that:First pacify in box beam, at the top of box beam Fill four 2T hoist engines, 4# suspension centres and corresponding hoist engine installed into steel wire rope, outside crane also installs steel wire rope, slowly to Outer side-lining;When slowly drawing 4# suspension centres and can not be displaced outwardly again, change 3# suspension centres and install steel wire rope and lifted, 4# is hung Point is untied, and crane continues slow outwards traction;When crossbeam 3# suspension centres are moved to below 2# suspension centres, 2# suspension centre steel wire ropes are changed, 3# suspension centres are taken off simultaneously, and crane continues outside traction;Send crossbeam to 1# suspension centres region when 2# suspension centres continue outwards to hang, change 1# and hang Point steel wire rope, while untiing 2# suspension centres, crane continues slowly to draw outside line;After 1# suspension centres are ajusted, pause traction, then with one 25T cranes are uniformly tied up with steel wire rope on transverse distribution beam suspension centre, start lifting, while taking off 1# suspension centre steel wire ropes;Will lifting Transverse distribution beam be transported to the material storing place of planning.
A kind of described across active service highway continuous beam protects the construction method of booth structure, it is characterised in that the step 9) Fixation steel plate is first removed before middle strip footing lifting.
The characteristics of present invention has following and beneficial effect:
(1)The problem of difficulty of construction is big is solved using the method for basis, crossbeam, longeron top layer integral hoisting splicing, sets up auxiliary Facility is helped to solve the problem of safety coefficient requires high, with preferable technical economic benefit.
(2)Crossbeam removes the method using traction lifting, reduces dismounting difficulty.
Brief description of the drawings
Fig. 1 is plan-view structure schematic diagram of the present invention;
Fig. 2 is strip footing of the present invention and column connection diagram;
Fig. 3 is longeron top layer overall structure diagram of the present invention;
Fig. 4 is that box beam of the present invention reserves hole pattern;
Fig. 5 is the schematic diagram of transverse distribution beam dismantling step one of the present invention;
Fig. 6 is the schematic diagram of transverse distribution beam dismantling step two of the present invention;
Fig. 7 is the schematic diagram of transverse distribution beam dismantling step three of the present invention;
Fig. 8 is the schematic diagram of transverse distribution beam dismantling step four of the present invention;
Fig. 9 is the schematic diagram of transverse distribution beam dismantling step five of the present invention;
In figure:1- strip footings, 2- columns, 3- transverse distribution beams, 4- longitudinal directions distribution beam, 5- damping planks, 6- splash guards, 7- cables Wind rope, 8- steel-pipe piles, 9- steel pipe preformed holes, 10- lifting preformed holes, 11- steel plates, 12- terminal pads, 13- pre-embedded bolts, 14- bands Bolt pulley, 15- fixing bolts, 16- band silk braid cylinders, the reserved lifting holes of 17-, 18- suspender belts hole.
Embodiment
Below in conjunction with Figure of description, the invention will be further described, the construction technical requirement of protection canopy, and the present invention is not Tire out again and state, emphasis illustrates structure of the present invention and construction method.
As shown in figs 1-9, a kind of across active service highway continuous beam protection booth structure and its construction method, including strip footing 1, Column 2, transverse distribution beam 3, longitudinal distribution beam 4, damping plank 5, splash guard 6, cable wind rope 7, steel-pipe pile 8, steel pipe preformed hole 9, Lift preformed hole 10, it is steel plate 11, terminal pad 12, pre-embedded bolt 13, strap bolt pulley 14, fixing bolt 15, band silk braid cylinder 16, pre- Stay lifting hole 17 and suspender belt hole 18.
Strip footing 1 is provided with layer of ground soil, strip footing 1 is designed and sized to 2*1*1m, and strip footing 1 is provided with steel pipe Preformed hole 9, lifting preformed hole 10 and pre-embedded bolt 13, i.e. M36 bolts, 2 A10 lifting preformed holes 10 and two A16 steel Pipe preformed hole 9, column 2 is provided with terminal pad 12, and column 2 is steel pipe post, and size is 512 × 10mm of Φ, fixation steel plate 11 Between terminal pad 12 and strip footing 1, by M36 bolt connections, transverse distribution beam 3 is located on column 2, transverse distribution beam 3 use I40a types, and gap length is 100 ㎝, and every section of weld length is 10 ㎝, and adjacent two sections using the connection of equal strength connecting plate; Longitudinal distribution beam 4, damping plank 5 and splash guard 6 are made as same entirety in advance, facilitate installing/dismounting and it is lifted, reduction The difficulty of construction.Longitudinal distribution beam 4 uses I40b types, lateral arrangement, spacing 2m, between every piece of damping plank 5 and splash guard 6 Bundled and connected with iron wire, connect integral, and be connected integral using Rebar rod type between longitudinal distribution beam 4, band spiral shell Bolt pulley 14 be fixed on it is above-mentioned on the whole, bolt 15 connects the band silk braid cylinder 16 on above-mentioned entirety and transverse distribution beam 3, uses Strap bolt pulley 14 can make longitudinal distribution beam 4, damping plank 5 and the prefabricated entirety of splash guard 6 enter line slip installation, reduce peace The difficulty of dress, improves the efficiency of installation;Cable wind rope 7 is connected with the steel-pipe pile 8 on the top of column 2 and ground, the φ of steel-pipe pile 8 325m steel pipes, the embedded depth 8m of steel-pipe pile 8, it is ensured that the stability of column 2, and can be to playing lightning-arrest effect.
Construction procedure is as follows:
Such as Fig. 4:The reserved lower position of lifting hole 17 on the left of box beam flange plate is on the right side of 1# suspension centres, box beam flange plate Reserved lifting hole 17 lower position is 4# suspension centres, is 2# suspension centres, bottom plate positioned at the lower position of suspender belt hole 18 on the left of bottom plate The lower position of right side suspender belt hole 18 be for 3# suspension centres.
1)Lift strip footing 1:Strip footing 1 uses prefabricated in advance, and wooden handcart is transported to behind job site and lifted.
2)Hoisting upright column 2:Fixation steel plate 11 is put in advance in reserved hole before lifting in strip footing 1;Column 2 is being hung to bar Column 2, is fixedly connected by the top of shape basis 1 by terminal pad 12 with strip footing 1 using pre-embedded bolt 13;The length root of column 2 Adjust accordingly, be adapted with road surface according to road gradient.
3)Construction of beam:Two transverse distribution beams 3 are placed side by side in the top of column 2;By transverse distribution beam 3 and the top of column 2 Steel plate two-sided welding.
4)Longeron top layer integral slipping is lifted:Longitudinal distribution beam 4 is molded by prior spreading is designed;By damping plank 5 with preventing Bundled and connected with iron wire between water plate 6, be connected integral using Rebar rod type between longitudinal distribution beam 4;In waterproof Strap bolt pulley 14, and the prepared screw-bolt hole on the splash guard 6 of 14 liang of side positions of strap bolt pulley are filled on plate 6;Carry out overall Sliding lifting, puts down strap bolt pulley 14 after the completion of sliding, bolt 15 is fixed on band silk braid cylinder 16.
5)Affiliated facility is constructed:Protection canopy frame both sides respectively set twice cable wind rope 7, and the one end of cable wind rope 7 is fixed on column 2 and pushed up Portion, other end steel-pipe pile 8 is fixed on ground, and ensures cable wind rope 7 by tension uniform;Strip footing 1 will be connected simultaneously Two ends connect ground connection facility;The embedded depth of steel-pipe pile 8 is 7-9m.
6)The lifting of longeron top layer integral slipping is removed:Bolt 15 is unclamped, by longitudinal distribution beam 4, damping plank 5 and splash guard 6 is overall using two cranes cooperation unloadings, integrally hangs to ground, then removed.
7)Crossbeam traction lifting is removed:Will be on box beam flange plate with the reserved hole for hoist of pvc pipe in constructing continuous beam Suspender belt hole 18 is reserved on hole 17, bottom plate;By the way of crane is drawn plus is lifted, worn at lifting hole 17 and suspender belt hole 18 Steel wire rope, and coordinate 25T cranes to carry out lifting dismounting with 2T hoist engines;Comprise the following steps that, step one:First in box beam, case Four 2T hoist engines are installed in back portion, 4# suspension centres and corresponding hoist engine are installed into steel wire rope, outside crane also installs steel wire Rope, other suspension centres do not stress, slowly outside side-lining;Step 2:When slowly drawing 4# suspension centres and can not be displaced outwardly again, change 3# suspension centres install steel wire rope and lifted, and 4# suspension centres are untied, and 1#, 2# suspension centre do not stress still, and crane continues slow outwards traction; Step 3:When crossbeam 3# suspension centres are moved to below 2# suspension centres, 2# suspension centre steel wire ropes are changed, while taking off 3# suspension centres, 1# is still not Stress, crane continues outside traction;Step 4:Send crossbeam to 1# suspension centres region when 2# suspension centres continue outwards to hang, change 1# suspension centres Steel wire rope, while untiing 2# suspension centres, crane continues slowly to draw outside line;Step 5:After 1# suspension centres are ajusted, pause traction, then Uniformly tied up with steel wire rope on the suspension centre of transverse distribution beam 3 with a 25T crane, start lifting, while taking off 1# suspension centre steel wire ropes; The transverse distribution beam 3 of lifting is transported to the material storing place of planning.
8)Column 2 is removed:The terminal pad 12 on column 2 is first unclamped, recycles ground crane to be removed.
9)Strip footing 1 is removed:Strip footing 1 first removes fixation steel plate 11 before lifting;Strip footing 1 passes through reserved lifting Hole 10, is removed using ground crane.
Installation effectiveness is improved using longitudinal distribution beam 4, damping plank 5 and the prefabricated overall progress installation of splash guard 6, and greatly Big to lower the difficulty installed, transverse distribution beam 3 coordinates crane to carry out lifting dismounting using hoist engine, lowers transverse distribution beam 3 and tears open The difficulty unloaded, improves the efficiency of dismounting.

Claims (9)

1. a kind of across active service highway continuous beam protection booth structure, it is characterised in that including strip footing(1), be fixedly installed on bar Shape basis(1)On column(2)And ride upon column(2)On transverse distribution beam(3), the transverse distribution beam(3)It is provided with One group of longitudinal distribution beam(4), longitudinal distribution beam(4)It is provided with splash guard(6), the transverse distribution beam(3)Two side positions Ground on steel-pipe pile is fixedly installed(8), the steel-pipe pile(8)It is provided with cable wind rope(7), the cable wind rope(7)One end and steel Pile tube(8)It is fixedly connected, the other end and transverse distribution beam(3)The corresponding column in both sides(2)Top be fixedly connected.
2. across the active service highway continuous beam protection booth structure of one kind according to claim 1, it is characterised in that the bar shaped base Plinth(1)Side be provided with steel pipe preformed hole(9), strip footing(1)It is set up in parallel two groups, and the corresponding bar shaped base in two groups of positions Plinth(1)Between pass through steel pipe and steel pipe preformed hole(9)Cooperation be fixed;The strip footing(1)Top end positions Provided with lifting preformed hole(10).
3. across the active service highway continuous beam protection booth structure of one kind according to claim 1 or 2, it is characterised in that the bar Shape basis(1)Crown center position provided with reserved hole, provided with pre-embedded bolt in the reserved hole(13), the pre-embedded bolt (13)It is provided with fixation steel plate(11), the column(2)It is provided with terminal pad(12), the terminal pad(12)Pass through pre-embedded bolt (13)By column(2)With strip footing(1)It is fixed.
4. across the active service highway continuous beam protection booth structure of one kind according to claim 1, it is characterised in that the longitudinal direction point With beam(4)With splash guard(6)Between be provided with damping plank(5), the splash guard(6)Provided with one group of strap bolt pulley(14), The splash guard(6)On positioned at strap bolt pulley(14)Two side positions at be provided with bolt(15), the transverse distribution beam(3) On with bolt(15)Corresponding position is provided with band silk braid cylinder(16), longitudinal distribution beam(4), damping plank(5)And waterproof Plate(6)Pass through bolt(15)With band silk braid cylinder(16)Cooperation be fixedly connected as overall structure.
5. protecting the construction method of booth structure according to a kind of any described across the active service highway continuous beams of claim 1-4, it is special Levy and be, comprise the following steps:
1)Lift strip footing(1):Strip footing(1)Using prefabricated in advance, wooden handcart is transported to behind job site and lifted;
2)Hoisting upright column(2):In strip footing before lifting(1)Reserved hole in put fixation steel plate in advance(11);By column(2)Hang To strip footing(1)Top, passes through terminal pad(12)By column(2)With strip footing(1)Using pre-embedded bolt(13)It is fixed to connect Connect;
3)Construction of beam:Column(2)Two transverse distribution beams are placed side by side in top(3);By transverse distribution beam(3)With column(2) Top steel plate two-sided welding;
4)Longeron top layer integral slipping is lifted:Longitudinal distribution beam(4)It is molded by prior spreading is designed;By damping plank(5)With preventing Water plate(6)Between with iron wire bundle connect, with longitudinal distribution beam(4)Between using Rebar rod type connect it is integral; Splash guard(6)Upper dress strap bolt pulley(14), and in strap bolt pulley(14)The splash guard of two side positions(6)Upper reserved bolt Hole;Integral slip type lifting is carried out, strap bolt pulley is put down after the completion of sliding(14), by bolt(15)It is fixed on band silk braid cylinder (16)On;
5)Affiliated facility is constructed:Twice cable wind rope is respectively set in protection canopy frame both sides(7), cable wind rope(7)Column is fixed in one end (2)Top, other end steel-pipe pile(8)It is fixed on ground, and ensures cable wind rope(7)By tension uniform;Simultaneously by connection strap Shape basis(1)Steel pipe two ends connect ground connection facility;
6)The lifting of longeron top layer integral slipping is removed:Unclamp bolt(15), by longitudinal distribution beam(4), damping plank(5)And waterproof Plate(6)It is overall to coordinate unloading using two cranes, integrally hang to ground, then removed;
7)Crossbeam traction lifting is removed:Will be on box beam flange plate with the reserved lifting hole of pvc pipe in constructing continuous beam (17), suspender belt hole is opened up on bottom plate(18);In reserved lifting hole(17)And suspender belt hole(18)Place wears steel wire rope, and uses elevator Machine coordinates crane to carry out lifting dismounting;
8)Column(2)Remove:First unclamp column(2)On terminal pad(12), recycle ground crane to be removed;
9)Strip footing(1)Remove:Strip footing(1)By reserving hole for hoist(10), removed using ground crane.
6. a kind of across active service highway continuous beam according to claim 5 protects the construction method of booth structure, it is characterised in that The step 2)Central post(2)Length is adjusted accordingly according to road gradient.
7. a kind of across active service highway continuous beam according to claim 5 protects the construction method of booth structure, it is characterised in that The steel-pipe pile(8)Embedded depth is 7-9m.
8. a kind of across active service highway continuous beam according to claim 5 protects the construction method of booth structure, it is characterised in that The step 7)Middle cross beam traction lifting is removed by the way of crane is drawn plus is lifted, and is comprised the following steps that:First in box beam, Four 2T hoist engines are installed at the top of box beam, 4# suspension centres and corresponding hoist engine steel wire rope are installed into, outside crane also installs steel Cord, slowly outside side-lining;When slowly drawing 4# suspension centres and can not be displaced outwardly again, change 3# suspension centres and install steel wire rope and Row lifting, 4# suspension centres are untied, and crane continues slow outwards traction;When crossbeam 3# suspension centres are moved to below 2# suspension centres, 2# is changed Suspension centre steel wire rope, while taking off 3# suspension centres, crane continues outside traction;Crossbeam is sent to 1# suspension centres area when 2# suspension centres continue outwards to hang Domain, changes 1# suspension centre steel wire ropes, while untiing 2# suspension centres, crane continues slowly to draw outside line;After 1# suspension centres are ajusted, pause is led Draw, then uniformly tied up in transverse distribution beam with steel wire rope with a 25T crane(3)On suspension centre, start lifting, while taking off 1# suspension centres Steel wire rope;By the transverse distribution beam of lifting(3)It is transported to the material storing place of planning.
9. a kind of across active service highway continuous beam according to claim 5 protects the construction method of booth structure, it is characterised in that The step 9)Middle strip footing(1)Fixation steel plate is first removed before lifting(11).
CN201710552095.1A 2017-07-07 2017-07-07 A kind of across active service highway continuous beam protection booth structure and its construction method Withdrawn CN107269013A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710552095.1A CN107269013A (en) 2017-07-07 2017-07-07 A kind of across active service highway continuous beam protection booth structure and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710552095.1A CN107269013A (en) 2017-07-07 2017-07-07 A kind of across active service highway continuous beam protection booth structure and its construction method

Publications (1)

Publication Number Publication Date
CN107269013A true CN107269013A (en) 2017-10-20

Family

ID=60073280

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710552095.1A Withdrawn CN107269013A (en) 2017-07-07 2017-07-07 A kind of across active service highway continuous beam protection booth structure and its construction method

Country Status (1)

Country Link
CN (1) CN107269013A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108589568A (en) * 2018-05-04 2018-09-28 中铁四局集团第二工程有限公司 Rapid construction method for shed tunnel T-shaped beam crossing business line in narrow space
CN108708578A (en) * 2018-06-26 2018-10-26 徐晓胜 A kind of flexible portable distribution box protection canopy and installation and application
CN109457988A (en) * 2018-11-27 2019-03-12 中铁十四局集团第工程发展有限公司 A kind of construction safety protection canopy
WO2023228201A1 (en) * 2022-05-27 2023-11-30 Govindaraju D An interlocking system and method for constructing a stone structure

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108589568A (en) * 2018-05-04 2018-09-28 中铁四局集团第二工程有限公司 Rapid construction method for shed tunnel T-shaped beam crossing business line in narrow space
CN108589568B (en) * 2018-05-04 2020-03-27 中铁四局集团第二工程有限公司 Rapid construction method for shed tunnel T-shaped beam crossing business line in narrow space
CN108708578A (en) * 2018-06-26 2018-10-26 徐晓胜 A kind of flexible portable distribution box protection canopy and installation and application
CN109457988A (en) * 2018-11-27 2019-03-12 中铁十四局集团第工程发展有限公司 A kind of construction safety protection canopy
WO2023228201A1 (en) * 2022-05-27 2023-11-30 Govindaraju D An interlocking system and method for constructing a stone structure

Similar Documents

Publication Publication Date Title
CN107269013A (en) A kind of across active service highway continuous beam protection booth structure and its construction method
CN105484164B (en) Spanning type bailey beam bracket and construction method thereof
CN207001991U (en) Hoist device that prefabricated case roof beam of high-speed railway was used
CN102912730A (en) Hoisting construction method for single-rib closure rope of large-span reinforced concrete arch bridge
CN108862045A (en) The method of special-shaped steel girder member bar turning device and member bar turning
CN105239510A (en) Dismounting beam support used for high pier small-radius curve cast-in-situ box beam and construction method
CN107119567A (en) Suspension bridge steel box-girder deck erection gantry and spreading hoist cable swing shifting construction method
CN106592962A (en) Large-height-difference long-span stiff-skeleton cladding concrete formwork construction method and apparatus
CN109098089A (en) A kind of suspension bridge column overhead main cable saddle hanging apparatus and construction method
CN110939069B (en) Construction method of suspension bridge catwalk
CN108862081A (en) A kind of chain block crane boom and the application in the adjusting of beam steel protective layer thickness
CN105464456A (en) Method and lifting sling for assembling extra-high voltage transmission iron tower through helicopter
CN106144929A (en) Group hoist device and construction method
CN208346656U (en) A kind of hanging basket for the construction of bridge coping prestress wire two times tensioning
CN105905815A (en) Work method of seating-type self-balance holding pole
CN208167536U (en) A kind of operation platform removed for bridge temporary support
CN207363285U (en) A kind of across active service highway continuous beam protection booth structure
CN108797339A (en) A kind of safe construction method of cast-in-situ steel reinforced concrete anticollision barrier
CN106006301B (en) A kind of Super High construction elevator high-altitude conversion servicing unit and construction method
CN106185618A (en) A kind of for Generator Stator hoisting structure and hanging method thereof
CN214329956U (en) Ring rail hoisting device for curtain wall installation
CN105883614B (en) The method that single device unbalance loading lifts gantry crane girder
CN102493367A (en) Non-blasting construction method for dismantling pier to land bridge
CN209940330U (en) Tower crane externally-hung detachable safety passageway for people to get on
CN108059088B (en) Method and device for deflection turning and transposition of carrying pole Liang Kongzhong of slot erecting machine

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20171020